Al Qooz Contracting LLC

Specialized Civil & Electro-Mechanical Contractors

METHOD STATEMENT DEWATERING

1. Introduction and Scope


This method statement provides the controlled sequences of work, methodology and safety precautions
that will be used to complete the Dewatering works. The content of this method statement reflects the
findings of the relevant risk assessment.

2. Location of Activity
outside of the building.

3. Scope of Work.
The method statement covers all activities related to the Dewatering works.

General Description
The purpose of this Method Statement is to give a general outline of the methodology that will be used
for Dewatering works s at, The WTC to identify the risk associated during the Dewatering works and to
identify the quality control system to ensure full compliance with the client’s requirements and as per
the project specification.

The works shall be executed in accordance with the following methodology and sequence;

1. Procedure

 Clearance shall be obtained from employer’s representative that the work area to proceed and
stating conditions & purpose of access, inclusive of topographical & terrace soil compaction
results, and highlighting all known existing services and hazards.

 Ensure that the instruction / information shall be obtained from employer’s representative when
excavating in the area of existing structures and/or underground facilities (if any), as per the
project site regulations.

 Care shall be taken to prevent dust being nuisance to the public, neighbours and other work at
site during dewatering.

 Care shall be taken to protect all existing structure & utilities during excavation and dewatering
works.

 Barricades shall be placed around all open excavations except where active work requires
opening of such devices and then only such portion of the barricade needed for work access will
be removed.

 Danger sign shall be provided and warning sign shall be written in English/Arabic and/or Hindi,
in day and night.

Best service with full customer satisfaction


P.O.Box 66554, Dubai – U.A.E. E-mail: info@aqc-co.com
Tel: 04-453 45 41 Fax: - 04–453 45 40
Al Qooz Contracting LLC

2.Prerequisites

 All the personnel shall work to the HSC and Area engineer’s instruction only and the same shall
be followed during the operation on progress.

 Continuous monitoring personals shall be employed to monitor all through the activity and plant
and equipments

3.Dewatering System

 Excavation should be kept free from water and arrangement shall be made to remove and dispose
of all water from every source entering the excavations and maintained at all times during
construction.

 Grading shall be done as may be necessary to prevent surface water from flowing into trenches or
other excavations, and any water accumulating therein shall be removed by pumping or by other
suitable methods. Pipes or flumes at such places as not to cause pollution of steams, waterways or
land shall discharge water from pumping, de-watering or other process.

4.Proposed Method

Our survey of likely water flow indicates that dewatering should be executed by a well
point system incorporating quantity one off diesel driven 6’’ vacuum assisted dewatering pumps
systems (pumps and accessories like headers, well point etc for a maximum of 100 metres for
normal conditions; more or less linear meters may be considered depending the actual
dewatering need & water permeability), each with maximum capacity 350 M3 / hour and
maximum discharge head of 30 Meter.

Dewatering is required for a maximum excavation depth of 7 meters from the existing
ground level. The system, installed around the site, will incorporate full sets of well points and
all associated required materials to draw the water from the ground, along with discharge hoses
from the pumps to the water storage lagoon area adjacent to the well point approximately 500
meter away.

The system, installed around the site, will incorporate full sets of well points and all
associated required materials to draw the water from the ground, along with discharge hoses
form the pumps to the lagoon, located adjacent to point of discharge, or other agreed discharge
solution following discussion with the EMPLOYER’S REPRESENTATIVE responsible for
execution of the ground works. 2nd stage dewatering may be required if the dewatering has to go
below 4.5 – 5 meter below the existing water table.

Well point dewatering systems will be installed 500 linear meter X 2 sides in one stage
depending on the requirements. Each system will be approx 70 – 80 meters depending on the
water content in the area.

2
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC

5.Prevention of Seepage

Up to 10 systems of 6’’ dewatering pumps along with accessories will be on the existing
ground level 1-2 meter outside the perimeter. They may be conveniently placed that access to the
lagoon. The pumps are place in the centre of the system so that the vacuum is equally divided
among to well points. This makes it conducive for the drained water to be sucked out of the
ground in a uniform pattern to make the draw down and control the seepage. This placement will
make the soil dry accordingly. The pumps may be reduced to two, depending the seepage of
water. This can be done by adequately placing the pump again at the centre of the system and
locking with male & female end caps.

One end of 6’’ Suction hoses will be connected to the pump inlets & other end
connected to the 6’’ X 6 meter headers pipe with 6 X 2’’ inlets with the help of the ‘T’ piece.
The 2’’ X 6 inlets of the header pipes are connected with the 2’’ quick action Millar fittings
along with the swing hoses and are connected to 2’’ X 6 meter uPVC well points. Discharge
hoses from the pumps will discharge the water up the point of discharge to the sever line.

Depending on the soil conditions the well point spacing is suggested as 1m. Installation
will be made by high pressure jetting or drilling dependence on the soil density. 6’’ X 6 m
drilling is suggested to be hired & made standby for possible requirement. Filter packs (6 mm
washed aggregate) will be required around each well point. Normal width 1-2 M will be required
to locate the pumps, header pipes, well points and swings required for the well point dewatering
system.

Day and night monitoring for the dewatering system has to be provided. After the system
is completely installed and nominally allowed for 1 week for dewatering, the area of the ground
will start to show the dryness. The well point systems at all ends are likely to kept operational, as
long as it is required by the site conditions.

Dewatering services will be provided in accordance with the specification & guidelines
from project engineer by EMPLOYER.

Dewatering will commence, continue & cease as per written confirmation received from
the EMPLOYER’S REPRESENTATIVE.

 Under no circumstances will permission be given for the discharge of groundwater into the
proposed lagoon until to receive written confirmation from Employer Engineer.

 Lagoon for the storage of groundwater are permitted, they will be suitably protected with fencing
and attended by day and night to prevent access by the general public and will not be
sited adjacent to near structure. Approved means of preventing the formation of
mosquito larvae on the surface of the lagoons will be employed.

3
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC

4. Responsibility

 Project Engineer:

The Project Manager and the Construction Manager have the responsibility for the overall operations of
this statement. The Project Manager and Construction Manager have the responsibility to implement the
Method statement and to delegate the responsibility to a Site Engineer and the QC Engineer to directly
supervise the work on site. The site Engineer is responsible for ensuring that all the works are executed
in accordance with the specified requirements.
The Project Manager will be responsible for the following.

 Plan and schedule the jobs, determine priorities, control workload, inspect projects and keep sufficient time
records for workflow and outputs.
 Performs technical responsibilities and make decisions to a substantial extent.
 Reviews and interprets proposed designs, drawings, and specifications for appropriateness to required
function and/or standard and initiates revisions.
 Ensure that project operations are in compliance with design specifications
 To provide all the necessary information to the site team.
 Engineer/Supervisor in charge to conduct a toolbox meeting and communicate both the Method Statement
& Risk Assessment to the workers before commencement of the activity.
 All safety precautions shall be followed as per established project safety procedure.
 Only experienced and skilled labor shall be engaged for carrying out screed work.
 People involved in the construction work shall wear PPE such as safety helmets, safety shoes, safety harness,
gloves safety glass, mask etc.as required.
 All Hose pipe joints are properly connected and tied with clips.
 Safety officer shall check and ensure that all safety precautions are followed.
 All the safety equipment’s shall be periodically inspected and checked for its durability before using them to
labor.
 Manual handling procedures to be followed
 Any incident or near miss incident shall be reported immediately to the concerned safety officer.

Site Supervisor:

The Site supervisor will be responsible for the following

 Distribution of the responsibilities to his site team.


 To provide all necessary information to his site team.
 To ensure that the works are carried out in accordance with the WMS and RA.
 To ensure the MS, ITP, & RA is communicated to the Forman and the site working team on a regular basis to
ensure that the proper work method is followed.
 To check and verify that the works completed complies with the specification prior to requesting inspection
by the consultant
 To ensure that inspections are carried out by the consultant through the main contractor’s QA/QC Engineer
prior to the next phase of activities
 To review and discuss any request that might be raised by the site working team.
 Primarily ensure that the job is being carried out to the approved WMS and ITP.

4
Tel: 04-453 45 41 Fax: - 04–453 45 40 P.O.Box 66554 Dubai
Al Qooz Contracting LLC

Foreman:

The Forman supervisor will be responsible for the following

 To provide the Site supervisor with daily progress reports and discuss with him planned works for the next
day.
 To ensure that all safety measures are maintained at site and workers have proper training for following all
current safety guidelines and housekeeping in accordance with the Main Contractors Safety Officer.
 To ensure good housekeeping is practiced and proper tools are being used by the site team.
 To ensure that all persons involved in the works are aware of their duties, and that they have enough
understanding of safety procedures.
 To conduct frequent toolbox meeting on safety awareness and to maintain a log of all meetings for
inspection.
 To keep a record of all toolbox talks.
 Liaises with the required personnel at the site for the required inspections with regards to safety.
 Attends all the safety coordination meetings.
 Ensure that the basic and activity specific PPE is worn regularly by the site working team.

5. Equipment Requirements

The requirements that will be engaged for Dewatering work will be as follows:
 Site In-charge.
 Charge Hand.
 Surveyor.
 Operator.
 Skilled Labour.
 Unskilled Labour.
 Water Pump
 Barricades

6. Health and Safety


Strictly followed as per the manufacturer’s Health and Safety recommendations for handling and use of the
materials. Ensure all involved personnel shall be aware of the same.

5