Professional Documents
Culture Documents
Emergency Operating Procedure
Emergency Operating Procedure
TRNEPL/
Shaping the future
2020 2 X 300 MW Power Plant Emergency/ 00
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
TRNEPL 2 X 300 MW
EMERGENCY
OPERATING
PROCEDURES
An Emergency Operating Procedure (EOP) is developed to provide the detailed
and comprehensible emergency conditions & also enabled operator to take action
within stipulated time period for the safe guard of men, machine & environment.
The validation shows that the load and pressure for the workers can be reduced
and the safety of TPP can be enhanced.
INDEX
Station/Unit Emergencies
2 Unit Tripping 5
6 Fire Disaster 12
INDEX
INDEX
INDEX
INDEX
INDEX
Electrical System Emergencies:
Sl. No. System Descriptions Page. No
1 Power Supply Failure on Emergency PCC 112
2 DG not Started in Auto 113
3 Station Transformer Failure 114-115
4 UPS Failure 116
5 DCDB Failure 117
6 DC Fails of Motor Feeder 118
7 Fast Bus Transfer Blocked 118-119
8 Flash Over 120
9 Gas Pressure Low of Circuit Breaker 121
10 Fire in Cable Gallery 122
11 Hot Spot 123
12 High Oil/Winding Temperature of Transformer 123
13 Oil Leakage in Transformer CB/CT/PT 124
14 Transformer Tripped 125
15 SCADA not Responding 125-126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
STATION/UNIT - EMERGENCIES
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
1. Station Blackout
Likely Causes:
1. Generator parallels off, working power of 6.6 KV all sections are off or UAT/ST transformer trips
and the primary and secondary safety source are not automatically put into operation successfully.
Plant Response:
1. Unit trip, boiler MFT, generator trip and generator parallel-off; alarming and each corresponding
alarm window lights.
2. The auxiliary bus bar voltage of all sections decreases to zero and its green light of power switch is
on.
3. All operating AC auxiliary equipment shut down and the spare AC auxiliary equipment do not
interlock; the electric-driven valve does not operate.
4. Start all DC equipment by interlock.
5. AC illuminating lamp is off, DC illuminating lamp is on and the control room gets dark.
Immediate Action to be taken:
1. Inform to WRLDC (Switchyard Engineer)
2. Ensure turbine DC EOP came into service. If not, start the EOP from DCS. In case of DCS problem,
there is provision to start EOP from desk hardwire push button. If not started from hardwire too, then
ask local operator to start it from local.
3. Ensure DC seal oil pump came into service. If not, start the SOP from DCS. In case of DCS problem,
ask local operator to start it from local.
4. Ensure generator circuit breaker, field breaker and unit bus incoming breakers have opened.
5. Ensure DC scanner fan came into service. If not, start the fan.
6. DG starts in auto and emergency PMCC gets charged. If not, start the DG from local and charge the
emergency EMCC.
7. JOP starts at 2500 rpm in auto. If emergency power (DG) has restored. If not, start the pump after
restoration of DG supply.
8. UPS, DC loads will be met by battery.
9. Diesel fire water pumps (hydrant) are available for fire.
10. Close steam lines & turbine drain valves (manual) to avoid failure of condenser rupture disc.
11. Inform DM plant to isolate CW Chlorine tonner.
12. Ensure both APH are running, if not start from DCS or Local, else rotate it manually.
13. Ensure that all fuel oil trip valves are closed
14. If soot blower was in service, retract manually.
15. Ensure all 6.6 KV drives breakers are open.
Turbine Side:
1. Fast close HP-LP bypass valves if opens in auto otherwise need not to open the same, close turbine
drain MIVs.
2. Open vacuum breakers after isolating all steam lines/drains to condenser, when turbine speed has
fallen to 2700 rpm and close gland steam supply valves.
3. Start turbine auxiliary oil pump. Stop EOP after restoration of emergency (DG) power.
Page 1 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
4. Start AC seal oil pump (A / B) and stop DC seal oil pump after restoration of DG power.
5. Start all BFP AOPs.( Not essential if pump is not in service before blackout )
6. Ensure turbine barring came into service. Otherwise start manual barring.
7. Ensure DCDB and UPS come on AC supply from battery source.
Boiler Side:
DC And UPS:
Note:
1. Note down the protections acted in Generator, Transformer, Switchyard, Boiler, Turbine & Switchgear.
2. Check for TG vibration during coasting down and note down the coasting down time and max vibration.
3. Ensure that all normally open tie breakers of 6.6 KV buses are open.
4. Turbine, boiler lifts will be available, don’t operate lifts and isolate the power supply after park at 0
mtr with caution tag.
5. All MOVs, motor operated dampers will be available on emergency power.
Normalization:
Firstly, coordinate with WRLDC clearance for charging the line, after clearance & receive code from
WRLDC & charged the line.
1. Co-ordinate with 400 KV switchyard operators for power restoration.
2. Charge ST once power is available.
3. Charge station switchgear, unit switchgear. (6.6 KV)
4. Charge Unit PMCC, Boiler MCC, Turbine MCC, ESP PCC.
Page 2 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Normalization Contd..:
5. Charge lighting PCC, Compressor PCC.
6. Charge water supply MCC, chemical water MCC. (DM plant )
7. Normalize EMCC and stop DG.
8. Charge CTMCC
9. Charge CHP PMCC.
10. Ensure DM plant and CHP power restored.
11. Start CCCW pump
12. Start air compressor and dryer.
13. Start circulating water pump as per SOP.
14. Start OCCW pump
15. Start control room air conditioning.
16. Stop diesel fire pumps.
17. Check the healthiness of battery chargers, UPS.
Page 3 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Emergency drives will not be in service during normal operation. To keep them in good condition and to know
the availability, periodical trial is required. Following points to be ensured for safe handling of blackout.
Page 4 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
2. Unit Tripping
Immediate checks if only turbo generator trips:
1. Ensure generator circuit breaker, field breaker and unit bus incoming breakers have opened and
turbine is coasting down, barring gear to be put into service manually.
2. Ensure turbine’s AOP started, else start manually.
3. Inform to WRLDC.
Page 5 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
1. Air compressors in operation trip and standby air compressors are not put into operation or air
compressors in operation are not loaded enough.
2. Sudden increase in consumption.
3. Malfunction of air compressor.
4. Instrument air receiver’s air leak/drain valve might be in opened condition.
5. Tripping of ST.
6. Tripping of CCCW pump.
7. Instrument air piping failure at valve flange or pipe welding joints.
8. The safety valve of compressed air system is jammed and cannot blow down after operation.
Page 6 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
Turbine Side
Sl. No. Valve Location Valve Descriptions Air Fail Operation
HPH-6 To D/A normal drain Close - air lock relay
Deaerator Floor PRDS To D/A Close
1
(El+22 mtr.) CRH To PRDS Close
CEP To expansion tank Close - air lock relay
Gen. H2 cooler CV Close - air lock relay
Gland steam to LPH#1 dump valve Open
LP bypass 3rd spray CV Close
Hood spray CV Open
Gland steam attemperation CV Open
Turbine Floor
2 LP bypass RHS drain CV Open
(El+6 mtr.) LP bypass LHS drain CV Open
CEP To CST CV Lose - air lock relay
Gland steam header diaphragm valve Open
Gland steam header main CV Open
CRH All POT drain Open
D/A level CV main Line Open - air lock relay
D/A level CV bypass line Open - air lock relay
LPH-03 drip to drain tank CV Open
LP drip pump to LPH-02 O/L CV Close
LPH-04 drip to LPH-03 CV Open
HP flash tank spray CV Close
LP flash tank spray CV Close
LPH-03 emergency drain CV Open
LPH-04 drip CV Open
HPH-06 emergency drain CV Close - air lock relay
HPH-07 emergency drain CV Close - air lock relay
HP turbine casing drain Open
Turbine Floor
3 MS line drain CV Open
(El+0 mtr.) CRH line drain CV Open
HRH line drain CV Open
All extraction drain CV Open
CRH to PRDS drain CV Open
BFP to HPH-06 inlet line drain CV Open
CCCW to turbine lube oil cooler CV Close - air lock relay
HPH 3-way valve drain CV Open
LP drain tank to Hotwell CV Open
Hotwell makeup CV Open
CEP re-circulation CV/CST make up CV Close
Vacuum oil tank level CV Air lock
Stator water temp. CV/Vacuum pump suction valve Open
Page 7 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Contd…
Boiler Side
Sl. No. Valve Location Valve Descriptions Air Fail Operation
1 Boiler, El+ 14 mtr. Feed control station Open - air lock relay
2 Boiler, El+ 60 mtr. Start-up vent Power cylinder holding type
3 Boiler (all corner) SADC Power cylinder holding type
4 Mill Area, El+10 mtr. Mill discharge valve Power cylinder switching type
5 Mill Area HAG & TAG Power cylinder switching type
6 Boiler, El+63 mtr. Soot blower line Close
7 Boiler, EL+14 mtr. LOTV, HOTV (SOVs) Close
Gun atomizing, purging & fuel oil valve
8 Boiler (all corner) Close
(SOVs)
9 Boiler, EL+14 mtr. LOCV, HOCV Close
10 ESP ESP lift valve & bypass valve Power cylinder switching type
11 Boiler, EL+ 65 mtr. MS line & HRH line PRV Power cylinder switching type
Parameters of Concern:
1. Sudden drop in condenser vacuum.
2. Controlling of unit load not possible.
3. Controlling of condensate flow not possible.
4. Gland steam pressure & temperature.
5. Mill HAGs & TAGs will not operate.
6. Controlling of deaerator level not possible.
Page 8 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Likely Causes:
1. A primary air fan trip.
2. An induced draft fan trip.
3. A forced draft fan trip.
4. A BFP trip.
5. Any mill trip.
Plant Response:
1. There is trip sound-light alarm of crucial auxiliary equipment and fluctuation of parameters controlled
by tripped auxiliary equipment.
2. Running coal mill is programmed to trip.
3. Unit load declines rapidly too and is stable at the setting load of related equipments.
4. Main steam flow, feed water flow and steam pressure drop by a large margin and the steam
temperature declines to some degree.
Parameters of Concern:
1. Load.
2. Air Flow, Feed water flow, drum level.
3. MS, HRH, CRH Temp and pressure.
4. Furnace Draft.
1. When there is 50% RB, the automatic tripping sequence of the coal mill from top to bottom is: F→E
mill trip with the interval of 10 seconds until the last four mills remain in operation. The interval of
mill trip is 5 seconds when PA fan trip.
2. Unit control mode is switched from CCS to “turbine follow mode” and reduces the load to 50%
MCR according to RB load reduction setting.
3. Operators shall closely monitor the parameter variation and put oil gun into service timely for
combustion-supporting during automatic RB. No interference shall be applied, only if the automatic
operation is normal until the unit goes steady.
4. If one BFP trip and standby BFP start in interlock immediately maintain feed water flow to maintain
drum level in manual.
Page 9 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Contd…
5. Boiler load>50% MCR, and one BFP trip while standby BFP pickup in interlock. The load shedding
comes up to 46% MCR.
6. Immediately switch automatic operation into manual operation for adjustment if abnormalities happen
during automatic RB process.
1. Immediately trip an upper coal mill manually and put the oil gun on one bottom running coal mill into
operation for combustion-supporting. Remove the furnace pressure automation; adjust parameters like
drum water level, drum pressure, furnace pressure, and oxygen content within allowable range
according to specific case. Keep stopping the operation of some coal mills, if necessary.
2. When primary fan trips, immediately disable the furnace pressure automation and closely monitor
primary air pressure variation. If it is not allowed for operation of three pulverizing systems, trip one
coal mill every 5 seconds until the last one coal mill is maintained to operate, and timely put oil gun of
this mill into operation as well as reduce electrical load down to 150 MW.
3. During manual RB operation, pay attention to the variation of main steam temperature and reheater
steam temperature preventing low temperature protection operation when sharply reducing boiler
thermal load to choose coal mills to be tripped.
4. Restore the system with load after fault is cleared.
Page 10 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Abnormal sound.
2. Damage to pipe lines.
3. Damage to hangers.
Parameters of Concern:
1. Put control on auto only after achieving designed system pressure and temperature.
Page 11 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
6. Fire Disaster
If fire disaster happens in the areas charged by the operators, they:
1. Should not leave their posts without permission or run around in panic.
2. Should strengthen the unit operation /maintenance and treat the accident based on rules.
3. Should implement the right order from upper level immediately.
4. Treatment of fire disaster.
5. Rush to the fire scene quickly after fire alarm signal is sent out, learn about the fire situation, check if
the fire-fighting system operates normally and make use of related fire extinguisher correctly to put
out the fire.
6. In case of the electrical equipment is on fire, cut off the power supply firstly, and then use the fire
extinguisher to put out the fire. If the electrical equipment is on fire, which may threaten the safety of
equipment, shut down the equipment and cut off the power supply.
7. Try to prevent the fire spreading, take away the inflammable substances around the fire scene and put
out the fire as soon as possible when the fire is not threatening the unit operation.
8. Strengthen monitoring operation and make preparation for shutdown.
9. Shut down for emergency immediately when fire disaster is seriously threatening the unit safety.
10. If the oil tank is on fire or the fire is near the oil tank, which is seriously threatening the oil tank safety,
open the emergency oil drain valve at the same time while shutting down by breaking vacuum.
However, the lubricating oil should not be interrupted before the unit stops to prevent the bearing
burnt.
11. Shut down for emergency when the fire of sealed oil system cannot be put out immediately and
threatens the equipment safety, and exhaust the hydrogen during the process of idling to ensure that
the sealed oil system can support the unit until it stop.
12. Shut down for emergency and charge CO2 into the generator to extinguish the fire by exhausting H2
when the generator or hydrogen cooling system is on fire. Operation of water cooling system should
be maintained.
1. Fire on sundries without being oil-immersed can be extinguished with water, foam extinguisher and
sands, etc.
2. Fire on oil-immersed sundries shall be extinguished with foam extinguisher and sand, etc.
3. Fire on oil in oil tank or other containers shall be extinguished with foam extinguisher, CO2, DCP.
Wet cloth extinguishing or air isolation can be applied if necessary but sand and water faucet
without nozzle is prohibited for extinguishing.
Page 12 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
4. Fire on charged equipment shall be extinguished with CO2, and powder extinguisher after power cutoff
but foam extinguisher shall not be applied. It is prohibited to extinguish fire of motor by filling sand or
large stream of water into the motor.
5. When charged equipment is on fire, CO2 and DCP extinguisher can be applied for extinguishing if the
power cannot be immediately cut off. It is forbidden to employ other non-insulated extinguisher.
6. When steam pipe or other high temperature components are on fire, CO2 extinguisher shall be
prohibited and water applying shall also be cautious in case thermal stress damages the equipment.
7. If running part and speed-regulating system of the equipment is on fire, sand is not to be applied for
extinguishing. And meanwhile, execute extinguishing fire according to the above mentioned
provisions.
8. Fire on hydrogen system is mainly extinguished with CO2 and DCP.
Page 13 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 14 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
1. FD Fan Trip
Likely Causes:
1. ID fan tripped & general interlock is in service.
2. Respective APH tripped. (delay 01 sec).
3. FD fan bearing bush vibration > 11 mm/s, 3 sec delay.
4. Fan bearing temperature high > 90°, 3sec delay
5. Motor bearing temperature high > 90°C, 3sec delay.
6. Motor winding temperature high > 135°C, 3 sec delay.
7. Lube oil pr. <0.5 MPa.
8. FD fan running & O/L gate closed (delay 60 sec).
9. Electrical protections.
10. Furnace pressure HH > 3000 Pa (delay 1 sec).
11. Any transmitter malfunction.
Plant Response:
Page 15 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Close tripped fan blade pitch & discharge damper, if it not closed.
2. Monitor running fan parameters and motor parameters.
3. Reduce coal flow according to total air flow.
4. Keep 4 mills in running (tripping of more mills reduce the PA flow contribution to total air flow).
5. Maintain furnace pressure.
6. Monitor MS temperature & pressure.
7. Reduce load set point w.r.t. MS pressure.
8. Inform local operator to check tripped fan condition.
9. Inform C&I, if any transmitter malfunctions.
Page 16 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
2. ID Fan Trip
Likely Causes:
Plant Response:
1. Particular FD fan trip (if general interlock put into service)
2. Furnace pressure goes to positive.
3. Oxygen rapidly decreases.
4. Total air flow decreases.
5. Wind box DP rapidly decreases.
6. Furnace flame may disturb.
7. Running ID fan and FD fan loading increase.
8. Top two mills will have to trip and BC layer guns will be taken manually.
9. Power generation will reduce.
Parameters of Concern:
Page 17 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 18 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
3. PA Fan Trip
Likely Causes:
1. Respective APH is tripped.
2. PA fan bearing temperature HH > 90° C, 3 sec delay.
3. PA fan motor bearing> 90° C, 3 sec delay.
4. PA fan motor winding temperature HH> 135° C, 3 sec delay.
5. PA fan bearing vibration HH>11 mm/s.
6. PA fan lube oil pressure LL <0.06 MPa, 5 sec delay.
7. Both lube oil pump tripped.
8. Motor protection acted.
Plant Response:
1. PA header pressure drop rapidly.
2. Furnace pressure decrease.
3. Tripped fan outlet damper close.
4. Mill inlet PA flow and pressure drops.
5. Mill outlet coal velocity decrease.
6. Running PA fan loading increase.
7. Power generation decrease.
8. Main steam pressure & temperature decreases rapidly.
Parameters of Concern:
1. Furnace pressure.
2. PA header pressure.
3. Mill inlet PA pressure and flow.
4. Running PA fan loading.
5. Power generation.
6. Main steam pressure & temperature.
7. Flue gas oxygen.
Page 19 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Furnace pressure.
2. Air flow.
3. Drum level.
4. Current fluctuation.
5. Fan vibration.
6. Generation.
Page 20 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 21 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Note: - Unit can’t be survived with aforementioned condition due to elimination of flue gas I/L dampers.
Plant Response:
1. Boiler will trip on < 3.5 Kpa scanner cooling air pressure low.
2. Scanner air fan tripped alarm
3. Inadequate cooling of scanners may cause damage to scanner sensing element.
4. Flame cool fan pressure LOW alarm.
Parameters of Concern:
1. Cooling air to scanner.
2. Unit tripping.
Expected Operator’s Action:
1. Try to start the fan by resetting the over load relay, even after boiler trip.
Page 22 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Alarm display on DCS of low seal air pressure.
2. Mill thrust bearing damaged.
3. Coal dust enters to mill seal and damages.
4. Mill current.
Parameters of Concern:
1. Mill thrust bearing temp,
2. Mill vibration.
3. Mill current.
4. Mill bowl assembly will be damage.
Page 23 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Likely Causes:
1. Mill outlet temperature maintaining high.
2. Foreign material in mill.
3. Coal quality (high CV).
4. High VM coal with mill inlet PA temp high.
5. Rejection not cleared for long time.
6. Mill internal damage.
7. Coal accumulation in scraper chamber due to scraper damage.
8. Coal flow established suddenly at high mill outlet temperature.
Plant Response:
1. Mill outlet temperature shoots up.
2. Mill may trip on protection.
3. Surrounding may catch fire.
4. Mill gates and damper may not operate damage done by explosion.
5. Duct and bellow may damage.
6. Fluctuation in furnace pressure.
7. PA header pressure dropped rapidly.
8. Main steam temperature decrease.
9. Power generation decrease.
Parameters of Concern:
1. Furnace pressure.
2. MS temp and PA header pressure.
3. Mill and duct surroundings.
4. Power generation.
Page 24 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 25 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Boiler make-up water consumption will increase.
2. Fluctuation in furnace pressure.
3. ID Fan will draw more current.
4. Water wall metal temperature will remain high around the leakage.
5. Abnormal sound comes from the boiler furnace.
6. Leakage detectors show high intensity.
7. O2 fluctuation at APH inlet.
8. Generation may vary.
Parameters of Concern:
1. DM water make-up.
2. Furnace pressure.
3. ID fan current.
4. Water wall metal temperatures.
5. Acoustics intensity.
6. O2 %.
Page 26 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
Page 27 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. DM water make-up.
2. Economizer outlet flue gas temperature.
3. ID Fan current.
4. Economizer de-ashing.
5. BTLD intensity.
6. Flue gas temperatures at APH Inlet and Outlet.
1. Check economizer zone in second pass for any abnormal sound inside.
2. Check economizer hoppers for any water leaking.
3. Closely monitor ID fan current.
4. Closely monitor DM water make-up.
5. Reduce the load, if necessary.
6. If the leakage is heavy and difficult to compensate feed water, shut down the boiler.
Page 28 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Fluctuation in furnace pressure.
2. Increase ID fans loading.
3. Leak detector shows high intensity in particular leakage area.
4. Increase DM water consumption.
5. SH tube metal temperature near to leakage may increase.
6. Drop in flue gas temperature at APH inlet.
7. Abnormal sound comes in boiler.
8. Increase difference between feed water and steam flow.
9. MS pressure and power generation will decrease.
10. Flue gas oxygen reading may go down.
Parameters of Concern:
1. Furnace pressure.
2. ID fans current.
3. SH metal temp.
4. DM water consumption.
5. Furnace pressure.
6. Flue gas temp.
7. Main steam pressure.
8. Power generation.
Page 29 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Fluctuation in furnace pressure.
2. Increase ID fans loading.
3. Increase metal temperature after particular tube leakage of reheater tube.
4. Drop of flue gas temperature at APH inlet.
5. Increase in DM water consumption.
6. Leak detector shows high intensity in particular leakage area.
7. Abnormal sound comes in boiler.
8. Power generation will decrease
9. Pressure drop across reheater coil will increase.
10. Flue gas oxygen may go down.
Parameters of Concern:
1. ID fans current.
2. Reheater metal temp.
3. DM water consumption.
4. Furnace pressure.
5. Flue gas temperature.
6. Power generation.
Expected Operator’s Action:
1. Check on line steam leakage detector system.
2. Check boiler at local for any abnormal sound inside.
3. Closely monitoring furnace pressure and ID fan loading and other concern parameters.
4. If require reduce generation and increase feed water for maintaining metal temp.
5. Closely monitor flue gas temp.
6. Shutdown the unit after confirming tube leakage.
Page 30 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Main Steam Temperature
2. Feed water flow
3. Coal flow
4. Flue gas O2
5. Total air flow.
Expected Operator’s Action:
1. Close the spray control valve by taking into manual.
2. Check air flow and adjust.
3. Top elevation can be taken in to service / firing can be raised and close secondary air damper if open.
4. Reduce load set point.
5. Stop soot blowing.
6. Adjust feed water flow
7. Check, if any feeders malfunction or chocked.
Page 31 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 32 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 33 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. RH metal temp high alarm will appear.
2. Spray control valves will go for further opening.
3. Load will rise for the same pressure.
Parameters of Concern:
1. Reheater tube metal temperature
2. Wall blowing.
3. SADC operation.
4. IP turbine expansion.
Page 34 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Load variation.
2. HP bypass will open if MS pressure crossed 17.5 MPa.
3. HP bypass will fast open if MS pressure crossed 19 MPa.
4. SH O/L ERV floats at 18.87 MPa.
5. MS safety valve floating if pressure more than 19.06 MPa.
Parameters of Concern:
1. Load.
2. Main steam pressure.
3. Main steam temperature.
4. Drum level
Expected Operator’s Action:
1. Increase generation / load, if margin is there in load set point.
2. Reduce coal flow.
3. Ensure PA pressure is normal and if possible decrease PA pressure for short duration.
4. Maintain drum level, MS temperature and feed water flow.
5. Inform C&I department to attend transmitter malfunction.
Page 35 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Load reduces.
2. MS temperature reduces.
3. Coal feeding increase if mills are in auto.
Parameters of Concern:
1. Load.
2. Main steam pressure.
3. Main steam temperature.
4. Drum level.
Page 36 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Main steam pressure drop rapidly.
2. Steam flow will increase.
3. Load reduces.
4. Main steam temp reduce.
5. Heavy noise.
Parameters of Concern:
1. MS temperature & pressure.
2. Drum level.
3. Fuel flow.
4. Load.
5. Feed water flow.
6. Water consumption.
7. HP/LP Bypass healthiness.
8. Metal temperature.
Page 37 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Load reduces.
2. Heavy noise due to valve floating.
3. HRH steam temperature drop.
4. HP heater#6/7 level may disturb.
5. Safety valve floating and simmering.
Parameters of Concern:
1. Load.
2. IPSV, IPCV operation.
3. Water consumption, condenser vacuum if LP bypass opened to reduce pressure.
Page 38 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Boiler furnace draught variation.
2. ID fan may trip due to overload.
3. Flame stability may disturb.
Parameters of Concern:
1. ID fan current /blade pitch.
2. Furnace draught.
3. Flame intensity.
4. Flue gas O2.
5. Unit load.
6. Seal trough over flow.
7. Bottom ash system sump level.
8. Total airflow.
9. Furnace to wind box DP.
Page 39 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 40 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Alarm display on DCS of furnace pressure variation.
2. Boiler will trip on heavy furnace fluctuation.
3. Chances of furnace flame disturbance.
Parameters of Concern:
1. ID fan current.
2. Furnace to wind box DP.
3. Blade pitch position.
4. Seal trough over flow.
5. Bottom ash system.
6. Furnace flame.
Page 41 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. PA I/C damper will open in auto.
2. PA header pressure goes down.
3. Mill PA flow goes down.
4. Decrease in generation.
5. Variation in furnace pressure (towards negative side).
6. Decrease in total primary air.
7. SH/RH temperature will drop.
Parameters of Concern:
1. Current of running or loaded PA fan.
2. PA flow in running mills.
3. PA header pressure.
4. Seal air discharge pressure.
5. Main steam and HRH temperature.
6. Flame stability due to mills taken out.
Page 42 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 43 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. As per DM plant report silica will vary.
2. Turbine vibration may be high, during long time operation.
3. Axial shift may increase.
4. Turbine first stage pressure increase.
Parameters of Concern:
1. Silica concentration in boiler drum.
2. Drum pressure.
3. Hot well conductivity.
Page 44 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Boiler conductivity also comes down
2. Internal corrosion of boiler tubes increases and chance of tube failure, if left for long duration.
3. Silica value variation.
4. Condenser tube leakage.
Parameters of Concern:
1. Boiler feed water pH.
2. Condensate water pH.
3. Entire water circuit pH will be drop gradually.
4. Main steam pH.
Page 45 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Local expansion reading is uneven,
2. Buck-stay may damage.
3. Boiler structure loading may change.
Parameters of Concern:
1. Boiler expansion local readings.
Expected Operator’s Action:
1. Rise metal temperature as per startup curves.
2. Maintain proper air/fuel flow.
3. Check buck stay healthiness.
4. Do local check for any physical obstruction.
Page 46 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Smoke or fire comes out from the bunker.
2. Travelling tippler conveyer may damage.
3. Coal feeder belt may damage.
4. Red spots may be observed at the outer wall of the coal bunker.
5. Coal feeder temperature will increase.
Parameters of Concern:
1. Bunker level.
2. Coal quality and coal handling plant.
3. Coal feeder belt.
4. Bunker structure.
Page 47 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. No proper flame intensity.
2. Increase in oil flow than normal observed.
Parameters of Concern:
1. Flame intensity.
2. Oil pressure.
3. Atomizing steam pressure.
Page 48 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Draught fluctuation.
2. ID fan may trip on over load.
3. Flame may disturb.
4. MS and RH temp variation.
Parameters of Concern:
1. Furnace pressure.
Page 49 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Soot blower may damage.
2. Damage coil tubes due to steam erosion.
Parameters of Concern:
1. Specific zone metal temperature.
Page 50 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Change in ∆P across APH.
2. Rise in metal temperature of SH/RH.
3. Increase in DM water consumption (in case of SH/RH tube leakage)
4. Difference between feed flow and steam flow increases (in case of SH/RH tube leakage)
5. MS temperature going down (in case of high air flow).
6. APH inlet temperature rise.
Parameters of Concern:
1. Furnace pressure.
2. SH/RH metal temperature
3. DM water consumption.
4. MS temperature
5. Feed water and steam flow.
6. APH inlet temperature.
Likely Causes:
1. Mixed combustion time with coal and oil is too long during boiler start up (shutdown) process, so that
fuel materials accumulate at tail heating surface and corrugated plated of air preheater.
2. Time of boiler running with low load is too long that combustible materials pile up in second pass.
3. Coarse pulverized coal or improper combustion adjustment causes unburnt pulverized coal to enter
boiler second pass.
4. Soot blower not available for long time.
Page 51 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Flue gas temperature at air preheater inlet/outlet and exhaust flue gas temperature rise high while flue gas
pressure goes abnormal. Oxygen content goes low.
2. Air preheater current fluctuates to a large degree. Bearing and case temperature rises high and
stagnation occurs when situation is serious.
3. Hot primary and secondary air temperature rises high.
4. Furnace pressure fluctuates and induced draft fan blade automatically opens wide with induced draft fan
current rising.
5. When re-burning occurs at reheater side, reheated steam temperature will rise high abnormally.
Simultaneously, the temperature at separation screen rises and primary water spray amount is
increasing.
Parameters of Concern:
1. MS and RH Temperature.
2. ID fan current.
3. APH current.
4. Furnace draught.
5. Hot SA and PA temperature.
Page 52 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Alarm will come on both soft and hard wire panel.
2. All water level transmitters will show high value.
3. Hydra step will show red indication confirming of high water level.
4. SH steam temperature decreases if drum level protection not acted.
5. Feed water flow will be greater than main steam flow.
6. Unit may trip on high drum level if not controlled till protection value +250 mm.
Parameters of Concern:
1. Drum level.
2. Feed water flow.
3. Total fuel flow.
4. MS temperature
5. Total air flow.
Page 53 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Low level alarm will come on both soft and hard wire panel.
2. All for water level transmitter will show low or negative value.
3. Hydra step will show red indication confirming of low water level.
4. Feed water flow will be lesser than main steam flow if feed water system is faulty.
5. Feed water flow will be greater than main steam flow if leakage is there in water wall tubes.
Page 54 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Drum level
2. Feed water flow.
3. Total fuel flow.
4. Total air flow.
Expected Operator’s Action:
1. If BFP scoop in auto, take it into manual.
2. Increase the BFP scoop to increase feed water flow.
3. If still drum level decreasing then close bottom ring header drain valve (if in opened condition).
4. Increase air flow.
5. Manually trip the boiler if drum level crossed -250 mm for 5 sec and protection not acted.
6. Check boiler locally for any leakage
Final Corrective Actions:
1. Maintain proper feed water flow.
2. Maintain proper fuel.
3. Maintain required air flow.
Page 55 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 56 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 57 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Condenser vacuum start decreasing.
2. Load decreases because of vacuum drop.
Parameters of Concern:
1. Condenser vacuum.
2. Hotwell conductivity.
3. Deaerator level.
4. Discharge pressure of CEP.
5. Healthiness of level transmitter.
6. Local level gauge reading.
7. Unit load.
8. Actual level of hotwell, if level transmitter has crossed its range.
Page 58 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Deaerator level drops fast.
2. CEP discharge pressure drop.
3. CEP may trip on hotwell level LL.
Parameters of Concern:
1. Condensate water flow.
2. Deaerator level.
3. Discharge pressure of CEP.
4. Healthiness of level transmitter.
5. Local level gauge reading.
6. Unit load.
Page 59 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Likely Causes:
1. Deaerator level control valve abnormal operation.
2. HP heater#7 drip coming more.
3. Any BFP tripped.
4. Load reduced very fast.
5. HPH tube leakage.
6. FW demand low (drum level high condition).
Plant Response:
1. Deaerator pressure may drop.
2. Deaerator temperature may drop.
3. Deaerator overflow valve open.
4. Hotwell level variation.
Parameters of Concern:
1. Deaerator control valve position.
2. Hot well level.
3. BFP parameters like recirculation valve position and suction flows.
4. CEP discharge pressure.
5. Deaerator overflow valve position.
6. Deaerator pressure and temperature
7. All HP heaters level.
Page 60 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Deaerator level low alarm will come.
2. If deaerator level control valve in auto, CEP outlet header pressure will drop & stand by CEP may
pick up.
3. Hot well level may drop.
4. All BFP will trip, if level goes below 400 mm.
Parameters of Concern:
1. Deaerator level.
2. CEP parameters like discharge pressure and condensate flow.
3. Deaerator level CV position.
4. HPH#6/7 levels and drip control valve positions.
5. Normal drain MIV position, emergency drain control valve position.
6. Deaerator drain MOV position.
Page 61 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. D/A level decreases fast.
2. If LP bypass system is in service its outlet temperature will rise and bypass will close on low
cooling pressure.
3. CEP discharge header pressure decreases.
4. Hot well level increases.
5. LP gland steam spray disturbed.
6. 3rd stage and LP exhaust spray disturbed.
Parameters of Concern:
1. CEP outlet pressure.
2. Hot well level & deaerator level.
3. Deaerator level control valve position.
4. Running CEP parameters.
5. Hot well level CV position.
6. Unit load.
7. Condenser vacuum.
8. Gland steam temperature.
Page 62 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 63 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Condenser vacuum start decreasing very fast.
2. Unit load decreases.
3. Fall in CW duct pressure.
4. CW forebay level may overflow.
Parameters of Concern:
1. Condenser vacuum.
2. Unit load.
3. CW discharge pressure, current and vibration of running pump.
4. Starting of 2nd vacuum pump.
5. OCCW pumps healthiness.
6. Trip pumps discharge valve fully closed and pump is not reverse rotating.
7. CW inlet and outlet temperature.
8. Exhaust hood temperature.
Page 64 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 65 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Heater will be cut off and bypass if level rising than specified limit.
2. If heater is cut off vacuum may be effected.
3. If heater is cut off turbine axial shift will be increase.
4. If heater is cut off, load rising temporary and then after sometime load will be decreases.
5. Hot well level rise.
6. Deaerator level fall (if heater got bypassed).
Parameters of Concern:
1. Generation
2. Feed water temperature
3. Deaerator pressure
4. Heater level
5. Condenser vacuum
6. Axial shift
7. MS pressure, MS temporal flow, feed water flow, feed water temp
8. Extraction pressure
9. Extraction temp
Expected Operator’s Action:
1. Switch over drip controls to manuals and regulate levels.
2. Check control valves operation, or air leakage.
3. Check emergency and normal drain MIV and control valve for opening.
4. Check heater levels in local gauge glass.
5. Check flow to deaerator. If flow does not take place due to high deaerator pressure, or low
extraction pressure or faulty interlock action, rectify it.
6. If deaerator pressure is high, reduce pressure by throttling extraction#5 from turbine.
Page 66 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 67 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Turbine vibration high alarm will come.
2. Turbine will trip if shaft vibration reaches to 150 microns.
3. Axial shift may increase.
4. Bearing metal temperature may rise.
5. Unit sound abnormal, vibration of bearing is obvious by hand feeling
Parameters of Concern:
1. Turbine vibration.
2. HP-IP differential expansion.
3. Turbine speed.
4. Rotor eccentricity.
5. Axial shift.
6. Lube oil pr. & temperature
7. Condenser vacuum.
8. Gland steam temperature
9. Main steam & Reheat steam parameters.
10. Bearing metal temperature and return oil temperature
11. Physical vibration.
Expected Operator’s Action:
1. Turbine vibration readings are to be crosschecked and also local actual vibration to be checked
physically.
2. Listen for any sound coming at turbine bearings.
3. When turbine vibration is very high, turbine should trip otherwise trip the unit manually.
4. Check and ensure whether lube oil pr. and temperature at bearings are normal whether bearing
metal temperature and return oil temperature is normal. Otherwise take appropriate action.
5. During start-up do proper soaking of turbine.
6. Reduce load to suit the condition.
7. Wait for frequency change, if it is high.
8. Try to maintain turbine steam parameters as per startup curve.
9. Avoid sudden change in steam temperatures & load.
10. Try to maintain axial shift, differential expansion, condenser vacuum, exhaust hood temp,
eccentricity within limits.
11. Isolate the source of cold steam and water and open drain if the vibration is caused by water impact.
Caution:
1. If the turbine vibration is very high, unit should be tripped immediately and fast coasting down to
bring zero rpm.
Final Corrective Actions:
1. During start up always ensure all the turbine drains should be in open condition, warm the line and
cylinder and follow the starting procedures carefully, sock the turbine and observe the casing
expansion.
2. During normal operation avoid sudden change in turbine operating parameters.
3. Follow the start-up and shutdown curves.
Page 68 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Bearing temperature high.
2. Bearing return oil temperature high
3. Friction noise at local.
4. Bearing vibration increases.
Parameters of Concern:
1. Bearing temperature.
2. Bearing return oil temperature.
3. Bearing vibration.
4. Lube oil temperature
5. Axial shift
Page 69 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Caution:
1. If any oil leakage is heavy, immediately contact fire person to prevent fire.
Plant Response:
1. Overloading of thrust pads and failure.
2. May contribute to turbine vibration.
3. Unusual sound from turbine.
4. Increase eccentricity.
5. High vibrations.
6. Gradual increase in turbine first stage pressure.
Page 70 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Load rate.
2. Steam temperature.
3. Condenser vacuum.
4. HP heaters status.
5. Extraction NRV position.
6. Lube oil temp/thrust bearing temperature.
7. Axial shift.
8. HP IP differential expansion and LP differential expansion.
9. Turbine vibrations.
10. Eccentricity.
Page 71 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Main steam temp, turbine metal temp.
2. Acceleration rate.
3. Heat soak time.
4. Gland steam temp.
5. Condenser vacuum.
6. Differential expansion of HP (DEH)/IP (DEH)/LP (DEH).
7. Turbine vibrations.
8. Eccentricity.
Expected Operator’s Action:
1. Reduce boiler steam temperature.
2. Hold turbine load, soak.
3. Check and control gland steam temp.
4. Reduce vacuum in case of LP differential expansion.
5. Maintain the rated steam pressure/temperature as per the startup curves.
Final Corrective Actions:
1. In case of high positive turbine expansion, tripping of turbine will help in reduction of HP
differential expansion so trip it with concern SCE permission.
2. Break vacuum to reduce damage after turbine tripped to reduce possible damages.
3. After turbine is rest running it on barring gear check any rub noise, metallic sound vibration
eccentricity, DEH/LOCAL. After all parameters in range try to roll turbine slowly with concern
SCE permission
4. If parameters are not in range than give time to cool turbine and permit to maintenance
department for inspection.
Page 72 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Seal rubs can be expected at extreme values. Metallic sound from turbine when interference exists.
2. Possible increase in turbine vibrations, eccentricity.
3. Turbine will have high alarm on -1.2 mm in case of HP differential expansion, -3.5 mm in case of
IP differential expansion & -2.2 mm in case of LP differential expansion.
4. Turbine will HH alarm on -2.0 mm in case of HP differential expansion, -4.5 mm in case of IP
differential expansion & -3.3 mm in case of LP differential expansion.
Parameters of Concern:
1. Main steam temp, turbine metal temp.
2. Acceleration rate.
3. Heat soak time.
4. Gland steam temp.
5. Condenser vacuum.
6. DEH and DEL.
7. Turbine vibrations.
8. Eccentricity.
Page 73 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Likely Causes:
1. Deflection of turbine rotor due to improper cooling after unit trip.
2. Improper draining of steam lines and turbine cylinders contributing water entry to turbine.
3. Abrupt drop of main steam temp due to water carryover from boiler.
4. Moisture in gland steam.
5. Deformation of cylinders.
6. Disengaged barring gear etc.
7. Lube oil temperature, quality.
8. Spray CV is open in turbine rest condition.
9. Barring gear not engaged for long time after rest down to 0 RPM or during blackouts.
Plant Response:
Parameters of Concern:
1. Eccentricity.
2. Acceleration rate.
3. Heat socking time.
4. MS Temperature.
5. Lube oil temperature.
6. Bearing temperature.
7. Gland steam temperature.
8. Vibrations.
9. Barring gear operation
Page 74 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Turbine not comes on barring and after coasting down remains stand still.
2. Turbine rotor sagging.
3. TG eccentricity may increase.
4. Rotor may get damaged.
Parameters of Concern:
1. Turbine metal temperature.
2. Rotors thermal state.
3. Bearing temperatures.
4. JOP status.
5. Availability of manual barring spanner.
6. Generator H2 pressure.
7. Seal oil system parameters.
Page 76 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Turbine speed less than 2500 rpm and JOP not in service alarm.
2. Barring motor will not start.
3. Bearing temperature and Bearing vibrations will increases
Parameters of Concern:
1. Turbine speed.
2. Turbine vibration.
3. Bearing temperature.
4. Axial shift.
5. Eccentricity.
6. MOT tank level.
Page 77 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Turbine speed.
2. MSV/CV/RSV/IPCV position.
3. Turbine vibration/axial shift.
4. Condenser vacuum.
Page 78 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Likely Causes:
1. Mechanical fault on HPCV/IPCV.
2. EH oil/ trip oil line oil leakage on that particular HPCV/IPCV.
3. HPCV/ IPCV servo valve fail.
4. HPCV/ IPCV servo valve card / Feedback failure.
Plant Response:
1. Unit Generation may reduce.
2. If IPCV close CRH/HRH pressure will increase, increase reheated temperature
3. In case of HPCV MS pressure will increase, MS temp increase.
4. If one CV closes, other CV opening may increase for same load.
5. Axial shift will increase.
6. Heaters levels may fluctuate.
7. In case of heavy EH oil leakage EH oil tank level drop and EH oil pressure also.
Parameters of Concern:
1. MS pressure/temperature.
2. CRH/HRH pressure/temperature.
3. Axial shift.
4. Turbine vibration.
5. HPCV/IPCV position.
6. HPH/LPH levels.
7. EH oil press/tank level.
8. HP/ LP bypass valve position.
Page 79 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. If passing is heavy or HPCV/IPCV is fully open turbine run fast and may over speed.
2. Turbine vibration/axial shift/DEH/DEL /eccentricity increase.
3. Due to passing acceleration rate may not be maintained.
4. Turbine rolling starts upon MSV/RSV opening.
5. Barring gear disengage.
Parameters of Concern:
1. Turbine CV/IPCV position.
2. Turbine speed and acceleration.
3. Turbine vibration/axial shift/DEL/DEH/eccentricity.
Page 80 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. AOP start on auto, if it fails to start, EOP will start.
2. If lube oil pressure drop up to 0.08 MPa unit will trip.
Parameters of Concern:
1. MOP discharge pressure.
2. Lube oil pressure.
3. MOT level.
Page 81 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. MOT level decrease.
2. Oil pressure low alarm if oil leaks from oil supply line to bearing.
3. Turbine bearing temperatures may increase.
Parameters of Concern:
1. MOT level.
2. Lube oil pr. and temp.
3. Generator LLD.
4. Turbine bearing temperature.
Page 82 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Caution:
1. If any oil leakage is heavy, immediately contact fire person to prevent fire.
Parameters of Concern:
1. MS temperature.
2. HP exhausts pressure.
3. CRH pressure.
4. CRH NRV position.
5. Unit load.
6. HP-IP differential expansion.
Page 83 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 84 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Gland steam pressure/temperature.
2. Condenser vacuum.
3. LP exhausts temperature.
4. Aux header pressure.
5. DEH/DEL.
Page 85 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Parameters of Concern:
1. Gland steam temperature.
2. Vibration.
3. GSC level.
4. Vacuum.
5. Moisture in lube oil.
Page 86 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Gland steam out from seals at turbine shafts.
2. Seal damages.
3. Turbine vibrations increase.
Parameters of Concern:
1. Gland steam header pressure.
2. Turbine vibrations.
Page 87 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. DEH/DEL increase.
2. Turbine vibration increase.
3. Damage of seals.
Parameters of Concern:
1. Vibration
2. Vacuum
3. GSC level
4. Gland steam temp
5. LP Gland steam attemperation CV Position.
Page 88 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. If leakage is heavy EH oil tank level, pressure fall and at <9.8 MPa pressure, turbine will trip.
2. If leakage is heavy in specific MSV/CV/RSV that valve will get close.
3. If leakage is heavy in common line, turbine will trip.
Parameters of Concern:
1. MSV/CV/RSV position.
2. EH oil tank level.
3. EH oil pressure.
4. EH oil temperature
Page 89 of 126
.
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Standby pump pickup in auto.
2. Turbine will trip on EH oil outlet pressure<9.8MPA.
3. If tank level is low low both EH oil pump will trip.
Parameters of Concern:
1. EH oil tank level.
2. Outlet header pressure.
3. Oil temperature.
Page 90 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 91 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. If DC seal oil pump does not start or not developing sufficient pressure, seal oil to hydrogen differential
pressure is low, then hydrogen leakage may happen.
2. If DC seal oil pump start and seal oil to hydrogen differential pressure is high than oil may be enter in
generator and continuous LLD alarm may be persisting.
3. If H2 press drops hot/cold gas temp may increase.
4. Generator winding temperatures may increase.
Parameters of Concern:
1. DC seal oil pumps current/discharge pressure.
2. VOT level/pressure.
3. H2 pressure.
4. Seal oil DP.
5. LLD alarms.
6. Lube oil pressure.
7. Hot /cold gas temperature.
8. Generator winding temperature
Page 92 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Likely Causes:
1. Pressure oil tank float not working/stuck up.
2. Pressure oil tank inlet MIV closed.
3. Pressure oil tank bypass MIV open.
4. Pressure oil tank drain MIV open.
5. Seal oil DP low (DPR malfunction).
6. Lube oil system trouble and air deterring section/float oil tank is supplying oil to seal oil system.
Page 93 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. H2 pressure decreases.
2. LLD in enlargement section observed.
Parameters of Concern:
1. POT level.
2. H2 pressure.
3. Seal oil DP.
4. Seal oil pump discharge pressure.
5. MOT level.
6. Lube oil pressure.
7. Hot/cold H2 gas temperature.
8. Generator temperature.
9. POT bypass valve position
10. POT inlet valve position.
Page 94 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. If pressure oil tank level is full and still raising the oil may enter in generator.
2. If oil enters in generator insulation value may go down and earth fault may result.
3. LLD in enlargement section and turbine and generator end found continuously.
4. H2 purity drop.
Parameters of Concern:
1. Pressure oil tank level.
2. H2 purity. LLD alarms.
3. Seal oil DP.
Page 95 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Purity of hydrogen less than 97% is not desire as heat transfer will not proper.
2. Alarm will appear at 97%.
3. Not safe to run the Unit at <95% H2 purity.
Parameters of Concern:
1. Hydrogen purity.
2. LLDS.
3. Hot/cold gas temperature.
4. Generator temperature.
5. H2 Dew Point Temperature.
Page 96 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. High H2 pressure drop rate.
2. H2 leakage alarm will come.
3. Hot-cold gas temperature high alarm will come.
4. Generator winding temp will increase.
5. If leakage is serious, chance of fire near leakage.
Parameters of Concern:
1. H2 pressure in generator.
2. Seal oil/H2 DP.
3. H2 leakage alarm.
4. Hot-cold gas temperature.
5. Generator winding temperature.
6. Generation
Page 97 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
5. If H2 pressure cannot be make up and drops further, reduce the load on generator by watching the
hot/cold gas, winding temperature.
6. If any leakage found contact maintenance person and take appropriate action to prevent risk of fire,
inform the fire man too.
7. If serious leakage found, stop the unit and purge the generator with CO2 as per procedure.
8. If H2 pr. stabilizes, fill H2 cylinder and maintain pr. as per requirement.
Plant Response:
1. Vacuum drops fast.
2. Unit load decreases.
3. Turbine exhaust hood temperature increases.
4. Howell temp starts increasing.
5. Axial shift may rise.
Parameters of Concern:
1. Condenser vacuum.
2. Unit load.
3. Exhaust hood temperature.
4. Hot well temperature.
5. Axial shift.
Page 98 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Page 99 of 126
TRN TRN Energy Pvt. Ltd. TRNEPL/
2 X 300 MW Power Plant Emergency/ 00
Shaping the future
EMERGENCY OPERATING PROCEDURE
Issue No: Issue Date: Revision: Revision Date: File no: Remarks
01 13.03.2020 00 02
Plant Response:
1. Condenser vacuum low alarm.
2. LP exhaust steam temp increase.
3. Hot well temperature increases.
4. Load reduces.
5. Fuel flow increases if unit is in CCS mode.
6. Turbine vibration may increase.
7. Unit trip at – 75 KPa vacuum.
8. Standby vacuum pump will pick up at -81 KPa.
Parameters of Concern:
1. LP exhaust steam temperature
2. Hot well water temperature & level.
3. CW inlet/outlet water temperature.
4. Drain manifold temp. Coming to HP/LP flash tank.
5. Condenser pressure.
6. CW flow.
7. Cooling tower range / No fans in service.
40. Condenser Pressure Rise after Vacuum Loss (In Blackouts & Shut down Condition)
Likely Causes:
1. Vacuum breaker closed condition.
2. Lack of condensation in condenser as CW pumps tripped.
3. Gland steam supply not cut off.
4. HP-LP flash tank attemperation not available as CEP not running.
5. MS, CRH, HRH, extraction line drains, HP heaters and LP heater drains CV open due to instrument air
pressure low and high temperature steam coming to flash tank (any drain to condenser open).
6. LP exhaust hood spray not available.
7. HP-LP bypass open/passing.
8. MS stop valve open (boiler side)/passing.
Plant Response:
1. Condenser vacuum low alarm.
2. LP exhaust temperature increases.
3. LP turbine rupture disc may damage.
Parameters of Concern:
1. Condenser pr. and temp.
2. LP exhaust temperature.
Plant Response:
1. Cation conductivity increases in Condenser leak detection system (CLD), CEP outlet and CPU
outlet.
2. CEP outlet Na+ Increases.
3. Condensate & feed water pH value decreases.
4. MS conductivity & Na+ increases.
5. If run for prolonged period chances of boiler tube failure and LP/HP heaters tube leakages, turbine
blade cracking.
Parameters of Concern:
1. Cation Conductivity in CLD & CEP outlet, value of pH, specific Conductivity, Na+ in feed water,
MS & condensate.
Plant Response:
1. Generator winding temperature rising.
2. H2 consumption may increase.
Parameters of Concern:
1. Generator winding temperature high alarm.
2. Generator hot and cold gas temperature high.
3. Stator cooling water flow and temperature.
4. H2 pressure.
5. H2 Purity.
6. Unit load
7. Stator water tank level and Makeup frequency.
Likely Causes:
1. DPR malfunctioning and maintaining high DP.
2. Defective seal component and oil entering generator casing.
3. H2 dryer not working properly.
Plant Response:
1. LLD level High alarm.
2. Liquid traces in Local LLD gauges
Parameters of Concern:
1. LLD level
2. MOT level.
3. Seal oil pressure at generator end.
Plant Response:
1. Condenser inlet water temperature increases.
2. If more than 2 fans tripped than condenser inlet water temperature increases fast and so vacuum
drops.
Parameters of Concern:
1. Condenser inlet water temperature.
2. Condenser vacuum.
3. Unit load.
Plant Response:
1. CW duct pressure may drop if fore bay level go to lower limit.
2. CW pumps vibration will increase.
3. CW pump motor current reduces.
4. CW pump trip on low level.
Parameters of Concern:
1. CT makeup valve status.
2. CT makeup pump.
3. Forebay level.
Plant Response:
1. Main steam and reheat temperature decreases sharply.
2. Water hammer sound and vibration in main and reheat pipe, extraction pipe, bypass piping.
3. Differential expansion and axial displacement have obvious changes or the rotor axial shifts, thrust
pad temperature and oil return temperature rises.
4. The temperature difference of turbine upper and lower cylinder increases.
5. The unit vibration increases and there may be severe vibration.
Parameters of Concern:
1. MS and RH temperature.
2. Turbine vibration
3. Thrust bearing temperature.
4. Differential expansion
5. Axial shift.
Plant Response:
1. There is metal impact sound inside the cylinder.
2. The unit vibrates severely.
3. The axial displacement and differential expansion changes abnormally, the thrust pad temperature
and oil return temperature increases
4. Steam extraction pressure changes abnormally.
5. In terms of LP cylinder blade breaking, the broken blade may go into the condenser and break the
tube, which will increase the conductivity and hardness of condensate and abnormality increases.
Parameters of Concern:
1. Water and steam quality.
2. Turbine vibration
3. Thrust bearing temperature.
4. Differential expansion
5. Axial shift.
6. Oil return temperature.
7. Heater and hot well level.
8. Turbine speed.
9. Steam temperature.
Expected Operator’s Action:
1. Shut down for emergency when the blade breaking and severe vibration of unit are confirmed.
2. Analyze and find out the causes immediately if there are obvious changes of the pressure on the
monitored section during normal operation of unit, and if the load decreases, temperature of
thrust pad increases and there is large axial displacement, etc. at the same time, please apply for
shutdown for treatment immediately.
3. If it is the breakage of final stage blade of LP turbine, causing the condenser tube leakage
resulting in increase of condensate hardness. If the water quality exceeds the standards, shut down
for emergency and pay attention to steam quality.
4. Maintain the normal water level by discharging water from the outlet valve of LP#4 heater when the
condenser water level increase
Precaution to prevent blade damage:
1. Keep the operation of unit within the allowable cycle range.
2. Keep the unit steam parameters normal.
3. Ensure the normal operation of heater and deaerator and keep the relevant water drain smooth.
4. Keep the normal output of unit and strictly prohibit overrun.
5. Strengthen the monitoring of steam water quality and prevent deposit and corrosion of blade.
Plant Response:
1. The bearing vibration is large.
2. The axial displacement increases at reverse direction.
3. The booster pump outlet pressure is high.
4. The deaerator pressure and water level rises.
Parameters of Concern:
1. Deaerator pressure
2. Deaerator level
3. BFP rpm
4. BFP suction and discharge pressure.
5. BFP bearing vibration.
Likely Causes:
1. Unit service transformer tripping and DG or stand by DG set not started on auto.
2. Bus fault on boiler/turbine PMCC and DG or stand by DG set not started on auto
3. Emergency MCC bus fault.
4. Fault on any outgoing feeder which extended up to main incomer of emergency MCC.
Plant Response:
1. If power supply fails on EMCC then incomer#1will open EMCC incomer#2 will close automatically.
2. Power supply of EPMCC fail than the unit UPS standby, boiler valve cabinet, Turbine valve cabinet,
AOP, JOP#A/B, SOP#A/B supply will interrupt. (important auxiliaries on EPMCC section are
ID/FD/PA Fan, lube oil supply power, APH#A/B aux motor power)
3. If power supply fails on incomer#2 then main DG will start automatically, if standby DG will not get
started.
Parameters of Concern:
1. EMPCC bus voltage.
2. 220 V DCDB voltage and battery voltage of respective section.
3. UPS battery voltage of respective section.
4. Switchyard ACDB voltage and battery voltage of respective section.
Plant Response:
1. 400 kV bus side breakers, 6.6 kV bus incomer will open & tie breaker charged thru FBTS.
2. If station 6.6 kV bus incomer trip on bus fault, then FBTS changeover will be blocked.
3. Respective PCC incomer of station PCC, DM water PCC incomer breaker will open.
4. Coal handling plant incomer will open.
5. Auxiliaries running on above PCC will trip.
6. Auxiliaries running on downstream side MCC of above mentioned PCC like station UPS bypass
supply, service water pump, DM transfer pump, control room AHU, raw water pump, cooling water
pump of VAM/chiller plant, H2 plant, HFO supply pump, IA & SA compressor control supply, mill
reject HP & LP water pump, chemical dozing pump & CHP belt conveyor will trip.
Parameters of Concern:
1. Station 6.6 kV/415V PCC/415V MCC bus voltage.
2. Service water header pressure.
3. Instrument air and service air header pressure.
4. Coal bunker level.
5. CST level.
6. If BFP#C is in service then feed water flow.
4. UPS Failure
Likely Causes:
1. UPS source failure.
2. Rectifier failure and reserve supply not available or reserve switch OFF condition also battery switch
is in OFF condition.
3. Battery voltage goes down then inverter trips and reserve supply not available or reserve switch OFF
condition.
4. Frequency variation between UPS frequency and reserve supply frequency.
5. UPS protection acted condition.
Plant Response:
1. Unit may trip.
2. UPS power to DCS protection not available.
3. Plant parameter readings will go bad.
4. DCS computers may fail.
Parameters of Concern:
1. UPS bus voltage, battery current, healthiness of incoming source supply and alarm on UPS panel.
5. DCDB Failure
Likely Causes:
1. Incomer at unit PMCC trips and battery backup source fails.
2. Battery backup source is in service and its voltage becomes low.
3. Electrical fault on DC bus.
4. Electrical fault on outgoing feeder which extended up to bus/ incomer.
Plant response:
1. Incomer at unit PMCC will trip if fault occurs on bus.
2. Remote operation of electrical drives will not possible.
3. Unavailability of DC emergency drives.
4. Protection relay of generator/GT/UAT/ST/6.6 kV bus/415V PCC will not act.
Parameters of Concern:
1. DC bus voltage.
2. Battery set voltage.
Plant Response:
1. Bad feedback comes on DCS of Motor.
2. Motor ON/OFF command not possible from DCS.
3. Motor ON/OFF command possible only through Breaker.
4. Motor electric protection bypass.
Parameters of Concern:
1. Flow/pressure/vibration/temperature of motor.
2. Bus voltage.
• Unit switchgear incomer breaker/ unit switchgear tie breaker (tie to station switchgear)/station
switchgear tie breaker (tie to unit switchgear) is in TEST MODE.
• Unit switchgear incomer breaker/ unit switchgear tie breaker (tie to station switchgear)/station
switchgear tie breaker (tie to unit switchgear) is in LOCAL MODE.
• Unit switchgear incomer breaker/unit switchgear tie breaker (tie to station switchgear)/station
switchgear tie breaker (tie to unit switchgear) LOCK OUT RELAY OPERATED in Breaker.
• Station switchgear tie breaker (tie to unit switchgear) is open condition.
3. Fast bus transfer relay control supply OFF condition (DCDB BUS#A).
4. Fast bus transfer relay is in MANUAL MODE.
5. Voltage difference between station and unit switchgear bus.
6. Difference in phase angle between station and unit switchgear bus.
Plant Response:
1. No permissive for bus transfer in FBT relay.
2. Transfer blocked in FBT Relay.
3. Bus transfer not possible (unit to station/station to unit).
Parameters of Concern:
1. 6.6 KV bus voltage of unit switchgear.
2. 6.6 KV bus voltage of station switchgear.
3. Unit blackout.
8. Flash Over
Likely Causes:
1. Flash over due to loose contacts at joints or clamps of bus bar, isolator, and breaker, CT, PT or CVT.
2. Due to heavy wind or stormy condition.
3. Due to accumulation of dust and moisture particle at string and support insulator.
4. Due to misalignment of isolator moving contact.
5. Due to breakdown of live conductor which falls on another live part.
6. Over loading.
7. Due to high oil temperature in case of oil immersed CB/CT/PT/CVT used.
8. CT failure due to opening of secondary coil or mfg. defects.
Plant Response:
1. Tripping of concern section/line/unit/bus bar.
2. Damage occurred to men and equipment due to flashover.
Parameters of Concern:
1. Bus voltage.
2. Line loading.
Likely Causes:
1. Gasket of circuit breaker is damaged.
Plant Response:
1. At 0.65 MPa gas pressure low alarm will come.
2. At 0.60 MPa gas pressure breaker will lockout.
Parameters of Concern:
1. Breaker operating gas pressure.
2. Breaker operation will not possible if lockout occurs.
Plant Response:
1. Many auxiliaries will trip if fire is severe.
2. Fire inert gas system charged on auto.
Parameters of Concern:
1. Parameter of affected system.
2. 6.6 kV/415V bus voltage.
Plant Response:
1. Temperature remains high at hot spot winding temp.
Parameters of Concern:
1. Temperature at hot spot. It should less than 70 deg. C.
2. Loading of respective line/bus bar/auxiliary.
Likely Causes:
1. Low oil level in conservator tank.
2. Short circuit or inter turn fault of winding.
3. High atmospheric temperature.
4. Malfunction of temperature detector switch.
Plant Response:
1. Winding temperature high alarm at 950 C and tripping at 105 0C.
2. Oil temperature High alarm at 850 C and tripping at 95 0 C.
Parameters of Concern:
1. Bus voltage.
2. Line voltage.
Plant Response:
1. Transformer winding and oil temperature remains high if oil level goes low.
2. Overheating of CT / PT / transformer core and winding.
Parameters of Concern:
1. Transformer winding temperature high alarm will comes at High alarm at 950 C and tripping at 1100 C.
2. Transformer oil temperature High alarm will comes at 850 C and tripping at 95 0C.
3. Feedback from CT/PT will interrupt or goes bad in case of winding damage.
Plant Response:
1. Process status will not available.
2. Remote operation will not possible.
3. Switch yard status will not updated in main control room DCS also.
Parameters of Concern:
1. Plant running parameter feedback will not update.
2. CB/isolator/earth switch status will not update.