Professional Documents
Culture Documents
Coating Procedure - Shuqaiq Desalination PJT - Rev.2
Coating Procedure - Shuqaiq Desalination PJT - Rev.2
:
COATING WEL-Coating
Procedure
PROCEDURE -001
Owner :
Manufacturer:
Purchaser :
Weltech Co., Ltd.
Project : Shuqaiq Desalination Project
TABLE OF CONTENTS
1 Scope
2 Application Specifications
3 Technical Requirements
5 Attachments
1. Scope
This procedure describes the internal and external linings applied to the steel line pipe, the
water transport system inside the fittings.
2. Application Specifications
The specifications and standards mentioned here use the latest version of code and standards
for detailed design work.
If the specifications and standards applied do not match the contract requirements, the
contractor shall inform the engineer of the inconsistencies in this specification and
the standards and the contract documents applied to the Fusion-Bonded Epoxy lining.
Exceptions to this specification and reference documents shall be submitted by the contractor
and approved by the engineer in writing.
3. Technical Requirements
3.2.1 General
Coating applications shall be in accordance with the material manufacturer's recommendations
and the procedures described below.
<F.B.E materials>
Item Data Sheet
description Brand Name Technical Name Ref. color
Pipe Coating Contractor shall provide prior application a proven Application Control Plan for
approval by the Engineer. The approval of the said procedure is required prior commencement
of coating.
The coating material shall be applied according to the Engineer approved written application
procedure which incorporates the Manufacturer's recommendations.
Coating operation shall be suspended if the substrate temperature is less than three (3) °C
above the dew point.
The finished coating thickness shall be in the range 305 to 505 micrometers. Pipe-made
fittings are allowed a maximum DFT of 1,000 micrometers.
Any line pipe and associated fittings having less than the specified minimum dry film thickness
shall be re-blasted and coated.
The finished coating shall have a cut back at each end of 150mm (+/-10mm) on all pipes,
measured from end of pipe. Cutback and bevels shall be temporarily protected against
corrosion during storage and shipment with weldable primer coat.
<3LPE Materials>
Item
description Brand Name Technical Name Data Sheet Ref. Ral color
A) Phase
The basic steps of pipe coating shall be as follows.
- Exterior (when applying a three-layer polyethylene clad steel tube coating)
• Abrasive blasting
• Application of FBE layer for three-layer polyethylene clad steel pipes
• Apply adhesive layer
• Polyethylene layer applied
B) Abrasive blasting
Abrasive blasting shall be carried out in accordance with the pretreatment procedure.
4.1.1.1 The production test shall be carried out with the frequency indicated below.
4.1.1.2 Products of the internal Epoxy and external 3LP coating shall be tested in
accordance with approved test procedure. Testing performed for a long time or in
a laboratory may be replaced by a material manufacturer's report card.
Property Acceptable Values Minimum
Frequency
Bare steel pipes
On Arrival
Pipe Damage Minor damage/grinding <3 Each Pipe
per pipe
After Cleaning
Chloride 2 µg/cm2 1 per 100 pipe
Oil No contamination 1 per 100 pipe
Salt 3 µg/cm2 1 per 100 pipe
After Abrasive Blasting
Cleanliness ISO-Sa 2.5 Each pipe
Profile 50-100 µm 1 pipe per 100
Contamination No contamination 1 pipe per 100
Pipe Damage See clause 4.2 Each pipe
The frequency of tests shown in the table above will be for normal production operations.
This frequency of tests is subject to change at the discretion of the Engineer as a result of
change of materials or consistent poor production performance.
Additional after cleaning checks regarding chloride, oil, salt shall be executed after every stop
and start for certain hours.
The Pipe Coating Contractor’s quality control system shall include the following, as a
minimum:
- Monitoring of blasting grit and shot size
- Visual checks, in good light, of the surface of the blasted pipe
- Temperature control of the pipe surface
- Coating testing as detailed in this Specification
- Supervision of the adequate and proper repair of all defects
The following shall be recorded and logged at least once per shift:
The total coating system shall be applied to the following minimum thickness requirements:
PIPE DIAMETER PIPE BODY OVER THE MANUFACTURING
WELD
The thickness of the cooled polyethylene coating system shall be checked using Engineer
approved equipment in accordance with the requirements of DIN 30670.
WELTECH Co., LTD.
Film thickness shall be measured by use of an electronic thickness gauge. Calibration of this
gauge shall be rechecked every 2 hours. The Pipe Coating Contractor’s proposed thickness
gauge type, manufacturer and model shall be submitted to the Engineer for review and
approval.
At least 3 of the measured points per pipe length shall be on the welds.
Any individual reading less than the values above shall be cause for the coated pipe length
concerned to be quarantined. The pipe shall be held for further review by the Engineer.
4.2.1 General
External coating shall be tested in accordance with specification M20 “Fusion- Bonded Epoxy
Lining”, section 5 “Inspection, Testing and Certification” as far as applicable for external
surfaces of steel welded line pipes and pipe-made fittings.
The coating thickness test shall be executed as defined in M20 “Fusion-Bonded Epoxy Lining”.
All results for the DFT shall be as specified in paragraph 4.6 of this M23 specification, and
shall be recorded.
Once per shift or every one hundred (100) pipe lengths (whichever is the more frequent) and
at the start of using a new batch of powder the flexibility of the coating shall be determined
by a bend test. The powder utilised for the test shall be taken from the plant application fluid
bed.
The test shall be carried out in accordance with AWWA C213. If either of the bend tests fail,
the tests shall be repeated.
If both bend re-tests are satisfactory, the bend test shall be accepted.
WELTECH Co., LTD.
If either (or both) of the re-tests fail, all the pipe coated since the previous successful bend
test shall be set aside. Further coating with the suspect batch of powder shall be immediately
stopped. Two (2) specimens with the same dimensions as given in this specification shall be
cold cut from the first pipe coated from the suspect batch or since the last successful bend
test, whichever occurred later. The edges of the specimens as necessary shall be chamfered
to remove stress raisers.
If the samples fail the bend test, all pipe that has been coated with the suspect material shall
be blasted off and the pipes shall be re-coated. If the samples pass the bend test, lot
narrowing shall be used until the Engineer is satisfied that all pipes with substandard coatings
have been identified. These pipes shall be re- blasted and re-coated.
The Engineer at any time may require that the Pipe Coating Contractor prepare a set of test
specimens as defined in the Qualification Procedure (paragraph 4.2.1 in M23), and arrange
for the performance of any or all of the tests covered by Qualification Procedure at a third-
party laboratory.
4.2.5 REPAIRS
4.2.5.1 General
Each length of coated pipe leaving the Pipe Coating Contractor premises shall be free of
holidays and visual coating defects.
Defects shall be repaired in accordance with the criteria and methods below.
The requirements and the standards of acceptability for inspection and testing shall be the
same as in Sec. 5 of AWWA C213 supplemented and/or amended by the following
requirements.
4.3.1 Inspection
The Contractor shall notify the Engineer not less than thirty (30) days in advance of the start
of each production run. The Contractor shall provide the Engineer with a detailed time
schedule to permit him to witness or monitor all processing and testing phases.
The Contractor shall be responsible for all quality control checking including visual inspection,
thickness measurements, and holiday testing, and shall keep records on the results of all such
inspections in a form suitable to the Purchaser's appointed Inspector.
The Purchaser's appointed Inspector shall have access to each part of the process, and shall
have the right and opportunity to witness or monitor any of the
quality control tests and/or perform such tests himself on a random sampling basis.
The Purchaser's appointed Inspector shall have the right to stop this work pending alterations
or corrections to the process to correct all faults found in the work that result in failure to
conform to this specification.
4.3.2 Testing
5. Attachments