Professional Documents
Culture Documents
SNNPRG South Omo Zone Construction Departement
SNNPRG South Omo Zone Construction Departement
SNNPRG South Omo Zone Construction Departement
Departement
½¬ú>ú a _________________ ¾Ñî lØ` ______________
Contract No. Page No.
yKFÃ MSKR wrqT q$_R 01
CERTIFICATE OF PAYMENT NO. /1ST PAYMENT
Y^¨<
TITLE የገንዘቡ ልክ ብር
Project:- HOSTEL MAINTAINANCE CONSTRUCTION PROJECT
x¨< መግለጫ AMOUNT /Birr/
Location:- SNNPRS, South Omo Zone, Dasenech and Gnangatom Woreda ዋናው ውል
›W]¨< S/u?ƒ Main agreement 2,974,622.08
Variation Order
Employer:- SNNPR, Pastoralist Affairs Bureaw No.-1 -
¾Y^¨< }s^ß Suppl Agr. -
Contractor:- GENENE KUMALO GENERAL CONTRACTOR Total Sum
›T"] SG”Ç=e ድምር 2,974,622.08
Consultant:- SNNPRG South Omo Zone Design & Construction Department VAT 15%
15%ተ.ዕ.ታ 446,193.31
ጠቅላላ ድምር
Total with 15%
V.A.T.
3,420,815.39
የገንዘቡ ልክ ብር
አባሪ በሆነው የክፍያ ሰነድ ጥያቄ መሰረት እስከ ዛሬ ድረስ ተቋራጩ የሠራው ሥራና ያቀረበው ዕቃ ዋጋ Total Amount
As per the attached statement the value of work executed and for material supplied to date is 964,788.80
Privious Payment/አስቀድሞ የተከፈለ 2,853,144.47
ቁጥር ቀን የገንዘቡ ልክ ብር ተ.እ.ታ 3,817,933.27
No. Date Amount /Birr/ Vat
1 Advance Pay 892,386.62 133,857.99 ተቀናሽ የገንዘቡ ልክ ብር
2 1st pay 600,026.28 90,003.94 Deductions Amount/Birr
3 2nd pay - - 1.አስቀድሞ የተከፈለ
4 2nd pay - - Previous paymen 600,026.28
5 2.ቅናሽ
6 Rebate .0% -
7 3.መያዣ
ድምር Retention (5%) 190,896.66
Total 600,026.28 90,003.94 4.መቀጫ
Penalty -
5. የቅድምያ ክፍያ
20% Advance Payment Chek Advance Payment (30%) 892,386.62
Amount of advance taken 892,386.62 6. ድምር
Amount of advance repaied 892,386.62 Total 1,683,309.57 1,683,309.57
Out standing advance payment - 7. የተጣራ ክፍያ
Net Sum Before 15% VAT 2,134,623.70
8. 15% ተ.ዕ.ታ
VAT 15% 320,193.56
9. ጠቅላላ ድምር+15%ተ.ዕ.ታ
Total with 15% VAT 2,454,817.26
We certify that the contractor is now entitled to the sum of birr 2,351,165.16 // // only including 15% VAT.
ÃzUjW ፊርማ ቀን
ÃidqW ፊርማ ቀን
Approved By:- _____________________________ Signature ______________________ Date ______________________
NB. To be paid if only approved by the DCS's Construction work process.
¥úsb!ý የዲ/ግ/አ/ቁ/የሥራ ሂደት µLidq tkÍY xYçNMÝÝ
በደ/ብ/ብ/ሕ/ክ/ የደቡብ ኦሞ ዞን SNNPR South Omo Zone
ኮንስትራክሽን መምሪያ Construction Department
የተ.ዕ.ታ ክፍያ ምስክር ወረቀት ቁጥር
For Certificate of VAT
Y^¨< ዋናው ውል
Project:- HOSTEL MAINTAINANCE CONSTRUCTION PROJECT Main Contract 2,974,622.08
x¨<
Location:- SNNPRS, South Omo Zone, Dasenech and Gnangatom Woreda Supplementry Contract 1 -
›W]¨< S/u?ƒ Var.Ord -
Employer:- SNNPR, Pastoralist Affairs Bureaw
¾Y^¨< }s^ß 2,974,622.08
Contractor:- GENENE KUMALO GENERAL CONTRACTOR 15% VAT 446,193.31
›T"] SG”Ç=e ድምር
Consultant:- SNNPRG South Omo Zone Design & Construction Department Total sum 3,420,815.39
Previous VAT
የተከናወነው ሥራ መጠን
አስቀድሞ የተከፈለ ተ.ዕ.ታ
Amount // Birr//
ተ.ቁ የገንዘቡ ልክ የተ.እ.ታ. Amount Excuted Amount (Birr)
ቀን DATE 2,853,144.47
No. Amount (Birr) (Birr)
ÃzUjW ፊርማ ቀን
Prepared By:- Ebrahim Dawud Signature __________________ Date _______________
iDÌL ርማ ቀን
Approved By _________________________ Signature _________________ Date _______________
SNNPRG South Omo Zone Construction
Departement
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
suplmentery work
Employer:- SNNPR, Pastoralist Affairs Bureaw
¾Y^¨< }s^ß
Contractor:- GENENE KUMALO GENERAL CONTRACTOR
›T"] SG”Ç=e
Consultant:- SNNPRG South Omo Zone Design & Construction Department
ተ. የማጠቃለያ ድምር በከፊል ጠቅላላ ድምር
ቀ. መግለጫ Sub Total (Birr) Total ( Birr )
Item Description የዉለታ የተሰራ የዉለታ
No Contract Excuted Contract
S
u Dasenech Hostel
p 1 metal work 28,262.00 28,007.20
e 2 paving & flooring 75,950.00 96,040.00
r 3 carpentary & joinery 223,355.50 257,428.00
v 4 roofing work 47,771.20 65,750.40
i
s TOTAL--------- 375,338.70
o knangatom Hostel
r 1 paving & flooring 92,736.00 76,176.00
/
2 carpentary & joinery 201,707.25 221,299.20
I
n 3 metal work 29,512.00 30,416.00
s TOTAL--------- 323,955.25
p Libemuqet Hostel
e
1 paving & flooring 65,688.00 101,568.00
c
t 2 metal work 58,064.00 55,464.00
o 3 walling 27,600.00 32,640.00
r TOTAL--------- 151,352.00
GRAND TOTAL-------------- ET BIRR 850,645.95
ጠቅላላ ድምር
Total ( Birr )
የተሰራ
Excuted
447,225.60
327,891.20
189,672.00
964,788.80
SNNPRG South Omo Zone Construction
Departement
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
omorate hostale
EXCUTED CONTRAT EXCUTED
It.No DESCRIPTION UNIT UNIT RATE
AMUNT AMOUNT
CONTRACT QTY QTY
1.PAVING AND FLOORING
3.3 Supply and fix small entrance gate (0.8*1.9m) No 2.00 2.00 5,000.00 10,000.00 10,000.00
T L DESCRIPION T L DESCRIPION
1.PAVING & FLOORING b,to internal wall & concrete surface
1.1 demolish any structure exist 4 14
0 Ls 2.8
1.2 mtainten any constracted 250mm thick
basaltic 2 313.6
1 Ls 4 7
1.3 stone pavement around building 2.8
1 Ls 4 313.6
1.4 enterance ramp 2 23
0 m3 2.8 128.8
1.5 half diameter of 30cm concrete pipe 4 10
- residence block 2.8 112
7 16 L=14m+1*2(pav.)=16.0m 868 m2
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
DASENCH, OMORATE HOSTEL
CLOTH WASHING BASIN
UNI UNIT CONTRAT EXCUTED
DESCRIPTION CONTR EXCUTE
T RATE AMUNT AMOUNT
AT QTY D QTY
1 earth work
clearing and remove top soil to an
1.1 average dipth of 200mm m2 26.88 26.88 15.00 403.20 403.20
excavation for base foundation 40cm
1.2 depth m3 8.12 8.12 120.00 974.40 974.40
1.3 cartaway of excavated earth material m3 8.12 8.12 30.00 243.60 243.60
2 masonry work - -
250mm thick basaltic stone hardcore
wall rolled ,consolidated and blinded with
2.1 crushed tone m2 17.28 17.28 200.00 3,456.00 3,456.00
constraction of stone masonry wall as per
2.2 the drawing m3 2.86 2.86 1,000.00 2,856.00 2,860.00
3 concrete work - -
3.1 5cm lean concrete (c-5) distrubuted m3 0.92 0.92 3,000.00 2,754.00 2,760.00
mass concrete (c-20) on the surface of
3.2 hard corefill m3 1.73 1.73 3,000.00 5,184.00 5,190.00
3.6 2cm drainage diches as per the drawing. ls 1.00 1.00 1,000.00 1,000.00 1,000.00
4 finishing work - -
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
excuted
DESCRITION UNIT contract Qty Rate contract amount excuted amount
Qty
A-SUB STRUCTURE
1.EXCAVATION & EARTH WORK
1.1 Site clearing & removing the top soil of the whole
area in which the should be rest on it in 200 mm
thick.
M2 52.30 82.32 15.00 784.50 1,234.80
1.2 Pit excavation depth not excedding 150cm M3 48.00 79.80 250.00 12,000.00 19,949.06
1.3 Pit excavation depth excedding 150cm M3 50.00 106.40 250.00 12,500.00 26,598.75
1.4 Excavation for treanch foundation to a depth not
excedding 85cm starting fro reduced ground level
- -
a, in grade beam M3 2.00 2.76 3,000.00 6,000.00 8,268.00
b, in 20cm suspanded floor slab M2 27.00 43.60 250.00 6,750.00 10,900.63
2.3 Provide, cut and fix in position sawn tiber form work
- -
a, in grade beam M2 4.00 17.23 140.00 560.00 2,411.50
b,to suspended floor slab M2 27.00 43.60 300.00 8,100.00 13,080.75
2.4 Steel reinforcement .price shal including cutting
bending placing in postioon & tyin wire
- -
a,diameter 6mm kg 20.00 57.14 65.00 1,300.00 3,714.28
b,diameter 10mm kg 460.00 - 65.00 29,900.00 -
c, diameter 12mm kg 92.00 1,057.09 65.00 5,980.00 68,711.04
Total to summery 59,010.00 107,815.20
3. MASONARY WORK
3.1 70cm thick at the bottem & 40cm thick top stone M3
masonry foundation wall bedded in cement mortar
(1:3)
55.00 56.70 1,000.00 55,000.00 56,700.00
3.2 50cm thick basaltic or equvalent stone masonry M3
foundation wall
5.40 0.96 1,000.00 5,400.00 963.00
Total to summery 60,400.00 57,663.00
B.SUPERSTURACTURE
1.CONCRETE WORK
1.1
a, elevation column M3 1 0.67 3000 3000 2,016.00
b,top tie beam M3 1 0.93 3000 3000 2,798.40
Provide, cut and fix in position sawn tiber form work
1.2 0 -
a, elevation column M2 11 15.12 100 1100 1,512.00
b,top tie beam M2 7 16.32 100 700 1,632.40
Steel reinforcement .price shal including cutting
bending placing in postioon & tyin wire
0 -
a,diameter 6mm kg 42 34.8096 65 2730 2,262.62
b, diameter 12mm kg 140 157.42464 65 9100 10,232.60
Total to summery 19630 20,454.03
2.walling
20cm thick HCB wall bedded in cement sand mortar M2
2.1 mix 1:3 72 69.02 400 28800 27,606.40
2.2 buttem to 15cm thick HCB wall M2 30 54.91 350 10500 19,217.10
Total to summery 39300 46,823.50
3.roofing
roofing cover in G-30 CIS including ridge cover M2
fixed to zigba wood purlin with dome head nail &
plastic washer roof measured in horizontal
projection . Purlin measured separatily CIS locally
manufactured & approved by enigeener
No. of No. of
No. Location Ref. No. Shape Dia Length Bars members Total Dia 6mm Dia 8mm Dia 10mm Dia 12mm Dia14 Dia16
A. Sub - Structure
1 Grade beam
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
bill of quantity kangaten hostal
1 ls 2 7.2
2.4 supply & fix PVC 80CM down pipe 3
0 ml 2 86.4
2 8.6
3.metal work 3
3.1 maintain door & window 2 103.2
a,windows 189.6 m2
No 4.2 apply one coat of rendering
external surface
24
b, doors 1 27.2
7 No 3.2
3.2 supply & fix main enterance gate 1 87.04
1 no 1 7.6
3.3 supply & fix small enterance gate 3.2
2 no 2 48.64
3.4 fance work with barbed wire 135.68 m2
1 ls 4.3 maintain,weleding of iron bed
150 No
4.4 supply & fix bed chip wood
0 No
5.PAINTING WORK
5.1 external wall painting
4 27.2
3.2
2 696.32 m2----add front side
4 7.6
3.8
2 231.04 m2----add left+right side
927.36 m2
5.2 to plastered intrnal wall surface
4 27.2
3
2 652.8 m2----add front side
4 7.2
3
6 518.4 m2----add left+right side
1171.2 m2
5.3 chipe wood work
3 27.2
7.2 587.52 m2
---------------------------- ---------------------------
_____________
ሥራ ተቋራጭ አማካሪ መሃንዲስ የሥራ ተቆጣጣሪ/ኢንስፔክተር
Contractor Consultant Supervisor/Inspector
excuted
DESCRITION UNIT contract Qty Rate contract amount excuted amount
Qty
A-SUB STRUCTURE
1.EXCAVATION & EARTH WORK
1.1 Site clearing & removing the top soil of the whole
area in which the should be rest on it in 200 mm
thick.
M2 52.30 82.32 15.00 784.50 1,234.80
1.2 Pit excavation depth not excedding 150cm M3 48.00 79.80 250.00 12,000.00 19,949.06
1.3 Pit excavation depth excedding 150cm M3 50.00 106.40 250.00 12,500.00 26,598.75
1.4 Excavation for treanch foundation to a depth not
excedding 85cm starting fro reduced ground level
- -
a, in grade beam M3 2.00 2.76 3,000.00 6,000.00 8,268.00
b, in 20cm suspanded floor slab M2 27.00 43.60 250.00 6,750.00 10,900.63
2.3 Provide, cut and fix in position sawn tiber form work
- -
a, in grade beam M2 4.00 17.23 140.00 560.00 2,411.50
b,to suspended floor slab M2 27.00 43.60 300.00 8,100.00 13,080.75
2.4 Steel reinforcement .price shal including cutting
bending placing in postioon & tyin wire
- -
a,diameter 6mm kg 20.00 57.14 60.00 1,200.00 3,428.57
b,diameter 10mm kg 460.00 - 60.00 27,600.00 -
c, diameter 12mm kg 92.00 1,057.09 60.00 5,520.00 63,425.58
Total to summery 56,150.00 102,244.02
3. MASONARY WORK
3.1 70cm thick at the bottem & 40cm thick top stone M3
masonry foundation wall bedded in cement mortar
(1:3)
55.00 56.70 1,000.00 55,000.00 56,700.00
3.2 50cm thick basaltic or equvalent stone masonry M3
foundation wall
5.40 0.96 1,000.00 5,400.00 963.00
Total to summery 60,400.00 57,663.00
B.SUPERSTURACTURE
1.CONCRETE WORK
reinforced concrete minimum cement content 360
kg/m3 filled in to formwork and vibrated around steel
reinforcement. Bar abd form work .
1.1
0 -
a,diameter 6mm kg 42 34.8096 65 2730 2,262.62
b, diameter 12mm kg 140 157.42464 65 9100 10,232.60
Total to summery 19630 20,454.03
2.walling
20cm thick HCB wall bedded in cement sand mortar M2
mix 1:3
2.1 72 69.02 400 28800 27,606.40
2.2 buttem to 15cm thick HCB wall M2 30 54.91 350 10500 19,217.10
Total to summery 39300 46,823.50
3.roofing
roofing cover in G-30 CIS including ridge cover M2
fixed to zigba wood purlin with dome head nail &
plastic washer roof measured in horizontal
projection . Purlin measured separatily CIS locally
manufactured & approved by enigeener
No. of No. of
No. Location Ref. No. Shape Dia Length Bars members Total Dia 6mm Dia 8mm Dia 10mm Dia 12mm Dia14 Dia16
A. Sub - Structure
1 Grade beam
3.2 mass concrete (c-20) on the surface of hard corefill m3 1.73 1.73 3000
403.2 403.2
974.4 974.4
243.6 243.6
0 0
3456 3456
2856 2860
0 0
2754 2760
5184 5190
1572 1560
644 644
3480 3480
2000 2000
0 0
3000 3000
26567.2 26571.2
53134.4 53142.4
bill of quantity lebemuket hostal
2.2 Supply and fix G-28 flat sheet gutter . Price shall ml 40 250
include metal bracket support all other necessery
.dev.t length 500mm
2.3 Demolish exist chip wood ceiling maintain and fix ls 1 1 5000
8mm thick chipwood ceiling. Price include
approparate conating material with steel truss
40*50mm zigba wood batten with c/c 600mm both
ways ,middle & corner list and all ather necessary
including angle iron welding and joinng with screw to
bind ceiling butten.
2.4 Supply and fix 80mm diameter PVC down pipe as per ml 50 120
the detail drawing , price shall include metal bracket
support and all other necessary acessories .devt
length =75mm
METAL WINDOW
a) type w1 size -120*180cm No 24 24 1000
METAL DOORS
a) type D1 size -90*280cm No 7 7 1500
Total Carried summmery
4.FINISHING WORK
Finshing work shall include all surface pre-cleaning
,prparation .application of finishing . Polishing and
cleaning at the end of finishing work and all edge
works.
4.3 Maintaine ,welding of the iron bed exist in the hostal . No 150 150 150
Price shll include pre-cleaning and preparation of the
surface for painting.
4.4 Supply and fix chip wood bed 90*190cm machine cut No 150 0 100
panels is fixed on hostal dormitary
Total Carried summmery
5.PAINTING WORK
Prpare and apply by brush three coat of approparate
paint types (plastic emulsion paint or oil paint) to
5.1 To external front side plastred wall and external m2 450 653.76 40
plastered wall surfaces
5.2 To plastered internal wall surface. m2 450 878.4 40
5.3 To chip wood ceiling surface. m2 180 40
Total Carried summmery
summary of bill of quantity
for
south omo zone ,dasench worda,omoratey village
TOTAL 244710.4
CONTRACT EXCUTED
AMOUNT AMOUNT
15000 0
8000 8000
0 0
23000 8000
10000 10000
10000 0
5000 5000
6000 0
31000 15000
0 0
0 0
24000 24000
0 0
10500 10500
34500 34500
0 0
0 0
10000 19232
20000 61920
5000 22272
22500 22500
15000 0
72500 125924
0 0
18000 26150.4
18000 35136
7200 0
43200 61286.4
TAKE OFF SHEET Lebemuket cloth washing
T L DESCRIPION T L
1.PAVING & FLOORING
24 No
b, doors 1 27.2
7 No 3.2
2 174.08
1 7.6
3.2
2 48.64
222.72
150
3 27.2
3
2 489.6
3 7.6
3.6
2 164.16
653.76
3 27.2
3
2 489.6
3 7.2
3
6 388.8
878.4
DESCRIPION
4.FINISHING WORK
m2
b,to internal wall & concrete surface
m2
4.2 apply one coat of rendering external
surface
m2
4.3 maintain,weleding of iron bed
No
4.4 supply & fix bed chip wood
No
5.PAINTING WORK
5.1 external wall painting
3.4 3cm plastring of external surface of the basin m2 6.44 6.44 100 644
3cm cement screed on the surface and face of the
3.5 basin. m2 34.8 34.8 100 3480
3.6 2cm drainage diches as per the drawing. ls 1 1 2000 2000
4 finishing work 0
supply and installation of 3 inch GI (class B) with
4.1 necessary gate valves and fittings. ls 1 1 3000 3000
Total cost for one 26567.2
Total cost for two (2) 2 53134.4
EXCUTED
AMOUNT
403.2
974.4
243.6
0
3456
2860
0
2760
5190
1560
644
3480
2000
0
3000
26571.2
53142.4
lebemuket fance work
4029.48
83947.5
203760
0
0
0
0
0
136850
0
18000
10000
456587
TAKE OFF SHEET FENCE
T L DESCRIPTION
1, excavation of pite foundation
533 0.3
0.3
0.7 33.579 m3
2, mass concrete for angle iron
533 0.3
0.3
0.7 33.579 m3
3, angle iron posts
566 566 No
4, 50*50*325cm gate column
0 0
c, forme work pad & column
0 0
steel reinforcemnt bars
6mm plan bars
12mm deformed bars
5, barbed wire fance
800
2.3 1840
50
2.3 115
1955 m2
6, metal doors
1 6.1 size 400*200cm
2 6.2 size 100*200cm
SNNPRG South Omo Zone
Construction Departement
ጠቅላላ ድምር
Total ( Birr )
የተሰራ
Excuted
--------------------------
31,536.00
31,536.00
Supervisor/Inspector
DESCRITION UNIT contract Qexcuted QtRate
A-SUB STRUCTURE
1.EXCAVATION & EARTH WORK
2.2
a, in grade beam M3 2 3000
b, in 20cm suspanded floor slab M2 27 250
Provide, cut and fix in position sawn tiber form
2.3 work
a, in grade beam M2 4 140
b,to suspended floor slab M2 27 300
1.1
a, elevation column M3 1 3000
b,top tie beam M3 1 3000
Provide, cut and fix in position sawn tiber form
1.2 work
a, elevation column M2 11 100
b,top tie beam M2 7 100
784.5
12000
12500
1200
2340
1995
3240
34059.5
420
0
6000
6750
0
560
8100
0
1200
27600
5520
56150
55000
5400
60400
3000
3000
0
1100
700
0
2730
9100
19630
28800
10500
39300
18240
1740
1440
21420
1560
1200
2000
8100
12860
21000
0
0
12000
33000
9700 0
5500 0
1800 0
10800 0
14400 0
5200 21024
3600 10512
51000 31536
6.finishing work
6.1 plastering internaal ,beam & column
0 m2
6.2, external rendered
0 m2
6.3 pointing work stone masonry wall
m2
6.6 pavement around the building
1 29.2 dormintery block
1.2 35.04
2 29.2
1.2 70.08
105.12 m2
6.7 1/2 dich dia 30cm pipe drainge
1 29.2 famel dorminitery
1 29.2
2 29.2
1 58.4
87.6 ml
FOR
OMORATE HOSTEL
Price Summary
Item excuted
no Description Unit Quantity quantity Rate
OMORATE HOSTEL
A.RESIDENCE + DINNING BLOCK
1.0/ Metal Work
Supply and fix 4mm thick wire mesh for window and
door fixed on 25*25*2.5mm angle iron frame . Price shall
include one coat of antirust and two coat of synthetic
1.01 enamel paint. , m2 54.35 53.86 520
TOTAL CARRIED TO SUMMARY ..............
2.0/ Paving and Flooring Work
Supply and fix New 5cm thick floor Cement screed in
Cement sand mortar to ratio 1:3. price include
2.01 demolishing existing floor and removing cart. m2 310 392 245
TOTAL CARRIED TO SUMMARY ..............
3.0/ Carpentary and Joinery Work library
67083.84
514309.4
contract excuted
amount amount
28262 28007.2
28262 28007.2
75950 96040
75950 96040
12747.29 21068
210607.4 236360
223354.69 257428
11094.4 14438.4
20910.4 26320
16051.2 24992
48056 65750.4
SUPLEMENTRY WORK OF DASNCH HOSTAL
TAKE OF SHEET
T L DESCRIPTION
A.RESIDENCE + DINNING HALL BLOCK
1.Metal work
1.01 supply & fix wire mesh under window
& door
4 2.8
1.8 20.16
3 2.8
0.75 6.3
20 1
0.8 16
10 1
0.9 9
2 1.5
1.2 2.4
53.86 m2
2.pavening and flooring
2.01 supply & fix floor cement screed
4 14
7 392 m2
3.carpentary & joinary work
3.01 demolishing existing chip wood
7 14
7 686
23
10 230
916 m2
3.02 supply & fix chip wood
8 7
7 392
23
10 230
622 m2
4.roofing work
4.01 demolish the exisisting roof cover
18.8
9.6 180.48 m2
4.02 fix demolished roof cover by
reconstracted
18.8
5 94 m2
4.03 supply & fix ribbed sheet
2 18.8
1 37.6
2 9.6
1 19.2
56.8 m2
SUMMARY OF BILL OF QUANTITIES
FOR
Supply and fix 4mm thick wire mesh for window and
door fixed on 25*25*2.5mm angle iron frame . Price
shall include one coat of antirust and two coat of
3.02 synthetic enamel paint. , m2 32.2 30.8 520
TOTAL CARRIED TO SUMMARY ..............
76,176.00
221,299.20
30,416.00
327,891.20
49,183.68
377,074.88
contract excuted
Amount amount
85146 76176
85146 76176
16905 13708.8
183540 148838.4
50347.2 58752
250792.2 221299.2
0
14400 14400
16744 16016
31144 30416
TAKE OFF SHEET SUPPLEMNTERY WORK KANGATEN
T L DESCRIPTION
1.0 Paving and flooring work
1.01 supply & strom water 30cm dia dich &
masonry curve stone.
3 29.2
2 175.2
3 7.6
2 45.6
220.8 ml
2.0 carpentry and joinery work
2 27.2 2.01 demolish the existing chip wood
7.2 391.68 m2
2.02 supply and fix new 8mm thick chipwood
ceiling
2 27.2
7.2 391.68 m2
2.03 supply and fix new G-28 ribbed sheet
3 28.4
0.8
2 136.32
3 7.6
0.8
2 36.48
172.8 m2
3.0 metal work
3.01 all metal door & window work
a, door size 280*120cm
2 No
3.02 supply & fix 4mm thick wire mashe
20 1
0.7 14
14 1.2
1 16.8
30.8 m2
FOR
LIBEMUQET HOSTEL
Price Summary
Supply and fix 30cm thick , 40cm under ground level and 40cm
above ground level depth masonry curb stone. Price Including
tranch excavation,plastring all part of masonry curb ston,cart
1.01 away and ather necessary work. ml 142.8 220.8
TOTAL CARRIED TO SUMMARY ..............
2.0/ Metal Work
supply and fix 1.5mm thick LTZ profile framed doors, price shall
include quality cylindrical lock, one coat of antirest and two
2.01 coat of synthetic.
A) DOORS
SIZE: 280*120cm No 1 1
SIZE: 280*100cm No 3 3
SIZE: 280*150 No 2 2
supply and fix 4mm thick wire mesh for window and door fixed
on 25*25*2.5mm angle iron frame . Price include one coat of
2.02 antirust and two coat of synthetic enamel paint. , m2 38 33
TOTAL CARRIED TO SUMMARY ..............
3.0/ Walling
Supply and fix a top of between wall and roof open space filling
by 20cm HCB . Price include plastring and pointing with cement
3.01 sand mortar mix (1:3). ml 138 163.2
TOTAL CARRIED TO SUMMARY ..............
101568
55464
32640
189672
28450.8
218122.8
contract Excuted
Rate Amount Amount
T L DESCRIPTION
1.0 Paving and flooring work
1.01 supply & strom water 30cm dia dich & masonry
curve stone.
3 29.2
2 175.2
3 7.6
2 45.6
220.8 ml
2.0 metal work
2.01 all metal door & window work
a, size 280*120cm
1 No
b, size 280*100 cm
3 No
c, size 280*150cm
2 No
2.02 supply & fix 4mm thick wire mashe
18 1
0.7 12.6
14 1.2
1 16.8
2 1.5 0
1.2 3.6
33 m2
3.0 walling
3.01 supply & fix top wall & roof open space filling by
HCB
3 27.2
2 163.2 ml