PH 3 PEP East Injection Improvement
PH 3 PEP East Injection Improvement
PH 3 PEP East Injection Improvement
PEP Number
Date August 3rd, 2007
Charge Center
Priority Medium
Required Completion Date: 30 April 2008
Target Completion Date: 31 March 2008
Estimated Cost: US$ 107,800
Prepared by: Requested Reviewed by Reviewed by Reviewed Approved by: Approved by:
by: by:
Background:
The current operating condition of the east condensate injection system which serves
Units 4/5/6 creates high O&M cost due to the operation of the water distribution
pump driven by diesel engine in addition to the operation of CIS-P-28 and P-29.
To improve the O&M cost, the one condensate pump that has enough capacity to
handle the current operation has been selected. During normal operation, P-28 and P-
29 is planned to be put in stand by mode.
Project Objective
Reduce the current operating cost of the east condensate injection system to
approximately US$ 96,000 per year and reduce CO2 releases by eliminating the diesel
engine usage.
Project Description
Perform engineering design and manage project implementation to install the new
condensate pump and all associated piping, electrical and instrumentation system
adjacent to the existing system. The tie-in works will be designed and executed in
such a way to ensure minimum process loss of the running units.
Scope of Work
Project Economics
This project is not subjected to return of investment, but will reduce the current
operating cost approximately US$ 96,000 per year. The project DPI is calculated at
10.24. The total initial costs to purchase and install all materials required with 10%
contingency is US$ 107,800
The cost estimate is attached. The cost estimation was based on preliminary
engineering. The cost may change as a result of market price. All CRF, Work request,
Material requisition developed to support this project shall be reviewed and sign by
the project coordinator.
Project Schedule
The project duration for this phase is approximately 30 days for administration work
and 4 (four) months for purchasing and construction work. For detail schedule of this
project, please see the schedule in the attachment.
Safety Issue
General safety rules must be applied. All workers must wear the necessary safety
gears as follow: hard hats, safety boots, hand gloves and goggles as appropriate. Lock
out/tag out procedure must be followed as necessary.
The system shall be designed and built according to the specification and standards set
by CGS. Special attention shall be given to the following:
1. Welder Qualification / Welding procedure
Ensure the validation of the Welding Procedure Specification (WPS), Procedure
Qualification Records (PQR) and Welder’s Performance Qualification (WPQ)
Utilize Certified Welder, verify MIGAS welding certification.
2. Material Availability
Schedule work based on material availability
Inspect material as it arrives on site
Mill certificate for all valves, pipes and fitting shall be provided
Condensate pump documents shall be provided
3. Safety Inspection
Conduct safety inspection of construction sites weekly
Review contractor’s record of safety inspection and meetings conducted in the
field.
Ensure that the contractor is in compliance with the company safety policy and
contractor requirements.
See Appendix D
Personnel
Equipment
Company asset
Environment
A hazard analysis (job safety analysis), will be performed for each non-routine task or
project in the field, and a Process Hazard Analysis will also be performed should there
be any changes to a previous design.
Appendix
$47,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00 $122,531.00
NPV @ 10% ra te $47,531.00 $144,475.29 $236,534.64 $320,224.96 $396,307.08 $1,063,664.37 $1,072,161.08 $1,079,885.36 $1,086,907.44 $1,093,291.14 $1,099,094.51 $1,104,370.30
DPI 10.24