Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

Contractor: PMC Employer:

JOB SAFETY ANALYSIS


FOR
PRECAST CONCRETE WORKS

PROJECT: RE-CONSTRUCTION OF NORTH JETTY AT NAVAL BASE, KOCHI ON EPC CONTRACT BASIS
Document No. Date. Rev. Page.
AFC/2951/HSE/JSA/DOC-11 05.07.2021 0 Page 1 of 3

S. No. Activity / Task Hazards / Risk Initial Risk Mitigation Measure Residual Risk
1 Loading/ unloading  Slip / trip / fall High  Plan before loading and unloading. Low
 Snake bite  Allocate space for placement of precast slab
 Insufficient space  While stepping back or sideways; watch ground
condition first; balance your feet properly.
 Gumboots to be used as additional precautionary to
avoid snake / insect bite while removing shrubs
 Transportation of material and traffic to be governed by
proper supervision.
 Daily inspection checklist for EOT / Crane must be
carried and recorded and any unsafe to be highlighted
 All operator shall possess driving license and competent
 Flag man must stand outside the radius of blind spot to
get a clear view of the operator.
 Incoming and outgoing to be registered and monitored.
 Night shift illumination shall be sufficient.
 Escape route and emergency route shall be free from
obstacles.
 Speed limit 15- 20km/hr shall be adhered.
 Housekeeping shall be continuous process.
 Finished goods shall be separated and stacked properly
 Certified lifting gears shall be used, appropriately
 Loaded slab/ material to be secured with proper tie-ups
 Stack height of slabs to be limited.
2 Manual handling of  Fall of a shuttering boards from High  Avoiding loose bolting and tie rods. Low
shuttering/de- shuttering height due mishandle.  Secure load properly
 Slip/trip fall  Follow kinematic principle during handling to avoid any
body muscular strain
 'Unwanted / free movement of
 Only trained personnel shall be deployed
Shuttering boards during lifting
 Pep talk shall be given to labour engaged for shuttering
 Hands/fingers trapped between work
shuttering plates  Ensure strict Supervision.
 Use hand gloves to avoid any cut injury
 Ensure proper illumination
 Housekeeping shall be ensured.
 Proper PPE shall be provided
Contractor: PMC Employer:
JOB SAFETY ANALYSIS
FOR
PRECAST CONCRETE WORKS

PROJECT: RE-CONSTRUCTION OF NORTH JETTY AT NAVAL BASE, KOCHI ON EPC CONTRACT BASIS
Document No. Date. Rev. Page.
AFC/2951/HSE/JSA/DOC-11 05.07.2021 0 Page 2 of 3

S. No. Activity / Task Hazards / Risk Initial Risk Mitigation Measure Residual Risk
 Tagging is used in case of exposed shuttering object
 All passageways should be free from accumulations of
dust, debris or similar material
 Work to be performed under the supervision of a
competent person.
 Give training and instructions to the workers for
performing the task.
 Any sharp projections or protruding nails or similar
projections, which may cause any cutting hazard to a
worker, shall be removed or otherwise made safe by
taking suitable measures by the employer
3 Fixing / Removal  Insertion of nails Injury due to Medium  Only experienced persons engaged for constructing the Low
Shuttering exposed shuttering objects shuttering
 Skin abrasion  PPE's like Safety shoes, hand gloves, helmet shall be
provided.
 Tagging is used in case of exposed shuttering object
4 Setup of guiding frame  Hot work Medium  Obtain Hot work permit and control measure to be Low
welding work  Cutting/grinding/welding/joints followed
 Experienced persons need to be engaged and
supervised
 Proper arrangements need to be setup for working
5 EOT  Unsafe operating High  Daily inspection checklist for EOT / Crane must be Low
 Blind spot carried and recorded and any unsafe to be highlighted
 Failure of rigging tools  All operator shall possess driving license and competent
 Flag man must stand outside the radius of blind spot to
get a clear view of the operator.
 Night shift illumination shall be sufficient.
 Movements of load shall be slow and carefully guided.
 Emergency brake, stopper shall be functional
 Movement alarm shall be audible.
 Proper earthing and cable management shall be followed
Contractor: PMC Employer:
JOB SAFETY ANALYSIS
FOR
PRECAST CONCRETE WORKS

PROJECT: RE-CONSTRUCTION OF NORTH JETTY AT NAVAL BASE, KOCHI ON EPC CONTRACT BASIS
Document No. Date. Rev. Page.
AFC/2951/HSE/JSA/DOC-11 05.07.2021 0 Page 3 of 3

Mr. Prabhu B Lingam Mr. V.V Jaidev


Manager – HSE Project Manager Engineer – HSE Resident Engineer
Prepared By Reviewed By Accepted By Accepted By
Afcons Infrastructure Limited Employer/ PMC

You might also like