R/…..

/2019 th Aug 2021

PROPOSED ……

Approximate Estimated Quantities for ………..

Reinforcement
Cast Area Conrete
Sr. No Description of Items Remarks
In Sft. in Cu.m Total
8 mm 10 mm 12 mm 16 mm 20 mm 25 mm 32 mm
in Kgs
1.0 Basement level. 26509.63
i Footings. (M-25) 1179.74 52446.10 - 8,350.81 4,371.84 33,481.38 6,242.07 - -
ii Columns / Shear walls. (M-30) 185.98 59664.37 13,587.93 2,517.93 1,429.51 7,644.96 18,109.63 15,004.63 1,369.78
iii Raft Slab. (M-25) 244.67 12779.80 12,779.80 - - - - - -
iv Raft Beam. (M-25) 25.31 4357.10 1,471.80 - 781.00 2,104.30 - - -
v Retaining wall. (M-30) 395.45 20182.52 4,574.71 6,686.85 8,920.97 - - - -
UGT (Including Top & Bottom slab,
vi 75.59 4542.39 2,245.88 1,849.21 103.95 186.90 156.45 - -
Beam & Pardi).
vii Drain Trench & Pit. (M-25) 31.87 2188.98 1,959.70 229.28 - - - - -
Lift formation pardi & Pardi near
viii 8.17 964.84 217.41 747.42 - - - - -
Footing of C57/C58/C59 (M-25)
Total of basement level. 2146.76 157126.11 36,837.23 20,381.51 15,607.27 43,417.53 24,508.15 15,004.63 1,369.78
2.0 Stilt level. 26017.68
i Columns / Shear walls. (M-30) 184.17 49218.57 12470.00 2265.81 1022.67 6231.96 13793.28 12317.90 1116.94
ii Beam. (M-30) 123.23 16847.06 2639.65 682.91 4291.96 3866.40 1890.50 2838.94 636.70
iii Slab. (M-30) 275.08 18409.52 6202.04 2409.06 2135.31 7,663.11 - - -
Total of Stilt level. 582.48 84475.15 21,311.69 5,357.78 7,449.94 17,761.47 15,683.79 15,156.84 1,753.64
3.0 1st Floor level. 21951.28
i Columns / Shear walls. (M-30) 116.29 33338.08 8449.13 363.77 966.95 5043.04 15289.88 3225.31 0.00
ii Beam. (M-30) 325.37 63065.43 5324.61 1680.99 9040.36 5011.58 5738.10 13336.37 22933.42
iii Slab. (M-30) 252.30 12949.69 9626.95 889.09 2433.65 - - - -
Total of 1st Floor level. 693.96 109353.20 23,400.70 2,933.86 12,440.96 10,054.61 21,027.97 16,561.67 22,933.42
4.0 2nd Floor level. 21248.43
i Columns / Shear walls. (M-30) 107.10 27020.63 7628.73 250.67 1403.84 7079.44 9627.85 1030.09 0.00
ii Beam. (M-30) 208.14 37146.06 6029.62 1847.18 3456.32 4514.72 7518.75 9573.58 4205.88
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 2nd Floor level. 571.33 77889.97 23,901.03 2,676.82 7,761.80 11,594.17 17,146.61 10,603.67 4,205.88
5.0 3rd Floor level. 21248.43
i Columns / Shear walls. (M-30) 106.20 23683.01 7379.98 264.59 2129.73 7615.18 6293.53 0.00 0.00
ii Beam. (M-30) 208.14 37146.06 6029.62 1847.18 3456.32 4514.72 7518.75 9573.58 4205.88
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 3rd Floor level. 570.43 74552.36 23,652.27 2,690.75 8,487.69 12,129.91 13,812.28 9,573.58 4,205.88
6.0 4th Floor level. 21248.43
i Columns / Shear walls. (M-30) 106.20 20420.65 7062.40 338.86 3403.46 6990.15 2625.78 0.00 0.00
ii Beam. (M-30) 208.14 37146.06 6029.62 1847.18 3456.32 4514.72 7518.75 9573.58 4205.88
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 4th Floor level. 570.43 71290.00 23,334.70 2,765.02 9,761.41 11,504.88 10,144.53 9,573.58 4,205.88
7.0 5th Floor level. 21255.92
i Columns / Shear walls. (M-30) 106.20 18243.17 6855.63 371.36 4670.34 5178.84 1167.01 0.00 0.00
ii Beam. (M-30) 208.27 36928.08 6030.57 1847.18 3436.74 4635.92 7356.84 9374.74 4246.10
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 5th Floor level. 570.56 68894.55 23,128.88 2,797.52 11,008.71 9,814.76 8,523.85 9,374.74 4,246.10
8.0 6th Floor level. 21255.92
i Columns / Shear walls. (M-30) 106.20 16163.11 6439.54 552.40 5272.96 3648.15 250.07 0.00 0.00
ii Beam. (M-30) 208.27 36928.08 6030.57 1847.18 3436.74 4635.92 7356.84 9374.74 4246.10
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 6th Floor level. 570.56 66814.48 22,712.78 2,978.55 11,611.33 8,284.07 7,606.91 9,374.74 4,246.10
9.0 7th Floor level. 21255.92
i Columns / Shear walls. (M-30) 106.20 14323.21 5926.91 742.72 5204.48 2449.10 0.00 0.00 0.00
ii Beam. (M-30) 208.27 36928.08 6030.57 1847.18 3436.74 4635.92 7356.84 9374.74 4246.10
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 7th Floor level. 570.56 64974.58 22,200.15 3,168.87 11,542.85 7,085.03 7,356.84 9,374.74 4,246.10
10.0 8th Floor level. 21255.92
i Columns / Shear walls. (M-30) 106.20 13981.14 5792.66 793.78 5149.70 2245.01 0.00 0.00 0.00
ii Beam. (M-30) 208.27 36928.08 6030.57 1847.18 3436.74 4635.92 7356.84 9374.74 4246.10
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 8th Floor level. 570.56 64632.51 22,065.90 3,219.94 11,488.07 6,880.93 7,356.84 9,374.74 4,246.10
11.0 9th Floor level. 21255.92
i Columns / Shear walls. (M-30) 106.20 14992.20 5928.77 793.78 4218.37 3801.21 250.07 0.00 0.00
ii Beam. (M-30) 208.27 36928.08 6030.57 1847.18 3436.74 4635.92 7356.84 9374.74 4246.10
iii Slab. (M-30) 256.09 13723.29 10242.67 578.98 2901.63 - - - -
Total of 9th Floor level. 570.56 65643.57 22,202.01 3,219.94 10,556.74 8,437.13 7,606.91 9,374.74 4,246.10
12.0 Terrace level. 21255.92
i Columns / Shear walls. (M-30) - - - - - - - - -
ii Beam. (M-30) 218.69 38774.49 6332.10 1939.54 3608.58 4867.72 7724.68 9843.48 4458.40
iii Slab. (M-30) 268.90 14409.45 10754.81 607.93 3046.72 - - - -
Total of Terrace level. 487.58 53183.94 17,086.91 2,547.47 6,655.29 4,867.72 7,724.68 9,843.48 4,458.40

Grand Total 265759.38 8475.77 958830.42 ######## 54738.03 ######## ######## ######## ######## 64363.36
Consumption (Cft/Sft. & Kg/Sft.) 1.13 3.61