Professional Documents
Culture Documents
1974 - Gervaise - High Precision Survey and Alignment Techniques in Accelerator Construction
1974 - Gervaise - High Precision Survey and Alignment Techniques in Accelerator Construction
1974 - Gervaise - High Precision Survey and Alignment Techniques in Accelerator Construction
..
:.f
CERN/Lab.II/SU/74-2
...
·•.· .
.. .
J. GERVAISE
I
•
Geneva
April 19, 1974
I. INTRODUCTION
For the PS, the task facing the Survey Group was to measure
ground movements and the alignment of the magnets. In the case of the
ISR, the Group dealt with magnet alignment. For the SPS, it carried out,
during 1964-1970, ground stability studies on sites proposed in Europe
for the 300 GeV project, with experts from Member States, especially in
Belgium, France, Germany, Italy and the United Kingdo~and is now working
on magnet alignment. For the first time, it was entrusted by the Magnet
Group with building measurement equipment to determine the geometric shape
of the pole-pieces of the quadrupoles.
What tools did the geodesist have at his disposal in 1954? Digi-
tal computers had only just made an appearance and adjustment computations
had still to be made on calculating machines (Facit, Friden, Monroe, etc.).
The direct consequence was that the geodetic reference figure had to be
as simple as possible to avoid major adjustments which were always
- 4 -
P.O
~====~~.\
t:::;W--~\
Figure III.l.
Basic survey configuration for the L8 GeV Proton Synchrotron
- 6 -
The only available tool was, therefore, the invar wire (or tape)
used for measuring the bases at the end of a primary triangulation cover-
ing the whole country. It was J~derin, from Sweden, who, in about 1885,
suggested measuring distances with wires in catenary hung at a constant
tension, but this process could not be used until the discovery of the
metal invar with almost zero expansion, thereby solving temperature dif-
ficulties.
The third of the three tools was the Wild N3 bubble level used
with Taylor spheres placed on the bevel edges of the sockets. This
method offers a standard deviation of 0.3 mm/km.
IV. RESULTS OBTAINED AT THE END OF 1959 WITH THE 28 GeV PROTON SYNCHROTRON
AND THEIR CONSEQUENCES ON ACCELERATOR METROLOGY
Table IV.l.
'
'''
'
!
:
dr = 0.1so mm
Figure IV.l.
- 9 -
9.11.66
22.8.67
14.11.65
-
3.3.66
O.Q1 mm
Figure IV.2.
- 11 -
amount used in the world. When the PS was being built it was necessary
to use wires tiaving a length of 105.85 and 81 m. It was necessary to use
frictionless pulleys, because an excess tension of 1 g on wires of such
length resulted tn variationsdZ of the order of 10 pm. The development
of pulleys in which the ball-bearings were replaced by balance knife-edges
enabled the excess tension to be reduced to 0.002 g. During microscopic
measurements of the scales fixed at each end, it was noted that the wires
were constantly becoming elongated under a tension of 196.18 N. As we
were the first to use wires longer than 100 m with pulleys that were vir-
tually frictionless, we were naturally in a position to detect this
non-elastic elongation. The International Office of Weights and Measures
in Sevres (Paris) was immediately informed and as a result carried out
a series of tests on 24m-length of invar wire which subsequently confirmed
our results. Figure IV.3. shows the elongation of invar wire and tape
when subjected to tension for a prolonged period.
250 microns
,,....
....
200
3/
I
,
~
~ 2 - A
-
I
150
I lu
~
/
100
,·I ~
'• ~ ~·
0
/ 1 ·········
r
50
'"' an nee 2
- annee
1 fit
3
d'
-
invar
anncie
BIPM
4 mo on nee
de 24m n•
s•
796 _
anne.
traction
SIM onnlie
98,09 N
7'"' onnee
Elongation of invar wire and tape as a function of the number of years use.
Figure IV.3.
- 12 -
These results were taken from the reports of meetings of the International
Committee of Weights and Measures, 49th, 51st and 52nd sessions held in
1960, 1962 and 1963 respectively.
The PS and the machines whose design was based on it were the
last to have radial tunnels. The studies carried out at that time for
the ISR (Figure V.l.) and the SPS (Figure V.2.) already illustrate a
basic survey system based on a chain of braced quadrilater als. In the
case of the PS, the centre is real and physically exists, whereas in the
case of the ISR and SPS the centre is virtual. It was therefore neces-
sary to find a way of superimposing two sets of successive measurements.
Furthermore, the elimination of all angle measurement and the sole use
of distance measurement modified the observation equations in the comput-
ations and obliged us to reconsider the entire problem of trilateratio n
adjustments. The studies were carried out simultaneously for the ISR
and 300 GeV Programme. Today, Table IV.l. can be replaced by Table V.l.
to WEST HAll
(Ill 300m)
®
INTERSECTING
(050m)
STORAGE
+>
RINGS
Figure V.l.
Synchrotron/ISR complex. Layout of survey monuments
- 15 -
:I
/
,.v,:
r-. . • -'
-;
f J
I Jj
'
Fi:gure V.2.
- 16 -
Table V.l.
How were these results obtained and what do they mean ? For
the PS, the results shown in table V.l. are not only those necessary for
smoothing the curve but they also define the absolute spatial position
of the magnets in a fixed system of coordinat es. For the ISR, the stand-
ard deviation s indicated are those of elements located inside two adjacent
quadrilat erals. The orbit has a FODO structure consistin g of 48 magnet
periods divided into four superperi ods, whereas the complete geodetic
figure comprises 32. quadrilat erals. Figure V.3. shows one of the eight
octants of the overall framework.
Figure V.3.
-
53
B5
116~
52
51--------
---- ------------_}00 m BB- -.87
----- ----
47 ........,.__ 48 ----- ---- ---- ---
---- ------ 11 • 12
13
- 14
15 ....
41
~
42
17
- 16
35
22 """" 18
"<:::::,.
C) 33
CJ <:::) 21
36
G 23
34
0 1mm
Figure V.4.
- 18 -
invar
contact
bars tensioning weight
jack- plug
I
knife-edge 2
dial
,--- -
knife-edge 1
motor
reducing
micrometric gear
screw
positioning
male end-piece
Figure V.5 .
•
IO CM
Figure V.6.
- l ~ -
This means that from one set of alignments to the next, the
variation dr in the radius of the orbit is of the order of 0.08 mm in
relation to the theoretical orbit, but its position in space has a 99 %
chance of being inside a circle of errors of l .2 mm in diameter. The
virtual centre of the ISR is therefore located in its horizontal plane
inside a 1.2 mm diameter circle, i.e. with a relative precision of 4.10- 6,
whereas the precision in the position of a magnet in relation to another
one, inside two adjacent quadr"flaterals, is better than 0.1 mm.
Figure V.7.
..• ..
...
........
......
.....
.......
......
.........
.....
..........
.....
.....
.....
.....
......
.....
.......
.......
••••••
.......
........
.......
........
........
.........
.........
...•.••..
------6-----0----+6------
VI. THE 300 GeV PROGRAMME- AUTOMATION OF THE EQUIPMENT SINCE 1971
from using it. With the experience gained, the standard deviation speci-
fied by the manufacturer was halved, thus reducing the figure of 60 dmg
to 30 dmg in site conditions, when operated manually. At the same time,
the mechanics and electronics Section of the Group was developing an
automatic measuring system for this gyroscope; although this system did
not make a substantial improvement in the overall accuracy when working
in tunnel conditions, it nevertheless enabled operators to leave the
gyroscope to carry out the work automatically and record the transit
times on tape. The automatic gyrotheodolite is described in Technology
Note Pl7. Figure VI.l. shows the gyrotheodolite and its print-out equip-
ment.
Figure VI.l.
~ 25 ~
NG NG NG
-----------...
n+2
Figure VI.2.
0.0067 (2)
!
o.(x>so (4)
0,0065 (5)
o,OOH (6)
!
:, 0.006~ (7)
0,0067 (B)
0.0069 (9)
0.0071 (10)
o.ocrn (11}
O,Cl070 ( 12)
o.OC66 (nJ
0.0065 (14)
0,0067 (15)
o.oon (16)
0.0069 ( 17)
'~.0062 (19)
0,0067 (20)
0,0067 (21)
0,0069 (22)
o.00?6 tnl
0,009} (24)
o.ooo2 (25)
0,0072 (26)
0,0067 (32)
Figure VI.3.
0. 0061 Mean
DIFFERENCES BETWEEN DIRECT AND REVERSE
GYROSCOPIC BEARINGS ON THE 36 SIDES
H I S T 0 GRAM
- 0.0100 +
+
+ "*
+
+ "*
- 0.0050 + *****
+ *****
+ **
+ ****************
+ ***********
0.0000 + ·****************
+ -*-*******
+ ********
+ ***********
+ **
0.0050 + **
+
+
+ **
+
0.0100 +
Each * represents 1%
Figure VI.4.
- 28 -
the automatic gyrotheodo lite. No doubt the work we have done at CERN
will have dissipated the mystery surrounding the gyroscope. The results
obtained prove the gyrotheodo lite to be a reliable instrument which can
be used without hesitation, provided due care is exercised.
Figure VI.5.
- 29 -
Figure VI.6.
- 31 -
Figure VI. 7.
- 32 -
Figure VI .8.
For the first time, the Survey Group has dealt with a problem
of workshop metrology involving the development of equipment known as the
"Centipede" (Figure VI.9.) for measuring the geometry of the 3.6 metre-
long pole pieces of the SPS quadrupoles.
Figure VI.9.
~ 33 -
VII. CONCLUSION
Table VII.l.
Figure VII.l.
involving a measurement time which may be ten to one hundred times greater.
It is quite possible that when setting up 300 GeV physics experiments in
the halls, such equipment will be necessary, and metrology will thus have
a further field in which exciting research can be made.