Desain Sistem Perpipaan 6 Days Fri 10/1/21 Fri 10/8/21 1
Desain Sistem Perpipaan 6 Days Fri 10/1/21 Fri 10/8/21 1
September 2021 Finish WBS October 2021 November 2021 December 2021
Mode 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7
1 Desain Sistem Perpipaan 6 days Fri 10/1/21 Fri 10/8/21 1
2 PFD 2 days Fri 10/1/21 Mon 10/4/21 1.1
3 P&ID 4 days Tue 10/5/21 Fri 10/8/21 1.2
4 Tinjauan Lokasi 9 days Mon 10/11/21 Thu 10/21/21 2
5 survey jalur pipa 2 days Mon 10/11/21 Tue 10/12/21 2.1
6 plotplan 2 days Wed 10/13/21 Thu 10/14/21 2.2
7 isometri 3 days Fri 10/15/21 Tue 10/19/21 2.3
8 routing pipa 2 days Wed 10/20/21 Thu 10/21/21 2.4
9 Persiapan pengerjaan 8 days Fri 10/22/21 Tue 11/2/21 3
10 pembelian material 2 days Fri 10/22/21 Mon 10/25/21 3.1
11 penyewaan alat 2 days Tue 10/26/21 Wed 10/27/21 3.2
12 transport material 5 days Tue 10/26/21 Mon 11/1/21 3.3
13 transport alat 4 days Thu 10/28/21 Tue 11/2/21 3.4
14 Instalasi 12 days Wed 11/3/21 Thu 11/18/21 4
15 PL-82502-2 (sistem penyaluran air bersih) 2 days Wed 11/3/21 Thu 11/4/21 4.1
16 PL-82513-2 (sistem penyaluran air buangan) 2 days Fri 11/5/21 Mon 11/8/21 4.2
17 PL-82517-2 (sistem ven) 2 days Tue 11/9/21 Wed 11/10/21 4.3
18 PL-82561-3 (sistem pencegah kebakaran) 2 days Thu 11/11/21 Fri 11/12/21 4.4
19 PL-82562-3 (sistem penyaluran air hujan) 2 days Mon 11/15/21 Tue 11/16/21 4.5
20 upgrade facilities & infrastructures 2 days Wed 11/17/21 Thu 11/18/21 4.6
21 PENGUJIAN 9 days Fri 11/19/21 Wed 12/1/21 5
22 TES TEGANGAN 2 days Fri 11/19/21 Mon 11/22/21 5.1
23 TES BEBAN 2 days Tue 11/23/21 Wed 11/24/21 5.2
24 FINISHING 5 days Thu 11/25/21 Wed 12/1/21 6