Sequence of Activities for House construction Project

Name Of the Starting and Finishing Description of activity Predecessor Time Duration
Activity event (Days)

A (0,1) Preaparing Working Drawings _____ 2 Weeks

B (1,2) Clean the Site A 2 Weeks

C (2,3) Excavate B 2 Weeks

D (3,4) Lay the Foundation C 5 Weeks

E (4,5) Column and Beam placement D 3 Weeks

F (5,6) Construction of rough wall E 3 Weeks

G (5,7) Put up the Slab/ roof E 3 Weeks

H (7,8) Plumbing Work G 2 weeks

I (6,9) Ceiling Work F 2 Weeks

J (9,10) , (7,10) Plastering Work G ,I 2 weeks

K (5,11) Do the electrical work E 1 Weeks

L (8,12) , (11,12) Put up the doors and Windows H ,K 1 Weeks

M (12,13) , (12,14) Install the flooring L 2 Week

N (13,16) , (14,16) Painting Work M 3 week

O (10,15) Compound fencing Work J 1 week

P (15,0) , (16,0) Complementry works N ,O 1 week


S 1 L 1
T 0 2 12 M
A 1 11 3
R
A 2 2 L 14
T B
2
K 8 M N
C H
2 5
3 2 1
3 16
3 4 5 7 13
D E G N
A. Prepare the Drawings
J P F
B. Clean the site F I
N
C. Excavate
I
D. Lay the Foundation
6 3 1
S
H
E. Column & Beam Placement I 2 15
F. Construction of Rough Wall 2 J P 245 Days
G. Put up the slab / Roof
9 10 O 35 Weeks
H. Plumbing Work
I. Ceiling Work
J. Plastering Work
K. Do the Electrical Work
L. Put up the Doors & Windows
M. Install the flooring
N. Painting Work
O. Compound Fencing Work
P. Complementary Works