Job Safety Analysis FOR Precast Concrete Works
Job Safety Analysis FOR Precast Concrete Works
PROJECT: RE-CONSTRUCTION OF NORTH JETTY AT NAVAL BASE, KOCHI ON EPC CONTRACT BASIS
Document No. Date. Rev. Page.
AFC/2951/HSE/JSA/DOC-11 05.07.2021 0 Page 1 of 3
S. No. Activity / Task Hazards / Risk Initial Risk Mitigation Measure Residual Risk
1 Loading/ unloading Slip / trip / fall High Plan before loading and unloading. Low
Snake bite Allocate space for placement of precast slab
Insufficient space While stepping back or sideways; watch ground
condition first; balance your feet properly.
Gumboots to be used as additional precautionary to
avoid snake / insect bite while removing shrubs
Transportation of material and traffic to be governed by
proper supervision.
Daily inspection checklist for EOT / Crane must be
carried and recorded and any unsafe to be highlighted
All operator shall possess driving license and competent
Flag man must stand outside the radius of blind spot to
get a clear view of the operator.
Incoming and outgoing to be registered and monitored.
Night shift illumination shall be sufficient.
Escape route and emergency route shall be free from
obstacles.
Speed limit 15- 20km/hr shall be adhered.
Housekeeping shall be continuous process.
Finished goods shall be separated and stacked properly
Certified lifting gears shall be used, appropriately
Loaded slab/ material to be secured with proper tie-ups
Stack height of slabs to be limited.
2 Manual handling of Fall of a shuttering boards from High Avoiding loose bolting and tie rods. Low
shuttering/de- shuttering height due mishandle. Secure load properly
Slip/trip fall Follow kinematic principle during handling to avoid any
body muscular strain
'Unwanted / free movement of
Only trained personnel shall be deployed
Shuttering boards during lifting
Pep talk shall be given to labour engaged for shuttering
Hands/fingers trapped between work
shuttering plates Ensure strict Supervision.
Use hand gloves to avoid any cut injury
Ensure proper illumination
Housekeeping shall be ensured.
Proper PPE shall be provided
Contractor: PMC Employer:
JOB SAFETY ANALYSIS
FOR
PRECAST CONCRETE WORKS
PROJECT: RE-CONSTRUCTION OF NORTH JETTY AT NAVAL BASE, KOCHI ON EPC CONTRACT BASIS
Document No. Date. Rev. Page.
AFC/2951/HSE/JSA/DOC-11 05.07.2021 0 Page 2 of 3
S. No. Activity / Task Hazards / Risk Initial Risk Mitigation Measure Residual Risk
Tagging is used in case of exposed shuttering object
All passageways should be free from accumulations of
dust, debris or similar material
Work to be performed under the supervision of a
competent person.
Give training and instructions to the workers for
performing the task.
Any sharp projections or protruding nails or similar
projections, which may cause any cutting hazard to a
worker, shall be removed or otherwise made safe by
taking suitable measures by the employer
3 Fixing / Removal Insertion of nails Injury due to Medium Only experienced persons engaged for constructing the Low
Shuttering exposed shuttering objects shuttering
Skin abrasion PPE's like Safety shoes, hand gloves, helmet shall be
provided.
Tagging is used in case of exposed shuttering object
4 Setup of guiding frame Hot work Medium Obtain Hot work permit and control measure to be Low
welding work Cutting/grinding/welding/joints followed
Experienced persons need to be engaged and
supervised
Proper arrangements need to be setup for working
5 EOT Unsafe operating High Daily inspection checklist for EOT / Crane must be Low
Blind spot carried and recorded and any unsafe to be highlighted
Failure of rigging tools All operator shall possess driving license and competent
Flag man must stand outside the radius of blind spot to
get a clear view of the operator.
Night shift illumination shall be sufficient.
Movements of load shall be slow and carefully guided.
Emergency brake, stopper shall be functional
Movement alarm shall be audible.
Proper earthing and cable management shall be followed
Contractor: PMC Employer:
JOB SAFETY ANALYSIS
FOR
PRECAST CONCRETE WORKS
PROJECT: RE-CONSTRUCTION OF NORTH JETTY AT NAVAL BASE, KOCHI ON EPC CONTRACT BASIS
Document No. Date. Rev. Page.
AFC/2951/HSE/JSA/DOC-11 05.07.2021 0 Page 3 of 3