DeKalb CIP BOC Presentation - 2021-04-20 - Moratorium - V1-FINAL

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24

2017-2027 - A Decade of Renewal

Strategy for Lifting the


Moratorium
DeKalb County CEO
Michael L. Thurmond

April 20, 2021


CONTENTS

01 A quick look back


CONTEXT

02 Celebrating what has been accomplished


A NEW DAY

03 What is next?
OUR ASK

April 20, 2021 PAGE 2


CONTEXT
How did we get here?

AJC October 7, 2016


TRUST LOST

In 2016 the
number of
metering and/or
billing issues
escalated

*Image from AJC article October 7, 2016.

April 20, 2021 PAGE 4


WATER BILLING ISSUES

Metering/Billing issues
led to:
• The 2016
disconnection
moratorium, and
• 37,000 held bills

*Image from Decaturish, September 20, 2016

April 20, 2021 PAGE 5


The Disconnection
Moratorium was
created by
Executive Order of
Interim CEO Lee May
in October 2016, and
extended by CEO
Thurmond

April 20, 2021 PAGE 6


A NEW DAY
Celebrating what has been accomplished

April 20, 2021


Contractor working on New Day Project
PAGE 7
The NEW DAY PROJECT is created to respond

April 20, 2021 PAGE 8


NEW DAY PROJECT
Key Successes
Held Bills Independently
Verified and Released

March 20, 2018

April 20, 2021 PAGE 9


NEW DAY PROJECT
Key Successes
METER ISSUES
ADDRESSED

Over 82,000 meters


have been replaced!
• Settlement agreed for potentially defective meters
• All 47,500 Pre-2014 iPerls meters replaced
• Over 34,000 out-of-life cycle meters replaced to date
April 20, 2021 PAGE 10
NEW DAY PROJECT
Key Successes

PEOPLE &
PROCESSES
Metering and Billing

• Additional staff hired and trained


• Meter reading SOPs, checklists and photo verification instituted
• Over 134,000 meters, about 70% of all customers, now have
transmitters for electronic usage reporting/Advanced Metering
Infrastructure (AMI)
• AMI provides more accurate, reliable and accessible data
April 20, 2021 PAGE 11
A NEW DAY

CORRECTLY INSTALLED AND PROVIDING TIMELY AND FOR TRUSTED AND VERIFIABLE
THE RIGHT METER
REPLACED TO SCHEDULE ACCURATE DATA BILLS

April 20, 2021 PAGE 12


TRUST RESTORED
Systemic Deficits in Leadership, Management & Oversight
The New Day Project
Water Meter / Billing Issues Flow Chart
Inaccurate Bills - Corrected

Newly installed meters are


Some meters not properly Pre-2014 Sensus iPerl more accurate than
Meter readers are 2010 early retirement plan
installed in field or billing Meters may have been replaced meters; incorrect
understaffed, underpaid, resulted in lack of
system; incorrect installed with manual reads; aggregated
and curbing institutional knowledge
multipliers; lost meters manufacturing defect bills; over-reliance on
estimating bills

• Replaced 47,500 potentially • The number of estimated bills • Hired 20 new Field Service • Began a comprehensive
• Modernized the work order
management system in 2017 defective pre-2014 iPerl has continued to decrease Representatives and 4 new review of all workflows
meters analysts.
• Researched and corrected • In process of replacing • 37k held accounts were • Documented all processes
multiplier issues 54,500 out–of-life cycle independently verified and • Retrained and promoted
meters released existing staff • Developed and conducted
• Verified meter operations in ongoing training with
the field • Added 1 General Foreman customer service, billing and
and 3 supervisors to provide field service teams
• Enhanced billing
greater supervision and
documentation and account
verification oversight

• Updated all meter information • Minimized curb side meter


within the billing system reading

April 20, 2021 PAGE 13


TRUST RESTORED
Systemic Deficits in Leadership, Management & Oversight
The New Day Project
Water Meter / Billing Issues Flow Chart Delayed Bills - Corrected

Reorganization Bureaucratic turf


incomplete; Exceptions threshold Billing & Watershed Political interference
Multi-cycled billing led guarding; lack of
department lowered; increase in departments not in day-to-day
to increased bills cooperation and
understaffed and number of exceptions properly aligned operations
communication
improperly trained

• Increased staffing to • Continue to experience a • Completed group • Verify and release bills • Weekly meetings held • Regular meetings of the
improve billing accuracy year over year decrease training sessions with in a timely manner with the CEO that CEO, CEO staff, BOC
in exceptions both the Billing unit and which has prevented included appropriate and Board committees
• Decreased the billing Meter Services Division multi-cycle bills staff from multiple held to receive updates
error rate from 3% to • Leveraged our AMI departments and answer questions
less than 1% infrastructure and
• Realigned the workflow • Affected departments
improved performance in
of both teams to better held accountable • No outside interference
• Added additional reading meters
address day-to-day directly by the CEO with county departments
staffing
• Many exceptions are issues caused by and operations
• Added a dedicated independent of any reading and /or billing • Staffing and assignment
billing trainer to conduct county activity, i.e., errors changes made by the
ongoing training undetectable leaks, CEO to remove silos
irrigation, unintentional and enhance
• Transitioned away from uses of water and communication and
temporary staffing pilferage cooperation
model
April 20, 2021 PAGE 14
TRUST RESTORED
Systemic Deficits in Leadership, Management & Oversight
The New Day Project
Water Meter / Billing Issues Flow Chart Customer Service &
Dispute Resolution Process - Corrected

Field technicians
Customer Service Reps Over
dispatched to “verify” No 3rd. Party hearing
understaffed, underpaid complicated/duplicated
184,000 meters; not officers as intended
improperly trained efforts to resolve issues
physically able to complete

• Increased the number of • Created an ongoing meter • Removed silos and • Third party hearing is still
Customer Service verification process streamlined workflow being developed
Representatives (CSR) (w/pictures) to field verify processes between
meter attributes Watershed and UCO units • Identified only 4 disputes
• Created a formal dispute
process through arbitration • This partnership has resulted
in improved billing, better
• Developed ongoing CSR customer service, and a more
training efficient and effective
operation.

April 20, 2021 PAGE 15


TRUST RESTORED
Systemic Deficits in Leadership, Management & Oversight
The New Day Project
Water Meter / Billing Issues Flow Chart
Erosion of Public Trust - Corrected

Rate increase not well Systems not integrated; no Many customers expressed
Inaccurate data distributed
publicized; impact of water internal chain of custody dissatisfaction with Sensus
to customers
restrictions for meters iPerl meters

• N/A • Streamlined the meter • Suspended the installation of • Shared EPA information with
inventory process so that the pre-2014 iPERL meters and customers to provide
DWM warehouse was solely began installing AccuStream independent data regarding
responsible for both, meters in December of 2016 average household water
physically receiving the usage along with the DeKalb
meters in stock, distributing • Assessed the impacted bill County commodity charges to
assist customers in determining
meters to contractors and cycle for customers disputing
their estimated usage and cost
uploading the matching iPERL meters and applied
electronic inventory file into account adjustment(s) where • Performed thorough account
the billing system appropriate reviews with verification work
orders
• Full system integration is set
to occur with the • Contacted customers with
implementation of the new unusually high consumption to
enQuesta billing system share work order results and
provide follow up when needed
April 20, 2021 PAGE 16
Trust Restored

We have gone from over 4,000


disputed bills to less than 200

• Out of ~200,000 customer accounts, only about 200 (~0.1%) of


bills are currently in dispute
• Reliable and timely data on water use results in a much higher
level of customer service

April 20, 2021 PAGE 17


Moving Forward
Next Steps

April 20, 2021 PAGE 18


NEXT STEPS
The CEO will rescind the
Executive Order and end the
disconnection moratorium
effective July 1, and

The County will begin a


thorough Communications
Plan.

April 20, 2021 PAGE 19


COMMUNICATIONS PLAN
• Key Themes:
– The historic deficits in leadership, performance and
infrastructure that drove the need for the moratorium
have been corrected
– Lifting the moratorium results in all paying their share
– COVID-impacted customers will receive special
considerations.

April 20, 2021 PAGE 20


COMMUNICATIONS METHODS
Outreach over multiple channels

▪ Outreach to elected officials


▪ News media
▪ Multiple platforms: flyers, Nextdoor,
GovDelivery, twitter/etc., FAQ
▪ County/DWM web sites

April 20, 2021 PAGE 21


COVID PAYMENT ARRANGEMENTS
• Implement special considerations for those affected by COVID:
– Commitment to structured re-payment plan
– Longer repayment period than standard repayment plans
– Formal application process available manually or over internet
– Explanation of COVID-related need
– Proof of residency (lease or homestead exemption)
– State of GA Utility Assistance
– Exploring potential for grant funds for outstanding water bill balances

April 20, 2021 PAGE 22


SUMMARY
We are ready to lift the moratorium:
– The legacy problems have been corrected
– Customers should pay their share
– COVID-impacted customers, will receive
extended payment arrangements.

April 20, 2021 PAGE 23


QUESTIONS?

You might also like