IRISE Detailed Action Plan
IRISE Detailed Action Plan
Formation of Operational Amy Fe/ Kagawad In- April, 3rd week NA NA Computer, FGD Date indicated on the
2 Management Structrure charge projector, ppt timeframe was only the target
date by the Livelihood Staff In-
Drafting of Operational Policy Amy Fe/ Kagawad In- May, 1st week NA NA Computer, FGD charge. Final Schedule
3 charge projector, ppt depending on the availability
of PB/ Kagawad to be confirm
4 Strategic Development Planning Amy Fe/ Kagawad In- May, 3rd week NA NA Computer, FGD upon PB was consulted. For
charge projector, the strategic planning, it
template for includes VMV formulation and
strategic plan, planning of activities.
ppt.
c. Finalization/Signing of MOP Amy Fe/ Kagawad In- May, 2nd week NA NA Printed MOP for FGD
charge signing