Professional Documents
Culture Documents
Preparatory Phase Inspection Meeting: Galvanized Steel Duct Work and Accessories
Preparatory Phase Inspection Meeting: Galvanized Steel Duct Work and Accessories
Preparatory Phase Inspection Meeting: Galvanized Steel Duct Work and Accessories
Date :
Time :
Venue :
1. Contract Documents :
The quality requirements for materials receiving, storage, handling, maintenance, inspection,
testing or tagging documentation shall be reviewed with PMCM. Turnover contained in the
following document were reviewed to ensure that all referenced documents were the last approved
revision.
2. Applicable :
The following listed codes, standards and applicable contract modifications must be reviewed with
the contractor to ensure that work on the items contained in the contract are to be performed in
accordance with specified requirements.
A ASHRAE (American society of heating Ref. and air cond)
B SMACNA (Sheet Metal and Air Conditioning Contractors National Association)INC
D Project Specs Ref. No. 15081, 15815
C Project Specs Ref. No. 15990
The requirements for approvals prior to construction must be reviewed with PMCM, no work may
proceed without the required approval and the understanding of their application to the work
included in this contract .
List of Submittals :
- Sheet Metal Duct Work .
- Duct Insulation .
- HVAC Duct Liner Insulation .
- Acoustical Treatment .
- Flexible Duct Connector .
- HVAC VAV BOX .
- HVAC Volume Damper .
- Anchors and Anchor Bolts .
- Fire Stop Sealant .
Samsung/Samcrete JV The American University in Cairo
New Campus Development
Contract NCD/CON/CAMPUS-01
- HVAC Gasket .
- HVAC Aluminum Tape .
- HVAC Insulation Fasteners .
- HVAC Duct Sealant .
- Access Door .
- HVAC Duct Heater .
- Duct Adhesives .
- HVAC Fire Dampers.
4. Comments: