Satellite Plaza Design option costing for RCC wall in Perimeter

10mm
Steel Quantities per Rmt of RCC 63.70 kgs
Wall 12mm 81.29 kgs
16mm 82.66 kgs For 57.93 Mts
Total 227.65 kgs 13,187.04 Kgs

Steel for Wall and Footing 190.00 Rft 57.93 Rmt

Rcc Wall option


Item Description Nos Qty Unit Rate Amount
Rcc Work for Retaining wall for
1
190 Rft 4,939.00 Cft 400.00 19,75,600.00
M.S. Bars for Reinforcement 1 13.19 Tonnes 65,000.00 8,57,157.77
Shuttering Cost 1 3,800.00 Sft 28.00 1,06,400.00
Excavation & Earthwork 1 3,990.00 Cft 5.00 19,950.00
29,59,107.77

No of piles required @ 750mm C/C = 77.24 nos


wt/Rmt Wt in Kgs
16mm 8 6.45 51.6 1.578 81.42
Each pile steel requirement
8mm 1 15.32 15.32 0.395 6.05
87.48

Piling Work option


Item Description Nos Qty Unit Rate Amount
Rcc Work for piles 78 1,276.08 Cft 380.00 4,84,910.40
M.S. Bars for Reinforcement 78 68.25 Tonnes 65,000.00 44,36,250.00
Labour for 6.45 Mt pile 78 503.10 Rmt 1,250.00 6,28,875.00
- -
55,50,035.40