Shifting and Tilting Occur Generally During The Sinking Phase of Well Foundations

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

Shifting and tilting occur generally during the sinking phase of well foundations.

If
proper care is not taken, they can cause grave problems which may lead to the
weakening of the stability of foundations. Precautions to avoid shifting and tilting,
limitations and rectifying methods are discussed below.

Shifting and Tilting of Well Foundations


 When the well is moved away horizontally from the desired position, it is called shifting
of the well foundation.
 When the well is sloped against vertical alignment, it is called tilting of the well
foundation.

Precautions to Prevent Shifting and Tilting


Following safety measures should be considered to prevent shifting and tilting of well
foundations:

 The diameter of well curb should be more than the external diameter of steining.
Generally, a difference of 40 to 80 mm is recommended.
 The well steining should be symmetrically placed over the curb.
 The outer surface of the well curb and steining should be smooth.
 All the sides should be uniformly dredged.
 The cutting edge should be uniformly thick and sharp.

Limitations
 The maximum tilt allowed in case of well foundation is 1 in 60.
 The shift in well foundation should not be more than 1 % of depth of sunk.
 Beyond the above limits, well foundation is considered as dangerous and in such a case,
remedial measures to rectify shifting and tilting should be followed.

Rectifying Methods
Rectifying methods for Rectification of shifting and tilting problems in well
foundations are as follows:

1. Eccentric loading
2. Excavation on higher side
3. Water jetting
4. Pulling the well
5. Using hydraulic jacks
6. Using struts
7. Excavation under cutting edge
8. Wood sleeper under cutting edge
1. Eccentric loading
 The well tilt can be rectified by placing eccentric loading on the higher side. Higher side
is nothing but the opposite side of tilt or lower side.
 A loading platform is constructed on the higher side and load is placed on it.
 This eccentric load will increase downward pressure on higher side and correct the tilt.
 The amount of load and eccentricity is decided based on the depth of sinking.
  Greater is the depth of sinking of well, larger will be the eccentricity and load.

Fig 1: Eccentric Loading on Well Foundation

2. Excavation on Higher Side


 When well is tilted to one side, excavation should be increased on the other side which is
opposite to tilted side.
 This technique is useful only in the initial stages of well sinking.
Fig 2:
Excavation on Higher Side

3. Water Jetting
 Water jetting on external surface of well on the higher side is another remedial measure
for rectifying tilt.
 When water jet is forced towards surface of well, the friction between soil and well
surface gets reduced and the higher side of well becomes lowered to make well vertical.
Fig 3: Water
Jetting on Higher Side

4. Pulling the Well


 The well can be pulled towards higher side using steel ropes.
 One or more steel ropes are wound around the well with wooden sleepers packed in
between well and ropes to prevent damage to the well steining by distributing load over to
larger area of steining.
 Pull should be carefully done otherwise, shifting of well foundation may occur.
Fig 4: Pulling
the Well Foundation

5. Pushing using Jacks

 Another method to rectify tilting and shifting of well foundation is using hydraulic jacks
or mechanical jacks, the tilted well can be pushed from lower side to higher side.

 Neighbor vertical well foundations or suitable arrangements made will give support to the
jack system.

 Care should be taken while pushing the well otherwise the well may shift.
Fig 5: Pushing using Jacks

6. Using Struts

 By providing struts as supports on the lower side or tilted side of well, further tilting can
be prevented.

 Wooden sleepers are provided between struts and well steining to prevent damage to well
steining and to distribute pressure to larger area.

 Struts are rested on firm base having driven piles.


Fig 6:
Strutting the Well From Lower Side

7. Excavation under Cutting Edge

 This technique is used for hard strata soils. In this method, the well is de-watered first and
open excavation is carried out exactly under the cutting edge on the higher side.

 If de-watering is not possible, soil strata is loosened using suitable equipment with the
help of professional divers.
8. Wood Sleeper under Cutting Edge

 If tilting towards lower side is increasing, then wooden sleepers are placed under cutting
edge on the lower side to control the tilting temporarily.

 When well is corrected to vertical level, these sleepers can be removed.


Fig 7: Wood
Sleeper under Cutting Edge

You might also like