Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

MM - 5004

OPERATION MANAGEMENT

AGGREGAT PRODUCTION PLANNING


YP63C

Farid Ardika Dasum

29120287

MASTER OF BUSINESS ADMINISTRATION


INSTITUTE TEKNOLOGI BANDUNG
2020
SCHOOL OF BUSINESS ADMINISTRATION

OPERATION MANAGEMENT

BACKGROUND
Green Production Company is producent that sell a custom apparel in Bandung. Type of
product that they sell is high involvement product which already have their own target
market. Early, Green Production company is facing bad situation because of economic
recession in 2020 that happened for Covid-19 affects. According to this condition, there
is a decreasing number of selling that is very significant. Based on this, there are many
acts that company did in respond to this situation and also survive to maintain
healthiness of this company.
Along the effort of recovery in 2020, with the appearance of the important event such as
“PILKADA” in December 2020 and other events, it can be projected that the amount of
selling will increased and it will fully recover this company.
To fully recovery, it should be balanced with good performance of this company. So,
Green Production company want to reconsideration about production strategies based
on newest situation. To utilize opportunities for big incoming events, they plan to join
tender and personal approach in any potential market. From those efforts, it resulted
projection demand in 6 months period by Green Production company, as follows :
 August: 1600
 September 1800
 October 1200
 November 800
 December 1000
 January 1400
From the calendar, it obtained total working days for each period.
Green Production Company consider three strategies which the first one is to produce
exact monthly production requirements by varying workforce size. Second plan is
strategic production to meet expected demand by maintain constant workforce. Third
plan is to produce minimum expected demand by using constant workforce and
subcontracting to meet requirements. These alternative plan is being considerate which
already correspondence to the strategic of this company while running their business.
To decide strategy, there are several consideration, as follows :
 Cost of materials for production is Rp 200.000 per unit
 Cost of subcontracting for production is Rp 20.000 more expensive than produce
it their selves
 Inventory cost is Rp 2500 per unit per month
 Recruitment and training cost is Rp 250.000 for each worker
 Lay-off cost is Rp 280.000 for each worker
 Losses from out of stock is Rp 6500 per unit
 Total amount of working hours in producing one unit is 6 hours
 Rates for each hour in normal working hour is Rp 5.000
 Over-time cost is Rp 7.000 per hour
 Production rate estimated for 4 hours per unit per workers
 Inventory left at the end of 2020 estimated as equal to 500 unit

This document is authorized for Final-Term Exam of Operational Management Subject


1
With those consideration in which there is fluctuation demand and also there is
probability that the product is not completely meet the quality control, so Green
Production Company put highest safety stock which is 30% from the total demand at
that period.

PROBLEM STATEMENT

According to the problem that explained above, company should think about the most
efficiency production strategic to meet demand fluctuation. It needs to decide so that the
production process is not interrupted by changed situation, and the amount cost that they
will expense will not be bloated.

ANALYSIST AND RESULT

Based on the problem statement above, Green Production Company begin to create
planning to know which strategies that benefit the company the most. First thing that
they do is create production planning, because it can be the most important to plan
because most of expense of this company is belong to production. Production planning
strategies intentionally do for meeting their demand. its calculation involve workers
employed, work hours in the company, inventory in and out at the company and
shortage. In common company can use pure strategy that only includes just one strategic
approach. But, It can also can use mixed strategy that involve two or more strategies.
Planning technique in terms of aggregate planning is use Cut-and-try approach which
involve costing out its various production planning that have been mentioned above and
the decision will select one that will be best strategies that will benefit company the
most and bring most efficiency.
Before start to the main calculation to decide fix strategies, it should calculate the
aggregate production for next six months. According to the calculation of aggregate
production planning, it is obtained production requirement as follows:
 August 1580
 September 1860
 October 1020
 November 680
 December 1060
 January 1520
With total production requirements from August until January is 7720 units. The
complete calculation can be seen at Exhibit 1.
To describe first alternative plan which is produce exact monthly production
requirements with the adjustment of the total amount of worker correspondent to their
needs. Based on aggregate production planning, it is obtained several number of
production requirement, the total production requirements that multiplied with the
production rates which is 6 hours per unit will resulted working hours needed in each
period. From that multiplication, it is resulted the total working hours need as follows:
 August 160
 September 144
 October 176
 November 176
 December 192
 January 152
Total of working hours above multiplied by normal working hour each day which is 8
hours to obtain total amount of workers needed each period. Based on that calculation,
total workers needed in each periods are:
 August 59
 September 78
 October 35
 November 23
 December 33
 January 60
From total workers, it can be calculated the amount of worker that should be hired or
cut- off. After that the total cost that involved adjustment of the total workers can be
obtained with multiplying the amounts of workers hired with the cost of hiring new
workers and the cost of workers laid-off with laid-off cost. Thus, total cost of this plan
is Rp 255.06 million.
Second plan is strategic that uses constant workforce and varying inventory and
stockout policy. This plan is minimizing the inventory cost and stockout based on fixed
amount of workforce. Before we begin the production modelling, it should be first
decide the optimal number of workers for the model. From the calculation, it is obtained
that total optimum workers required as 46 workers. Then, we can use the production
requirement from the production aggregate to calculate inventory cost and stock out in
December. The complete calculation can be seen at exhibit 2. From the model, we can
conclude that there is shortage trough out September and October while there is an
overstock on December. The total of stockout cost is equal to Rp 4.89 Million while
total inventory cost is equal to Rp 753 Thousand. Also, there is straight time cost of the
workers which equal to Rp
235.65 million.
Third plan is to produce minimum expected demand by using constant workforce and
subcontracting to meet requirements. This plan is considering on minimum number of
workforce while transferring the unfilled demand to third party producer or sub-
contractor. To create modelling of the plan, it needs to decide first how much workers
should be used for this plan. The number of workers is based on the lowest demand
projection on the given case, which is on November 2020 has total production
requirement of 680 unit. The calculation of number workers on that periods obtained as
much as 23 workers. Using that minimum workers means that there is an unfilled
demand from the gap of production requirement and the actual production. That gap is
the number of units to be carried by sub-contractor with marginal cost of Rp 20
Thousand increase from inhouse production. From the explanation above, it can be
calculated the total sub- contracting cost of Rp 77.13 Million on 6 months period. Also,
from the total 26 number
of workers, we can find the total straight time cost which equal to Rp 115.91 Million.
So, the total cost for this alternative plan is equal to Rp 193.04 Million. The complete
calculation for this plan can be seen at Exhibit 3.

DISCUSSION

From the result and analysist at previously chapter, company need to find which
strategy that benefit them the most. In this case, it is tightly related to the cost in which,
what strategies that has the cheapest cost to meet production requirement in this bad
situation. From the model calculation, we find that the lowest total cost is on plan 3.
This plan is using minimum amounts of workers while transferring unfilled production
requirement to sub-contractor. This alternative plan resulted the total cost of Rp. 193.04
million which is 18% saving cost from plan two and 24% saving cost from plan one.
The summarize of the total cost in each alternative plan can be seen at Exhibit 4.

CONSLUSION

From the explanation in the previous chapter, Green Production Company should use
plan 3 as their strategy in next 6 months periods which are from august until January.
This strategy is choosen because it provides the cheapest cost in compared to plan 1 and
plan 2 which will give most beneficial to the company. For sustainability needs, it is
suggested to creat good relation with subcontractor with aim to surpress the marginal
cost.
SCHOOL OF BUSINESS ADMINISTRATION

OPERATION MANAGEMENT

REFERENCE AND EXHIBIT

Operation and supply chain management fifteenth edition, F.Robert Jacobs, Richard B. Chase.
Exhibit 1 : Calculation of Plan 1
PRODUCTION PLAN 1 : EXACT PRODUCTION; VARY WORKFORCE

August September October November Desember January Total

Production requirement 1580 1860 1020 680 1060 1520 7720

Production hours requirement (Production requirement


9480 11160 6120 4080 6360 9120
x 6 hr/unit)

Working days per month 20 18 22 22 24 19

Hourse per mont per worker (Working days / 8 hr.day) 160 144 176 176 192 152

Worker required (Production hours require/Hours per


59 78 35 23 33 60
month per worker)
New workers hired (Assume opening workforce equal
0 0 0 0 10 23
to first months requirement of 59 workers)

Hiring coat (new workers hired x $250) Rp - Rp - Rp - Rp - Rp 2,500 Rp 5,750

Workers laid off 0 0 43 12 0 0

Layoff cost (Workers laif odd x $280) Rp - Rp - Rp 11,964 Rp 3,245 Rp - Rp -

Straight-time cost (production hourse require x $5 Rp 47,400 Rp 55,800 Rp 30,600 Rp 20,400 Rp 31,800 Rp 45,600

Rp 255,059

This document is authorized for Final-Term Exam of Operational Management Subject


5
Exhibit 2 : Calculation of Plan 2
Plan 2 Constant Workforce ; Vary Inventory and Stockout

August September October November Desember January Total

Beginning Inventory 500 127 -569 -420 129 601

Working days per month 20 18 22 22 24 19

Production hours available 7360 6624 8096 8096 8832 6992

Actual Production 1227 1104 1349 1349 1472 1165

Demand Forecast 1600 1800 1200 800 1000 1400

Ending Inventory 127 -569 -420 129 601 367

Shortage Cost Rp - Rp 2,845 Rp 2,050 Rp - Rp - Rp - Rp 4,895

Safety Stock 480 540 360 240 300 420

Units Excess 0 0 0 0 301 0

Inventory Cost Rp - Rp - Rp - Rp - Rp 753 Rp - Rp 753

Straight-time Cost Rp 36,800 Rp 33,120 Rp 40,480 Rp 40,480 Rp 44,160 Rp 34,960 Rp 230,000

workers 46 Rp 235,648
Exhibit 3 : Calculation of Plan 3
Plan 3: Constant Low Workforce; Subcontract

August September October November Desember January Total

Production Requirement 1580 1860 1020 680 1060 1520

Working days per Quarter 20 18 22 22 24 19

Production hours available 3709 3338 4080 4080 4451 3524

Actual Production 618 556 680 680 742 587

Unit Subcontracted 962 1304 340 0 318 933

Subcontracting cost (assuming


$20 for subcontracting)
Rp 19,236 Rp 26,073 Rp 6,800 Rp - Rp 6,364 Rp 18,655 Rp 77,127

Straight-time cost Rp 18,545 Rp 16,691 Rp 20,400 Rp 20,400 Rp 22,255 Rp 17,618 Rp 115,909

workers 23 Rp 193,036
Exhibit 4 : Summary of Total Cost in Each Plan

Production Plan Total Cost (in Rp 000)


Plan 1 Rp 255,059
Plan 2 Rp 235,648
Plan 3 Rp 193,036

Exhibit 5 : Aggregate Planning Production

Agregate production Planning Requirements

August September October November Desember January Total


Beginning
500 480 540 360 240 300 2420
Inventory
Demand
1600 1800 1200 800 1000 1400 7800
Forcaste
Safety stock (30
x Demand 480 540 360 240 300 420 2340
Forecase
Production
1580 1860 1020 680 1060 1520 7720
Requirements
Ending
480 540 360 240 300 420 2340
Inventory

You might also like