Electrical PRO RED Daily Progress Report Date: 15-Oct-20

Block Detail Activity Total Qty Cumm Percentage Progress Pending Daily Plan / Plan Daily Actual / Real Forecast / Pronóstico Resource Plan / Plan Resource actual / Remark / Support Required // Observación / soporte
Achived diario diaria de recursos Recurso real requerido

Excavation 1,628 1,628 100%


laying of DC and Solar cable 5,980 5,980 100%
BLOCK 12 laying of Earthing cable 712 712 100%
laying of Solar cable 17,324 17,324 100%
backfilling 1,628 1,628 100%
Excavation 5,397 5,397 100%
laying of DC and Solar cable 21,446 21,446 100%
BLOCK 13 laying of Earthing cable 666 666 100% 20-06/termofusiones 8/21-06 termofusiones 11
laying of Solar cable 40,488 40,488 100%
backfilling 5,397 5,691 105%
Excavation 3,927 3,927 100%
laying of DC and Solar cable 14,762 14,762 100%
BLOCK 14 laying of Earthing cable 699 699 100%
laying of Solar cable 40,716 40,716 100%
backfilling 3,927 3,290 100%
Excavation 3,927 3,927 100%
laying of DC and Solar cable 14,762 14,762 100%
BLOCK 15 laying of Earthing cable 699 699 100%
laying of Solar cable 41,796 41,796 100%
backfilling 3,927 3,978 101%
Excavation 3,735 3,735 100%
laying of DC and Solar cable 14,964 14,964 100%
BLOCK 16 laying of Earthing cable 724 724 100% 30-05/ 25 unid/02-06 42 unid/24-06 38 unid/25-06 32 unid
laying of Solar cable 41,790 41,790 100%
backfilling 3,735 3,735 100%
Excavation 5,130 5,158 101%
laying of DC and Solar cable 17,453 17,453 100%
BLOCK 17 laying of Earthing cable 858 858 100%
laying of Solar cable 41,850 41,850 100%
backfilling 5,130 5,000 97%
Excavation 4,867 4,867 100%
laying of DC and Solar cable 18,626 18,626 100%
BLOCK 18 laying of Earthing cable 737 737 100% 03/06 6 termofusiones
laying of Solar cable 41,850 41,850 100%
backfilling 4,867 4,767 98%
Excavation 4,638 4,658 100%
laying of DC and Solar cable 17,372 17,372 100%
BLOCK 19 laying of Earthing cable 737 737 100%
laying of Solar cable 41,696 41,696 100%
backfilling 4,638 4,798 103%
Excavation 4,837 4,837 100%
laying of DC and Solar cable 17,450 18,084 104%
BLOCK 20 laying of Earthing cable 737 737 100% 05/06 28 termo/06/06 55 termo/08/06 19 termo
laying of Solar cable 44,624 44,624 100%
backfilling 4,837 4,715 97%
Excavation 4,638 4,617 100%
laying of DC and Solar cable 17,496 17,496 100%
BLOCK 21 laying of Earthing cable 737 737 100% 25-06 50 termo/03-07 50 termofuciones
laying of Solar cable 56,784 56,784 100% 27-06 50 termo
backfilling 4,638 4,400 95%
Excavation 4,841 4,841 100% -
laying of DC and Solar cable 18,168 18,168 100%
BLOCK 22 laying of Earthing cable 735 735 100% 03/06 50 termofusiones04/06 50 termofusiones
laying of Solar cable 41,687 41,687 100%
backfilling 4,841 4,841 100%
Excavation 4,688 4,677 100%
laying of DC and Solar cable 17,147 16,632 97%
BLOCK 23 laying of Earthing cable 732 732 100% 72 termofusiones 29-05/ 25 termofusiones 30-05
laying of Solar cable 44,624 44,624 100%
backfilling 4,688 4,627 97%
Excavation 4,841 4,695 97%
laying of DC and Solar cable 18,533 18,533 100%
BLOCK 24 laying of Earthing cable 732 732 100%
laying of Solar cable 41,696 41,696 100%
backfilling 4,841 4,695 94%
Excavation 4,841 4,841 100%
laying of DC and Solar cable 17,147 17,147 100%
BLOCK 25 laying of Earthing cable 732 732 100% - Se realizaron 28 termofusiones el 25/05
laying of Solar cable 41,696 41,696 100%
backfilling 4,841 4,695 97% Se realizó el tapado de 120 m de la primera capa
Excavation 4,688 4,688 100% -
laying of DC and Solar cable 17,888 17,888 100%
BLOCK 26 laying of Earthing cable 732 732 100% 19/06 50 termo/25-06 4 termo/27-06 29 termo/
laying of Solar cable 45,624 45,624 100%
backfilling 4,688 4,601 98%
Activity Total Qty 4597 Percentage Progress OBS:
Otras actividades realizadas: Se continua con el retiro de material excedente.
PERYMETER TRENCH FOR CCTV Excavation 1848 4587 50
AND EARTHING laying of Earthing cable 1848
laying of AC cable 1848 550 279
laying of fiber cable 550

Activity Total Qty Cumm Percentage Progress 400 Sqmm Comments


Achived
Excavation
MV laying of Earthing cable
laying of AC cable 400 Sqmm
laying of AC cable 240 Sqmm
laying of fiber cable
12
Block Detail Activity Total Qty

Instalation 17 (SCB)
Conection of DC SCB side 34 (Termination)
Conection of Earthing cable 17 (Termination)
Conection of SCB MC4 600 (Termination)
BLOCK 12
Conection of Inverter DC 37
Conection of Inverter AC 34 (Termination)
Conection of tracker MC4 600 (Termination)
Dressing of solar panels 7,722 (Panel)
Instalation 40 (SCB)
Conection of DC SCB side 80 (Termination)
Conection of Earthing cable 40 (Termination)
Conection of Inverter DC 80 (Termination)
BLOCK 13
Conection of SCB MC4 1,440 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,440 (Termination)
Dressing of solar panels 18,252 (Panel)
Instalation 40 (SCB)
Conection of DC SCB side 80 (Termination)
Conection of Earthing cable 40 (Termination)
Conection of SCB MC4 1,440 (Termination)
BLOCK 14
Conection of Inverter DC 80 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,440 (Termination)
Dressing of solar panels 18,252 (Panel)
Instalation 40 (SCB)
Conection of DC SCB side 80 (Termination)
Conection of Earthing cable 40 (Termination)
Conection of SCB MC4 1,440 (Termination)
BLOCK 15
Conection of Inverter DC 80 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,440 (Termination)
Dressing of solar panels 18,252 (Panel)
Instalation 40 (SCB)
Conection of DC SCB side 80 (Termination)
Conection of Earthing cable 40 (Termination)
Conection of SCB MC4 1,440 (Termination)
BLOCK 16
Conection of Inverter DC 80 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,440 (Termination)
Dressing of solar panels 18,252 (Panel)
Instalation 45 (SCB)
Conection of DC SCB side 90 (Termination)

BLOCK 17
Conection of Earthing cable 45 (Termination)
Conection of SCB MC4 1,488 (Termination)
BLOCK 17
Conection of Inverter DC 90 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,488 (Termination)
Dressing of solar panels 19,422 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 18
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 19
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 20
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 21
Conection of Inverter DC 88
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 22
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)

BLOCK 23
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 23
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 24
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
39 Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 25
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
Instalation 44 (SCB)
Conection of DC SCB side 88 (Termination)
Conection of Earthing cable 44 (Termination)
Conection of SCB MC4 1,464 (Termination)
BLOCK 26
Conection of Inverter DC 88 (Termination)
Conection of Inverter AC 48 (Termination)
Conection of tracker MC4 1,464 (Termination)
Dressing of solar panels 19,032 (Panel)
10/15/2020

Cumm Percentage Total Qty


Pending Daily Actual
Achived Progress worker
17 100%
34 100%
17 100%
600 100%
37 100%
34 100%
600 100%
7722 100%
40 100%
80 100%
40 100%
80 100%
1440 100%
48 100%
1137 79%
18252 100% -
40 100%
80 100%
0%
1440 100%
12 15%
48 100%
1148 80% 718 11
30652 168%
40 100%
80 100%
0%
1440 100%
80 100%
48 100%
210 15% 210 6

0%
0%
0%
0%
53 66%
48 100%
0%
13668 75%
44 98%
86 96%
0%
1416 95%
90 100%
48 100%
360 24%
19422 100%
44 100%
86 98%
0%
1428 98%
88 100%
12 25%
0%
11154 59% 11154 29
40 91%
88 100%
0%
1464 100%
14 16%
12 25%
0%

42 95%
88 100%
0%
1170 80%
0%
48 100% 48 6
0%

0%
0%
0%
0%
0%
0%
0%

40 91%
0%
0%
1314 90%
0%
0%
0%

42 95%
0%
0%
468 32% 468 4
0%
0%
0%

0%
0%
0%
0%
0%
0%
0%

39 89%
78 89%
0%
1048 72%

0%

39 89% 10 2
0%
0%
0%
0%
0%
0%
Electrical PRO RED Daily Progress Report 10/15/2020

Block Detail MV Activity Total Qty Cumm Percentage Progress Pending 400/300 Daily Actual Total Qty worker Remark / Support Required //
Achived Sqmm Observación / soporte requerido

Excavation 529 529 100%


laying of AC cable 1,515 1,515 100%
BLOCK 12-13 laying of Earthing cable 95 Sqmm 1,268 570 100%
Laying of F.O 1,268 1,268 100%
backfilling 550 550 100%
Excavation 529 549 104%
laying of AC cable 1,515 1,515 100%
BLOCK 15-16 laying of Earthing cable 95 Sqmm 500 500 100%
Laying of F.O 456 476 104%
backfilling 529 533 101%
Excavation 529 571 108%
laying of AC cable 1,515 1,511 100%
BLOCK 17-18 laying of Earthing cable 95 Sqmm 500 500 100%
Laying of F.O 456 476 104%
backfilling 529 529 100%
529 Excavation 529 529 100%
laying of AC cable 1,395 1,512 108%
BLOCK 20-21 laying of Earthing cable 95 Sqmm 500 500 100%
Laying of F.O 456 456 100%
backfilling 529 529 100%
Excavation 529 529 100%
laying of AC cable 1,515 1,456 96%
BLOCK 25-26 laying of Earthing cable 95 Sqmm 500 500 100%
Laying of F.O 456 950 208%
backfilling 529 529 100%
Excavation 780 780 100% -
laying of AC cable 2,340 2,809 120%
BLOCK 19-24 laying of Earthing cable 95 Sqmm 780 780 100%
Laying of F.O 778 778 100%
backfilling 780 780 100%
Excavation 529 621 117%
laying of AC cable 1,515 970 64%
BLOCK 22-23 laying of Earthing cable 95 Sqmm 529 529 100%
Laying of F.O 456 476 104%
Backfilling 529 529 100%
Excavation 125 166 133%
laying of AC cable 375 402 107%
BLOCK Line 13-MCR laying of Earthing cable 95 Sqmm 125 288 230%
Laying of F.O
Backfilling 125 117 94%
Excavation 1,015 1,015 100%
laying of AC cable 3,045 3,045 100%
BLOCK Line15-MCR laying of Earthing cable 95 Sqmm 1,015 1,015 100%
Laying of F.O 476 476 100%
backfilling 1,015 1,015 100%
Excavation 610 610 100%
laying of AC cable 1,830 3,250 178%
BLOCK Line 14-MCR laying of Earthing cable 95 Sqmm 610 610 100%
Laying of F.O 607 620 102%
backfilling 610 530 87%
Excavation 1,330 1,333 100%
laying of AC cable 3,990 3,990 100%
BLOCK Linea 20-MCR
laying of Earthing cable 95 Sqmm 1,330 0%
backfilling 1,330 1,250 94%
Excavation 925 930 101%
laying of AC cable 2,775 3,330 120%
BLOCK Line 19-MCR
laying of Earthing cable 95 Sqmm 925 1,560 169%
backfilling 925 558 60%
Excavation 1,660 1,587 96%
laying of AC cable 4,980 4,900 98%
BLOCK Line 25-MCR
laying of Earthing cable 95 Sqmm 1,660 0%
backfilling 1,660 1,520 92%
Excavation 1,240 1,190 96%
laying of AC cable 3,720 3,720 100%
BLOCK Line 23-MCR
laying of Earthing cable 95 Sqmm 1,240 1,250 101%
backfilling 1,240 1,172 95%
Excavation 905 905 100%
laying of AC cable 2,715 2,715 100%
BLOCK Line 18-MCR laying of Earthing cable 95 Sqmm 905 905 100%
Laying of F.O 825 484 59%
backfilling 905 880 97%
MCR-Bloque 12 668 527 79%
Bloque 12-Bloque 13 570 570 100%
Bloque 13 -Bloque 18 825 875 106%
Bloque 18- Bloque 17 456 476 104%
Bloque 17- Bloque 22 820 0%
Bloque 22-Bloque 23 456 476 104%
Bloque 23-Bloque 26 1268 870 69%
Bloque 26-Bloque 25 456 950 208%
FIBRA OPTICA
Bloque 25-Bloque 24 456 465 102%
Bloque 24-Bloque 19 778 785 101%
Bloque 19-Bloque 20 456 456 100%
Bloque 20-Bloque 21 456 475 104%
Bloque 21-Bloque 16 783 794 101%
Bloque 16-Bloque 15 456 476 104%
Bloque 15-Bloque 14 456 476 104%
Bloque 14-MCR 607 620 102%
12
Electrical PRO RED Daily Progress Report Date :15/10/2020

Cumm 400/300 Remark / Support Required // Total Qty


Activity Total Qty Percentage Progress Pending Daily Actual Machine
Achived Sqmm Observación / soporte requerido worker

Bloque 12-13 laying of Earthing cable 95 Sqmm 570 Telehandler


laying of Earthing cable 25 Sqmm

Bloque 14 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

Bloque 15-16 laying of Earthing cable 95 Sqmm 500 Telehandler


laying of Earthing cable 25 Sqmm

Bloque 17-18 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

Bloque 20-21 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

Bloque 22-23 laying of Earthing cable 95 Sqmm 476 Telehandler


laying of Earthing cable 25 Sqmm

Bloque 25-26 laying of Earthing cable 95 Sqmm 375 Telehandler


laying of Earthing cable 25 Sqmm

Bloque 19-24 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

MCR-13 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

MCR-14 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

MCR-15 laying of Earthing cable 95 Sqmm Telehandler


laying of Earthing cable 25 Sqmm Telehandler

MCR-18 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

MCR-23 laying of Earthing cable 95 Sqmm 1,217 Telehandler


laying of Earthing cable 25 Sqmm 671 Telehandler

MCR-25 laying of Earthing cable 95 Sqmm 465


laying of Earthing cable 25 Sqmm

MCR-20 laying of Earthing cable 95 Sqmm


laying of Earthing cable 25 Sqmm

MCR-19 laying of Earthing cable 95 Sqmm 1,560


laying of Earthing cable 25 Sqmm
B24-B23 laying of Earthing cable 95 Sqmm 406
laying of Earthing cable 25 Sqmm

Cumm 400/300 Remark / Support Required // Total Qty


Activity Total Qty Percentage Progress Pending Daily Actual Machine
Achived Sqmm Observación / soporte requerido worker

laying of Earthing cable 95 Sqmm Telehandler


Earthing CT
Block 12
laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm 143 Telehandler
Block 12 laying of Earthing cable 25 Sqmm 132
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 13 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm 500 Telehandler
Block 14 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm 687 Telehandler
Block 15 laying of Earthing cable 25 Sqmm 32
Earthing CT laying of Earthing cable 95 Sqmm 94 Telehandler
Block 16 laying of Earthing cable 25 Sqmm 8
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 17 laying of Earthing cable 25 Sqmm 29
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 16 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm 200 Telehandler
Block 18 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm 100 Telehandler
Block 19 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 20 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 21 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 22 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm 160 Telehandler
Block 23 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 24 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 25 laying of Earthing cable 25 Sqmm
Earthing CT laying of Earthing cable 95 Sqmm Telehandler
Block 26 laying of Earthing cable 25 Sqmm
12
Electrical PRO RED Daily Progress Report 10/15/2020

Cumm Remark / Support Required //


Block Detail MV Activity Total Qty Achived Percentage Progress Daily Actual Total Qty worker Observación / soporte requerido

RMU Instalation 1 1 100%


RMU Conection 1 0 0%
Scada Panel Instalation 1 1 100%
Scada Panel Conection 1 0 0%
UPS Instalation 1 1 100%
BLOCK 12 UPS Conection 1 0 0%
Transformer LV Box Instalation 1 1 100%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 1 100%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 1 100%
RMU Instalation 1 1 100%
RMU Conection 1 0 0%
Scada Panel Instalation 1 1 100%
Scada Panel Conection 1 0 0%
UPS Instalation 1 1 100%
BLOCK 13 UPS Conection 1 0 0%
Transformer LV Box Instalation 1 1 100%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 1 100%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 1 100%
RMU Instalation 1 1 100%
RMU Conection 1 0 0%
Scada Panel Instalation 1 1 100%
Scada Panel Conection 1 0 0%
UPS Instalation 1 1 100%
BLOCK 14 UPS Conection 1 0 0%
Transformer LV Box Instalation 1 1 100%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 1 100%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 1 100%
RMU Instalation 1 1 100%
RMU Conection 1 0 0%
Scada Panel Instalation 1 1 100%
Scada Panel Conection 1 0 0%
UPS Instalation 1 1 100%
BLOCK 15 UPS Conection 1 0 0%
Transformer LV Box Instalation 1 1 100%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 1 100%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 1 100%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
Scada Panel conection 1 0 0%
UPS Instalation 1 0 0%
BLOCK 16 UPS Conection 1 0 0%
Transformer LV Box Instalation 1 1 100%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 1 100%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 1 100%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
Scada Panel Conection 1 0 0%
UPS Instalation 1 0 0%
BLOCK 17 UPS Conection 1 0 0%
Transformer LV Box Instalation 1 1 100%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK 18
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Intalation 1 0 0%
laying of AC cable 1 0 0%
laying of Earthing cable 95 Sqmm 1 0 0%
Laying of F.O 1 0 0%
Backfilling 1 0 0%
BLOCK Line 19
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK Line 20
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK Line 21
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK Linea 22
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK Line 23
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK Line 24
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK Line 25
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%
RMU Instalation 1 0 0%
RMU Conection 1 0 0%
Scada Panel Instalation 1 0 0%
UPS Instalation 1 0 0%
UPS Conection 1 0 0%
BLOCK Line 26
Transformer LV Box Instalation 1 0 0%
Transformer LV Box Conection 1 0 0%
Transformer HV Box Instalation 1 0 0%
Transformer HV Box Conection 1 0 0%
Cable Tray 1 0 0%