Professional Documents
Culture Documents
CH3 Design Considerations of Primary Systems Mars 2020
CH3 Design Considerations of Primary Systems Mars 2020
CH3 Design Considerations of Primary Systems Mars 2020
Design Considerations of
Primary Systems
1. Introduction
The part of the electric utility system which is between the
distribution substation and the distribution transformers is called the
primary system.
The use of shunt capacitors also improves the power factor involved
which in turn lessens the voltage drops and currents, and therefore
losses, in the portions of a distribution system between the capacitors
and the bulk power buses.
Usually, the size of the feeder conductor is kept the same throughout
the loop. It is selected to carry its normal load plus the load of the other
half of the loop.
In addition to main feeder loops, normally open lateral loops are also
used, particularly in underground systems.
Dr. Sadek DHBAIBI 11
3. Loop - Type Primary Feeder
Primary network is a
system of interconnected
feeders supplied by a
number of substations as
shown in FIGURE 3.7.
However, it is more
difficult to design and
operate than the radial or
loop systems.
FIGURE 3.7 Primary network
Dr. Sadek DHBAIBI 14
5. Primary-Feeder Voltage Levels
The primary-feeder voltage level is the most important factor
affecting the system design, cost, and operation.
The primary-feeder voltage level selection are affected by many
factors, as shown in FIGURE 3.8.
TABLE 3.1
Typical Primary Voltage Levels
In general, for a given percent voltage drop, the feeder length and
loading are direct functions of the feeder voltage level. This relationship
is known as the voltage-square rule.
Further, the same percent voltage drop will always result provided
that the following relationship exists:
where
and
FIGURE 3.10
Feeder area coverage
principle as related to
feeder voltage and a
uniformly distributed load.
Dr. Sadek DHBAIBI 20
5. Primary-Feeder Voltage Levels
For a constant percent voltage drop and a uniformly distributed load,
the feeder service area is proportional to
For example, if the new feeder voltage level is increased to twice the
previous voltage level, the new load and area that can be served with the
same percent voltage drop is
If the new feeder voltage level is increased to three times the previous
voltage level, the new load and area that can be served with the same
percent voltage drop is
Assume that all data represent either per phase dimensional values or
per unit values.
where
where
or
or
where
Therefore
FIGURE 3. 26
A distribution transformer with
internal high-voltage fuse and
load-break connectors
FIGURE 3. 27
A distribution transformer with
internal high-voltage fuses and
load-break switches
The percent voltage drop from the feed point (A) to the end of the
lateral (a) is:
%VDAa = %VDAB + %VDBa
%VDBa %VDBa’
%VDAB
FIGURE 3. 30
Voltage drops illustration
In Equation (3.32), K is a
constant determined from
FIGURE 3.31 for various
voltages and copper
conductor sizes.
The load is connected at the end of the main as lumped sum, the
effective feeder length is:
By projection
(# 4 Copper ; VLL = 4.16 kV) K = 0.01
The load is uniformly distributed along the main, the effective feeder
length is:
By projection
(# 4 Copper ; VLL = 4.16 kV) K = 0.01
The load has an increasing load density, the effective feeder length is:
By projection
(# 4 Copper ; VLL = 4.16 kV) K = 0.01
(a) Draw the one line diagram of the longest primary circuit.
(b) Determine the peak demands per lateral.
(c) Determine the peak demands on the main.
(d)Determine the percent voltage drops at the ends of laterals and main.
(e) If the 4% maximum voltage drop criterion is exceeded, find a
reasonable combination of larger conductors for the main and for the
laterals that will meet the voltage drop criterion.
FIGURE 3.35
The "longest"
primary circuit.
1 mi = 5280 ft
− The main is considered to have a lumped-sum load of 1036 kVA at
the end of its length,