Professional Documents
Culture Documents
EGP3-03.04 Piping Layout, Support and Flexibility
EGP3-03.04 Piping Layout, Support and Flexibility
EGP3-03.04 Piping Layout, Support and Flexibility
Notes
i.) Revisions numbers shall be A, B, C, etc. up through the issue for Invitation to Bid.
iii.) Revisions after the issue for Invitation to Bid shall be 1, 2, 3, etc. Any revisions made after
Revision 0 shall be denoted by a vertical line in the left hand margin against the revised text.
iv.) A brief description of the key changes made in each revision shall be included on this page.
PAGE
1.1 Scope 7
1.2 Definitions 7
2.0 REFERENCES 8
3.1 General 10
4.0 LAYOUT 10
4.1 General 10
4.2 Piping 11
4.4 Pumps 14
4.5 Exchangers 14
4.6 Compressors 16
5.1 General 18
7.1 General 22
7.8 Filing 27
8.1 General 28
8.2 Supports 29
8.5 Guides 30
8.6 Anchors 30
8.7 Restraints 30
8.9 Materials 31
9.1 General 36
TABLE 1. CLEARANCES 42
1.1 Scope
This general specification, in addition to the "Piping- Valves, Material and
Service Classification”, General Specification 03.00, covers the minimum
technical requirements for the design, layout, support and flexibility of piping
systems to be installed.
CONTRACTOR shall notify COMPANY of any conflicts between this specification
and other project documents or referenced industry standards.
1.2 Definitions
Definitions used in this specification are as follows:
1.3.2 Supports – Supports provide mountings for a piping system and control
flexibility within the system. Supports consist of the following types.
Spring supports
Pipe shoes
Guides
Anchors
Dummy supports
API 610 - Centrifugal Pumps for Petroleum, Heavy Duty Chemical, and Gas
Industry Services
API 614 - Lubrication, Shaft-Sealing, and Control-Oil Systems and Auxiliaries for
Petroleum, Chemical and Gas Industry Services
API 616 - Gas Turbines for Petroleum, Chemical, and Gas Industry Services
API 617 - Centrifugal Compressors for Petroleum, Chemical, and Gas Service
Industries
National Standard
WRC 107 - Local Stresses in Spherical and Cylindrical Shells Due to External
Loadings
EGP3-5.1.9.17 “Requirements for Labels and signs for Onshore Gas Processing
Facilities”
Exclusions
Piping applicable to domestic heating and ventilation, air, water and sewage
systems in buildings, instrument and control piping downstream of the
first block valves and all piping excluded by the chemical plant &
petroleum refinery Piping Code ASME B31.3 (Para. 300.1.3)
3.1 General
3.1.2 Design criteria shall include the effects of material, pipe thickness and
insulation requirements.
4.0 LAYOUT
4.1 General
4.1.1 Plant and equipment spacing shall satisfy the minimum spacing specified
in Project Specification EGP3-15.00 “Loss Prevention Design Basis” and
the requirements in EGP3-5.1.9.06 “Mechanical Handling and Access
Plan”.
4.1.3 Space for future units and equipment shall be provided only when
specifically requested by the COMPANY. The size allocation shall also
be advised.
4.1.6 All items shown on Plot Plans, including the boundary lines of each
drawing, shall be located by means of their co-ordinates on an overall
grid system. The COMPANY shall specify the base co-ordinates of each
unit.
4.1.9 All proposed Plot Plans shall be checked by the CONTRACTOR before
being submitted to the COMPANY for approval.
4.1.10 Similar equipment shall be grouped together to simplify the piping layout.
4.1.11 Minimum clearances for maintenance shall be provided per Table 1 and
Mechanical Handling and Access Plan, EGP3-5.1.9.06.
4.2 Piping
4.2.1 Piping and equipment shall be arranged to meet the maximum safety
requirements for the areas through which the piping runs.
4.2.5 All un-insulated lines shall be located so that the bottom of pipes (BOP)
or top of pipes (TOP) are at the same elevation depending upon the
method of support.
4.2.6 Insulated lines shall have the bottom of shoes at the same elevation as
the bottom or top of pipes of adjacent un-insulated lines, whichever is the
reference.
4.2.7 The difference in elevation between lines running north or south and
lines running east or west shall be a minimum of 610mm (2 foot)
intervals.
4.2.8 Piping shall be routed for the shortest possible run and shall have the
minimum number of fittings adequate for expansion and flexibility.
4.2.9 Block valves used in branch lines at headers shall be located to allow
complete drainage on each side of the closed valve.
4.2.10 Piping shall be arranged for ease of removal of equipment for inspection
or servicing. Maintenance areas shall be clear of piping.
4.2.17 For welded sections, sufficient breakout flanges shall be supplied for
servicing valves and equipment.
1) With restriction orifices except for minimum size purge gas and air
to instruments.
4.2.20 Branch connections in utility lines shall be valved and located in the top
of the header. Valves shall be located in the horizontal section of the
line.
4.2.21 Process branches 2 inches and smaller shall be equipped with valves at
the main unless otherwise specified in the project specifications. The
branch connections shall be located at the top or side of the main.
4.2.22 Branch connections 2 inches and smaller shall be equipped with break
flanges in the following services.
● Flushing
4.2.24 Lines for air (including instrument air) and hydrocarbon lines shall be
arranged to allow free blow through a full size opening prior to final
closings of the systems to achieve line dryout as described in Project
Specification EGP3-03-13. Suitable precautions shall be taken for
excessive noise.
4.4 Pumps
4.4.1 Pumps shall be located close to the equipment from which they take
suction to minimize the length of suction lines. All pump drivers shall be
located adjacent to vehicular access ways.
4.5 Exchangers
4.5.3 Stacked shell and tube exchangers shall be limited to two shells high in
similar service unless approved in writing by COMPANY. They shall not
exceed a centerline elevation of 5.5 m above high point of finished
surface unless mounted in a structure. Stacked exchangers do not
require platform access to top channel for bundle removal. Temporary
scaffolding shall be used for this purpose.
4.5.4 Parallel exchangers shall provide space and suitable access to blind if
block valves are not provided.
4.5.5 Channel end and shell covers shall be kept clear of piping, structural
members and other items which could interfere with the unbolting of
exchanger flanges or the removal of heads and tube bundles. Spool
pieces shall be provided as appropriate to facilitate head and bundle
removal.
4.5.6 Exchangers with removable tube bundles shall be provided with a clear
tube pulling area away from the pipe rack, and space for Hydroextractor
504 bundle extractor for channel and flanges up to 84 inches diameter.
Main or secondary site roads shall not be utilized for this purpose unless
approved by COMPANY.
4.5.11 Air-coolers shall not be installed above any item of equipment handling
flammable products that may be opened or vented for periodic servicing.
4.5.13 Access to all air cooler motor drives shall be designed so vibration
monitoring instruments are accessible and so motors and drives can be
readily lowered to the fin fan maintenance deck.
4.6 Compressors
4.6.1 Access for maintenance by fixed overhead crane shall be provided for
large lifts such as bundle pulling and unit removal per specification
EGP3-5.1.9.06. A suitable dropout area shall also be provided.
4.6.2 Lube and seal oil consoles shall be located adjacent to and a minimum
distance from the compressor.
4.6.3 All centrifugal compressors shall have full platforming at operating level.
4.7.1 Platforms within a 21 m radius from the outside edge of a heater stack
shall be at least 4 m below a line extending upward at 45 o from the
projected top of the stack to the end of the 21 m radius.
4.7.3 Clear access shall be provided to furnaces for removal of tubes. For
spacing between furnaces and equipment, see Project Specification
EGP3-15.00.
4.7.4 Access and clearance shall be provided at fired equipment for removal of
tubes, soot blowers, air pre-heater baskets, burners, fans and similar
equipment.
4.9.3 A clear drop zone at grade shall be provided for vessels within
removable internals or appurtenances and for vessels and reactors
requiring loading or unloading of catalyst.
4.10.1 The location and spacing of LPG spheres shall be in accordance with
API 2510 and API 2510A.
4.10.3 LPG spheres shall have at least one side adjacent to an access road.
4.10.4 Pumps and other equipment associated with tankage shall be located
outside of the bunded area and grouped together for common operation
and economical pipe routing.
4.11 Flare
4.11.2 Flare knockout drums shall be located as close as possible to the flare
stacks with sufficient protection for knock-out product pump away
operation.
5.1 General
5.1.1 Valves shall be accessible from grade or platform per Standard drawing
GB-L99961-6 and EGP3-5.1.9.15, first or second choice position.
Emergency Shutdown valves shall always be accessible from grade .
5.1.3 Utility header valves that are required for infrequent maintenance
purposes may be accessible by portable ladder if approved by
COMPANY.
5.1.4 Valves shall not be installed with stems pointing down (below horizontal)
unless specifically approved by COMPANY.
5.1.6 Drains for removal of water from hydrocarbon during operation shall be
located so that the operator can see the gage glass while holding the
valve open and throttling the block valves upstream of the valve. For
high-pressure systems (Class 600 and above), double-valved drains
shall be used when the system is routinely opened at full system
pressure.
5.1.7 Vent and drain connections shall be in accordance with Pipe class.
They shall not be less than ¾ inch and shall be as close to vessels,
equipment, headers, etc., as practical.
5.1.8 All vents and drains, as well as any other “open-ended” connections,
shall be provided with threaded plugs, blind flanges, or spectacle blinds,
whichever is required. In socket-weld services, threaded round bar stock
plugs are still required. This will normally require the use of a threaded
valve with a short nipple with one end plain and the other end threaded
on the valve side. Threaded caps are not acceptable. Atmospheric
drains shall not include ells, tees, or other fittings that will prevent
rodding out drain piping.
5.2.1 Chain wheels shall not be used on screwed valves and shall only be
used on flanged valves when specifically approved.
5.2.3 Valves 2 inches and smaller shall not be provided with chain operators.
5.3.2 Manually operated valves shall be accessible from grade. Where this is
not physically possible, access may be provided from a platform located
no more than 6m above grade. The platform shall be accessible by
stairway. Access to the platform by ladder is not acceptable.
5.3.3 Block valves shall be provided close to column, vessel and tank
connections below liquid level to provide shutoff in emergencies. They
must, therefore, be located where access is easy from grade. Where
lines from such connections run to pumps or other valved equipment
located within 9100 mm, measured horizontally from the column or
vessel, the valves at such equipment fulfill this requirement, except for
the following:
5.3.4 These block valves should be operable from grade and be located on
the side away from the pump to allow safe access during a fire
surrounding the pump. If remotely operated, the source of power and the
control wiring or pneumatic tubing should be fireproofed. The fire
resistant butterfly valve is acceptable, subject to COMPANY approval,
only when a gate, ball or plug valve is installed at the connected pump.
5.3.5 The vessel “fire resistant” valves may be eliminated by locating the pump
valves at least five feet horizontally away from the seals or other
potential leaks, and fully fireproofing the valve and operator.
5.4.1 Fuel gas or oil piping to fired heaters in a plant shall be provided with a
single block valve in the main line, located a minimum of 15 m
horizontally from the equipment and accessible for rapid operation in an
emergency.
5.4.2 The line to each individual furnace shall have a valve, a valved
connection for a pressure gage and a quick-change blind.
5.4.3 The fuel gas or oil piping to each burner from the branch header shall
consist of a tight shutoff valve, boss, sockolet or weldolet for pressure
connection, and a line blind to insure positive shutoff. Provide sufficient
piping flexibility to permit operation of the blinds.
5.5.1 CONTRACTOR shall provide plot limit manifolds at the locations where
plant pipe ways leave the plot limit.
5.5.2 CONTRACTOR shall prepare a plot limit manifold diagram early for
COMPANY approval. This diagram shall show all lines, as well as all
drain, blowdown, flush, and vent connections, valves and auxiliary piping
with an indication of the source and final disposition of all fluid streams.
CONTRACTOR shall also send COMPANY his plot limit layout drawings
early as possible, prior to design of off-plot lines and facilities.
5.5.3 All overhead lines entering or leaving process plants will drop from the
overhead plant pipe way in vertical rows at the plot limit. An exception is
the relief line (and other special lines that do not permit low points),
which will remain overhead. In an integrated process plant area
consideration shall be given to the elimination of the plot limit valve at
one plant with no other connections to the line between the plants.
Elimination of plot limit valves must be approved by COMPANY.
5.5.4 Plot limit valves shall be installed vertically near grade or above pipe way
elevation with appropriate regard for accessibility and shall be made
accessible for operation and maintenance by means of elevated
platforms, with stairways, suitably arranged for such work to be done
without need for personnel to leave platforms.
5.5.5 Plot limit valves and blinds shall be staggered to avoid interference when
operating valves or when changing blinds.
6.1.1 The piping system shall be constructed with flanged joints wherever
disassembly may be required.
6.1.3 Jack screws shall not be provided at spectacle blinds. Provide sufficient
piping flexibility to permit operation of the blinds.
6.2.1 The piping arrangement shall provide for sufficient changes in direction
of piping, pipe loops, anchors, and/or expansion joints to keep pipe
stresses, vibration, and mechanical and thermal shock within the limits
allowed by ASME B31.3. Also, any additional codes required by
equipment manufactures.
6.2.2 The locations of anchors and guides shall not cause excessive stress by
severely restricting movement of the piping.
6.3.2 Hot and insulated lines shall be grouped together and separated from
cold lines to control corrosion, condensation, and vapor problems.
6.4.1 Piping inside process units shall generally be routed on elevated pipe
racks. No process piping shall be installed in trenches.
6.4.2 Major Electrical and Instrument cables shall be routed on the pipe racks
above the pipe work.
6.4.4 Pipe racks shall be designed to provide proper support for the smallest
diameter line to be run in the rack.
6.4.5 Piping shall not be run over stanchion columns in case future piping
additions require the construction of another level.
6.4.6 Utility and service lines shall be placed on the top level and process lines
on the lower level.
6.4.7 If process lines must run to higher elevations, the process lines shall be
located on the top level.
6.4.8 The outer edges of pipe racks, whether double-level or single-level, shall
be allocated to heavy, large-diameter piping.
6.4.9 The center of pipe racks shall be allocated to light, small-diameter piping
lines for utility service.
6.4.10 Process lines shall be placed on both sides of utility lines. If process
lines run to equipment on the left, the lines shall be placed on the left
side of the rack. If the lines run to equipment on the right, the lines shall
be placed on the right side of the rack.
6.4.11 Pipe way takeoff lines shall be designed to change direction and
elevation from the main piping.
6.4.12 Pipe loops shall be installed over the top of their pipe rack level, except
for flare lines, which shall be horizontal loops. Loops that extend beyond
the limits of the pipe rack shall have COMPANY approval.
6.4.13 Instrument lines, conduit lines, and trays shall be installed on the upper
horizontal member of the rack.
6.4.14 New racks shall allow for 25% future capacity, except where stated
otherwise on the plot plan or other project documents.
6.4.15 The interconnecting pipe way between the process plants shall be
sleeper racks. Other off-plot pipe ways generally will be grade level;
improvement of plant access, or space requirements may require a
different solution in some areas.
6.4.16 The spacing of lines in pipe ways shall not be less than shown on Table
1. Economic insulation thickness selection may dictate wider spacing.
7.1 General
7.1.1 Static and cyclic movement of piping shall be within the stress range
allowed by this specification throughout the service life of the piping
installation.
7.1.2 All piping systems shall be evaluated and analyzed for applicable
conditions in accordance with ASME B31.3 (henceforth referred to as
the Code) and the requirements of this section.
7.1.4 The flexibility analysis shall consider the most severe specified
temperature condition anticipated during start-up, normal operation,
depressuring, shutdown, defined upset, cold branch, and regeneration.
Analysis of this situation may require the combination of more than one
load case to determine the total displacement stress range. Cold branch
shall include cases dealing with parallel lines where at least one line (not
always the same one) may be cold at any time. An example is parallel
pumps where one pump (not always the same one) is normally shut
down.
7.3.1 Thermal Effects - The analysis shall be for the maximum temperature
differential. Metal design temperature and climatic effects shall be
considered in determining maximum differential temperature.
7.3.2 Wind Effects - The wind loads on piping systems shall be determined by
the procedure outlined in ASCE 7 or as specified by COMPANY site
conditions EGP3-00.01.
7.4.2 Both axial and torsion stresses shall be included in all stress cases
7.4.3 When analyzing the sustained load case, 75% of the normal stress
intensification factors (SIF) is acceptable, provided the resulting factor
(0.75 X Normal SIF) is not less than 1.0.
7.4.5 During initial piping layout and design of pump suction and discharge
with temperatures over 149 deg. C, and all compressor piping, nozzle
loads shall be limited to 50% of specified allowable load. Only where it is
not possible to achieve this limit by changing piping layout, shall higher
loads be considered. COMPANY approval is required.
7.4.6 Large diameter thin wall (D/T ≥ 100) lines shall be analyzed for crushing
loads at local stress points and reinforced as necessary.
7.4.7 When piping lifts off a support due to thermal movements, either that
support shall be removed for sustained load calculations or spring
supports shall be considered.
7.4.10 Tees with aspect ratios of 3:4 have been found to be non-conservative.
These tees shall have their stress intensification factor increased by
25%.
7.5.1 Loads imposed on equipment by the piping shall not exceed the lesser
of that allowed by the equipment manufacturer or that listed in the table
below.
7.6.1.2 Pipe size NPS 2 or larger with line temperature in excess of 149
deg C or minus 10 deg C and below.
7.6.1.4 All process, regeneration, and decoking lines to and from steam
generators and fired heaters
7.6.1.8 Lines NPS 3 and larger to and from centrifugal pump nozzles
7.6.1.17 Analysis for other materials other than steel shall be per
agreement with COMPANY.
7.7.1 The Design CONTRACTOR shall assign calculation numbers and store
the flexibility analysis files.
7.7.2 When the project has been completed, the Design CONTRACTOR shall
furnish all stress calculations and documentation as required by
COMPANY.
7.8 Filing
All new drawings (Special support drawings etc) shall have a master
copy filed by drawing number for reference by the piping design and
stress sections.
8.1 General
8.1.3 Pipe supports or anchor shoes in services for carbon steel and stainless
steel lines, shall be of similar metal materials & welded directly to the
pipe.
8.1.5 Spans shall be based on one-half the allowable stress value specified in
ANSI B31.3, and the deflection shall not exceed 1/4 inch for line sizes 2"
& smaller, or 1/2-inch for line sizes 3" and larger.
8.1.6 Piping anchors shall transmit the entire load directly to the supporting
structural member.
8.1.8 Supports for suction and discharge piping at pumps and compressors
shall be anchored to the pump or compressor foundation and not to an
independent foundation. Spring supports in these locations shall not be
used without specific COMPANY approval.
8.2 Supports
8.2.1 Piping supports, anchors and struts shall be designed to withstand the
wind and earthquake loads specified in the latest edition of ASCE 7,
Minimum Design Loads in Buildings and Other Structures. The basic
wind speed, exposure and earthquake risk zone is given in the project
specifications EGP3-00.01.
8.2.3 If a line turns out of a pipe way and needs support at the next stanchion,
this shall be accomplished by welding a smaller size pipe extension to
the outside of the ell to form a dummy leg.
8.2.5 Piping supports for valves, control valves, and mechanical equipment,
such as pumps requiring periodic maintenance, shall be designed for
easy removal of the valves and equipment.
8.2.7 Piping that shifts vertically shall be supported by variable support spring
hangers. If thermal movement is not overstressing pipe, rigid supports
may be used.
8.2.9 Sizes and types of spring supports shall be selected so that the supports
can carry the full design load through a displacement 50 percent more
than the calculated amount.
8.2.11 If concrete is used for pipe supports, top of concrete shall have a steel
plate or steel structural shape to act as a sliding surface.
8.2.12 All lines shall have support systems detailed on piping drawings. Lines
shall have supports indicated on isometrics.
8.4.1 Pipe shoes for piping 1-1/2-inch through 10 inches shall comply with the
requirements shown in Appendix IV unless otherwise approved by the
COMPANY.
8.4.2 Pipe shoes for piping from 12 inches to 18 inches shall comply with the
requirements shown in Appendix V unless otherwise approved by the
COMPANY.
8.5 Guides
8.5.1 Guides for un-insulated piping shall comply with the requirements shown
in Appendix VI unless otherwise approved by the COMPANY.
8.5.2 Guides for insulated piping shall comply with the requirements shown in
Appendix VII unless otherwise approved by the COMPANY.
8.6 Anchors
8.6.1 Anchors for piping 1-1/2-inch through 10 inches shall comply with the
requirements of Appendix VIII unless otherwise approved by the
COMPANY.
8.6.2 Anchors for piping 12 inches through 18 inches shall comply with the
requirements of Appendix IX unless otherwise approved by the
COMPANY.
8.7 Restraints
8.7.1 Restraints for un-insulated piping shall comply with the requirements of
Appendix X unless otherwise approved by the COMPANY.
8.7.2 Restraints for insulated piping shall comply with the requirements of
Appendix XI unless otherwise approved by the COMPANY.
8.8.1 Dummy supports shall comply with the requirements of Appendix XII
unless otherwise approved by the COMPANY.
8.8.2 Mechanical stresses and size shall be calculated for dummy supports
longer than 1.8m.
8.9 Materials
8.9.3 For ferrous piping materials with design temperatures less than 500º F
(260º C), piping supports shall be carbon steel.
8.9.4 For higher design temperatures or lines using low temp carbon steel, the
support material shall be the same material as the piping.
8.9.5 Material for load-bearing sleeves on insulated piping (hot and cold
service) shall be galvanized steel.
8.11.1 Piping 1-1/2 inches and smaller shall be supported directly from the
insulation by addition of a load-bearing metal sleeve outside of the
insulation.
8.11.2 Piping 2 inches and larger shall be supported on pipe shoes or saddles
that allow for the full insulation thickness.
8.11.3 Pipe shoes for insulated hot piping shall include slots, as required, for
continuous metal bands to secure the insulation weather-proofing jacket
near the shoe.
8.13.3 Unit areas shall not be cluttered with scattered columns supporting
randomly placed overhead lines.
8.14.1 Small lines that branch off from main piping runs shall be routed with
other lines unless the shortest direct route is required. The small lines
shall be supported on supports of the other lines.
8.16.2 Supports for flare lines may be designed for pneumatic testing; other
certain large vapor lines may be designed for pneumatic testing with
COMPANY approval.
8.16.3 Springs and lever arms shall be protected against overload during
hydrostatic testing. Restraints or stops installed for testing shall be
removed immediately after testing has been satisfactorily completed.
8.17.1 Flare system piping shall be designed, anchored, and guided to resist
the forward, lateral and upward dynamic forces developed at bends due
to high-velocity vapors and condensed liquids, as well as to
accommodate sudden thermal expansion or contraction. The design
values for forces to be restrained shall be in accordance with the
following table.
Pipe Size Force
(inches) (tons)
4 0.75
6 1.5
8 2.5
10 4
12 6
14 7
16 10
18 12
20 15
24 and above 15
8.17.3 Flare piping within process units and flare headers shall slope
continuously downward toward the flare knockout drum. The total drop
produced by a minimum slope of 1mm in 200mm shall be added to the
sum of the calculated deflections of empty pipe between supports. The
total slope shall be as uniformly distributed as practicable throughout the
entire length of the lines by shimming the pipe where necessary. After
installation, shims shall be welded into place to prevent displacement
and loss.
__10__
P1 (percent) = (PL)1/3
a. Piping design layout shall avoid wet legs and vertical risers if
possible.
8.19.1 The term "Low Temperature" applies to any system below ambient
design dew temperature and including cryogenic systems.
a) The support shoe must protect the supporting structure from the
effects of low temperatures where the structure would otherwise
fail due to notch embitterment.
a) Flare systems.
b) Process systems.
The types of support shoe can vary considerably between the systems
because flare systems are only cold intermittently, whilst generally
process systems are continuously cold.
Pipe support index (list of pipe supports), List of pipe supports to include:
line number, type, standard detail number, piping drawing number,
coordinate location of support.
9.1 General
9.1.2 Pipe spring supports shall comply with project specification EGP3-03.31.
9.1.3 Pipe supports shall be capable of supporting the pipe under all con-
ditions of operation.
9.1.4 Pipe supports shall allow free expansion and contraction of the piping.
9.3.2 Constant-load supports shall be installed with travel stops. The travel
stops shall be factory installed so that the hanger level is at the non-
operating installed position. The travel stops shall permit future
re-engagement without making hanger rod adjustments even if the lever
is not in the non-operating installed position.
Headroom available
a) Type A hangers are suitable for both vertical and horizontal pipe
runs that are supported from above.
b) Type C supports shall be furnished with two lug plates at the top for
attachment to a building or structure. The hangers permit
attachment of piping by means of eye rods or a single plate.
b) The hanger is set above the supporting beams with the pipe
suspended below.
10.1 General
10.1.2 Piping system and fabricated pipe supports shall be identified by color
code, labels, or special marking in accordance with individual project
specifications.
10.1.3 Spring hangers shall be furnished with a 316 stainless steel nameplate
attached with stainless steel screws or rivets. The nameplate shall show
the following information.
Manufacturer
Guaranteed load
10.1.4 Detail drawings of piping supports shall include the following information
for spring hangers.
Reference number
Any support or trunnion welded to a pipe shall match the parent pipe material. Most
supports shall be attached to the pipe in the "Shop". For this application, "Field" is
designated as the location where pipe spools are erected. "Shop" welded supports are
those supports welded to the pipe during spool fabrication and are shown on the
isometrics.
For fabrication and installation requirements, refer to EGP-3.03 'Piping Fabrication and
Installation'.
12.1.1 CAD piping studies shall show the following and shall be submitted to
the COMPANY for review:
12.3.1 All isometrics are to be submitted to COMPANY for review & comment.
12.3.3 Welded attachments include all items welded directly to the pipe except
for anchors and shoes for non-stress relieved lines.
1. If dimension, L, is greater than 6 feet, dummy support size shall be calculated or increased
to line size.
2. Dummy supports on heat-treated carbon steel or stainless steel shall be of the same
material as the ell up to the field weld. The remaining portion of the dummy support shall be
carbon steel.
3. On insulated lines, the dummy support shall be insulated from the weld for a minimum
distance of four times the line insulation thickness.
4. On heat-treated carbon steel or stainless steel lines, the dummy support shall be insulated
a distance equal to four times the insulation thickness plus 1 inch or for a total of 9 inches,
whichever is greater.
5. The dummy support shall be insulated for a minimum distance of four times the insulation
thickness, plus one half of the line outside diameter, plus the distance the line moves.