Sr No BU Name of the Project Idea Owener

1 APH Gate Assy - Partician Bin implementation Anbu.S

Isuzu - Early Warranty two Tranmission Received from Customer -


2 APH Anbu.S
Replace the defect part and resell the resold unit

3 APH AL-Dust Cover -Sheet metal that is being replaced by plastic Prabhu.R

4 APH Q-Box - Outsorcing the Machining Process Anbu.S


Project Leader Team Members IL1 IL2 IL3 IL4 IL5

Raja.M Srinivasan

Raja.M Prabhu,Sugumar,Srinivsan, Sathish

Prabhu.R,Anbu.S,Srinivasan,Rajend
Raja.M
er Kumar- R& D,Sathis, Kumaravel

Raja.M ME team
Planned savings in Planned savings in Planned savings in Planned savings in
Status as on date
Q1 (INR) Q2 (INR) Q3 (INR) Q4 (INR)
Total saving
Saving in Q1 completed as on Bucket