Download as rtf, pdf, or txt
Download as rtf, pdf, or txt
You are on page 1of 11

Page 1

HGCRA 1996 payment provisions—key cases

This Practice Note lists key cases concerning the construction contract payment provisions of the Housing
Grants, Construction and Regeneration Act 1996 (HGCRA 1996) as amended by the Local Democracy,
Economic Development and Construction Act 2009.
For further guidance, see Practice Notes: Payment in construction contracts under the HGCRA 1996 and
Summary of payment provisions in the HGCRA 1996. In relation to interim payments, see also Practice Note:
Interim payments in construction contracts.
CAUTION: From December 2014 (when judgment was handed down in ISG v Seevic) up until February
2018 (when judgment was handed down by the Technology and Construction Court (TCC) in Grove v S&T),
payment cases proceeded on the basis that, where a paying party failed to give a payment or pay less notice
in relation to an interim payment, it was deemed to have agreed to the amount stated in the payee’s payment
application/default payment notice. Accordingly, in relation to the relevant interim payment, the paying party
could not then challenge the ‘true value’ of the works in adjudication (or otherwise). Following Grove v S&T,
which has since been confirmed on appeal, this is no longer good law.

References:
ISG Construction v Seevic College [2014] EWHC 4007 (TCC), 157 ConLR 107
Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC), 177 ConLR 30
S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448, 181 ConLR 66
Cases relating to pay less notices may also be relevant to payees’ payment applications/payment notices,
and vice versa. In Grove v S&T, the TCC did not think that the courts should generally adopt a different
approach to the construction of the two different kinds of notices, but did note that the particularly adverse
consequences for a paying party that follow from a payee's unanswered payment application/payment notice
would be relevant to the test of the reasonable recipient.

References:
Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC), 177 ConLR 30 at para [27]

2019
Everwarm v BN Rendering
Topic: Corrective payment clauses
Date of judgment: 18 November 2019
Decision: The TCC held that a term in a sub-contract entitling the main contractor to carry out its own
assessments of the value of the works and recover any overpayments from the sub-contractor did not offend
the HGCRA 1996 nor was it unenforceable by reason of UCTA 1977. However, certain terms concerning the
timing and carrying out of the assessments were implied, as were provisions of the Scheme for Construction
Contracts in relation to notices.
Comment: A particular benefit for the paying party of including such a provision is that, if it fails to give a
valid payment notice or pay less notice in respect of an interim payment, it is able to recover any
overpayment made without having to wait for the final account process or commence a ‘true value’
adjudication.
See News Analysis: Court upholds corrective payment clause (Everwarm v BN Rendering).

References:
Everwarm Ltd v BN Rendering Ltd [2019] EWHC 3060 (TCC), 187 ConLR 240
Page 2

C Spencer v MW High Tech Projects


Topic: Payment notices/hybrid contracts
Date of judgment: 2 October 2019
Decision: The TCC held that, where a hybrid contract contained an HGCRA 1996-compliant payment
scheme which applied to both construction and non-construction operations, it was not necessary for a
payment notice to separately identify the sums due in respect of construction operations
Comment: This can be contrasted with the position where a contract contains separate payment
mechanisms in respect of construction and non-construction operations, in which case the payment notice
must separately identify the sums due in respect of construction operations (per Severfield v Duro Felguera
below).
See News Analysis: Payment notices under hybrid contracts (C Spencer v MW High Tech Projects).

References:
C Spencer Ltd v MW High Tech Projects UK Ltd [2019] EWHC 2547 (TCC), 186 ConLR 117

M Davenport v Greer
Topic: Adjudication as to true value of the works
Date of judgment: 20 February 2019
Decision: The TCC held that an employer was prohibited from using a ‘true value’ adjudication decision as a
defence or set-off to enforcement proceedings for an earlier adjudication decision in favour of the contractor
(regarding a lack of pay less notice in response to the final account application). This was because the
employer had not made payment of the earlier adjudication award before commencing its true value
adjudication.
Comment: This case follows in the footsteps of the Court of Appeal’s decision in S&T v Grove.
See News Analysis: Employer could not rely on true value adjudication (M Davenport v Greer).

References:
M Davenport Builders Ltd v Greer & another [2019] EWHC 318 (TCC)

2018
S&T v Grove
Topic: Adjudication as to true value of works/pay less notices
Date of judgment: 7 November 2018
Decision: The Court of Appeal upheld the decision of the TCC, confirming that an employer was able to
challenge, by way of further adjudication, the amount due to a contractor in respect of an interim application,
by reference to the true value of the works—even if the employer had not given a valid payment notice or pay
less notice. However, the Court of Appeal confirmed that it can only do this if it has paid the ‘notified sum’.
The court also upheld the TCC’s findings that a pay less notice was valid, even though it specified the basis
of calculation by reference to an earlier document.
Comment: The ruling confirms that, where a paying party fails to give a valid payment or pay less notice, it is
required to pay the amount in the payee’s application (ie the ‘notified sum’), but if (and only if) it has paid this
amount, it is then able to refer a dispute to adjudication as to the true value of the works.
See News Analysis: Court of Appeal confirms right to adjudicate true value of the works in absence of
payment/pay less notice (S&T v Grove Developments).

References:
S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448, 181 ConLR 66

ICI v Merit Merrell


Topic: Overpayments
Page 3

Date of judgment: 21 June 2018


Decision: In determining the final value of the works following termination, the TCC noted that the burden of
proof was on the employer to show that the contractor had been overpaid following adjudication decisions in
the contractor’s favour. It did not matter that the contractor had been successful in the adjudications merely
due to the employer’s failure to give pay less notices (ie the adjudicator had not determined the value of the
works).
Comment: The court rarely likes to decide issues on the burden of proof. It was also the first reported
judgment in which the TCC referred to the ruling in Grove v S&T, with Fraser J citing extensively from the
judgment.
See News Analysis: Court assesses quantum following repudiatory breach of contract (ICI v Merit Merrell).

References:
Imperial Chemical Industries Ltd v Merit  Merrell Technology Ltd [2018] EWHC 1577 (TCC), 178 ConLR 89

Re A Company (No 008654 of 2017)


Topic: Winding-up proceedings
Date of judgment: 18 April 2018
Decision: The Chancery Division struck out a contractor’s winding-up petition, brought following the
employer’s failure to pay the amount stated in the contractor’s interim payment application (in circumstances
where no pay less notice was given). In the court’s view, the employer had a genuine cross-claim, due to a
subsequent adjudication decision which had determined the true value of the works.
Comment: It had previously been established that, even though a valid application for payment which has
not been the subject of a pay less notice creates an immediately enforceable debt, a winding-up petition
based on the failure to pay is likely to be stopped where a genuine cross-claim exists—the present case
reinforced this position following Grove v S&T.
See News Analysis: Court strikes out winding-up petition, in light of true value of the works (Re A Company
(No 008654 of 2017)).

References:
Re A Company (No 008654 of 2017) [2018] EWHC 1143 (Ch), [2018] All ER (D) 111 (May)

Grove v S&T
Topic: Adjudication as to true value of works/pay less notices
Date of judgment: 27 February 2018
Decision: The TCC held that an employer was able to challenge by way of further adjudication the amount
due to a contractor in respect of an interim application, by reference to the true value of the works—even if
the employer had not given a valid payment or pay less notice. In the court’s view, this conclusion was
supported by first principles and Court of Appeal authorities, and it described analysis in the earlier TCC
decisions of ISG v Seevic and Galliford Try v Estura as ‘erroneous and/or incomplete’. The court also held
that a pay less notice was valid even though it specified the basis of calculation by reference to an earlier
document.
Comment: The decision has since been upheld by the Court of Appeal (see above).
See News Analyses: Failure to give a payment or pay less notice—a change of approach (Grove
Developments v S&T) and Uncertainties after Grove v S&T.

References:
Grove Developments Ltd v S&T (UK) Ltd [2018] EWHC 123 (TCC), 177 ConLR 30

2017
Adam Architecture v Halsbury Homes
Page 4

Topic: Final payments/pay less notices


Date of judgment: 2 November 2017
Decision: The Court of Appeal held that HGCRA 1996, s 111, which requires the paying party under a
construction contract to pay the ‘notified sum’ unless it gives a pay less notice, applies to applications for final
payment.
Comment: The decision confirms the position as it had been generally understood, ie that HGCRA 1996, s
111 applies to both interim and final payment applications. Final payment applications include those for
payment on completion of the works and those following termination.
See News Analysis: Pay less notices required for both interim and final payment applications (Adam
Architecture v Halsbury Homes).

References:
Adam Architecture Ltd v Halsbury Homes Ltd [2017] EWCA Civ 1735, 175 ConLR 1

Muir Construction v Kapital


Topic: Pay less notices
Date of judgment: 18 October 2017
Decision: The Scottish Court of Session, Outer House found that a pay less notice was invalid, as there was
no means for a reasonable recipient of the pay less notice to make any sense of how the zero amount had
been arrived at (the employer had not provided any calculation or even any figures).
Comment: HGCRA 1996, s 111(4) requires a pay less notice to state the sum that the payer considers to be
due and the basis on which the sum is calculated.
See News Analysis: Employer not entitled to withhold sums on housebuilding project (Muir Construction v
Kapital).

References:
Muir Construction Ltd v Kapital Residential Ltd [2017] CSOH 132

Kersfield v Bray
Topic: Payment applications (default payment notices)
Date of judgment: 18 January 2017
Decision: The TCC held that a lack of substantiation did not affect the validity of an interim payment
application, that the contractor remained entitled to the amount in its payment application even though in
correspondence it had sought payment of the sum acknowledged as due by the employer, and that deemed
date of delivery provisions in the contract were not incompatible with the payment provisions of the HGCRA
1996.
Comment: To be valid, a payment application must set out the amount claimed and the basis on which it is
due. Provided these criteria are met, a failure to provide sufficient substantiation of the amounts claimed will
not affect the validity of the application (unless the contract expressly states that it will).
See News Analysis: Interim payment—substantiation requirements and deemed delivery provisions
(Kersfield v Bray).

References:
Kersfield Developments (Bridge Road) Ltd v Bray and Slaughter Ltd [2017] EWHC 15 (TCC), 170 ConLR 40

Trilogy v Windsor
Topic: Default payment notices
Date of judgment: 17 January 2017
Decision: The Scottish Sheriff Appeal Court held that a letter from a contractor’s solicitor to its employer,
attaching an invoice sent previously by the contractor, amounted to a valid default payment notice. It rejected
Page 5

the employer’s argument that it had been necessary for the contractor to demonstrate its intention to give
such a notice—the court thought that the contractor’s intention was clear from the factual context.
CAUTION: The outcome of this case on its facts is surprising, as the contractor's intention appeared to be to
chase an unpaid invoice rather than give a payment notice. It remains to be seen whether it would be
followed by an English court in similar circumstances.
See News Analysis: Letter from solicitor was valid default payment notice (Trilogy v Windsor).

References:
Trilogy Services Scotland Limited v Windsor Residential [2017] SAC (Civ) 2

Surrey and Sussex v Logan


Topic: Default payment notices/pay less notices
Date of judgment: 13 January 2017
Decision: The TCC declared that a contractor’s default payment notice was valid, even though it was not
referred to in a covering email (sent in advance of a meeting about the final account). The court also
declared that a valid pay less notice had been given on behalf of the employer, even though it was
‘contingent’ (the sender’s primary position was that the default payment notice was not valid).
Comment: The sender of a statutory notice must have the requisite intention when giving such a notice, and
this case confirms that the intention is to be assessed from the manner in which the notice would have
informed the reasonable recipient.
See News Analysis: Default payment notice and pay less notice were valid (Surrey and Sussex NHS Trust v
Logan).

References:
Surrey and Sussex Healthcare NHS Trust v Logan Construction (South East) Ltd [2017] EWHC 17 (TCC),
170 ConLR 65

2016
Universal Piling & Construction v VG Clements
Topic: Payment applications (default payment notices)
Date of judgment: 1 November 2016
Decision: The TCC found that, under the NEC short form contract, there was an obligation on the sub-
contractor to assess the amounts due and issue an application for payment by each assessment date.
Comment: A payee is unable to ‘lock in’ an amount due to it (following the paying party’s failure to give the
required notices) by declining to make any further payment applications if doing so would put it in breach of
its contractual obligations.
See News Analysis: Multiple adjudication decisions and the NEC short form contract (Universal Piling &
Construction v VG Clements).

References:
Universal Piling & Construction v VG Clements [2016] EWHC 3321 (TCC)

Cosmur v St Lewis
Topic: Winding-up proceedings
Date of judgment: 27 October 2016
Decision: The Companies Court granted an injunction to restrain the presentation of a winding-up petition
following a statutory demand for the amount in a sub-contractor’s final account, where the contractor had not
given a pay less notice in time. There was a real question over whether the sub-contractor was entitled to
serve its final account (and also whether an earlier interim payment application had been made at the correct
time).
Page 6

Comment: An injunction to restrain a winding-up petition will likely be granted if there is uncertainty around
whether the payment application was valid. Even if the payment application is valid and the paying party has
failed to give a pay less notice, an injunction may nonetheless be granted where the paying party has a
genuine cross claim that exceeds the amount of the debt.
See News Analysis: Injunction to restrain winding up petition for non-payment (Cosmur v St Lewis).

References:
Cosmur Construction (London) Ltd v St Lewis Design Ltd [2016] EWHC 2678 (Ch), [2016] All ER (D) 64
(Nov)

Kilker v Purton
Topic: Final payments/adjudication as to true value of the works
Date of judgment: 14 October 2016
Decision: The TCC held that a party can adjudicate the valuation of a final payment even though there is no
payment notice or pay less notice, and that there is a difference between final payment (where such an
adjudication is permitted) and interim payments (where it is not).
CAUTION: The distinction between interim and final payments no longer appears to be valid following Grove
v S&T (see 2018 above).
See News Analysis: Adjudication and final payment valuations (Kilker Projects Ltd v Purton).

References:
Kilker Projects Ltd v Purton [2016] EWHC 2616 (TCC), [2016] All ER (D) 130 (Oct)

Balfour Beatty v Grove (CA)


Topic: Entitlement to interim payments
Date of judgment: 13 October 2016
Decision: The Court of Appeal, confirming the earlier decision of the TCC, held that a contractor was not
entitled to interim payments after the final date in a schedule specifying dates in the interim payment process
had elapsed. The court confirmed that there was no express or implied term extending the schedule, and that
the contract was not non-compliant with HGCRA 1996, s 109 simply because the interim payment regime did
not cover the entirety of the works.
Comment: HGCRA 1996, s 109 is broadly drafted and affords employers and contractors considerable
freedom to agree among themselves the frequency and amount of interim payments.
See News Analysis: Court of Appeal confirms no interim payments after schedule expired (Balfour Beatty v
Grove).

References:
Balfour Beatty Regional Construction Ltd v Grove Developments Ltd [2016] EWCA Civ 990, 168 ConLR 1

Volkerlaser v Nottingham
Topic: Payment applications (default payment notices)
Date of judgment: 7 July 2016
Decision: The TCC held that a contractor’s interim payment application notice was not valid as it had not
been made at the end of a month in which a task had commenced or been completed (as required by the
contract).
Comment: The court agreed with and followed the approach of the TCC in Grove Developments v Balfour
Beatty that HGCRA 1996, s 109(1) does not require the contract to provide for interim payments for all of the
work that is to be carried out.
See News Analysis: In brief: no summary judgment for interim payment application (Volkerlaser v Nottingham
CC).
Page 7

References:
Volkerlaser Ltd v Nottingham City Council [2016] EWHC 1501 (TCC), [2016] All ER (D) 123 (Jul)

Bouygues v Febrey
Topic: Non-compliant contracts
Date of judgment: 10 June 2016
Decision: The TCC corrected an obvious error in the parties’ payment schedule, so as to make it compliant
with the HGCRA 1996.
Comment: The court’s approach was to give effect to the contract by amending provisions which were non-
compliant with HGCRA 1996, rather than implying in terms from the Scheme for Construction Contracts. It
can be contrasted with the approach taken in the earlier case of Manor Asset v Demolition Services in which
the court implied a term to ensure compliance (see below).
See News Analysis: In brief: amendment of 'obvious error' in a payment schedule (Bouygues v Febrey).

References:
Bouygues (UK) Ltd v Febrey Structures Ltd [2016] EWHC 1333 (TCC), [2016] All ER (D) 165 (Jun)

COD Hyde v Space Change


Topic: Winding-up proceedings
Date of judgment: 14 April 2016
Decision: The Chancery Division refused to grant an injunction to stop a contractor presenting a winding-up
petition against an employer following service of a statutory demand. The statutory demand was for unpaid
amounts in interim applications in respect of which the employer had not given a valid payment notice or pay
less notice. The fact that the employer disputed the amounts in the interim applications, and that the
contractor was itself in breach, did not change this position.
CAUTION: In light of Re A Company (No 008654 of 2017), Cosmur v St Lewis and Grove v S&T, it appears
unlikely that the same outcome would be reached today.
See News Analysis: In brief—Statutory demands and interim applications (COD Hyde v Space Change).

References:
COD Hyde Limited v Space Change Management Ltd [2016] EWHC 820 (Ch), [2016] All ER (D) 97 (Apr)

Jawaby v Interiors Group


Topic: Payment applications (default payment notices)/pay less notices
Date of judgment: 16 March 2016
Decision: The TCC held that an 'initial assessment' given by a contractor in respect of an interim valuation
did not amount to a valid payment application. The court also concluded (on an obiter basis) that the
employer’s pay less notice was not valid, as it was not intended to be a pay less notice.
Comment: It is an essential requirement that the sender of a contractual notice must have the requisite
intention to serve it. This intention is to be assessed objectively.
See News Analysis: In brief—'initial assessment' not a valid interim payment application (Jawaby v Interiors
Group).

References:
Jawaby Property Investment Ltd v Interiors Group Ltd [2016] EWHC 557 (TCC), [2016] All ER (D) 148 (Mar)

Manor Asset v Demolition Services


Topic: Non-compliant contracts
Date of judgment: 15 February 2016
Page 8

Decision: In circumstances where the parties had amended their contract so badly on payment, with very
short timescales for payment notice and final date for payment, that it was impossible to find any agreement
as to the prescribed period, and the Scheme for Construction Contracts could not be used to fill in the gaps,
the TCC implied a term that a pay less notice could be given at any time immediately up to the final date for
payment (including a nil period).
CAUTION: This decision is likely to be confined to its own facts and it is doubted that it is correct. In the
subsequent case of Bouygues v Febrey (see above), the court did not consider that it was necessary to take
the same approach.
See News Analysis: Adjudication—construction and implication in light of the Scheme (Manor Asset v
Demolition Services).

References:
Manor Asset Ltd v Demolition Services Ltd [2016] EWHC 222 (TCC), [2016] All ER (D) 180 (Feb)

Grove v Balfour Beatty (TCC)


Topic: Entitlement to interim payments
Date of judgment: 3 February 2016
Decision: The TCC held that a contractor was not entitled to apply for interim payment after the latest date in
the payment schedule. It was not possible to construe the contract as including an implied term that interim
payments would continue to be made after the latest date in the schedule.
Comment: This ruling was upheld by the Court of Appeal (see above).
See News Analysis: In brief—no entitlement to make interim application after latest date in payment schedule
(Grove Developments v Balfour Beatty).

References:
Grove Developments Ltd v Balfour Beatty Regional Construction Ltd [2016] EWHC 168 (TCC), 165 ConLR
153

2015
Harding v Paice (CA)
Topic: Final payments/adjudication as to true value of the works
Date of judgment: 1 December 2015
Decision: The Court of Appeal held that (in relation to a final payment) where a party fails to issue a valid
pay less notice and loses an adjudication on that basis, it can start a fresh adjudication on the question of
valuation.
CAUTION: The distinction between interim and final payments no longer appears to be valid following Grove
v S&T (see 2018 above).
See News Analysis: Court of Appeal confirm ability to adjudicate on valuation despite earlier adjudications
(Harding v Paice).

References:
MJ Harding trading as MJ Harding Contractors v Paice [2015] EWCA Civ 1231, 163 ConLR 299

Severfield v Duro Felguera


Topic: Pay less notice
Date of judgment: 24 November 2015
Decision: In relation to a contract that included both construction operations under HGCRA 1996, s 105 and
excluded operations, the TCC held that the contractor could not subsequently alter the amount it had claimed
in its original payment notice to make a new claim under HGCRA 1996.
Page 9

Comment: In relation to hybrid contracts containing separate payment mechanisms for construction and
non-construction operations, any claim for payment in respect of construction operations must be clear that it
is a notice for the purposes of the HGCRA 1996, and it must be clear which works are covered by HGCRA
1996 and which are not.
See News Analysis: Claiming payment in hybrid contracts for construction operations and excluded
operations (Severfield v Duro).

References:
Severfield (UK) Ltd v Duro Felguera UK Ltd [2015] EWHC 3352 (TCC), 163 ConLR 235

Wilson & Sharp v Harbour View


Topic: Winding-up proceedings
Date of judgment: 13 October 2015
Decision: The Court of Appeal confirmed that a winding-up petition should not be used to enforce an interim
payment obligation, where the employer challenges the valuation or has a genuine cross claim.
Comment: Adjudication followed by enforcement in the TCC is the better way to enforce interim payments
than winding-up proceedings.
See News Analysis: Enforcing interim payments—winding-up or TCC?

References:
Wilson & Sharp Investments Ltd v Harbour View Developments Ltd [2015] EWCA Civ 1030, 162 ConLR 154

Henia v Beck
Topic: Pay less notices/payment applications (default payment notices)
Date of judgment: 14 August 2015
Decision: The TCC held that an employer was entitled in its pay less notice to give a different valuation from
that set out in a certificate, and that the pay less notice was not restricted to cross-claims. It also found that
the contractor’s payment application could not be considered to be an interim application in relation to the
due date alleged by the contractor.
Comment: A payment application must be clear in substance, form and intent, stating the amount the
contractor considers is due at the relevant due date and be free from ambiguity.
See News Analysis: In brief—payment, pay less notices and liquidated damages under JCT contracts (Henia
Investments v Beck Interiors).

References:
Henia Investments v Beck Interiors [2015] EWHC 2433 (TCC), 161 ConLR 51

Caledonian v Mar City


Topic: Payment applications (default payment notices)
Date of judgment: 29 June 2015
Decision: The TCC held that documents submitted by the contractor could not constitute
a payment notice as the contractor did not make it clear that it was making a fresh application for an interim
payment.
Comment: The payee must set out its claim with proper clarity and the employer must be given reasonable
notice that the payment period has been triggered.
See News Analysis: Clarity of interim applications (Caledonian v Mar City).

References:
Calendonian Modular v Mar City Developments [2015] EWHC 1855 (TCC), 160 ConLR 42
Page 10

Leeds v Waco
Topic: Payment applications (default payment notices)
Date of judgment: 22 May 2015
Decision: The TCC held that an interim payment application was invalid as it was made a week earlier than
allowed by the contract.
Comment: The employer needs to have some idea when the interim application is to be made so that it has
the necessary resources to be able to respond to it.
See News Analysis: Stick to the timetable—interim payments in construction contracts (Leeds v Waco).

References:
Leeds City Council v Waco UK Ltd [2015] EWHC 1400 (TCC), 160 ConLR 58

Galliford Try v Estura


Topic: Adjudication as to true value of the works
Date of judgment: 27 February 2015
Decision: The TCC confirmed the decision in ISG v Seevic, but emphasised that the employer was only
taken to have agreed to the value of the works in a particular interim application and it did not constitute any
agreement as to the value of the works at some other date. However, the court granted a partial stay on
enforcement of the adjudicator’s decision, to avoid 'manifest injustice' to the employer.
CAUTION: The analysis in this decision regarding the paying party being deemed to agree to the value of
the works is no longer regarded as good law following Grove v S&T (see 2018 above). Further, it appears
that the stay was only necessary as a result of the application of this principle, and therefore the scope for
such stays may have been reduced.
See News Analysis: Blurring the lines of pay now/argue later regime (Galliford Try v Estura).

References:
Galliford Try Building v Estura [2015] EWHC 412 (TCC), 159 ConLR 10

2014
ISG v Seevic
Topic: Adjudication as to true value of the works
Date of judgment: 3 December 2014
Decision: The TCC granted a declaration that a second adjudication was invalid for want of jurisdiction,
where an employer had previously been ordered to pay in full an interim application for payment. The court
held that, if an employer failed to serve a pay less notice in time, it must be taken to be agreeing to the value
stated in the contractor’s application, right or wrong. Accordingly, the employer was not entitled to bring a
second adjudication to determine the true value of the works.
CAUTION: This is no longer regarded as good law following Grove v S&T (see 2018 above).
See News Analysis: Second adjudication fails to rectify the absence of a withholding notice (ISG v Seevic
College).

References:
ISG Construction v Seevic College [2014] EWHC 4007 (TCC), 157 ConLR 107

Harding v Paice (TCC)


Topic: Final payment/adjudication as to true value of the works
Date of judgment: 21 November 2014
Decision: The TCC refused to injunct a second adjudication relating to the true value of a post-termination
account, finding that the first adjudication had not determined what was properly due, but rather had
determined what was immediately payable in the absence of a pay less notice.
Page 11

Comment: This decision was upheld by the Court of Appeal (see 2015 above).
See News Analysis: Injunction restraining adjudication refused where issues were not determined in an
earlier adjudication (Harding v Paice).

References:
Harding (t/a M J Harding Contractors) v Paice [2014] EWHC 3824 (TCC), 157 ConLR 98

You might also like