Epe-196mld-Dc-Str-Sct - 105a
Epe-196mld-Dc-Str-Sct - 105a
CLIENT :
CMSC :
TITLE :
NAME SIGN DATE
PRED JMK JMK 18-Dec-19 STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING TANK
CHKD SVK/JTP SVK/JTP 18-Dec-19 FOR 196MLD WTP AT ANNUR,TIRUPPUR.
APPD MGK MGK 18-Dec-19
SIZE REV.
DOC.No. EPE/196MLD/DC/STR/SCT - 105A
A4 0
CONTENTS
1. PRESSURE CALCULATION
Unit Weight of Soil = 17.00 kN/m3
(16.83)
Total Triangular load (Soil pressure) = 16.83 kN/m2
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
2. Hydro dynamic pressure Calculation :
Height of the tank hw = 3.5 m
1.WEIGHT CALCULATION
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
mi/m = 0.36
Hence mi = 103844.04 kg
mc/m = 0.63
Hence mc = 181727.07 kg
hi/h = 0.7
Hence hi/h = 0.38 m
hi = 1.33 m
hc/h = 0.54
hc = 1.89
hi*/h = 1.25
hi* = 4.38
hc*/h = 1.39
hc* = 4.87
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
3.TIME PERIOD
Mass of one tank wall is obtained by considering itys inner dimension only,
= 20068.807 kg
= 1.45 m
2
= 26.9 kN/m
As per section 4.3.1.2 , a strip of unit width of wall is considered as cantilever and subjected
to a concentrated force
P = q*h*1
= 94.15 kN
Length of the cantilever is h' = 1.45 m
Hence d =
2
= 2.50E+07 kN/m
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
4
= 1.30E-03 m
Hence d =
= 0m
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
Multiplying factor of 1.75 is used to obtain sa/g values for 0.5% damping from that
for 5% damping
5.BASE SHEAR
Mi = 335.02 kN.m
Mc = 67.39 kN.m
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
7.OVERTURNING MOMENT
Overturning moment at the bottom ofbase slab in impulsive mode,
8.HYDRODYNAMIC PRESSURE
Distance of a point on tank wall from the bottom y = 0m
Circumferential angle φ = 0
Where Qiw,
= 0.86
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
Where Qib,
= 0.08
At base wall, y =0 ;
Where Qcw,
= 0.269
Where Qcb,
= 0.27
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
Av = 0.03
Pv = 1.03 kN/m2
Name of Project:
DOCUMENT NO. DATE
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
OPERATE AND TRANSFER BASIS FOR NEW WATER SUPPLY
SCHEME IN TIRUPPUR CITY MUNICIPAL CORPORATION.
PERIOD OF COMPLETION 24 MONTHS FOLLOWED BY 6 DESIGNED CHECKED APPROVED REV
MONTHS TRAIL RUN AND COMMISSIOING PACKAGE-2
From the above calculation, maximum hydrodynamic pressure is about 18.5 % of the hydrostatic
pressure. Hence hydrostatic pressure is considered for the design of Sludge sump.
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING
DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
3. DESIGN OF SHORT WALL
Structural Properties
2
ρ (due to water) = 34.34 kN/m (refer load calc.)
Ast Required =
2
Ast Required for Moment = 647.89 mm
Minimum Reinforcement = 0.24 %
Depth of surface zone = 125 mm
(IF(250>500,250,250/2))
Minimum Reinforcement = 300.000 mm
2
2
Ast Provided = 826.737 mm
(1000/190*0.7854*10*10) +(1000/190*0.7854*10*10)
Hence Provided Ast is ok
2
ρ (due to water) = 34.34 kN/m (refer load calc.)
Ast Required =
2
Ast Required for Moment = 128.39 mm
Minimum Reinforcement = 0.24 %
Depth of surface zone = 125 mm
(IF(250>500,250,250/2))
Minimum Reinforcement = 300.000 mm
2
2
Ast Provided = 413.368 mm
(1000/190*0.7854*10*10) +(1000/200*0.7854*0*0)
Hence Provided Ast is ok
Ast Required =
2
Ast Required for Moment = 375.66 mm
Minimum Reinforcement = 0.24 %
Depth of surface zone = 125 mm
(IF(250>500,250,250/2))
Minimum Reinforcement = 300.000 mm
2
2
Ast Provided = 420.000 mm
(1000/200*0.7854*10*10) +(1000/200*0.7854*0*0)
Hence Provided Ast is ok
(0.15<0.2)
Check for shear
((52.73*10^3)/(195*1000)
Percentage of Reinforcement = 0.22 %
(100*420/1000/132)
β = 16
Refer figure 4 for Triangular Pressure distribution & figure 1 for Rectangular Pressure Distribution
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING
DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
(17.76x1.5/0.87*500)
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING
DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
Net Moment & shear: Moment (M1+M2) = 17.53 kN-m (9.76+7.77)
Shear (R1+R2) = 24.93 kN (12.93+12)
Load factor = 1.5
Factored Moment = 26.30 kN-m
Factored Shear = 37.4 kN
The above Moment & shear is used for the Design of wall
Tension Reinforcement
Rebar diameter = 10 mm
Spacing = 200 mm
Cover = 50.00 mm
Depth of the section = 250.00 mm
Breadth of the section = 1000.00 mm
Effective depth = 195 mm
Ast Required =
2
Ast Req. for factored BM(Ast1) = 318.69 mm
Ast Req. for Axial tension(Ast2) = 61.24 mm
2
2
Ast Provided = 392.700 mm
(1000/200*0.7854*10*10)
Hence Provided Ast is ok
Check for Crack width
2
Characteristic cube strength of concrete, fck = M30 N/mm
Yield Strength of steel, fy = 500 N/mm2
Modulus Elasticity of concrete Ec= 5000xSQRT(f = 27386.13 N/mm2
Modulus Elasticity of Steel Es = 200000 N/mm2
Modulur Ratio, m, Es/Ec = 14.6
(0.099<0.2)
2
ρ (due to water) = 34.34 kN/m (refer load calc.)
(30.3299465x1.5/0.87*500)
Load factor = 1.5
Factored Moment = 40.4 kN-m (26.93)
Factored Shear = 46.23 kN
Tension Reinforcement
Rebar diameter = 10 mm
Spacing = 125 mm
Cover = 45.00 mm
Depth of the section = 250.00 mm
Breadth of the section = 1000.00 mm
Effective depth = 200 mm
Ast Required =
2
Ast Req. for factored BM(Ast1) = 483.91 mm
Ast Req. for Axial tension (Ast2) = 104.59 mm
2
2
Ast Provided = 628.320 mm
(1000/125*0.7854*10*10)
Hence Provided Ast is ok
Check for Crack width
2
Characteristic cube strength of concrete, fck = M30 N/mm
Yield Strength of steel, fy = 500 N/mm2
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING
DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
Modulus Elasticity of concrete Ec= 5000xSQRT(f = 27386.1279 N/mm2
Modulus Elasticity of Steel Es = 200000 N/mm2
Modulur Ratio, m, Es/Ec = 14.6
(0.15<0.2)
Check for shear
Unfactored Shear = 24.93 kN
Factored Shear = 37.395 kN
Nominal shear stress = 0.19 N/mm
2
((37.395*10^3)/(1000*195)
Percentage of Reinforcement = 0.2 %
(100*250/1000*195)
β = 17
2 (refer load
ρ (due to water) = 34.34 kN/m calc.)
Moment coefficient (My) = 0.1262
(The above Coefficients are taken from (mody's chart figure 4 ))
shear coefficient (Ry) = 0.5047
(The above Coefficients are taken from (mody's chart figure 4 ))
Moment @ bottom of wall = 53.09 kN-m
(0.1262x34.34x3.5x3.5)
Shear @ bottom of wall = 60.66 kN
(0.5047x34.34x3.5)
Load factor = 1.5
Ast Required =
2
Ast Required for Moment = 998.55 mm
Minimum Reinforcement = 0.24 %
Depth of surface zone = 125 mm
(IF(250>500,250,250/2))
Minimum Reinforcement = 300.000 mm
2
2
Ast Provided = 1008.619 mm
(1000/190*0.7854*10*10) +(1000/190*0.7854*12*12)
Hence Provided Ast is ok
2 (refer load
ρ (due to water) = 34.34 kN/m calc.)
Moment coefficient (My) = 0.0474
(The above Coefficients are taken from (mody's chart figure 4 ))
shear coefficient (Ry) = 0.2452
(The above Coefficients are taken from (mody's chart figure 4 ))
Moment @ bottom of wall = 19.94 kN-m
(0.0474x34.34x3.5x3.5)
Shear @ bottom of wall = 29.47 kN
(0.2452x34.34x3.5)
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF
DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
Load factor = 1.5
Ast Required =
2
Ast Required for Moment = 354.27 mm
Minimum Reinforcement = 0.24 %
Depth of surface zone = 125 mm
(IF(250>500,250,250/2))
Minimum Reinforcement = 300.000 mm
2
2
Ast Provided = 413.368 mm
(1000/190*0.7854*10*10) +(1000/180*0.7854*0*0)
Hence Provided Ast is ok
Ast Required =
2
Ast Required for Moment = 536.25 mm
Minimum Reinforcement = 0.24 %
Depth of surface zone = 125 mm
(IF(250>500,250,250/2))
Minimum Reinforcement = 300.000 mm
2
2
Ast Provided = 840.000 mm
(1000/200*0.7854*10*10) +(1000/200*0.7854*10*10)
Hence Provided Ast is ok
Provide 10 mm dia@ 200 + 10 mm dia @ 200 mm c/c(Net spacing 100 c/c )as vertical reinf. upto 1200mm height
Check for Crack width
2
Characteristic cube strength of concrete, fck = M30 N/mm
Yield Strength of steel, fy = 500 N/mm2
Modulus Elasticity of concrete Ec= 5000xSQRT(f = 27386.1279 N/mm2
Modulus Elasticity of Steel Es = 200000 N/mm2
Modulur Ratio, m, Es/Ec = 14.6
(0.14<0.2)
Check for shear
((53.28*10^3)/(195*1000)
Percentage of Reinforcement = 0.43 %
(100*840/1000/132)
β = 8
2
Ast Required for Moment = 226.14 mm
Minimum Reinforcement = 0.24 %
Depth of surface zone = 125 mm
(IF(250>500,250,250/2))
Minimum Reinforcement = 300.000 mm
2
2
Ast Provided = 395.000 mm
(1000/200*0.7854*10*10) +(1000/200*0.7854*0*0)
Hence Provided Ast is ok
Provide 10 mm dia @ 200 mm c/c as vertical reinforcement above 1200mm height
(0<0.2)
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF
DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
Check for shear
Unfactored Shear = 14.79 kN
Factored Shear = 22.19 kN
Nominal shear stress = 0.11 N/mm
2
((22.19*10^3)/(195*1000)
Percentage of Reinforcement = 0.2 %
(100*395/1000/132)
β = 17
(17.575x1.5/0.87*500)
Net Moment & shear:
Moment (M1+M2) = 22.81 kN-m (12.99+9.82)
Shear (R1+R2) = 31.83 kN (15.79+16.04)
Load factor = 1.5
Factored Moment = 34.22 kN-m
Factored Shear = 47.75 kN
The above Moment & shear is used for the Design of wall
Tension Reinforcement
Rebar diameter = 10 mm
Spacing = 150 mm
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF
DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
Cover = 50.00 mm
Depth of the section = 250.00 mm
Breadth of the section = 1000.00 mm
Effective depth = 195 mm
Ast Required =
2
Ast Req.factor BM (Ast1) = 418.34 mm
2
Ast Provided = 523.600 mm
(1000/150*0.7854*10*10)
Hence Provided Ast is ok
Check for Crack width
2
Characteristic cube strength of concrete, fck = M30 N/mm
Yield Strength of steel, fy = 500 N/mm2
Modulus Elasticity of concrete Ec= 5000xSQRT(f = 27386.13 N/mm2
Modulus Elasticity of Steel Es = 200000 N/mm2
Modulur Ratio, m, Es/Ec = 14.6
(0.151<0.2)
Horizontal Reinforcement (water Face)(For 250 thk):
Horizontal Moment (Mx)
a = 5.3
b = 3.5
a/b = 1.52
Refer figure 4 for Triangular Pressure distribution & figure 1 for Rectangular Pressure Distribution
2
ρ (due to water) = 34.34 kN/m (refer load calc.)
(27.547548x1.5/0.87*500)
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur City Municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Anna Nagar West Ext, Chennai
Corporation, Tiruppur. Ltd (NTADCL), Tiruppur
Name of Project:
CONSTRUCTION OF WATER TREATMENT PLANT OF
DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
CORPORATION PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE JMK SVK / JTP MGK 0
CONDITIONING TANK
Ast Required =
2
Ast Required = 657.83 mm
Ast Req. for Axial tension (Ast2) = 94.99 mm
2
2
Ast Provided = 785.400 mm
(1000/100*0.7854*10*10)
Hence Provided Ast is ok
Check for Crack width
2
Characteristic cube strength of concrete, fck = M30 N/mm
Yield Strength of steel, fy = 500 N/mm2
Modulus Elasticity of concrete Ec= 5000xSQRT(f = 27386.1279 N/mm2
Modulus Elasticity of Steel Es = 200000 N/mm2
Modulur Ratio, m, Es/Ec = 14.6
(0.188<0.2)
Check for shear
Unfactored Shear = 31.83 kN
Factored Shear = 47.745 kN
Nominal shear stress = 0.24 N/mm
2
((47.745*10^3)/(1000*195)
Percentage of Reinforcement = 0.27 %
(100*250/1000*195)
β = 13
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
0.25 m
0.25 m
FGL
Water Side
1
Earth Side
3.50 m
0.25 m 2
3.50 m
3.00 m
4
0.25 m
0.250 m
3
Structural Properties
Unit weight of soil = 3
17 kN/m (As per soil report)
Unit weight of liquid = 9.81 kN/m
3
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
Safe
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
0.25 m
FGL
0.25 m
0.25 m
3.5
3.00 m
0.250 m 0.250 m
Structural Properties
Unit weight of soil = 3
17 kN/m (As per soil report)
Unit weight of liquid = 9.81 kN/m
3
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
0.25 2.00 m
d
c
b
a
(128.12-6.25)
Net upward pressure @ b = 112.31 kN/m
2
(118.56-6.25)
Net Pressure at "d" distance from stem = 80.4598 kN/m
2
(86.71-6.25)
Depth of toe slab = 250 mm
Clear cover = 50 mm
Diameter of bar = 10 mm
Contractor : Client : CMSC :
M/s.Eco Protection Engineers Pvt Ltd., Tiruppur City Municipal New Tiruppur Area
Plot No:943,54th street, TVS Corporation, Tiruppur. Development
Colony,Anna Nagar West Ext, chennai Corporation Ltd
(NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY DOCUMENT NO. DATE
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, OPERATE
EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
AND TRANSFER BASIS FOR NEW WATER SUPPLY SCHEME IN
TIRUPPUR CITY MUNICIPAL CORPORATION.PERIOD OF
COMPLETION 24 MONTHS FOLLOWED BY 6 MONTHS TRAIL RUN
DESIGNED CHECKED APPROVED REV
AND COMMISSIOING PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
2
Ast Required = 23.75 mm
2
Ast Provided = 392.700 mm
(1000/200*0.7854*10*10)
Hence Provided Ast is ok
Distribution Bar:
Diameter of bar = 10 mm
2
Ast Provided = 392.700 mm
(1000/200*0.7854*10*10)
Hence Provided Ast is ok
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
2
Characteristic cube strength of concrete, fck = M30 N/mm
Yield Strength of steel, fy = 500 N/mm2
Modulus Elasticity of concrete Ec= 5000xSQRT(f = 27386.12788 N/mm2
Modulus Elasticity of Steel Es = 200000 N/mm2
Modulur Ratio, m, Es/Ec = 14.6
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
2
Concrete stress 'fc' = 0.35 N/mm
Distance 'a' = 250 mm
Strain Es in steel for the stress of 18.85 = 0.00009425 mm
Strain at the level considered ε1 = (h-x)/(d-x)*εs
Strain at the level considered ε1 = 0.0001281 mm
Strain due to stiffening effect of concrete ε2
For a limiting design surface crack width of 0.2mm
2
Self weight of Heel Slab = 6.25 kN/m (25x0.25)
2
Downward Liquid pressure = 34.335 kN/m
(9.81*3.5)
2
Total Downward Pressure = 40.585 kN/m
(34.335+6.25)
Net Upward pressure @ c = 62.06 kN/m
2
(102.64-40.585)
Net Downward pressure @ d = 39.88 kN/m
2
(40.585-0.704)
Contractor : Client : CMSC :
M/s.Eco Protection Engineers Pvt Ltd., Tiruppur City Municipal New Tiruppur Area
Plot No:943,54th street, TVS Corporation, Tiruppur. Development
Colony,Anna Nagar West Ext, chennai Corporation Ltd
(NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY DOCUMENT NO. DATE
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, OPERATE
EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
AND TRANSFER BASIS FOR NEW WATER SUPPLY SCHEME IN
TIRUPPUR CITY MUNICIPAL CORPORATION.PERIOD OF
COMPLETION 24 MONTHS FOLLOWED BY 6 MONTHS TRAIL RUN
DESIGNED CHECKED APPROVED REV
AND COMMISSIOING PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
Diameter of bar = 10 mm 12
2
Ast Required = 483.49 mm
2
Ast Provided = 987.951 mm
(1000/200*0.7854*10*10)+((1000/190*0.7854*12*12)
Hence Provided Ast is ok
Distribution Bar:
Diameter of bar = 10 mm
2
Ast Provided = 392.700 mm
(1000/200*0.7854*10*10)
Hence Provided Ast is ok
Contractor : Client : CMSC :
M/s.Eco Protection Engineers Pvt Ltd., Tiruppur City Municipal New Tiruppur Area
Plot No:943,54th street, TVS Corporation, Tiruppur. Development
Colony,Anna Nagar West Ext, chennai Corporation Ltd
(NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY DOCUMENT NO. DATE
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, OPERATE
EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
AND TRANSFER BASIS FOR NEW WATER SUPPLY SCHEME IN
TIRUPPUR CITY MUNICIPAL CORPORATION.PERIOD OF
COMPLETION 24 MONTHS FOLLOWED BY 6 MONTHS TRAIL RUN
DESIGNED CHECKED APPROVED REV
AND COMMISSIOING PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
2
Check for Shear: Nominal Shear stress tv = 0.38 N/mm
2
Characteristic cube strength of concrete, fck = M30 N/mm
Yield Strength of steel, fy = 500 N/mm2
Modulus Elasticity of concrete Ec= 5000xSQRT(f = 27386.12788 N/mm2
Modulus Elasticity of Steel Es = 200000 N/mm2
Modulur Ratio, m, Es/Ec = 14.61
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
(0.108<0.2)
Reinforcement summary
Provide Y10 @200 c/c + Y12 @190 mm C/C at top as main reinforcement and Y10@ 200 mm at top as Distribution
reinforcement.
Provide Y10 @200 mm C/C at bottom both direction
Contractor : Client : CMSC :
M/s.Eco Protection Engineers Pvt Ltd., Tiruppur City Municipal New Tiruppur Area
Plot No:943,54th street, TVS Corporation, Tiruppur. Development
Colony,Anna Nagar West Ext, chennai Corporation Ltd
(NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF CAPACITY DOCUMENT NO. DATE
196MLD EXPANDABLE TO 270MLD WITH COMPLETE SCADA
SYSTEM FOR THE ENTIRE PROJECT ON DESIGN BUILD, OPERATE
EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
AND TRANSFER BASIS FOR NEW WATER SUPPLY SCHEME IN
TIRUPPUR CITY MUNICIPAL CORPORATION.PERIOD OF
COMPLETION 24 MONTHS FOLLOWED BY 6 MONTHS TRAIL RUN
DESIGNED CHECKED APPROVED REV
AND COMMISSIOING PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING JMK SVK/JTP MGK 0
TANK
Bottom steel
Minimum Bottom steel is provided as per IS 3370 part2
Reinforcement summary
Provide Y10@200 C/C as top bar (Both Direction)
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur city municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Corporation , Thiruppur.
Anna Nagar West Ext, Chennai Ltd (NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE
JMK SVK / JTP MGK 0
CONDITIONING TANK.
6. DESIGN OF MONORAIL
Capacity of Crane = 0.5 MT
5 kN
A B
1.1m 1.1m
Consider the case - One of the Wheel load acts at Mid point & other out of span
Maximum Moment
Wheel moment
Due to Point Load (WL/4) = 3 KNm
Dead load
(wt of rail+wt of girder+self wt 1 KN/m) = 0.25 KN/m
Shear force
Maximum Shear force in the gantry girder occurs when one of the wheels is exactly over the support
Channel section
2
A2 = 0 cm
*y2 (top) = 0 cm (From Table)
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur city municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Corporation , Thiruppur.
Anna Nagar West Ext, Chennai Ltd (NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE
JMK SVK / JTP MGK 0
CONDITIONING TANK.
Top plate
2
A3 = 0 cm
*y3 (top) = 0 cm
Bottom plate
2
A4 = 0 cm
*y4 (top) = 15 cm
4
Total M.I Ixx = 726.4 cm
4
Iyy 53 cm
Section Modulus (Zxx)
3
(Ixx/Ytop) Zxx(top) = 96.853 cm
3
(Ixx/Ybot) Zxx(bot) = 96.853 cm
3
Zyy = 13.15 cm
Check for Bending stress in Tension
2
Actual stress in bottom fibre = 32.8 N/mm
(M / Z bot)
2
Allowable stress in bending = 165 N/mm
(0.66fy)
32.8 < 165 Safe Hence Ok
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur city municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Corporation , Thiruppur.
Anna Nagar West Ext, Chennai Ltd (NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE
JMK SVK / JTP MGK 0
CONDITIONING TANK.
(l T / ry D) = 6.715
X = 272.185
2
Y√(1+(1/20)*(l*T/ry*D) )
2
fcb = 272.185 N/mm
2
Permissible comp stress = 104.80 N/mm
(0.66*fcb*fy)/(fcb^1.4+fy^1.4)^(1/1.4)
2
Actual comp stress = 32.77 N/mm
(M / Z top)
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur city municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Corporation , Thiruppur.
Anna Nagar West Ext, Chennai Ltd (NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE
JMK SVK / JTP MGK 0
CONDITIONING TANK.
(l T / ry D) = 1.83
X = 2191.863
2
Y√(1+(1/20)*(l*T/ry*D) )
2
Permissible comp stress = 159.58 N/mm
Contractor : CMSC :
Client :
M/s.Eco Protection Engineers Pvt Ltd., New Tiruppur Area
Tiruppur city municipal
Plot No:943,54th street, TVS Colony, Development Corporation
Corporation , Thiruppur.
Anna Nagar West Ext, Chennai Ltd (NTADCL), Tiruppur
Name of the Project :
CONSTRUCTION OF WATER TREATMENT PLANT OF DOCUMENT NO. DATE
CAPACITY 196MLD EXPANDABLE TO 270MLD WITH
COMPLETE SCADA SYSTEM FOR THE ENTIRE PROJECT ON
DESIGN BUILD, OPERATE AND TRANSFER BASIS FOR NEW EPE/196MLD/DC/STR/SCT - 105A 18/12/2019
WATER SUPPLY SCHEME IN TIRUPPUR CITY MUNICIPAL
CORPORATION. PERIOD OF COMPLETION 24 MONTHS
FOLLOWED BY 6 MONTHS TRAIL RUN AND COMMISSIOING DESIGNED CHECKED APPROVED REV
PACKAGE-2
Title :
STRUCTURAL DESIGN CALCULATION OF SLUDGE
JMK SVK / JTP MGK 0
CONDITIONING TANK.
(0.66*fcb*fy)/(fcb^1.4+fy^1.4)^(1/1.4)
2
Actual comp stress = 34.53 N/mm
(M / Z bottom)
2
Allowable bending tensile stress = 165 N/mm
2
Actual tensile bending stress due to cantilever moment = 34.53 N/mm
In tension 34.53/165 = 0.21 < 1, OK SAFE.
In compression 34.529/159.581 = 0.22 < 1, OK SAFE.
TITLE :STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING TANK JMK SVK / JTP MGK 0
= 600 mm2
TITLE :STRUCTURAL DESIGN CALCULATION OF SLUDGE CONDITIONING TANK JMK SVK / JTP MGK 0
REINFORCEMENT SUMMARY
Provide is 2 Nos of 16 dia bar @ Top Reinforcement
Provide is 2 Nos of 16 dia bar @ Bottom Reinforcement
Provide 8 @ 150 c/c as stirrups Reinforcement.