CASES

STUDIES – PLANNING, COORDINATION AND CONTROL IN THE SUPPLY CHAIN



Short case (6) Bababass Hypermarket

Bababass Company has a big supermarket in Ho Chi Minh Ville. Zaza is his main supplier in
electronic gadget.

Forecast demand is as follows:
January February March
Forecast Demand
ZazaElectronic Pen 600 items 450 Items 500 Items

Zaza S33 Smartphone 1800 items 2500 Items 800 Items


Hypothesis
The hypermarket is opened from Monday to Saturday and is closed on
January 1st.
very little variation in daily sales
Bababass hypermarket wants to b wants to be delivered to the limit of the
safety stock

Zaza Electronic Pen Zaza S33 Smartphone


Batch size for replenishment 480 400
(Supplier Constraint)
Time Delay for replenishment 3 5
Safety stock 20 40
On Hand (beginning M1) 160 380

With Xls :

1. Make the aggregate planning for each month (Evaluate for each month the daily
demand; Evaluate the available products in the end of each month; evaluate the
reorder point).
2. Disaggregate the monthly schedule and propose a file which will be used for the
replenishment that Bababass company will send to Zaza at the beginning of
January.
3. Bababass Supply Chain manager proposes to split the inventory with Zaza by
reducing time delay for replenishment. The safety stock is not modified by this
idea. Than, the time delay for replenishment is 2 days. Could you evaluate:
- The stock level for Zaza and for Bababass each day after each day;
- The file that Bababass company will send to Zaza at the beginning of January if
this scenario is validated.

Pr. P. FENIES – Supply Chain Planning and Control – Tactical problems



CASES STUDIES – PLANNING, COORDINATION AND CONTROL IN THE SUPPLY CHAIN



Short case (7) Sivabonga textiles (2)

Siyabonga Textiles, a manufacturer of women’s garments has compiled the following sales
forecast for the next time period of 9 weeks.
We are at time period 0.
The safety stock has to be 20% of the forecast demand.
Very little variation in daily sales
The opening inventory for this period was 850 units and the factory cab only produce batches
of 1000 units.


1 2 3 4 5 6 7 8 9

Forecast Units 4900 4500 6000 6200 8000 4985 5280 6560 7750


Customer
Orders 4300 4200 4125 4000 4100 3000
(Committed)


Projected on-
hand
Inventory


MPS


Available to

Promise (1)


With Xls:

1. Calculate for all the horizon time, and if we are just before week 1:

Projected on hand inventory


Master Production Schedule
Available to Promise (ATP)
Take into account safety stocks.




Pr. P. FENIES – Supply Chain Planning and Control – Tactical problems



CASES STUDIES – PLANNING, COORDINATION AND CONTROL IN THE SUPPLY CHAIN


2. The forecasts at the end of week 1 are as follows:


2 3 4 5 6 7 8 9 10

Forecast Units 4500 6000 6200 8000 4985 5280 6560 7750 6800


Customer
Orders 4400 5800 4260 5000 2460 2000
(Committed)


Projected on-
hand
Inventory


MPS


Available to

Promise (1)


Calculate for all the horizon time, at the begining of week 2 .

Projected on hand inventory (4)
Master Production Schedule (4)
Available to Promise (ATP) (3)
Take into account safety stock.
The on hand inventory at the end of time period 1 is : 680.


3. Disaggregate the weekly schedule and propose a daily schedule with the date of
replenishment. Take into account that the manufacture is closed on Sunday.

Pr. P. FENIES – Supply Chain Planning and Control – Tactical problems