SANDVIK ASIA PVT. LTD.

[DOCUMENT TITLE]

METHOD STATEMENT FOR FAS

OBJECTIVE
The objective of this method statement is to describe the methodology to be followed for
installing Power Cabling as per the approved drawings to the required line and level as per the
approved specifications

SCOPE
Procedure shall be adopted for all the works of Architects Evolution for the Sandvik Asia Pvt.
Ltd.

REFERENCE
o Technical Specification
o Approved relevant shop drawings
o BOQ item no :- SAND-BOQ-FF-00 – SECTION D

RESPONSIBILITY
o Section in-charge/Supervisor
Concern section in-charge/Supervisor shall execute out work as per procedure and
maintain the check list for work
o QA/QC Engineer
To ensure proper methodology is being followed during execution.

SAFETY PRECAUTION
o Only skilled persons shall handle the activities
o Ensure that material handling shall be done in proper manner
o Use of PPE’s like goggles, hand gloves, helmet and safety shoes shall be ensured
o Proper lighting in work area shall be ensured
o Proper platform for the height works shall be ensured

TOOLS
o Electric drill, Measuring tape, Multi meter, Spirit level, Screw driver, Cable stripper,
Scaffolding, Ladder

METHOD STATEMENT

o Refer and understand interior layout SAND-G-FF-2002-R0 provided by designer


o Check the existing fire alarm panel and cabling route from panel to FAS system
o Establish the cabling route and mark using liner on ceiling
o Mark the position for manual call point, hooter with flasher, above and below addressable
photoelectric smoke detector
o Laying of 2C X 1.5Sq.mm red color armored cable as per marking and fixing on ceiling
using metal saddle
o Ensure that space between saddles should not exceed 1mtr
o Additional cable to be provided and tie up for smoke detector which are coming in false
ceiling and response indicator
o Installation of above false ceiling smoke detector on surface junction box and cable
termination for the same
o After false ceiling grid work completion installation of below false ceiling smoke
detector and cable termination for the same
o Covering of smoke detector after installation to avoid any damages
o Installation of manual control point and hooter with flasher and cable termination for the
same
o Termination of cable at fire alarm panel
o Necessary checking and approval shall be taken
o Necessary cleaning to be done
o Testing and commissioning of FAS system before handing over
o Creation of as built drawing