GT & GTD Oil Cooler line Oil Flushing

Execution Services

- Project Execution Plan


- Cleaning Contractor – FNC
Contents
1. Introduction ............................................................................................................... 3
1.1. Purpose .................................................................................................................... 3
1.2. Contractual Relation ................................................................................................. 3
1.3. Objectives ................................................................................................................ 3
1.4. Revision and Distribution.......................................................................................... 3
1.5. Definitions and Abbreviations ................................................................................... 4

2. Health and Safety...................................................................................................... 5

3. Organization and Accountabilities .......................................................................... 6


3.1. Work Locations......................................................................................................... 6
3.2. FNC Lubrication Oil Flushing Execution Services Team ........................................... 7
3.3. Project Personnel ..................................................................................................... 7
3.4. FNC's Representative .............................................................................................. 8
3.5. Client’s Representative ............................................................................................ 8

4. Scope of Work........................................................................................................... 8
4.1. Overview .................................................................................................................. 8
4.2. Contractor(FNC) Responsibility................................................................................ 9
4.3. Company Responsibility ......................................................................................... 10
4.4. Acceptance Criteria ................................................................................................ 12
4.5. Equipment requirement .......................................................................................... 12
4.6. Sequence of Execution .......................................................................................... 18
4.7. Key interface .......................................................................................................... 18

5. Interface and Risk Management ............................................................................ 18


5.1. Interface Management ........................................................................................... 18
5.2. Risk Management .................................................................................................. 19

6. Project Controls ...................................................................................................... 19


6.1. Project Controls ...................................................................................................... 19
6.2. Information Management ....................................................................................... 20
6.3. IT and Communications ......................................................................................... 20
6.4. Document Control .................................................................................................. 19

7. Reference Documents ............................................................................................ 20

fnceng001@fnceng.com
1. Introduction

1.1. Purpose
The purpose of this Project Execution Plan (PEP) is to describe the management processes used to effectively
execute the Works associated with oil flushing
This document details the execution plans/principles which are specific for the:
• Project Management Set-up;
• Lube Oil Cooler line Oil Flushing Execution Services;
• Other services which is available by client request

It describes the strategies and processes that will be in place to enable all team members to achieve their
goals and targets.
This project execution plan aids the standardization and ongoing improvement of the oil flushing work methods
of execution and delivery by facilitating the following:
• A Senior Management commitment.
• Assignment of functional positions to GT & GTD Oil Cooler Line Oil Flushing Execution Services
personnel.
• Assignment of authority levels for GT & GTD Oil Cooler Line Oil Flushing Execution Services personnel.

1.2. Contractual Relation


Client
Company
Contractor GK International , FnC Cleaning Engineering

1.3. Objectives
The objectives of the PEP are to:
• Define the work including all deliverables, activities and tasks that form the GT & GTD Oil Cooler Line Oil
Flushing Execution Services scope;
• Provide a clear and planned approach to progressing the lubrication oil flushing / equipment rental / waste
oil disposal services to successful execution;
• Describe audits, reviews and reporting mechanisms required to adequately monitor and control;

1.4. Revision and Distribution


This project execution plan is not a static document and will be reviewed and updated as necessary to reflect
any process changes that arise.

1.5. Definitions and Abbreviations


Unless noted otherwise, definitions listed in ISO 9000:2000, Quality Management System – Fundamentals and
fnceng001@fnceng.com
Vocabulary, shall apply.

Definitions:
Contract No. XXXXX GT & GTD Oil Cooler Line Oil Flushing Execution Services in
“Contract”
China Fabrication yards
“Contract Schedule” Client schedule for performing the Works.
FNC and any person of any tier engaged by FNC or another subcontractor to
“Contractor”
Company (Client) to provide any of the Work, including vendors.

The product of all work, including Client’s work under the Contract, collectively
“Project” comprising the total improvement commonly known as the Lubrication Oil Flushing
Execution Services

Are interchangeable and include all works, services, labor, operations or activities
“Works” and “Services”
required under the Contract.
Abbreviations:
HAZID Hazard Identification

HR Human Resources

HSE Health, Safety and Environment

HSEMP Health, Safety and Environment Management Plan

HSEMS Health, Safety and Environment Management System

IR Industrial Relations

ISO International Organization for Standardization

PDS Project Deliverables Schedule

PEP Project Execution Plan

PMS Project Management System

PMT Project Management Team

PQP Project Quality Plan

fnceng001@fnceng.com
2. Health and Safety
FNC is recognized for its commitment to safety, sustainable development and the wellbeing of the people,
communities and environments in which we operate.
Our commissioning and completions work is underpinned by our Health, Safety and Environmental (HSE)
Policies and HSE Manuals within the FNC Management System.
Backed by our experienced management team, we have access to industry-experienced personnel and
sophisticated project management systems to ensure safety is applied across all phases of a project.
Our Target Zero programme provides the policies and systems to ensure all staff take responsibility and
care for their team mates, and the communities and environments in which we work.
Our Target Zero values are:

• Commitment – To a culture of Zero Harm, where any incident or injury is unacceptable;


• Empowerment – Every employee has the right and duty to stop work if they believe an activity is unsafe,
or could harm to the environment or community;
• Team work – We will work together to achieve the vision of Zero Harm and will support each other when
preparing or performing any activity;
• Accountability – All employees contribute to the support and delivery of our projects, therefore every
employee is accountable for making Zero Harm a reality.

fnceng001@fnceng.com
3. Organization and Accountabilities

GT & GTD Oil Cooler Line Oil Flushing Execution Services team organisation and reporting lines will be
defined as below organization chart. The organisation chart will show the key functional areas of GT & GTD
Oil Cooler Line Oil Flushing Execution services and the reporting lines through Site Manager to client’s
management team.
The organization is based on the Lubrication oil Flushing execution team consisting of Client personnel and
FNC personnel together. Client will provide temporary piping supervisor, pipe fitter and welders and FNC will
focus on lube oil flushing execution and temporary piping work coordination. We believe that a combined
CLIENT and FNC team for GT & GTD Oil Cooler Line oil Flushing execution will provide the best solution for
the execution of the project. This joint execution team will supplement each other.

3.1. Work Locations


Lubrication Oil Flushing Execution Services team will have 2 main work locations during the execution phases
as follows:

Working yard, China


Responsible for All packages of Lubrication Oil Flushing execution scope and reporting documents
Supporting FNC Site team for procurement / administrations

FNC office, Yantai, Shandong, China


Responsible for contracts, invoicing, payment, supporting all discipline work and providing management
system and other project support works

fnceng001@fnceng.com
3.2. FNC Lube Oil Cooler line Oil Flushing Execution Services Team
FNC will mobilize GT & GTD Oil Cooler Line Oil Flushing Execution Services team to manage which is
composed as site manager and others, to control and coordinate the execution of the Works. FNC’s site
manager will be responsible for FNC’s overall project management while being supported by the FNC
management.

3.3. Project Personnel


The key personnel required managing the delivery of the Project and their responsibilities are listed below.

FNC Director of Operations (Project Director)


• FNC Director of Operations has the overall responsibility of ensuring the execution of the services is
performed in a safe manner and the health and wellbeing of the execution team is maintained in all
locations. The project administration, finance, HSE and operation team will be based in Yentai, Shandong,
China and will liaise with the project teams and provide all the necessary support that may be required to
deliver the requirements of the project.

The key role and responsibilities of the Director of Operations include:


• Health, Safety, Security, and Environment
• Ensuring that the Site Manager is supported in his efforts to ensure that the Project is appropriately
resourced;
• Supporting the project team to meet the project objectives;
• Keep abreast of changes in scope and submit Change Order’s within the specified durations noted in the
contract
• Ensure that project management systems and procedures are effectively implemented and adhered to;
fnceng001@fnceng.com
• Authorising Project expenditure in accordance with the Project budget and the Delegation of authority;

FNC GT & GTD Oil Cooler line Oil Flushing Execution Service Site Manager
• The Site Manager will report directly to the Director of Operations (within the FNC team) and to the
Client’s representative is responsible to:
• Responsible for safe completion of all work.
• Client Management Liaison. Managing the day-to-day operations of the Project to ensure the Project
deliverables are produced to scope, schedule, budget and quality;
• Report Project status and schedule to CLIENT and FNC management team
• Timesheet management
• Mobilization & Demobilization management
• Feedback to management on Progress, Constraints, Variance and Issues.
• Ensuring that the other Coordinators are supported in his efforts to ensure that the Project is appropriately
resourced

3.4. FNC's Representative


FNC's Representative and Executive Sponsor for this contract is:
Director of Operations – FNC
Jeongsup Kim

808, Feilong Zhongrun BLD, Jintan East Road, Laishan Zone, Yantai, China
fnceng001@fnceng.com

3.5. CLIENT’s Representative

4. Scope of Work
4.1. Overview
The Cleaning Contractor to execute all packages of GT & GTD Oil Cooler Line oil flushing execution scope at
Client yard in China.
The Cleaning Contractor FNC to self-perform the scope with his own equipment and personnel at fixed
reimbursable rates basis. (It could be discussed further based on client request.)
For the breakdown and timeline of the all the modules schedule, we refer to client initial schedule, reviewing
drawings and considering preparation time.

fnceng001@fnceng.com
4.2. Contractor (FNC) Responsibilities
• Mobilize, demobilize personnel and cleaning equipment
• Contractor shall provide the GT & GTD Oil Cooler Line Oil Flushing skid, specialty tools and test
equipment required to complete the work. The contract also need to provide consumables as a part of
base scope of work such as high pressure hoses, nozzles, valves, gaskets and all related materials to
execute the work
• Contractor is responsible to provide all temporaries as per attached marked-up P&IDs to perform lube oil
flushing scope.
• It is expected that the lube oil flushing oil will be re-used from one flush to the other, previous polishing
and cleaning of the used oil.
• Execution of Lubrication Oil Flushing scope, rig up/rig down equipment, supervision, execution of
Lubrication Oil Flushing and cleanliness acceptance.
• Contractor is responsible to design and supply the appropriate waste Oil collection including drip trays,
hoses and fittings, berms, and collection tanks as required by the local site and environmental authorities
• Contractor is responsible to prevent/manage oil spills and to dispose waste generated oil during
lubrication oil flushing execution.
• Safety PPE, Barricades, flagging, signage, and taping
• Contractor is responsible to complete Lubrication Oil Flushing check sheet
• Contractor is responsible to provide an oil flushing report at the completion of each oil system flush. The
report should include a chronological history of the respective flushing program, including photographs, oil
flow, pressure, and temperature. The report will also document the condition of the final target screens

fnceng001@fnceng.com
4.3. Company (CLIENT) RESPONSIBILITIES
• Provide Contractor with engineered Lubrication Oil Flushing work packages
• Supply the oil required to perform this activity.
• Removal of pipes, Control valves, Flow elements. etc. prior to start Lubrication Oil Flushing
• Temporary piping supervisors, Pipefitters & welders support, including loading/unloading, crane, rig in/out
support
• Reinstatement of pipes, Control valves, check valves, RO plates, Flow elements etc.
• Suitable equipment lay down area.
• Lifting and handling of equipment as required (Overhead crane, fork lift, rigging etc.)
• Scaffolding as required
• Permit to work
• Temporary Lighting, Power, and Fuel (if required).
• Emergency Services.
• Suitable on-site office space and lunch facility.
• Witness and accept oil flushing target screens
• Sign time sheets
• Contractor to specify in his quotation if there is any other utilities that needs to be provided by others

4.4. ACCEPTANCE CRITERIA


• The GT & GTD Oil Cooler Line Oil Flushing is complete once all parties (Cleaning Contractor and CLIENT
representatives) are satisfied with the system cleanliness.
• Acceptance Criteria: The cleanliness specification for this work is API 614, ISO 4406. The cleanliness of
the system will be determined by inserting 100 mesh screen paddles at critical points such as the points
described on the engineering work packs and at other strategic points mutually agreed upon by CLIENT
and the cleaning contractor.
◼ The screens shall have no more particles than listed in Table D.1 of API 614
Table D.1

• Acceptance criteria: The cleanliness specifications for this operation are in accordance with ISO 4406. The
cleanliness of the system is analyzed in real time through an oil analyzer connected to the sample points of
the oil flushing Skid.

fnceng001@fnceng.com
◼ Overall flushing is formally acceptable when the particles count executed on an oil sample, taken from
the most distant oil feed, can be classified as ISO 4406 class 16/14/12.

fnceng001@fnceng.com
4.5. EQUIPMENT REQUIREMENT
Cleaning Contractor shall provide the following equipment to assist in the completion of the GT & GTD Oil
Cooler Line Oil Flushing scope.

Equipment Description

Trailer mounted High Velocity Oil Flushing skid should have the flow capacity
to achieve a minimum Reynolds number of 4000 (turbulent flow). Oil pump driver
can be electric motor. This skid will provide the high flow, high temperature oil
required for the activity. Recommended capacity of:

Type : Screw / Gear pump type


Oil Flushing Skid
⚫ Oil Flushing Skid (2000LPM)
- Circulation tank
- All Stainless Steel
- Heater
- Bag Filter (1miron)
- Fine Filter(3micron)

To perform temporary connections to/from flushing skid to the pipes to be


Hoses
flushed, and drained later after.
Place under all potential leak and drain points and used to collect oil from any
Drip Trays and Berms leaks.

Used to assist in Oil transfer to fill the unit/oil reservoir and for drainage of piping
Oil Transfer Pump
and collection of waste oil from drip trays and berms at the end of the job.

The oil flushing service provider will provide the 100 mesh target screens
100 Mesh Paddle
required for validation of oil piping cleanliness. See Oil Piping Cleanliness
Target Screens
“Acceptance Criteria”
Rubber Hammer To help loose the small particles on the pipe wall

Waste Oil Tank Tank to hold waste oil collected during the Oil flushing

Particle Counter To analyze the Oil cleanness “Acceptance Criteria”

4.6. SEQUENCE OF EXECUTION


• OIL FLUSHING PREPARATION STEP
1) All piping systems shall be pressure tested before Oil Flushing work.
2) Items such as pressure gauges, transmitters, flow meter, orifice plates, rupture discs etc.
must be disconnected and removed during Oil Flushing.
3) A job safety procedure (JSP) must be carried prior to starting the works and be readily available
at the job site.
4) Oil Flushing Skid shall be equipped with a thermometer, pressure gauge, sampling cock and filter
screen, etc.
5) When Oil Flushing carry out, temperature, pressure, etc. shall be monitored periodically. This can
be determined by examining the return line to the circulation tank. Screen filter with 100mesh shall
fnceng001@fnceng.com
be installed at the end of return line connected to circulation tank and to the suction line connected
to circulation pump from the tank.
6) Any temporary piping shall be installed such that air pockets or dead legs are not introduced into
the system / equipment being cleaned to ensure that all areas to be cleaned.
7) Mark-up drawings shall be prepared and approved by company before starting the oil flushing.
8) Lines shall be flushed using temporary connections to provide a "flushing loop." The Loop shall
be prepared together with supply ports in the main Line with hoses and valves. The main Line supply
& return header shall be flushed first using end loop and then each branch line shall be flushed using
port loop.
9) Branch loop for main Line shall be fitted with isolation valves and the flow shall be managed by
opening / closing the valves to enable all branch piping to be flushed properly.
10) Verification of acceptable velocity & Reynolds No. in each branch line of the particular package
shall be followed as per the below

fnceng001@fnceng.com
Condition
Oil ISO 32
VELOCITY TABLE Temperature
Viscocity
60
15.2
PIPE REYNOLDS 3000 REYNOLDS 4000

VELOCITY FLOW RATE FLOW RATE VELOCITY FLOW RATE FLOW RATE
PIPE SCH OD THK ID
(m/sec) (m3/h) (l/min) (m/sec) (m3/h) (l/min)
10 21.30 2.10 17.10 2.67 2.20 36.75 3.56 2.94 49.00
40 21.30 2.80 15.70 2.91 2.02 33.74 3.87 2.70 44.98
1/2 80 21.30 3.70 13.90 3.28 1.79 29.87 4.38 2.39 39.83
160 21.30 4.70 11.90 3.83 1.53 25.57 5.11 2.05 34.10
XXS 21.30 7.50 6.30 7.24 0.81 13.54 9.66 1.08 18.05
10 26.70 2.10 22.50 2.03 2.90 48.35 2.70 3.87 64.47
40 26.70 2.90 20.90 2.18 2.69 44.91 2.91 3.59 59.88
3/4 80 26.70 3.90 18.90 2.41 2.44 40.61 3.22 3.25 54.15
160 26.70 5.50 15.70 2.91 2.02 33.74 3.87 2.70 44.98
XXS 26.70 7.80 11.10 4.11 1.43 23.85 5.48 1.91 31.80
10 33.40 2.80 27.80 1.64 3.58 59.74 2.19 4.78 79.65
40 33.40 3.40 26.60 1.72 3.43 57.16 2.29 4.57 76.21
1" 80 33.40 4.60 24.20 1.89 3.12 52.00 2.51 4.16 69.34
160 33.40 6.40 20.60 2.21 2.66 44.27 2.95 3.54 59.02
XXS 33.40 9.10 15.20 3.00 1.96 32.66 4.00 2.61 43.55
10 42.20 2.80 36.60 1.25 4.72 78.65 1.66 6.29 104.87
40 42.20 3.60 35.00 1.30 4.51 75.21 1.74 6.02 100.28
1 1/4 80 42.20 4.90 32.40 1.41 4.18 69.62 1.88 5.57 92.83
160 42.20 6.40 29.40 1.55 3.79 63.18 2.07 5.05 84.24
XXS 42.20 9.70 22.80 2.00 2.94 49.00 2.67 3.92 65.33
10 48.30 2.80 42.70 1.07 5.51 91.76 1.42 7.34 122.34
40 48.30 3.70 40.90 1.12 5.27 87.89 1.49 7.03 117.19
1 1/2 80 48.30 5.10 38.10 1.20 4.91 81.87 1.60 6.55 109.16
160 48.30 7.10 34.10 1.34 4.40 73.28 1.78 5.86 97.70
XXS 48.30 10.20 27.90 1.64 3.60 59.95 2.18 4.80 79.94
10 60.30 2.80 54.70 0.83 7.05 117.55 1.11 9.40 156.73
40 60.30 3.90 52.50 0.87 6.77 112.82 1.16 9.03 150.42
2" 80 60.30 5.50 49.30 0.93 6.36 105.94 1.23 8.48 141.26
160 60.30 8.70 42.90 1.06 5.53 92.19 1.42 7.38 122.92
XXS 60.30 11.10 38.10 1.20 4.91 81.87 1.60 6.55 109.16
10 88.90 3.00 82.90 0.55 10.69 178.15 0.73 14.25 237.53
40 88.90 5.50 77.90 0.59 10.04 167.40 0.78 13.39 223.20
3" 80 88.90 7.60 73.70 0.62 9.50 158.38 0.83 12.67 211.17
160 88.90 11.10 66.70 0.68 8.60 143.33 0.91 11.47 191.11
XXS 88.90 15.20 58.50 0.78 7.54 125.71 1.04 10.06 167.62
10 114.30 3.00 108.30 0.42 13.96 232.73 0.56 18.62 310.30
40 114.30 6.00 102.30 0.45 13.19 219.83 0.59 17.59 293.11
80 114.30 8.60 97.10 0.47 12.52 208.66 0.63 16.69 278.21
4"
120 114.30 11.10 92.10 0.50 11.87 197.92 0.66 15.83 263.89
160 114.30 13.50 87.30 0.52 11.26 187.60 0.70 15.01 250.13
XXS 114.30 17.10 80.10 0.57 10.33 172.13 0.76 13.77 229.50
10 141.30 3.40 134.50 0.34 17.34 289.03 0.45 23.12 385.37
40 141.30 6.60 128.10 0.36 16.52 275.28 0.47 22.02 367.03
5" 80 141.30 9.50 122.30 0.37 15.77 262.81 0.50 21.02 350.42
160 141.30 15.90 109.50 0.42 14.12 235.31 0.56 18.82 313.74
XXS 141.30 19.10 103.10 0.44 13.29 221.55 0.59 17.72 295.40
10 168.30 3.40 161.50 0.28 20.82 347.05 0.38 27.76 462.73
40 168.30 7.10 154.10 0.30 19.87 331.15 0.39 26.49 441.53
80 168.30 11.00 146.30 0.31 18.86 314.39 0.42 25.15 419.18
6"
120 168.30 14.30 139.70 0.33 18.01 300.20 0.44 24.02 400.27
160 168.30 18.20 131.90 0.35 17.01 283.44 0.46 22.68 377.92
XXS 168.30 21.90 124.50 0.37 16.05 267.54 0.49 21.40 356.72

fnceng001@fnceng.com
Viscosity / Temperature Chart (VG32 60℃)

11) Temporary piping and flexible hoses shall be at least same size as the flushed piping to minimize
flow restriction. In case multi-hoses are required due to hose size limit, the quantity of hose shall be
determined to have same sectional area so that no flow restriction occurred.
12) Flushing and sampling to verify cleanliness shall take place at turbulent flow at the return line.
13) Oil flushing will be carried out utilizing system oil, as specified for normal operation of the
system/equipment.
14) All instruments shall be removed, blanked off, tagged and stored in suitable place.
15) Visual cleanliness inspection for temporary components by Company shall be done prior to
installation.
16) Grinding / Welding or shot blasting activities shall not be carried out in the area immediately prior
to flushing.

• OIL FLUSHING STEPS


Oil flushing shall be carried out as per following scope:

No System Name Oil Cleanliness Level

GT & To be provided by
1 Lube Oil API614 & ISO 4406 class 16/14/12
GTD Company

fnceng001@fnceng.com
• FLUSHING PROCESS DIAGRAM

1) During the flushing of the pipes, it is necessary to reach turbulent flow to achieve efficient removal of
and transport of particles with the turbulent flow. The Reynolds Number defines the turbulent condition
as per following equations.
Re = vXD/Q

- Q is the flow in the pipeline given in liter/min (l/min)


- D is inner diameter given in millimeter (mm)
- v is kinematic viscosity given in centistokes (cSt)
- Transition between turbulent and Laminar flow 2300<Re<4000
fnceng001@fnceng.com
2) The local flow-meter has to be installed on the downstream of each branch to confirm local velocity and
flow rate. Those values are to be recorded in the check sheet.
3) Oil flushing shall continue until the cleanliness level of the fluid is the minimum in accordance with API
614 and ISO 4406 class 16/14/12.
4) When flushing is completed, the piping shall not be opened again to ensure the system stay clean.
5) Drains, vents, instrument connections, dead legs, etc., shall be fitted with temporary hoses to facilitate
periodic blow-downs.
6) The system shall be thermally, mechanically and hydraulically shocked to dislodge dirt, particulate and
foreign material.
1. Thermal Shock

During the flushing, the oil temperature will be oscillated but if the fluid temperature exceeding 80℃

shall not be re-used.

- Hydraulic Shock
The system shall be hydraulically shocked by shutting down the pumps to interrupt the flow.
The pumps shall be shut down to allow the lines to drain and then restarted to restore full flow.

- Mechanical Shock
Vibrator or hammering device shall be installed on the horizontal and corner of the line to apply
hammering effect on the pipe. The vibrator shall be re-locating from one horizontal section to the
other horizontal section during flushing work in order to provide hammering effect so that particles
can’t settle down in any part of the piping.
The vibrator operating time at each point is recommended about 10~15min.

• Acceptance of Cleanliness - Final Acceptance


◼ 1st acceptance shall be determined when the oil quality complies with the specified API 614.

fnceng001@fnceng.com
◼ Final acceptance shall be determined when the oil quality complies with the specified ISO 4406 class
16/14/12

• WASTE OIL DISPOSAL STEP


All waste oil generated during lubrication oil flushing will be handled by third party for further processing.
Waste oil/water must be stored to Client indicated place to protect any fire. If it is not exists special
storage area, Cleaning contractor will install the barricade not to approach anybody to waste oil/waster
area and it is also required to stick MSDS.
All waste oil must be proceeded disposals with specialized & government approved/registered vendor.
Cleaning Contractor will provide Wastes disposal completion certification after disposal work cleared.
Entire waste oil disposal process is as below.

※ Wastes oil will be reported to Penglai environment bureau 1 week in advance for collecting.

4.7. Key Interfaces


Key internal interfaces for the FNC within project works will exist with the following entities:
• Project Execution Team located in Qingdao

Key external interfaces for the FNC will exist with the following entities:
• CLIENT’s Commissioning Team

5. Interface and Risk Management

5.1. Interface Management


Interface Management for the individual phases of GT & GTD Oil Cooler Line Oil Flushing Execution Services
fnceng001@fnceng.com
will be controlled in accordance with document XXXX, Interface Management Plan. The Site Manager will co-
ordinate and maintain the interface management process.

5.2. Risk Management


Risk management for the individual phases of GT & GTD Oil Cooler Line Oil Flushing Execution Services will
be controlled by means of risk profiles in accordance with document XXXX, Risk Management Plan.
During preparation phase, risks will be identified by FNC and assigned owners. The risk profile will be
periodically reviewed and updated as new risks are identified and old risks are mitigated.

6. Project Controls

6.1. Project Controls


The project controls function manages all aspects of scheduling and cost control. Further, it manages
information management across the project and will generally collect track and report information for the
duration of the Works.

6.2. Information Management


The Information Management Plan will be applied for all information gathering, sharing, usage, and handover
for the duration of Works.
Information Management consists of the processes, organisation, systems, and technology associated with the
efficient management and delivery of information. The Information Management (IM) Strategy supports the
overall Work strategy and is driven by Contractors and contractual requirements as well as requirements for
data integrity, efficiency, security, and availability.

6.3. IT and Communications


On China Fabrication work sites, it is the responsibility of Client to provide all infrastructures in accordance
with its own IT policies and to provide infrastructure to FNC.

6.4. Document Control


The FNC’s project team will be integrated into the Client’s team and therefore utilise the Client’s Document
Control Plan. The Client’s Document Control Plan sets out the practices and procedures to effectively control
of Lubrication oil flushing Execution work documentation. The plan provides a framework for storing, accessing
and exchanging documentation whilst maintaining strict data security. The plan defines the systems, processes
and responsibilities for the control of Lubrication oil flushing execution work documentation generated for and
by the Client.

fnceng001@fnceng.com
7. Reference Documents
Document No. Description

XXXX Client’s Document Control Plan

XXXX Travel and Expense standard

XXXX Integrated Master Schedule

XXXX HSE Management Plan

XXXX HSE Execution Readiness Plan

XXXX Interface Management Plan

XXXX Project Deliverables Schedule (PDS).

XXXX Risk Management Plan

Requisition for Lubrication Oil Flushing Execution


XXXX
Services in China Fab Yards

fnceng001@fnceng.com
8. Appendix

1. Temporary Piping drawing.

2. Resumes for key positions.

3. Equipment List.

4. Tool Consumable Material Equipment List.

5. Oil Flushing Schedule.

6. Oil Flushing Report (FGH-FAN) Sample.

fnceng001@fnceng.com
FNC Cleaning Engineering CO., LTD

Oil Flushing Skid (20


FnC Resumes for Key positions
Positions Candidate name China Experiences Remark

PJOE Penglai 16 years experiences


Site Manager KIM Chang Hyun
QMW Qingdao Offshore./plant experience
PJOE Penglai 16 years experiences
Supervisor LEE Dong Hyun
QMW Qingdao Offshore./plant experience
PJOE Penglai 17 years experiences
Supervisor SONG Geun Bong
QMW Qingdao Offshore./plant experience

F&C
Cleaning Engineering Co.,Ltd

发恩思(烟台)清洗工程有限公司
CANDIDATE DETAILS:

NAME: Chang Hyun KIM


POSITION: Site Manager
DATE OF BIRTH: April 15th 1975
NATIONALITY: KOREAN

SUMMARY

⬧ Supervisor of FNC in Korea at present


⬧ Flushing Supervisor with 18years experience in on boarding Fuel Oil and Gas, Lubricating Oil, Compressor System
etc.

QUALIFICATION

EDUCATION

⬧ Bachelor’s degree of Mechanical Engineering in Kyungpook National University in Korea

WORK EXPERIENCE

FEB 2014 – Present

F&C Corporation Co., Ltd, Korea

Supervisor of Operations –oil flushing and Chemical cleaning

⬧ Participate projects

⬧ Maersk Line PC ships (Series 9) Oil Flushing, Chemical cleaning, SUS Passivation In Samsung Heavy
Industries Ningbo, China
⬧ GS Caltex Daesan Petrochemical Complex
⬧ Hyundai Engineering Uzbekistan UGCC Gas Chemical Complex
⬧ Daelim Manjung #5, Malaysia TNB Fast Track A3 Power Plant
⬧ Hyundai Engineering Uzbekistan UGCC Gas Chemical Complex
⬧ Posco E&C Colon, Panama LNG Combined Cycle Power Plant
⬧ Daewoo E&C Pocheon Power Plant
⬧ Lotte E&C Al Qatrana, Jordan Alcatana Power Plant
⬧ SAMSUNG CNT Co.,Ltd. Qurayyah Independent Power Project Power Plant (12Unit)
⬧ Hanwha Co.,Ltd. Saudi Arabia MARAFIQ STG UNITS 5&6 PROJECT
⬧ SAMSUNG CNT Co.,Ltd. U.A.E RUWAIS S2 Thermal Power Plant
⬧ Hyundai Heavy Industries BP Clair Ridge project
⬧ Daewoo Shipbuilding & Marine Engineering Inpex Ichthys FPSO

This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
⬧ Scope of work
⬧ On-site Supervisor
⬧ Adjust manpower Supply And Demand Plan
⬧ Equipment And Materials Managerment
⬧ Chemical Cleaning And Oil Flushing, Water Jet to Carry Out Inspection

2006 – 2016

⬧ Scope of work
⬧ Check the Field Pipe Lines (PKG)
⬧ Calculate The BM(Bill Of Materials)
⬧ Chemical Cleaning And Oil Flushing, Water Jet to Carry Out Inspection

⬧ DSME Co.,Ltd. Total E&P Angola PAZFLOR FPSO Project


 Chemical Cleaning(pickling): Fuel Oil, Riser Tension, Drilling Hydraulic Power, BOP Control,
 Well Test Equipment System.
 Oil Flushing: Riser Tension, Drilling Hydraulic Power, BOP Control System.
 Water Flushing: Riser Tension, HP Mud & Cement, Choke & Kill, HP Manifold, Fresh Cooling
 Water, Well Test Equipment, Portable Water System.
 Air Blowing (5~7 kg/m2): Fuel Oil, Inergen, Bulk Air, Chilled Water, Compressed Air System, etc.

⬧ DSME Co.,Ltd. Vantage Drill Ship Project


 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)
 Pig Cleaning

⬧ Hyundai Heavy Industries Co.,Ltd SAKHALIN DC-1


 Chemical Cleaning & Oil Flushing construction

⬧ DSME Co.,Ltd. 3610 OOG DRILL SHIP


 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)
 Pig Cleaning

⬧ Hyundai Heavy Industries Co.,Ltd KISOMBA-A FPSO


 Chemical Cleaning & Oil Flushing construction

⬧ DSME Co.,Ltd. 6048 CHAYVO ON SHORE


 Pneumatic Testing (Including Air Blowing)
 Chemical Cleaning

⬧ DSME Co.,Ltd. 6049 CLOV FPSO


 Chemical Cleaning (pickling)

This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
 Oil Flushing
 Water Flushing
 Water Jet Cleaning
 Pig Cleaning
 Air Blowing
 GALT

⬧ DSME Co.,Ltd. 3614 ATWOOD DRILL SHIP Chemical Cleaning & Oil Flushing Construction
 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)
 Pig Cleaning

⬧ DSME Co.,Ltd. 3613 TRANS OCEN DRILL SHIP


 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)

⬧ Kunsan Combined Cycle Power Plant


 HRSG Chemical Cleaning Construction

⬧ DSME Co.,Ltd. 3613 TRANS OCEN DRILL SHIP


 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)

This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
CANDIDATE DETAILS:

NAME: Dong Hyun LEE


POSITION: Supervisor
DATE OF BIRTH: June 18th 1976
NATIONALITY: KOREAN

SUMMARY

⬧ Supervisor of FnC in Korea at present


⬧ Hydro Test Supervisor with 4years experience in on boarding Thruster, Air Line, Fuel Line, Oil Line etc.
⬧ Flushing Supervisor with 16years experience in on boarding Fuel Oil and Gas, Lubricating Oil, Compressor System
etc.

QUALIFICATION

EDUCATION

⬧ Graduated of INJE University in Korea

WORK EXPERIENCE

FEB 2014 – Present

Supervisor of Operations – Chemical cleaning and oil flushing

⬧ Participate projects
⬧ GCGV(ExxonMobil+SABIC) Yosemite MEG, Olefin
⬧ Samsung C&T QURAYYAH Power Plant (12 UNIT)
⬧ Lotte E&C Al Qatrana, Jordan Alcatana Power Plant
⬧ Hyundai Engineering Uzbekistan UGCC Gas Chemical Complex
⬧ Hyundai Heavy Industries BP Clair Ridge project
⬧ Daelim Manjung #5, Malaysia TNB Fast Track A3 Power Plant
⬧ Posco E&C Colon, Panama LNG Combined Cycle Power Plant
⬧ Hanwha MARAFIQ STG UNITS 5&6
⬧ Hyundai Oilbank Ulsan Factory
⬧ Hyundai Heavy Industries BP Clair Ridge project
⬧ Daewoo Shipbuilding & Marine Engineering Inpex Ichthys FPSO
⬧ Daewoo Shipbuilding & Marine Engineering Allseas Pieter Schelte Pipelay vessel

⬧ Scope of work
⬧ On-site Supervisor

This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
⬧ Adjust manpower Supply And Demand Plan
⬧ Equipment And Materials Managerment
⬧ Chemical Cleaning And Oil Flushing, Hydro-milling to Carry Out Inspection

OCT 2000 – FEB 2014

Chemical Cleaning & Oil Flushing Foreman

⬧ Scope of work
⬧ Check the Field Pipe Lines (PKG)
⬧ Calculate The BM(Bill Of Materials)
⬧ Chemical Cleaning And Oil Flushing, Water Jet to Carry Out Inspection

⬧ DSME Co.,Ltd. 6045 PAZFLOR FPSO


 Chemical Cleaning (pickling) : Diesel Oil, Lube. Oil, Chilled Water, Fuel Gas, Hydrocarbon, Vent, Etc.
 Oil Flushing: Diesel Oil, Lube. Oil, Hydraulic Oil (VRC, Fire Water, Mooring, Hatch, OOL Winch,
 Work Boat
 Water Flushing : Chiller Water Cooling, Fresh Water Cooling System etc.
 Water Jet Cleaning : Hydrocarbon, Hydrocarbon Gas, Hydrocarbon Liquid, Seawater,
 Produce Water
 Air Blowing : Hydrocarbon, Hydrocarbon Gas, Hydrocarbon Liquid, Seawater, Produce Water.
 GALT : Hydrocarbon, Hydrocarbon Gas, Hydrocarbon Liquid, Seawater, Produce Water, ETC.

⬧ DSME Co.,Ltd. 3604 OOC DRILL SHIP


 Chemical Cleaning(pickling): Fuel Oil, Riser Tension, Drilling Hydraulic Power, BOP Control,
 Well Test Equipment System.
 Oil Flushing: Riser Tension, Drilling Hydraulic Power, BOP Control System.
 Water Flushing: Riser Tension, HP Mud & Cement, Choke & Kill, HP Manifold, Fresh Cooling
 Water, Well Test Equipment, Portable Water System.
 Air Blowing (5~7 kg/m2): Fuel Oil, Inergen, Bulk Air, Chilled Water, Compressed Air System, etc.

⬧ SAMSUNG CNT Co.,Ltd. U.A.E RUWAIS S2 Thermal Power Plant


 HRSG Chemical Cleaning Construction

⬧ DSME Co.,Ltd. 3609 OOC DRILL SHIP


 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)
 Pig Cleaning

⬧ DSME Co.,Ltd. 3610 OOG DRILL SHIP


 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)
 Pig Cleaning

This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
⬧ DSME Co.,Ltd. 6048 CHAYVO ON SHORE
 Pneumatic Testing (Including Air Blowing)
 Chemical Cleaning

⬧ DSME Co.,Ltd. 6049 CLOV FPSO


 Chemical Cleaning (pickling)
 Oil Flushing
 Water Flushing
 Water Jet Cleaning
 Pig Cleaning
 Air Blowing
 GALT

⬧ DSME Co.,Ltd. 3614 ATWOOD DRILL SHIP Chemical Cleaning & Oil Flushing Construction
 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)
 Pig Cleaning

⬧ DSME Co.,Ltd. 3613 TRANS OCEN DRILL SHIP


 Chemical Cleaning(pickling):
 Oil Flushing- Water Flushing.
 Air Blowing (5~7 kg/m2)

⬧ Hyundai Heavy Industries Co.,Ltd KISOMBA-A FPSO


 Chemical Cleaning & Oil Flushing construction

⬧ Hyundai Heavy Industries Co.,Ltd HUIZHOU PJT


 Chemical Cleaning construction

⬧ Hyundai Heavy Industries Co.,Ltd ON-BOARD


 Sus Pipe Passiivation construction

⬧ Hyundai Heavy Industries Co.,Ltd SAKHALIN DC-1


 Chemical Cleaning & Oil Flushing construction

⬧ Hyundai Heavy Industries Co.,Ltd KIZOMBA-B FPSO


 Chemical Cleaning & Oil Flushing construction

⬧ POSCO Co.,Ltd #2 Equipment Corporation


 Chemical Cleaning & Oil Flushing construction

⬧ SAMSUNG Heavy Industries Co.,Ltd. Ship 7045 WEST E-DRILL


 Chemical Cleaning & Oil Flushing construction

⬧ SAMSUNG Heavy Industries Co.,Ltd. Ship 7056 WEST EMINANCE


 Chemical Cleaning & Oil Flushing Construction
This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
⬧ SAMSUNG Heavy Industries Co.,Ltd. Ship 7062 PRIDE DRILL SHIP
 Chemical Cleaning & Oil Flushing Construction

⬧ Kunsan Combined Cycle Power Plant


 HRSG Chemical Cleaning Construction

This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
CANDIDATE DETAILS:

NAME: Geun Bong SONG

POSITION: Supervisor

DATE OF BIRTH: May 9th 1973

NATIONALITY: KOREAN

SUMMARY

⬧ Supervisor of FNC in Korea at present


⬧ Flushing Supervisor with 18years experience in on boarding Fuel Oil and Gas, Lubricating Oil, Compressor System
etc.

QUALIFICATION

EDUCATION

⬧ Bachelor’s degree of Mechanical Engineering in Daegu University in Koea

WORK EXPERIENCE

2014 – Present

Supervisor of Operations –oil flushing and Chemical cleaning

⬧ Participate projects

⬧ Maersk Line PC ships (Series 9) Oil Flushing, Chemical cleaning, SUS Passivation In Samsung Heavy
Industries Ningbo, China
⬧ GS Caltex Daesan Petrochemical Complex
⬧ Hyundai Engineering Uzbekistan UGCC Gas Chemical Complex
⬧ Daelim Manjung #5, Malaysia TNB Fast Track A3 Power Plant
⬧ Hyundai Engineering Uzbekistan UGCC Gas Chemical Complex
This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
⬧ Posco E&C Colon, Panama LNG Combined Cycle Power Plant
⬧ Daewoo E&C Pocheon Power Plant
⬧ SAMSUNG CNT Co.,Ltd. Qurayyah Independent Power Project Power Plant (12Unit)
⬧ SAMSUNG CNT Co.,Ltd. U.A.E RUWAIS S2 Thermal Power Plant

⬧ Daewoo Shipbuilding & Marine Engineering Inpex Ichthys FPSO
⬧ DSME Co.,Ltd. Total E&P Angola CLOV FPSO Project

⬧ Scope of work
⬧ On-site Supervisor
⬧ Adjust manpower Supply And Demand Plan
⬧ Equipment And Materials Management
⬧ Chemical Cleaning And Oil Flushing, Water Jet to Carry Out Inspection

2006 – 2016

⬧ Scope of work
⬧ Check the Field Pipe Lines (PKG)
⬧ Calculate The BM(Bill Of Materials)
⬧ Chemical Cleaning And Oil Flushing, Water Jet to Carry Out Inspection

⬧ DSME Co.,Ltd. Total E&P Angola PAZFLOR FPSO Project


 Chemical Cleaning(pickling): Fuel Oil, Riser Tension, Drilling Hydraulic Power, BOP Control,
 Well Test Equipment System.
 Oil Flushing: Riser Tension, Drilling Hydraulic Power, BOP Control System.
 Water Flushing: Riser Tension, HP Mud & Cement, Choke & Kill, HP Manifold, Fresh Cooling
 Water, Well Test Equipment, Portable Water System.
 Air Blowing (5~7 kg/m2): Fuel Oil, Inergen, Bulk Air, Chilled Water, Compressed Air System, etc.

This information is provided on the understanding that the contents are confidential.
No references or contacts shall be taken without prior permission from FnC.
Equipment Specifications

F&C
Cleaning Engineering Co.,Ltd

发恩思(烟台)清洗工程有限公司
EQUIPMENT: OIL & CHEMICAL FLUSHING

Oil Flushing Unit

PUMP TYPE SCREW

VOLUME 2000LPM

HEATER 40KW X 3EA

FILTER ELEMENT 3㎛ + 1㎛
Country of
KOREA
Manufacture

Laser Particle Counter (STAUFF)


ISO 4406
Analysis range NAS 1638
SAE 4059
Operating
2 bar ~ 400bar
pressure
Fluid
temperature 5.0℃ ~ 80℃
range
Country of
Germany
Manufacture

Page 6
Tool, Consumable, Material and Equipment List
GT & GTD Oil Cooler Line Oil Flushing Execution Services IN CHINA FAB. YARDS FNC
>> Tool and Consumable List:

NO. Item Description (General) Quantity Unit Specification Remark

1 Pipe Wrench 250mm EA 6

2 Pipe Wrench 350mm EA 6

3 Adjustable Spanner 150mm EA 6

4 Adjustable Spanner 250mm EA 6

5 Adjustable Spanner 450mm EA 6

6 Spanner 10mm EA 5

7 Spanner 13mm EA 5

8 Spanner 17mm EA 5

9 Spanner 19mm EA 5
Tools &
Consumable
10 Spanner 21mm EA 5

11 Spanner 24mm EA 5

12 Spanner 27mm EA 5

13 Spanner 30mm EA 5

14 Spanner 32mm EA 5

15 Spanner 36mm EA 5

16 Spanner 42mm EA 5

17 Ratchet Wrench 17x19 EA 5

18 Ratchet Wrench 22x24 EA 5

www.fnceng.com
GT & GTD Oil Cooler Line Oil Flushing Execution Services IN CHINA FAB. YARDS FNC
>> Tool and Consumable List:

NO. Item Description (General) Quantity Unit Specification Remark

19 Ratchet Wrench 22x24 EA 5

20 Ratchet Wrench 24x27 EA 5

21 Ratchet Wrench 30x32 EA 5

22 Ratchet Wrench 32x36 EA 5

23 Ratchet Wrench 36x41 EA 5

24 Ratchet Wrench 41x46 EA 5

25 L Wrench set inch SET 1

26 Socket Wrench Set 1/2" 24pcs SET 1

27 Lever Block 1 Ton EA 2


Tools &
Consumable
28 Lever Block 2 Ton EA 2

29 Chain Block 1 Ton EA 2

30 Chain Block 2 Ton EA 2

31 Sling Belt 50mm x 2M EA 2

32 Sling Belt 50mm x 5M EA 2

33 Driver(+) 6mm x 38mm EA 1

34 Driver(+) 6mm x 150mm EA 1

35 Driver(+) 6mm x 200mm EA 1

36 Driver(-) 6mm x 150mm EA 1

www.fnceng.com
GT & GTD Oil Cooler Line Oil Flushing Execution Services IN CHINA FAB. YARDS FNC
>> Tool and Consumable List:

NO. Item Description (General) Quantity Unit Specification Remark

37 Driver(-) 6mm x 200mm EA 1

38 Teflon seal Tape BOX 4

39 Walkie-Talkie EA 8

40 Cotton Gloves EA 300

41 Rubber Coated Gloves EA 300

42 Face Protector EA 2

43 Respirator (Safety Gas Mask) EA 10

44 Respirator filter EA 5

45 Safety Helmet EA 15
Tools &
Consumable
46 Rope 100m EA 2

47 Spill Kit EA 2

48 Spill Trays EA 2

49 Bag Filter 1micron EA 10

50 Fine Filter 3micron EA 3

51 Rag KG 250

52 Whip check 1", 3”" EA 50

53 Cable Tie 400mm EA 100

54 Plastic Basket EA 3

www.fnceng.com
GT & GTD Oil Cooler Line Oil Flushing Execution Services IN CHINA FAB. YARDS FNC
>> Tool and Consumable List:

NO. Item Description (General) Quantity Unit Specification Remark

55 Tool Box EA 1

56 Absorbent sheet 30cm x 30cm EA 100

57 Air Gun with quick connection EA 2

58 Air Hoses flexible 1/2" with quick connectors 30m EA 1

59 Plastic sheet 1.8m x 50m EA 2

60 White Cloth KG 100

61 Warning tapes/signs EA 10

62 Fire extinguishers EA 4

63 Tag EA 200
Tools &
Consumable
64 Oil sampling bottles EA 10

65 PVC tarpaulin 5x5, 7x7, 10x10 EA 2

www.fnceng.com
GT & GTD Oil Cooler Line Oil Flushing Execution Services IN CHINA FAB. YARDS FNC
>> Materials List:

NO. Item Description (General) Quantity Unit Specification Remark

1 Fitting, Temporary Spool, spades, blind 1 Lot Stainless Steel

2 Butterfly Valve 10kg/cm2 12 EA 3"

3 Ball Valve 10kg/cm2 100 EA 1",2"

4 Stainless Steel Nipple (Hose Type) 20 EA 1"

5 Steinless Steel Nipple (Valve Type) 20 EA 1"


Korea
6 High Pre. Rubber Hose 40kg/cm2 200 M 3"
Korea
7 High Pre. Rubber Hose 100kg/cm2 400 M 1"

8 100Mesh Screen 20 EA

9 Non- Asbestos Gasket 50 EA Korea


Materials
10 Butterfly V/V Bolt/Nut (50A~250A) 200 set Korea

11 Bolt/Nut (50A~100A) 200 set Korea

12 Waste oil Drum 4 EA

13 Temporary pipe tools & Consumables 1 set Unit

14

15

16

17

18

www.fnceng.com
GT & GTD Oil Cooler Line Oil Flushing Execution Services IN CHINA FAB. YARDS FNC
>> Equipments List:

NO. Item Description (General) Quantity Unit Specification Remark

1 Oil Flushing Unit (Dual 3micron Filter, Tank, Heater To Include) 1 Set 2000LPM Line Cleaning

2 Diaphragm Pump 1 EA 1" Oil Filling

3 Portable Ultra-Sonic Flow Meter 1 EA

4 particle counter 1 EA

5 Container Office (site) 1 EA 20FT

Equipment 6

10

11

www.fnceng.com
GT & TGD Oil Cooler Line FLUSHING SCHEDULE

Pre - Commissioning Execution


Procedure Clarification, Execution Preparation Final Document Submission

Key Event
Execution start Execution Finish

Schedule
D-6 D-5 D-4 D-3 D-2 D-1 D D+1 D+2 D+3 D+4 D+5 D+6 D+7 D+8 D+9 D+10 D+11 D+12 D+13 D+14 D+15

Equipment Pump Area 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Equipment Setup

Temporary Hose installation

Air Leak test

Loo1 Oil Flushing/Inpection

Loo2 Oil Flushing/Inpection

Oil Flushing Loo3 Oil Flushing/Inpection

Reinstallation & Move to Equipment

Temporary Hose installation

Air Leak test

Loo4 Oil Flushing/Inpection

Reinstallation/ withdrew
OIL FLUSHING REPORT
GCGV M135
(FE-FAN01LO, FF-FAN01LO Lube Oil Flushing)
FOR REFERENCE ONLY
PROJECT NAME GCGV M135 REPORT No. 20-OF-M-005

F-169 YOSEMITE FURNACE


OWNER GCGV SYSTEM
I.D Fan

CONTRACTOR SNC-Lavalin START DATE 2020-11-16

SUBCONTRACTOR FNC END DATE 2020-11-21

F&C
Cleaning Engineering Co.,Ltd

发恩思(烟台)清洗工程有限公司
Contents

1. Log Sheet(1~5)

2. Flushing Boundary (CVI)

3. Certificate (1~7)

4. Progress Photos(1~7)

5. Sign-Off Sheet
- Loop1, Loop2, Loop3, Loop4

Sample document
Reference Only
1. Log Sheet

LOG SHEET

Sample document
Reference Only
1. Log Sheet

Log Sheet (1)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO
Pressure(kg/cm2)
Progress Time Temp(℃) Work
Discharge Return
16.Nov.2020
Filter Change 7:00 1 micron
Oil Heating 7:15 25

Pump Start 7:30 32 4 1 All Line Circulation

8:00 52 4 1 Circulation

10:00 64 4 1 All Return Line Open

11:00 69 4 1 Valve Control 2"

12:00 67 4 1 All Line Circulation

13:00 68 4 1 "

14:00 64 4 1 "

15:00 66 7 1 Valve Control 2"

16:00 62 7 1 “

17:00 68 4 1 "

18:00 64 4 1 "

19:00 65 4 1 "

20:00 65 7 1 Valve Control 2"

21:00 66 4 1 "

22:00 62 4 1 "

23:00 63 7 1 “

17.Nov.2020 0:00 65 4 1 "

1:00 62 4 1 "

2:00 66 4 1 "

3:00 67 4 1 "

4:00 64 4 1 "

Sample document
Reference Only
1. Log Sheet

Log Sheet (2)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO

Pressure(kg/cm2)
Progress Time Temp(℃) Work
Discharge Return
17.Nov.2020 5:00 66 7 1 "
6:00 66 4 1 "

7:00 66 4 1 "

8:00 64 4 1 "

9:00 67 7 1 ½”, 1” Valve Control

10:00 68 7 1 "

11:00 65 7 1 "

12:00 64 7 1 "
Valve Change & Control
LOOP 1 13:00 68 7 1
LOOP1 (R1, R2, R6)
Flow Check
14:00 67 7 1
R1 (2") : 1.72
15:00 66 7 1 Circulation without Mesh

16:00 63 5 1 "

17:00 66 5 1 "

18:00 65 5 1 "

19:00 63 5 1 "

20:00 67 5 1 "

21:00 62 5 1 "

22:00 65 5 1 "

23:00 67 5 1 "
Pump Stop
Pump Stop 0:00 64 5 1 RT INSPECTION ON SITE
(0:00 am - 6:00 am)
Pump Start
18.Nov.2020 6:00 38 5 1
Circulation without Mesh
7:00 65 5 1 "

8:00 68 5 1 "

Sample document
Reference Only
1. Log Sheet

Log Sheet (3)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO
Pressure(kg/cm2)
Progress Time Temp(℃) Work
Discharge Return
18.Nov.2020 9:00 64 5 1 "
10:00 65 5 1 "
11:00 62 5 1 "
12:00 63 5 1 100 Mesh Screen Insert

13:00 67 5 1 Circulation

14:00 67 5 1 "

15:00 65 5 1 "
LOOP1 Inspection
16:00 63 5 1 Pass: R1, R2, R6
LOOP 2 Start (R3, R7, R10)
LOOP 2 17:00 65 5 1 Circulation without Mesh

18:00 68 5 1 “

19:00 65 5 1 “

20:00 65 5 1 “

21:00 64 5 1 “

22:00 63 5 1 “

23:00 66 5 1 “
Pump Stop
19.Nov.2020 0:00 63 5 1 RT INSPECTION ON SITE
(0:00 am - 6:00 am)
6:00 35 5 1 Circulation without Mesh

7:00 65 5 1 “

8:00 63 5 1 “

9:00 66 5 1 “

10:00 62 5 1 “

11:00 68 5 1 “

12:00 63 5 1 100 Mesh Screen Insert

Sample document
Reference Only
1. Log Sheet

Log Sheet (4)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO
Pressure(kg/cm2)
Progress Time Temp(℃) Work
Discharge Return
19.Nov.2020 14:00 65 5 1 Circulation
15:00 64 5 1 “
LOOP2 Inspection
16:00 70 7 1 Pass: R3, R7, R10
LOOP 3 Start (R4, R8)
LOOP 3 17:00 64 7 1 Circulation without Mesh

18:00 68 7 1 “

19:00 67 7 1 “

20:00 65 7 1 “

21:00 63 7 1 “

22:00 65 7 1 “

23:00 63 7 1 “
Pump Stop
20.Nov:2020 0:00 64 7 1 RT INSPECTION ON SITE
(0:00 am - 6:00 am)
6:00 38 7 1 Circulation without Mesh

7:00 59 7 1 “

8:00 66 7 1 “

9:00 70 7 1 “

10:00 64 7 1 “

11:00 65 7 1 “

12:00 64 7 1 100 Mesh Screen Insert

13:00 66 7 1 Circulation

14:00 68 7 1 “

15:00 63 7 1 “
LOOP3 Inspection
16:00 65 7 1
Pass:R4, R8
LOOP 4 17:00 68 7 1 Circulation without Mesh

Sample document
Reference Only
1. Log Sheet

Log Sheet (5)


Project. : GCGV M135
Progress : FG-FN01LO, FH-FAN01LO

Pressure(kg/cm2)
Progress Time Temp(℃) Work
Discharge Return

20.Nov:2020
19:00 66 7 7 Circulation without Mesh
LOOP 4

20:00 65 7 7 "
21:00 65 7 7 "
22:00 67 7 7 "
23:00 65 7 7 "
21.Nov:2020 0:00 68 7 7 "
1:00 65 7 7 "
2:00 67 7 7 "
3:00 66 7 7 "
4:00 63 7 7 "
5:00 63 7 7 "
6:00 65 7 7 "
7:00 67 7 7 "
8:00 65 7 7 "
9:00 67 7 7 "
10:00 65 7 7 "
11:00 63 7 7 "

100 Mesh Screen Insert


12:00 67 7 7
LOOP 4

13:00 68 7 7 Circulation
14:00 64 7 7 "
15:00 65 7 7 "

LOOP4 Inspection
16:00 69 7 7
Pass: R5,R9,R8 (Loop3)

16:30 Pump Stop


17:00 Oil Drain

Sample document
Reference Only
2. Flushing Boundary (CVI)

FG-FAN01, FF-FAN01 CVI

Sample document
Reference Only
2. Flushing Boundary (CVI)

Sample document
Reference Only
2. Flushing Boundary (P&ID) & CVI

Sample document
Reference Only
3. Certificate

CERTIFICATE

Sample document
Reference Only
3. Certificate

Prsssure Gauge (-1 ~15KGf/Cm2)


Project. : GCGV M135
Progress : FE-FAN01LO, FF-FAN01LO

Sample document
Reference Only
3. Certificate

Prsssure Gauge (-1 ~15KGf/Cm2)


Project. : GCGV M135
Progress : FE-FAN01LO, FF-FAN01LO

Sample document
Reference Only
3. Certificate

PSV : 50Ax50A (25.5Kgf/cm2)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO

Sample document
Reference Only
3. Certificate

Ultrasonic Flow Meter (GE Panametrics PT878)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO

Sample document
Reference Only
3. Certificate

Pressure Gauge (0~25Kgf/Cm2)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO

Sample document
Reference Only
3. Certificate

Pressure Gauge (0~25Kgf/Cm2)


Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO

Sample document
Reference Only
4. Progress Photos

PROGRESS PHOTOS

Sample document
Reference Only
4. Progress Photos

Photo (1)
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Move Equipment & Materials Plastic foundation

Install the scaffolding Install the covering


on the oil flushing area on the oil flushing area

Sample document
Reference Only
4. Progress Photos

Photo (2)
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Flushing pipe disassembly complete Movning the flusing pipe to area

Flushing Pipe Interconnection Flushing Pipe Interconnection

Sample document
Reference Only
4. Progress Photos

Photo (3)
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Flushing Pipe Interconnection Flushing Pipe Interconnection

Air Blowing Air Blowing

Sample document
Reference Only
4 Progress Photos

Photo (4)
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Flushing Pipe Air leak Test Bag Filter Change

Pipe Hammering Pipe Hammering

Sample document
Reference Only
4. Progress Photos

Photo (5)
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Supply Pressure Bag Filter Housing Pressure

Oil Temperature Mesh Inspection

Sample document
Reference Only
4. Progress Photos

Photo (6)
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Mesh Inspection Flow Rate Check (2”)

Flow Rate Check (2”) Pipe Masking on Blind Flange

Sample document
Reference Only
4. Progress Photos

Photo (7)
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Pipe Masking on vinyl Sheet Pipe masking complete

Pipe masking complete Pipe masking complete

Sample document
Reference Only
5.Sign-Off Sheet

SIGN-OFF SHEET

Sample document
Reference Only
Mesh Screen Detail

Loop 1
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Mesh Screen R1 Mesh Screen R2

Mesh Screen R6

www.mydus.com.cn
Sample document
Reference Only
Mesh Screen Detail

Loop 2
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Mesh Screen R10 Mesh Screen R3

Mesh Screen R7

www.mydus.com.cn
Sample document
Reference Only
Mesh Screen Detail

Loop 3
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Mesh Screen R4 Mesh Screen R8

www.mydus.com.cn
Sample document
Reference Only
Mesh Screen Detail

Loop 4
Project. : GCGV M135
Progress : FG-FAN01LO, FH-FAN01LO Oil Flushing

Mesh Screen R5 Mesh Screen R9

Sample document
Reference Only