Professional Documents
Culture Documents
EB8 G0 QHR6 Form 1
EB8 G0 QHR6 Form 1
At: Plot No. SC-01/CS, Sector 152, Noida, District: Gautam Budh Nagar, State: U.P. (Form -1)
APPENDIX - I
(See par
paragra
agraph-
ph-6)
FORM 1
I. Basic Inform
Information
rmation
Annexure II
III
(b)Case No.
(c) Orders/directions of the Court if
any and its relevance with the
proposed project
II. Acti
Activity
construction workers? nearby area. The construction work will be done only
in the daytime.
There will be provision of facilities such as rest shelter,
drinking water, toilet etc. for workers at the project site
& will be arranged by contractor.
1.8 Above ground buildings, Yes Excavation will be carried out for foundation and
structures or earthworks construction of basements. The total excavated quantity
including linear structures, cut of earth material will be used at the site itself for the
and fill or excavations purpose of development of project site and
horticultural development.
1.9 Underground works including No No underground works including mining / tunneling
mining or tunneling? is required except excavation of earth only for the
foundation and construction of basement.
1.10 Reclamation works? No As, this is a new construction project hence; no
reclamation work required.
1.11 Dredging? No No dredging required, as case of “International Level
Cricket Stadium cum Sports Complex” building
development project.
1.12 Offshore structures? No There are not any offshore structures, as case of
“International Level Cricket Stadium cum Sports
Complex” building development project.
1.13 Production and manufacturing No Since, it is a construction Project, hence, no production
processes? / manufacturing process is involved.
1.14 Facilities for storage of goods or Yes Separate raw material storage yard will be made
materials? during construction phase:
• Cement will be separately stored under cover in
bales.
• Sand will be stacked neatly under tarpaulin
cover.
• Bricks and steel will be laid in open
• The raw material handling yard will be located
within the project site and separated by enclosures.
1.15 Facilities for treatment or Yes Solid Waste
disposal of solid waste or liquid Solid waste generated will be comprising of domestic
effluents? waste (inorganic and organic waste) and e-waste
(generate after a latency period of 4 -5 years).
Domestic wastes:
wastes:
Approximately, 13469.25 kg/day domestic solid waste
M/s. ATS Infratech Pvt. Ltd. 5 JM EnviroNet Pvt. Ltd.
Proposed International Level Cricket Stadium cum Sports Complex
At: Plot No. SC-01/CS, Sector 152, Noida, District: Gautam Budh Nagar, State: U.P. (Form -1)
Management of E-
E-waste
Liquid Effluent:
Effluent :
During construction phase, sewage will be treated and
disposed through septic tanks with soak pits. During
operation phase, 137.18 KLD waste water will be
generated which will be treated in the Sewage
Treatment Plant (STP) having capacity of 170 KLD up to
M/s. ATS Infratech Pvt. Ltd. 6 JM EnviroNet Pvt. Ltd.
Proposed International Level Cricket Stadium cum Sports Complex
At: Plot No. SC-01/CS, Sector 152, Noida, District: Gautam Budh Nagar, State: U.P. (Form -1)
tertiary level.
Dewatered/ dried sludge from STP will be used as
manure in horticulture.
Hazardous Wastes:
Wastes :
No hazardous wastes will be produced from project
activities except some Spent Oil (Category 5.1)
generated from D.G. sets; it will be sold to recyclers
authorized by State Pollution Control Board.
1.16 Facilities for long term housing of No No facilities for long term housing of operational
operational worker worker are proposed.
1.17 New road, rail or sea traffic No The project site is well connected by wide service road,
during construction or So no new road will be laid during construction or
operation? operation of the project activities except for internal
roads.
1.18 New road, rail, air waterborne No The area is already developed. It is well connected by
or other transport infrastructure roads to whole of the city, so there will be no
including new or altered routes alteration of routes or lying down of new routes done
and stations, ports, airports etc? due to project activity. Internal roads within t h e
project site will be constructed for smooth movement
of traffic.
1.19 Closure or diversion of existing No There will not be any closure or diversion of existing
transport routes or infrastructure transport routes, as the “International Level Cricket
leading to changes in traffic Stadium cum Sports Complex” Sports Complex building
movements? is proposed within site premises. Thus there will not be
any change in traffic movement.
1.20 New or diverted transmission No There will not be any provision for new or diverted
lines or pipelines? transmission lines or pipelines for the proposed project.
1.21 Impoundment, damming, No No river is present near the project or crossing the
culverting, realignment or other project site; hence no impoundment, damming,
changes to the hydrology of culverting, realignment, or other changes to the
watercourses or aquifers. hydrology of surface watercourses are applicable here.
1.22 Stream crossings? No As such no river or drain is passing by the project site.
Hence not applicable in case.
1.23 Abstraction or transfers of water Yes The total water requirement of the project will be
form ground or surface waters? 927.10 KLD during peak days (which will be included
the fresh water requirement of 314.50 KLD.
Recycled treated water requirement of 612.60 KLD for
flushing) & 171.50 KLD during non-peak days (which
1.31 Any other actions? None No other action will be undertaken except the above
mentioned for the Sports Complex building
construction project.
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-
non-renewable or in short supply):
2.1 Land especially undeveloped or No The Proposed ‘‘International Level Cricket Stadium
agricultural land (ha) cum Sports Complex’’ development of Sports
Complex building Project on 141860.66 sq. m. (14.186
ha.) (Effective plot area) vacant land.
2.2 Water (expected source & Yes The total water requirement of the project will be
competing users) unit: KLD 927.10 KLD during peak days (which will be included
the fresh water requirement of 314.50 KLD.
2.4 Construction material-stone, Yes Usual construction materials will be utilized like
aggregates, sand/ soil (expected Cements, Bricks, Sand, Iron rods, Fly ash based products,
source-MT) etc.
Source: Steel and cement will be procured from
authorized vendors. Sand & aggregate will be
procured from local material suppliers.
2.5 Forests and timber (source–MT) No Timber required will be taken from nearby markets.
2.6 Energy including electricity and Power requirement for the project will be 2229 KW.
fuels (source, competing users) Peak Days power requirement will be same as non-peak days
Unit: fuel (MT), energy (MW) as the facilities will be on D.G. backup and additional D.G. Sets
will be rented during peak days.sourced from Local grid
supply of Noida For emergency situation during power
failure, 4 D.G. sets of total capacity of 2500 KVA (2x750
KVA + 2x500KVA) will be used for back-up.
2.7 Any other natural resources (use None No other natural resource will be involved in the
appropriate standard units) project except the mentioned above.
3. Use, stor
storage,
orage, transpo
ansport,
port, handling or produ
productio
ction of subs
substances or materials, which could
be harmful to human health or the env
environment or raise concer
oncerns
erns about actual or
perc
perceiv
eived risks to human health
health.
3.2 Changes in occurrence of disease No Suitable drainage and waste management measures will
be adopted in both construction and operational
or affect disease vectors (e.g.
phase, which will restrict the stagnation of water or
insect or water borne diseases)
accumulation of waste. This will effectively restrict the
reproduction and growth of disease vectors.
3.3 Affect the welfare of people e.g. No No use, storage, transport, handling or production of
by changing living conditions? any harmful product is envisaged from the proposed
project activities. Thus, no major adverse impacts on
the human health / environment are envisaged.
3.4 Vulnerable groups of people who No No effect is envisaged due to this project.
could be affected by the project
e.g. hospital patients, children,
the elderly etc.,
3.5 Any other cause None No, other causes are involved except the mentioned
above.
4.1 Spoil, overburden or mine wastes No No such spoil, overburden or mine wastes will be
generated.
4.2 Municipal waste (domestic and Yes Solid wastes likely to be generated in project are of
or commercial wastes) domestic & commercial nature.
Approximately, 13469.25 kg/day domestic solid waste
(Permanent Population: 202.50 kg/day & Floating
Population: 13266.75 kg/day) is estimated to be
generated during Peak days & Approximately, 876.75
kg/day domestic solid waste (Permanent Population:
202.50 kg/day & Floating Population: 674.25 kg/day) is
estimated to be generated during Non-Peak days from
the project activity. Base of calculation @
450gms/person/day for residential and 250
gm/person/day for floating population.
4.3 Hazardous wastes (as per Yes Spent Oil from D.G. sets will be carefully stored in
Hazardous Waste Management High Density Polythene (HDPE) drums in isolated
Rules) covered facility. This spent oil will be sold to vendors
authorized by HSPCB/ MoEF for the treatment of
same. Suitable care will be taken so that spills / leaks
of spent oil from storage could be avoided.
4.4 Other industrial process wastes No Not applicable, as this is a Sports Complex building
development of “International Level Cricket Stadium
cum Sports Complex” project
4.6 Sewage sludge or other sludge Yes The mechanism of sludge drying will be centrifugation
from effluent treatment and the dewatered/ dried sludge from STP will be
converted to cakes and will be used as manures in
horticulture and also disposed to designated municipal
area.
4.7 Construction or demolition Yes Construction waste generation will be limited to the
wastes construction phase only and will be limited to project
site only. These will be reused for backfilling after
manual segregation. Unusable and excess construction
debris will be disposed at designated places in tune
with the local norms. These wastes will be used for
road development activities.
4.9 Contaminated soils or other No No Contaminated soils or other materials are involved.
materials
4.11 Other solid waste No Not applicable, as this is a Sports Complex building
development of “International Level Cricket Stadium
cum Sports Complex” project
5.1 Emissions from combustion of Yes The operation of proposed project does not envisage
fossil fuels from stationary or any major air pollutant generating sources except D.G.
mobile sources sets and vehicular movement. The emissions from
stationary sources (D.G. sets) have been predicted.
5.2 Emissions from production No Not applicable, as this is an “International Level Cricket
processes Stadium cum Sports Complex” Sports Complex building
development project.
5.3 Emissions from materials Yes Dust emissions may arise due to the materials handling
handling including storage or during construction phase; These will be restricted to the
transport construction phase and to the construction site only.
Regular water sprinkling & tarpaulin covers will be
provided to prevent dust emissions.
5.4 Emissions from construction Yes This will be restricted to the construction phase and to
activities including plant and the construction site only. Though these will be
equipment negligible in amount as they will occur from the
equipments movement involved in the construction.
Still suitable preventive measure will be taken.
5.5 Dust or odours from handling of Yes Dust is likely to be generated during construction, this
materials including construction will be water sprinkled and tarpaulin covers will
materials, sewage and waste be provided over stored raw material to reduce
dust emission.
5.6 Emissions from incineration of No Not applicable, as this is an “International Level Cricket
wastes Stadium cum Sports Complex” Sports Complex building
development project and there will be not any
incineration waste involved in this project.
5.7 Emissions from burning of waste No Not applicable, as this is an “International Level Cricket
in open air (e.g. slash materials, Stadium cum Sports Complex” Sports Complex building
construction debris) development project within the premises. So, Open
burning of biomass / other material will be prohibited.
5.8 Emissions from any other sources No No other Emissions from any other sources, except
mentioned above.
6.1 From operation of equipment Yes The machinery which will be used for construction will
e.g. engines, ventilation plant, be of high standard and of reputed make and
crushers will adhere to international standard. These
standards itself take care of noise pollution control /
vibration control and air emission control. Hence
insignificant impacts due to construction machinery are
envisaged. Apart from this, the construction
activities will be restricted to daytime only.
6.2 From industrial or similar No No major noise and vibration generating activities are
processes involved in the project, except due to running of
various construction equipments/ machinery & D.G.
Sets during renovation & expansion phase of the
project. Proper maintenance of machineries will reduce
the generation of noise and vibration. All the workers
will be equipped with PPE’s during construction phase
and the D.G. Sets will be installed in acoustic enclosures
with proper padding system to reduce vibration impact.
6.3 From construction or demolition Yes Due to the various construction activities, there will be
short-term noise impacts in the immediate vicinity of
the project site. The construction activities will include
the following noise generating activities:
• Construction plant
6.5 From construction or Yes Some noise will be generated from vehicular movement
6.6 From lighting or cooling systems Yes Cooling system will be efficient & of latest technology.
6.7 From any other sources No There will be no other sources for noise & vibration
generation except the mentioned above.
7. Risks of contamination of land or water from releases of pollutants into the ground or into
sewers, surface waters, groundwater, coastal waters or the sea:
7.1 From handling, storage, use or No Used oil from D.G. sets will be handled with care, it
spillage of hazardous materials will be stored in HDPE drums and provided to
authorized vendor. Hence, no risk of contamination is
envisaged.
7.2 From discharge of sewage or No The total water requirement of the project will be
other effluents to water or the 927.10 KLD during peak days (which will be included
land(expected mode and place the fresh water requirement of 314.50 KLD and
of discharge) recycled treated water requirement of 612.60 KLD for
flushing) & 171.50 KLD during non-peak days (which
will be included the fresh water requirement of 113
KLD and recycled treated water requirement of 58.50
KLD for flushing). The waste water generated from the
project site will be treated in STP of Capacity 170 KLD,
treated water will be reuse for green area, flushing,
HVAC/D.G. Cooling & Road Washing etc.
7.3 By deposition of pollutants No Minor Air emissions will be generated due to increased
emitted to air into the land or vehicular movement and occasional use of D.G. sets for
into water which effective measures will be taken like adequate
greenbelt development and use of low sulphur diesel in
D.G. sets etc. So there would not be any deposition of
pollutants emitted to air, land or water.
7.4 From any other sources No No any other sources are involved except the
mentioned above.
7.5 Is there a risk of long term build No Likelihood of such an event is not foreseen till now in
up of pollutants in the the area and suitable measures will be adopt to control
environment from these sources? and reduce emission, so that there will be no such risk
8.1 From explosions, spillages, fires No This is an “International Level Cricket Stadium cum
etc from storage, Sports Complex” Sports Complex building
handling, use or development project, does not involve major
production of hazardous hazardous construction activity. Hence chances of
substances explosions, spillages, fires are minimal.
8.2 From any other causes No No any other causes are involved except the
mentioned above.
8.3 Could the project be affected by Yes The area under study falls in Zone-II, according to
natural disasters causing the Indian Standard Seismic Zoning Map. Suitable
environmental damage (e.g. seismic coefficients in horizontal and vertical
floods, earthquakes, landslides, directions respectively, have to be a d o p t e d w h i l e
cloudburst etc)? designing the structures.
9.1 Lead to development of Yes The proposed “International Level Cricket Stadium cum
supporting utilities, ancillary Sports Complex” project is for Sports Complex building
development or development development; it may lead to development of supporting
stimulated by the project services and infrastructure in and around the area.
which could have impact on
the environment e.g.:
• Supporting infrastructure Yes The project will have positive impact on the ancillary
(roads, power supply, waste infrastructure like roads, markets, public health, amenities,
or waste water treatment, conveyance facilities etc. in the area.
etc.)
9.2 Lead to after-use of the site, No Negligible impact is envisaged on air, noise and aesthetic
which could have an impact on parameters due to the proposed Sports Complex building
the environment development project.
9.4 Have cumulative effects due to No The proposed project is an “International Level Cricket
proximity to other existing or Stadium cum Sports Complex” Sports Complex building
planned projects with similar project. A better-planned and executed project has to
effects yield better result individually.
where existing legal environmental Air, Water, and Noise etc. will be
standards are exceeded) maintained within permissible limits
specified by SPCB / CPCB with proper
mitigation measures.
12 Areas susceptible to natural hazard None The area under study falls in Zone-IV,
which could cause the project to according to the Indian Standard
present Environmental problems Seismic Zoning Map. Suitable seismic
(Earthquakes, subsidence, landslides, coefficients in horizontal and
erosion, flooding or extreme or vertical directions respectively, will be
adverse climatic conditions) adopted while designing the structures
to mitigate the seismic impacts.
There are no possibilities of the
proposed project site getting flooded
as per records available.
Place:
Mr. S. J. Raza
Authorized Signatory
M/s ATS Homes Pvt. Ltd.
711/92, Deepali, Nehru Place, New Delhi-110019
NOTE:
1. The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall submit
with the application a C.R.Z map duly demarcated by one of the authorized agencies, showing
the project activities, w.r.t. C.R.Z (at the stage of TOR) and the recommendations of the State
Coastal Zone Management Authority (at the stage of EC). Simultaneous action shall also be
taken to obtain the requisite clearance under the provisions of the C.R.Z Notification, 1991 for
the activities to be located in the CRZ.
2. The projects to be located within 10 km of the National Parks, Sanctuaries, Biosphere Reserves,
Migratory Corridors of Wild Animals, the project proponent shall submit the map duly
authenticated by Chief Wildlife Warden showing these features vis-a-vis the project location
and the recommendations or comments of the Chief Wildlife Warden "thereon (at the stage of
EC)."
3. All correspondence with the Ministry of Environment & Forests including submission "of
application for TOR/Environmental Clearance, subsequent clarifications, as may be required
from time to time, participation in the EAC Meeting on behalf of the project proponent shall
be made by the authorized signatory only. The authorized signatory should also submit a
document in support of his claim of being an authorized signatory for the specific project".