Daily Report:: Contractor Manpower in Site

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Daily Report

Report No: SAPAC-RMAF-SAR-DR-58 Date: 26-Jul-2021


Project Name Remedial Measures Against Flooding In Al Jouf Province Annex 2

Owner Saudi Railway (SAR)

Consultant Khatib & Alami

Contractor Saudi Pan Kingdom Company -(SAPAC)


Cumulative Planned Progress % 8.22% Cumulative Actual Progress % 20.33%
Day
Sat Sun Mon Tue Wed Thu Fri

Weather Status:
Windy Rainy Cloudy Sunny/Clear
Humidity: Low Medium High
Temperature: 37°-20°
Contractor Manpower in Site : ‫األيدي العاملة لدى المقاول في الموقع‬

Administration officer
Planning Engineer

Quantity Surveyor

Auto cad operator

Total Direct M.P


QA/QC inspector
QA/QC Engineer

Total direct M.P


QA/QC Manager

Security guard
Design Engineer
Tech. office Eng
Project Manager

Auto Electrion

Desil Mechanic
Safety inspector
Chief Surveyor

-Skilled /Labor
Payroll Officer
HSE Engineer
HSE Manager

Site Engineer

Safety officer

Doc. control

Office Boy

-Operator
Surveyor

Lab tech

Driver
Forman

Total
Actual
1 1 1 1 1 1 1 2 1 1 1 1 1 5 1 1 1 1 1 23 1 1 4 27 1 1 4 5 1 43 66
Planned
1 1 1 1 1 1 1 2 1 1 1 1 1 5 1 1 1 1 1 23 1 1 1 11 1 1 4 5 1 24 47

Contractor Equipment in Site :‫المعدات لدى المقاول في الموقع‬


Roller Compactor

Concrete mixer
Concrete pump

DISEL Truck

Service Truck
Mobile Crane

ISuzu Pickup
Dump Truck
Boom Truck

Water Truck

Rental Car
Excavator

Small Car
Generator
Buldozer

Raw 4x4
Poclain
Loader

Bobcat
Grader

Total
JCB

Actual
1 3 0 3 7 1 2 0 1 1 1 0 0 1 3 6 1 10 4 6 0 51
Planned
0

Work in Progress Today Work in Progress Tomorrow & RFIs


Compaction for Bottom of Aggregate Erosion Protection ,Zone-7, Point 49, Station @ 1220+075
1 Earth Work at Points (35,36,37,41,45,47,51,54,55,56) 1
To1220+150.
2 Survey Work for Point 2 checking of cutting in point (54,55,56,35,36,37)

3 Shop Drawing Point 5,6 3

4 Riprap at Point (47) 4

5 Riprap at Point (51) 5

6 Aggregate Slope Protection Point 53 6

7 7

8 8

Progress Photograph ( Site Office Mobilization & Survey Work)

Earth Work Point 36 Earth Work Point 36

26/07/2021
Point 53 aggregate layer 2 Point 53 aggregate layer 2

Earth Work Point 37 Cut work for ditch P. 54,55,56

Areas where Work Not Available as Planned (Issue if any needed to be cleared)

Submitted By Contractor: Reviewed By Consultant:

Name: Said Mohamed (PM / Contractor Annex-2) Name: Engr. Ihab Shokry (PM - Consultant)]

Signature: Signature:

26-Jul-2021 Date:

26/07/2021