Professional Documents
Culture Documents
JURNAL
JURNAL
Nur Rizky Akbar Eza*a), Sukamdi, S.T., M.MT.a), Chandra Wiharya, S.ST., M.T.a)
(Artikel diterima: 2019, direvisi: 2019)
Abstract: Voltage drop is one of the problems in the electrical energy distribution system, this also happens to GI Trenggalek. For the
Trenggalek GI condition, a 10 MVar large capacity shunt capacitor has been installed, and a voltage drop still occurs, this is evident from
the measurements at 10:00 on October 8, 2018 that the voltage measured on the Trenggalek GI is 62 kV. Thus, in this thesis the author
analyzes the planning of adding a second shunt capacitor to obtain good system performance with a system voltage that is always stable
based on SPLN No. 1: 1995 Article 4, concerning the provision of variations in operating voltage where the permitted voltage drop is only
-10% to + 5%. The purpose of this final project / thesis is to determine the large capacity of the shunt capacitor installed on the Trenggalek
70 kV GI bus to improve the voltage profile and power loss that occurs on the 70 kV transmission line using the Newton power flow
method. Raphson on E-TAP 12.6.
Based on the results of the analysis, a large capacity of 10 MVar mounted shunt capacitor was obtained. Additional installation of a 10
Mvar shunt capacitor can inject a 3.7% voltage, ie an initial voltage of 61.3 kV to 64 kV, so with the addition of a 10 shunt capacitor MVar
can also reduce channel power loss before adding a 0.63 MW shunt capacitor and 1.14 MVAR reduced to 0.58 MW and 1.05 MVar.
Keywords: method of the newton-raphson power flow, shunt capacitor, voltage drop
Abstrak: Jatuh tegangan merupakan salah satu permasalahan dalam sistem penyaluran energi listrik, hal ini juga terjadi pada GI
Trenggalek.. Untuk kondisi GI Trenggalek sudah terpasang shunt capacitor dengan besar rating 10 MVar, dan masih terjadi drop
tegangan, hal ini dibuktikan pada pengukuran pukul 10:00 tanggal 8 oktober 2018 bahwa tegangan yang terukur pada GI Trenggalek yaitu
62 kV. Sehingga dalam skripsi ini penulis melakukan analisis perencanaan penambahan shunt capacitor yang kedua demi mendapatkan
kinerja sistem yang baik dengan tegangan sistem yang selalu stabil berdasarkan SPLN No. 1:1995 Pasal 4 tentang ketentuan variasi
tegangan pelayanan dimana jatuh tegangan yang diijinkan hanya sebesar -10% s/d + 5% . Tujuan Tugas Akhir/Skripsi ini adalah
menentukan perencanaan besar rating shunt capacitor yang dipasang pada bus 70 kV GI Trenggalek untuk memperbaiki profil tegangan
dan rugi daya yang terjadi pada saluran transimisi 70 kV dengan metode aliran daya newton-raphson pada E-TAP 12.6.
Berdasarkan hasil analisis, diperoleh besar rating shunt capacitor yang dipasang sebesar 10 MVar. Tambahan pemasangan shunt
capacitor dengan nilai 10 MVar dapat menginjeksi tegangan sebesar 3,7 % yaitu tegangan awal 61,3 kV menjadi 64 kV, kemudian dengan
tambahan shunt capacitor 10 MVar juga dapat mengurangi rugi daya saluran dari sebelum penambahan shunt capacitor yaitu 0,63 MW
dan 1,14 MVar berkurang menjadi 0,58 MW dan 1,05 MVar.
Kata kunci: jatuh tegangan, shunt capacitor, metode aliran daya newton-raphson
1. Pendahuluan. Pada gardu induk Trenggalek terdapat trafo tenaga 70 kV
Kondisi kapasitas pembangkitan yang tidak mampu mengikuti yang berfungsi sebagai penyaluran energi listrik dari pembangkit
kecepatan laju pertumbuhan beban, serta letak beban-beban menuju trafo distribusi, terdapat permasalahan mengenai jatuh
besar yang jauh dari pusat pembangkit, menyebabkan tegangan pada sisi primer. Ketidakstabilan tegangan tersebut
dibutuhkannya transmisi panjang yang dapat mengakibatkan berpengaruh pada kerja OLTC pada transformator yang bekerja
kondisi penurunan tegangan sistem di luar batas toleransi yang terlalu sering, sehingga jika kondisi ini dibiarkan maka akan
telah diatur. Salah satu daerah yang mengalami masalah ini berpengaruh terhadap umur trafo. Salah satu cara untuk
adalah Trenggalek, karena Trenggalek termasuk wilayah diujung mengatasi permasalahan ketidakstabilan tegangan tersebut pihak
saluran. Pada kondisi normal GI Trenggalek mendapatkan suplai PLN mengeluarkan kebijakan untuk dilakukan penambahan
energi dari IBT Ponorogo dan dalam sistem interkoneksi GI pemasangan shunt capacitor pada sisi primer trafo. Pemasangan
Trenggalek juga terhubung pada GI Banaran Kediri. Spesifikasi kapasitor yang dipasang secara paralel pada bus 70 kV
atau nameplate dari IBT Ponorogo adalah 150 kV/66 kV, dimana digunakan untuk mengurangi kerugian tegangan dan
spesifikasi tersebut adalah spesifikasi yang dikeluarkan dari memperbaiki tingkat tegangan pada sistem saluran udara pada
pabrik, akan tetapi sistem yang kita gunakan adalah 70 kV, faktor daya yang normal sesuai fungsi penempatan kapasitor
sehingga untuk merubah tegangan sekunder IBT Ponorogo bank yang dilakukan oleh PLN. Sehubungan dengan hal diatas
menjadi 70 kV digunakanlah tap changer dengan mengatur posisi maka saya sebagai penulis melakukan penelitian tentang:
tap nya sehingga dapat mendekati tegangan nominal sistem yaitu “ANALISIS PERENCANAAN PEMASANGAN SHUNT
70 kV. CAPACITOR UNTUK MEMPERBAIKI PROFIL TEGANGAN DAN
MENGURANGI RUGI DAYA DI GARDU INDUK TRENGGALEK
BUS 70 KV”
*
Korespondensi: email penulis : akbarezan70@gmail.com
a) Prodi Sistem Kelistrikan, Jurusan Teknik Elektro, Polinema.
Jalan Soekarno-Hatta No. 9 Malang 65141 1 © 2019, Sistem Kelistrikan,, Jurusan Teknik Elektro, Polinema
ELPOSYS: Jurnal Sistem Kelistrikan POLINEMA
2. Tinjauan Pustaka.
2.1.Sistem Jaringan
Sistem interkoneksi merupakan gabungan dari pusat pembangkit Gambar 3. Rugi Penghantar
tenaga listrik melalui jaringan transmisi.[1] Drop tegangan pada konduktor
ΔE = IL x Z (Volt)
Rugi daya = ΔE x I (watt)
2
Beban
= I x Z (watt)
GI 2.5. Metode Gauss Siedel
pada percobaan pembuktian dengan cara manual, metode
Saluran Transmisi
yang di pakai yaitu menggunakan metode gaus siendel. [5]
Pembangkit
n
1 Snip
Vi =
[ -
Yii V*I ∑ i=0
Yik V k
k≠i
] *
1 [ ( Pg + jQ g ) - ( P l + jQ l ) ]
[ ]
n
= - ∑ Y ik V k
Y ii V *I i=0
Gambar 1. Sistem Interkoneksi. k≠i
2.2.Koreksi Faktor Daya *
1 [ ( 0 ) - ( Pl + jQ l ) ]
[ ]
Ketika kapasitor shunt Qc kVA dipasang pada beban, factor n
∑ Yik V k
i=0
k≠i
]
P 3. Metodologi.
Ø2 3.1.Waktu dan Tempat Penelitian.
Q2
Waktu melakukan penelitan dimulai dari semester 7, pada
Ø1 S2 bulan November hingga bulan Desember melaksanakan survei
S1 Q1 lapangan dan melakukan pengambilan data dengan melakukan
observasi langsung pada instansi yang terkait dengan pengerjaan
Skripsi.
Penelitian dalam rangka pembuatan skripsi dilaksanakan pada:
Gambar 2. Perubahan Faktor Daya
Waktu : Desmber 2018 – Juli 2019
Tempat : Gardu Induk Trenggalek, PT. PLN
2.3.Persamaan Aliran Daya.
(persero) UIP2B, PT.PLN (persero) UPT
Dari hasil load flow selain dapat diketahui aliran daya P dan Q
Madiun, Kampus Politeknik Negeri Malang
antar bus, juga dapat diketahui besarnya tegangan pada setiap
bus pada saat beban puncak, sehingga dapat dihitung besar drop
tegangan dengan presamaan (Emmy Hosea 2002). [3]
(kVAR)(x)(d)
% drop=
10( kV 2 )
kVAR = besar kVAR yang diperlukan
X = reaktansi saluran dalam satuan ohm/km
d = panjang konduktor dalam kilometer
kV = tegangan nominal
2.4.Rugi Daya
Kerugian ini selalu berhubungan dengan besarnya arus
karena beban, jadi semakin besar arus yang mengalir maka
kerugian juga meningkat bahkan temperatur yang mempengaruhi
nilai tahanan dan berkaitan langsung dengan kerugian pula. [4]
Rugi Penghantar
*
Korespondensi: email penulis : akbarezan70@gmail.com
a) Prodi Sistem Kelistrikan, Jurusan Teknik Elektro, Polinema.
Jalan Soekarno-Hatta No. 9 Malang 65141 2 © 2019, Sistem Kelistrikan,, Jurusan Teknik Elektro, Polinema
ELPOSYS: Jurnal Sistem Kelistrikan POLINEMA
Gambar 4. Diagram Alir Penulisan Perencanaan Shunt Penentuan nilai base yang akan digunakan dalam
Capacitor. perhitungan sesuai dengan gambar 4.7.
3.3.Data Penelitian. MVA base = 200 MVA
Jenis data yang diambil untuk penelitian ini yaitu meliputi kV base = 70 kV
data-data berikut : kV 2 702
1. Single line gardu induk Trenggalek.
Z base = = =24 ,5 Ω
MVA Base 200
2. Konfigurasi subsistem Kediri. Tabel 2. Reaktansi Saluran GI Trenggalek
3. Data logsheet tanggal 8, dan 23 oktober 2018. Line R1 (Ohm) X1 (Ohm) L (km) Rtot Xtot
4. Data single line diagram Jatim tahun 2018. Trenggalek - Ponorogo 0.217 0.387 38.8 8.419 15.016
5. Data impedansi saluran transmisi sub sistem Jatim. Trenggalek - PLTA Tulungagung 0.217 0.387 26.37 5.722 10.205
Trenggalek - Tulungagung 0.217 0.387 33 7.161 12.771
6. Data trafo.
Z pu ( 2-1 ) =
4. Pembahasan R + X j 8,419+15,016 j 17,215<60,72
4.1.Hasil Pengukuran Tegangan pada bulan Oktober 2018 = =
Z base 24,5 24,5
bus Trenggalek 70 kV.
= 0,702 < 60,72
Beban puncak trafo 1
Y ( 2-1 ) = = 1,42<-60,72
70
0,702 < 60,72
Z pu ( 2-3 ) =
68
R + X j 5,722+10,205 j 11,699<60,72
tegangan (kV)
66 = =
Z base 24,5 24,5
= 0,477 < 60,72
64
62
1
Y ( 2-3) = = 2,096<-60,72
60
0,477 < 60,72
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31
Oktober Z pu ( 2-4 ) =
Gambar 5. Beban Puncak Trafo
Dari gambar 5 diatas mengalami penurunan tegangan hingga R + X j 7,161+12,771 j 14,641<60,71
= =
mencapai 62 kV pada tanggal 8 untuk beban puncak pukul 10:00 Z base 24,5 24,5
WIB dan 64 kV pada tanggal 8 untuk pukul 19:00 WIB.
= 0,597<-60,71
4.2.Perhitungan Manual Nilai Tegangan
1
Dari hasil validasi tegangan yang terukur dari dua trafo di GI Y ( 2-4) = = 1,675<60,71
trenggalek selama tiga bulan, maka dipilih salah satu yaitu 0,597<-60,71
Perhitungan nilai tegangan pada bus trenggalek sebelum pemasangan
*
Korespondensi: email penulis : akbarezan70@gmail.com kapasitor pada sisi 70 kV :
a) Prodi Sistem Kelistrikan, Jurusan Teknik Elektro, Polinema.
Jalan Soekarno-Hatta No. 9 Malang 65141 3 © 2019, Sistem Kelistrikan,, Jurusan Teknik Elektro, Polinema
ELPOSYS: Jurnal Sistem Kelistrikan POLINEMA
V2 = d = 38,8 km
* kV =70 kV
1
Y22 V2* [
[ ( Pg + jQ g ) - ( P l + jQ l ) ] +(Y21 V1+Y23 V3+Y24 V4) (3)10 (70)2 147000
kVar= =
(0,387)(38,8) 15,015
]
= 9790,209 kVar = 9,79
MVar
= Dari perhitungan diatas, besarnya kapasitor yang dibutuhkan
* untuk memperbaiki profil tegangan sebesar 9,79 MVar. Dalam
1
Y22 V2* [
[ ( 0 ) - ( Pl + jQ l ) ] +(Y21 V1+Y23 V3+Y24 V4)
] hal ini rating kapasitor akan di sesuaikan dengan spesifikasi dari
PLN yaitu 10 MVar.
=
1 0.095+(−0,025 j)
( 1,42←60,72+2,096 ←60,72+1,675←60,71 ) 1< 0 [
+ ( ( 1,42←60,72. 0,919←15,92 ) + ( 2,096<−60,72 . 0
=
1 0,098<-14,74
5,190<-60,71 1<0 [ +(4,536<-79,70) ] Gambar 7. Posisi tap trafo 1
4,578<-78,58
=
5,190<-60,71
= 0,882<-17,87 pu
= 61,74<-17,87 kV
Mencari error yang terjadi adalah
V pengukuran-V perhitungan
%Error = ×100% Gambar 8. Posisi tap trafo 2
V pengukuran Dilihat dari gambar 7 dan 8, menunjukkan posisi tap changer
62-61,74 trafo distribusi GI trenggalek sebelum dilakukan penambahan
= ×100%=0,4 %
62 shunt capacitor sebesar 10 MVar, yaitu trafo 1 pada posisi tap
Dari hasil error yang dihitung masih dianggap dalam batas yang maksimal yaitu tap 17 dan trafo 2 pada posisi tap maksimal yaitu
normal antara hasil data real dan hasil perhitungan, error tidak tap 18.
lebih dari 5 %. Dengan kondisi tegangan pada bus 70 kV pada GI
Trenggalek dengan metode perhitungan didapat nilai tegangan
sebesar 61,74 kV untuk pengukuran pukul 10:00.
menggunakan data real pukul 10:00 pada tanggal 8 oktober 2018 Subsistem Kediri 70 kV
yang didapat dari UIP2B.
3.8%
3.7% 3.8%
2.1%
2.1% 0.8%
0.8% 0.8%
0.8% 0.8%
0.8%
0.1%
0.1%
0.1% 0.0%
0.0% 0.1%
0.1%
0.0%
PONO DLOP TRENG PLTA TULUN TULUN PARE GUDA MANIS MANIS MRAN MAGE CARU NGAN NGAN PLOSOKERTO BANA BANA
ROGO O GALEK TULUN GAGU GAGU NG REJO REJO GGEN TAN BAN JUK A JUK B SONO RAN A RAN B
GAGU NG A NG B GARA A B
NG M
70 kV sebelum 70 kV sesudah
Gambar 14. Grafik rugi daya saluran
Dari gambar 10 untuk subsistem kediri 70 kV dapat diketahui
total MVA losses mengalami penurunan setelah penambahan
shunt capacitor 10 MVar pada GI trenggalek di sisi 70 kV. Total
MVA losses saat kondisi sebelum penambahan shunt capacitor
sebesar 10 MVar pada GI trenggalek sebesar 9,111 MVA,
kemudian MVA losses mengalami penurunan setelah
penambahan shunt capacitor sebesar 10 MVar pada GI
trenggalek menjadi 8,936 MVA.
5. Penutup
5.1 Kesimpulan
Gambar 12. Kondisi tegangan setelah penambahan kapasitor Kesimpulan yang dapat diambil dari pembahasan menggunakan
Dilihat dari gambar 12, nilai tegangan yang terbaca pada bantuan perangkat lunak E-TAP 12.6 adalah:
simulasi etap untuk bus trenggalek sebesar 64 kV untuk 1. Dengan metode perhitungan manual pemasangan shunt
pengukuran pukul 10:00. kondisi tersebut juga sudah sesuai capacitor pada GI Trenggalek 70 kV diperoleh besar nilai
dengan ketentuan variasi tegangan pelayan dimana jatuh rating shunt capacitor 2 yang akan dipasang sebesar 10
tegangan yang diijinkan menurut SPLN No.1:1995 Pasal 4 hanya MVar.
sebesar -10% s/d +5%. 2. Dari hasil analisis simulasi E-TAP 12.6 untuk kondisi terburuk
tanggal 8 oktober 2018 pada GI Trenggalek setelah
penambahan shunt capacitor sebesar 10 MVar naik dan
terinjeksi tegangan 3,7 % yaitu sebesar 2,7 kV, dengan
tegangan awal 61,3 kV menjadi 64 kV untuk pengukuran
pukul 10:00.
3. Penambahan shunt capacitor sebesar 10 MVar pada sisi 70
kV GI Trenggalek mampu mengurangi rugi daya saluran di
*
Korespondensi: email penulis : akbarezan70@gmail.com
wilayah susbsistem Kediri pada saat pengukuran pukul 10:00
a) Prodi Sistem Kelistrikan, Jurusan Teknik Elektro, Polinema.
Jalan Soekarno-Hatta No. 9 Malang 65141 5 © 2019, Sistem Kelistrikan,, Jurusan Teknik Elektro, Polinema
ELPOSYS: Jurnal Sistem Kelistrikan POLINEMA
5.2 Saran
Ada beberapa hal yang dapat dikembangkan dari hasil
analisis skripsi ini, yaitu:
1. Lebih mempertimbangkan keuntungan penggunaan shunt
capacitor di banding kan dengan melakukan up-rating untuk
mengatasi masalah ketidakstabilan tegangan di GI trenggalek.
2. Untuk trafo IBT Ponorogo jika usia trafo sudah tua dan tiba
saatnya pergantian trafo maka disarankan untuk memilih
spesifikasi trafo yang sesuai dengan sistem yang ada yaitu
150/70 kV.
Daftar Pustaka
[1] Hermawan, A. 2008. Distribusi dan Transmisi Sistem Tenaga
Listrik. Malang: Politeknik Negeri Malang, hal 57-64.
[2] Boylestad, R.L. 2010. Introductory Circuit Analysis. Newy
Jersey: Prentice-Hall International Inc.
[3] Hosea, E. 2001. Optimasi Penentuan Lokasi Switched 20 kV
Power Capacitor pada Jaringan Distribusi 20 kV Jawa
Timur. Surabaya: Universitas Kristen Petra, hal 3.
[4] Anonim 5. (2014). Buku PLN : Teori Dasar Listrik, Jakarta:
PT.PLN (Persero), hal 8 & 38.
[5] Sigi, S. 2017. Anslisis Sistem Tenaga 2. Malang: Politeknik
Negeri Malang, hal 49-50 dan 90-91.
*
Korespondensi: email penulis : akbarezan70@gmail.com
a) Prodi Sistem Kelistrikan, Jurusan Teknik Elektro, Polinema.
Jalan Soekarno-Hatta No. 9 Malang 65141 6 © 2019, Sistem Kelistrikan,, Jurusan Teknik Elektro, Polinema