Daily Report: Contractor Manpower in Site
Daily Report: Contractor Manpower in Site
Cumulative Planned Progress % (11.71 %) under review Cumulative Actual Progress % (10.30 %) under review
Day
Sat Sun Mon Tue Wed Thu Fri
Weather Status:
Windy Rainy Cloudy Sunny/Clear
Humidity: Low Medium High
Temperature: 38°-20°
Administration officer
Construction Manager
Quantity Surveyor
Planning Engineer
Design Engineer
Project Manager
Safety inspector
Chief Surveyor
Track Engineer
Security guard
-Skilled /Labor
&Accountant
HSE Engineer
HSE Manager
Site Engineer
Office Boy
-Operator
Surveyor
Lab tech
Forman
Driver
Total
Actual
1 1 1 1 3 1 1 1 1 1 3 1 1 5 22 2 17 1 3 7 4 34 56
Planned
0 0 0
Concrete mixer
Concrete pump
Low/High Bed
DISEL Truck
Mobile Crane
Boom Truck
Dump Truck
Water Truck
Machinary
Excavator
Generator
Borehole
Back hoe
Loader
Bobcat
Grader
Roller
Dozer
Total
bus
Actual
1 1 1 1 2 4 1 1 1 1 14
Planned
0
2 finish application of sealant at culvert sta 1209+550 2 Survaying Work at sta. 1228+000 (R/S) Zone 4 .
3 application of sealant at culvert st 1202+750 3 Lining of the Joint at sta. (1209+950) (RFI)
4 Surface preparation at culvert sta 1203+250 4 Borehole - SPT Machine not working (Major Maintenance requerd)
5 Borehole work at sta 1226+796 & sta 1225+987 5 Preperation for Dismantling Railway at Sta. (1212+950)
6 6
7 7
8 8
9
7/10/2021
Daily Report
Report No: OTC-SAR-DR-0030 Date: 010/07/2021
7/10/2021
Daily Report
Report No: OTC-SAR-DR-0030 Date: 010/07/2021
finish application of sealant at culvert sta 1209+550
Name: Mustafa Amer (PM / Contractor Annex-1) Name: Engr. Abdulrahman Abdullah (PM - Consultant)]
Signature: Signature:
7/10/2021