Professional Documents
Culture Documents
03b.sch B - Scope of Work and Technical Provisions
03b.sch B - Scope of Work and Technical Provisions
4000069324
1. INTRODUCTION
2. SCHEDULE REQUIREMENTS
3.1.1 Plant Number Tags, 6.35 cm X 2.54 cm or 4.445 cm X 1.112 CM, for
each individual item of equipment and independent components to be
tagged. Normally the COMPANY Plant Number Tags are made of
brass, however COMPANY may issue Plant Tags made from other
material in cases where brass tags are not suitable for a particular
type of equipment.
- NONE -
B-1
The WORK shall include but not necessarily limited to, the following:
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 8007 and
S/S # 7097, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 8.345Km
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 8007 and
S/S # 7077, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 5.590Km
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 7035 and
S/S # 7036, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 5.590Km
B-2
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 8091 and
S/S # 7029, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 3.013Km
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 7222 and
S/S # 7029, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 2.371Km
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 7083 and
S/S # 7231, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 3.644Km
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 7172 and
S/S # 7019, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 7.882Km
B-3
CONTRACTOR shall replace the existing 33 kV U/G cable circuit by New XLPE
U/G Cable circuit. Complete design, Supply and installation of One (01) new
33KV underground cable circuits, each circuit consisting of 2-3CX240MM²,
XLPE, copper cable + Fiber Optic Cable, to be laid between S/S # 7054 and
S/S # 7067, complete with all required, insulated joints, earthing, and other
accessories in accordance with COMPANY Standard Code & Specifications as
shown in cable route drawing Appendix I - List of Attached Conceptual and
Reference Drawing.
Approximate Route Length of Cable Circuit = 1.42Km
5.10 All the new equipment to be installed under this PROJECT shall be provided
with grounding conductors and connected with the grounding grid.
5.12 All required WORK, materials and accessories in all above items shall be
provided and performed by the CONTRACTOR .
5.13 The cable outer jacket shall be flame retardant inside the substation, which
may be achieved by painting as per COMPANY Standard TES-H-107.01. The
supply of the paint shall be the responsibility of the CONTRACTOR
/Manufacturer.
5.14 PVC conduits and fittings shall be provided in all underground concrete duct
banks. The PVC conduits and fittings shall be designed, manufactured and
tested in accordance with the COMPANY'S Materials Standard Specification
23-TMSS-01.
5.15 Sub duct on hand hole and inside the building shall be corrugated, flexible
and fire retardant (2 Hours UL rating) with 25mm outside diameter. Subduct
installation shall be in accordance with TCS-T-111. 08.
5.16 Sub duct on the underground duct banks and direct buried conduit in
trenches shall be rigid with 32mm outside diameter and made from HDPE
piping compound, its inner wall must be smooth. It must comply with STC
specification MAT 2301 and pulling length must not exceed 450 meters.
5.17 The duct sealing units for conduit fittings shall be in accordance with
COMPANY'S Materials Standard Specification 23-TMSS-02.
5.18 Unless otherwise indicated, the size of the PVC Conduit for fiber optic cable
and Power cable shall be 100 mm inner diameter and 200 mm inner diameter
respectively or double the diameter of respective Cables.
B-4
CONTRACTOR shall dismantle and remove all the cables associated with the
33kv SWGR at 33kv S/S’s (8007, 7097, 7077, 7035, 7036, 8091, 7029,
7222, 7083, 7231, 7172, 7019, 7054 and 7067)
In case of the cable route for the new cable in the same trenches of the old
cable, the CONTRACTOR shall be responsible to dismantle the old power
cable and return back to SEC Store.
All dismantled materials shall be packed in proper way and handed over to
SEC store.
A. Survey for the complete route of the proposed 33kV circuits shown in
Appendix I - List of Attached Conceptual and Reference Drawing.
E. CONTRACTOR shall satisfy all the conditions listed in the approvals. All
WORK shall be coordinated with the concerned local authority for their full
satisfaction.
G. Design and Supply and installation of 33kv Cable Tray at S/S 8007, 7097,
7077, 7035, 7036, 8091, 7029, 7222, 7083, 7231, 7172, 7019, 7054 and
7067 as per COMPANY Standard Codes & Specifications.
B-5
6.1.2 CONTRACTOR shall provide all Start-Up Spare Parts required during
testing and commissioning up to Preliminary Acceptance of the
PROJECT, pursuant to Paragraph 6.1 of Schedule “A” of this
CONTRACT. The compensation payable to CONTRACTOR for the
provision of all these items is included in the CONTRACT Price set forth
in Paragraph 1.1 of Schedule "C" and specifically included in the
relevant equipment/material price components indicated in Pricing
Attachment to Schedule "C".
6.1.3 CONTRACTOR shall deliver the Start-up-Spare parts together with the
materials and equipment for the PROJECT.
B-6
6.6.2 TRANSPORTATION
Not required
7. SUMMARY OF DOCUMENTS
This Schedule “B” includes all of the documents listed below which are hereby
made part of this contract.
B-7
CLARIFICATION CORRESPONDENCES
B-8
7.4.2 Addenda
Reference Title Date
B-9