CONSTRUCTION BID
PROPOSAL
Prepared by:
2017-ME-62
Project Manager
muqadir1@gamil.com
+923166531625
Saturday, June 1, 2019
Lahore
We have received government of Punjab’s invitation for bid for the Metro train construction project
that you want to start in second quarter of this year. Please consider this a formal bid proposal for the
construction work. I have attached our bed proposal containing the scope of work, deliverables and
other terms and conditions.
We have measure up with you biding requirement sent in your original invitation. We hope to meet
your departments approval. It will bring us great pleasure to work with you.
If you have any questions or in need of additional information, you may contact or email at
+923166531625, muqadir1@gmail.com.
Respectfully yours,
Project manager
Hilla Group
1 Work breakdown structure
Stabling area
Control center
Central control
Depots
Workshops
Pilars
Reinforcement
Elevated stations
Reachability Passenger elevators
Freight elevators
Mechanical,electrical
Lighting
and plumbing
Uninterruptible
power supply (UPS)
Gardens and
pavilions
Environmental
control system
Smoke evacuation
Air pip
and damper system
Air conditioning
Chill
system
Wat
Generators
Core electrical and Power supply and
mechanical works distribution
Solar power units
Testing
Figure 1 Elevated station
Activities Tasks a m b TE σ2
Central control Stabling area 60 85 100 83 44.4
Control center 300 400 450 392 625
Depots 90 110 120 108 25
Workshops 365 500 550 486 950.7
Elevated track Pillars 400 550 600 533 1111
Track 250 320 350 313 277.8
Elevated stations Ticket centers 120 150 160 147 44.4
Escalator 120 150 170 148 69.4
Passenger elevators 100 140 150 135 69.4
Freight elevators 60 75 80 73 11
MEP & ECS Mechanical, electrical 100 180 200 170 277.8
(MES) and plumbing
Environmental control 40 55 60 53 11
system
Gardens and pavilions 190 230 250 227 100
Air conditioning system 70 120 130 113 69.4
Core electrical and Power supply and 120 160 180 157 10
mechanical works distribution
Generators 60 80 90 78 25
Automation 130 150 160 148 25
Solar power units 70 77 80 76 2.8
Tasks
engineering
engineering
engineering
Sub project
Mechanical
Electrical
manager
head
head
head
Civil
Central control
Stabling area
Control center
Depots
Workshops
Pillars
Track
Core electrical and mechanical works MEP & ECS (MES) Elevated stations Elevated track
Ticket centers
Escalator
Passenger elevators
Freight elevators
Responsible Authority
Consultant Informed
4 Network diagram
As MS project is paid software, neither I nor my university can afford it. As we are Muslims,
we also can’t afford the crack version. So, hand calculations are here.
5 Action plan
Start Pillaring Track Environmental control system Gardens and pavilions Power
supply and distribution Finish
D−μ
z= 2
√σ u
Where,
Thus,
z = 4.95
Thus, the probability that the project will be completed in 4 years is 100%.