Professional Documents
Culture Documents
Exam 4-200 Q&A
Exam 4-200 Q&A
Explanation
For any change in the project, the first thing you should evaluate the impact on the project constraints,
then Raise a change request to address the change through the change control process.
Question: 2
Correct
Explanation
The next process after acquiring the project team is developing the team. During this process, the team is
provided with the required training as documented in the Project Management Plan.
Question: 3
Correct
Explanation
Earned Value is the work actually completed to date. It shows you the value that the project has
produced if it were terminated today.. The project's total earned value will be at its maximum during the
closing processes.
Question: 4
Correct
Explanation
The scenario implies the project is in its closing stage. Prior to delivering the final product deliverables to
the customer, formal acceptance of all relevant stakeholders must be obtained based on the project
scope, quality standards, and acceptance criteria. With stakeholder confirmation, then the project can
confidently deliver the final product to the customer.
Question: 5
Correct
Performance specifications.
Explanation
Seller performance evaluation documentation is prepared by the buyer and documents the seller’s ability
to continue to perform work on the current contract, indicates
whether the seller can be allowed to
perform work on future projects, or rates how well the seller is performing the project work or has
performed in the past.PMBOK 6th edition, Page 501
Question: 6
Correct
Create WBS
Explanation
Every project must determine the quality standards for that project and how to assure those standards.
The Plan Quality Management process identifies quality requirements and standards for the project and
its deliverables. The plan also documents how the project will demonstrate compliance with these quality
Question: 8
Correct
Cost reimbursable
Purchase Orders
Explanation
Time and material contracts are best suited when the effort is not known though the scope is clear, and
when specialist skills are required, or when staff size fluctuates. [PMBOK 6th edition, Page 472]
Question: 9
Correct
Review the issue log in order to minimize the impact on the project .
Explanation
Very important question for PMP Real exam. Based on the above options, the First step to do in project
closure is archive project information and documents for future use by the organization.
The Last step to
do in project closure is: Obtain feedback from relevant stakeholders in order to evaluate their satisfaction.
Question: 11
Correct
Cannot be determined
Explanation
Since three data points fall outside of the control limits, then the process is said to be out of control
Explanation
It’s important to update the stakeholder register on a routine basis so that new stakeholders are added,
and those who have finished their role on the project are noted as completed. .( PMBOK Guide 6th
Edition, page 480)
Question: 13
Correct
Explanation
since the Unidentified risk discovered during the project, so the fırst step is Update the Risk Register.
Question: 14
Correct
Identify Risks
Question: 15
Correct
You have been just assigned to a new project during the initiation
phase. Which of the following technique can be used to validate
project alignment with organizational strategy and expected
business value?
Present the project management plan to the relevant stakeholders for approval
Explanation
Conduct benefit analysis with relevant stakeholders to validate project alignment with organizational
strategy and expected business value.
Refer to PMP Exam Outline in the Initiating Process Group ( Task
no. 7 )
Question: 16
Correct
Update the change log and Communicate the change request status to the stakeholders
Inform the stakeholders that their change requests have been rejected
Update the lessons learned register and Communicate why the change request was rejected
Explanation
After the change request has been rejected, the Next step is Update the change log and Communicate
the change request status to the stakeholders .
Question: 17
Correct
You are the project manager for your organization that has
multiple internal stakeholders in a various department, IT
department, HR department and technical department. You
decide to prepare a stakeholder engagement strategy. Before
preparing this strategy, you first should—
Explanation
Since the new project sponsor misses weekly status meetings and Meeting minutes are regularly sent,
but appear to remain unread, there is an issue in communication. So the project manager should Send
the communication management plan to the sponsor.
Question: 19
Correct
Explanation
In the Manage Quality process, one tool and technique is quality measurement methods. Quality
improvements often occur based on recommendations from quality control, findings from quality audits,
or problem-solving. Plan-do-check-act and Six Sigma are two common quality improvement tools used to
analyze and evaluate improvement opportunities.. ( PMBOK Guide 6th Edition, page 296 )
Question: 20
Correct
Emphasize the advantage of the new method and change the technique with which costs
are managed.
Explanation
The experienced professional uses an effective cost control technique, so the project manager should
Emphasize the advantage of the new method and change the technique with which costs are managed.
Option ( Initiate a change request to resolve the issue. ) not correct because no need to issue a change
request to solve this issue. Option ( Search for solutions that are similar to the existing technique. ) not
correct because The experienced professional uses an effective cost control technique. Option ( Require
the new employee to follow the agreed-upon technique. ) wil increase the conflict and not solve the issue
Question: 21
Correct
Explanation
The resource management plan is the component of the project management plan that provides
guidance on how project resources should be categorized, allocated, managed, and released..( PMBOK
Guide 6th Edition, page 318)
Question: 22
Correct
Team charter
Project charter
Determine how many resources are required to complete the project according to the project
baseline
Explanation
A phase gate is a review point at the end of a phase to determine if the project will continue to the
succeeding phase, end the project, repeat the phase, or continue with some modifications. The business
documents and project charter are needed to determine whether or not the project should progress to the
next phase.( PMBOK Guide 6th Edition, page 21 )
Question: 25 Correct
Implement the change request in the direct and manage project work process
Update the change log and Communicate the change request status to the stakeholders
Explanation
The first step in processing any change request is to fully analyze and understand its impact on the
project constraints.
Question: 26
Correct
Explanation
He should have reviewed the communication management plans; it contains the following: • who needs
what information, and who is authorized to access that information; • When they will need the information;
• Where the information should be stored; • what format the information should be stored in; • How the
information can be retrieved. According to the PMI® Project Management Professional (PMP) ®
Examination Content Outline, the communications management plan defines and manages the flow of
project information For the exam, know that the communications management plan documents how the
communication needs of the stakeholders will be met, including the types of information that will be
communicated, who will communicate it, who receives the communication, the methods used to
communicate, the timing and frequency, the method for updating this plan as the project progresses, the
escalation process, and a glossary of common terms. [(PMBOK® Guide) – Sixth Edition, Page 377]
Question: 27 Correct
Effective Listening
Trust building
Negotiation skills
Presentation skills
Explanation
Effective listening is attempting to understand the perspective of the speaker and empathize, not
sympathize, with him or her.
Project managers must exercise both skills because they have to interact
and communicate with many stakeholders. these skills enable project managers to understand the
interests of each stakeholder and how to align those interests to achieve the goals and objectives of their
projects.
Question: 28
Correct
He should setup a meeting with a team and collaborative approach to resolve the problem.
He should take disciplinary action against team members who are not sticking to deadline
Explanation
Since the project is critical for the organization and Sometimes the team’s morale is down and can impact
the project, so the project manager should setup a meeting with a team and collaborative approach to
resolve the problem.
Question: 29
Correct
You are a buyer side project manager and have given a contract
to a small startup company. In the middle of the project, the
supplier reported to you that he won't be able to deliver all the
deliverables which are required to be completed as a part of this
project. The regular monthly payment for this supplier is
Hold a meeting with the supplier to understand delivery problems and possibly solve them.
Explanation
The best course of action in this scenario, the project manager should hold a meeting with the supplier to
understand delivery problems and possibly solve them.
Question: 30
Correct
Co-location
Explanation
Colocation involves placing many or all of the most active project team members in the same physical
location to enhance their ability to perform as a team. Colocation strategies can include a team meeting
room, common places to post schedules, and other conveniences that enhance communication and a
sense of community.[PMBOK 6th edition, Page340 ]
Question: 31
Correct
Explanation
Question: 32
Correct
Explanation
Bidder Conference is tools & Techniques used in the process "Conduct Procurement", and the output of
this is "Selected sellers", so it has to be before awarding the contract. But it takes place "Prior to the
submission" and not after "submission of bid" so that vendors can take inputs from these meetings before
final submission.[PMBOK 6th edition, Page 487]
Question: 33
Correct
Create a revised RFP containing the new information and send it by email to all vendors
Send the required information by email to only the vendor who requested the information.
Send the required information by email to all vendors who have submitted the proposals.
You should hold the bidder conference again and explain the importance of the point that
was initially missed.
Explanation
Sending the revised RFP to all vendors, explaining the required information, and receiving updated
responses to the RFP in this scenario would be fair to all vendors. It may not be practical or cost-effective
to conduct another bidder conference, especially as other aspects of the project have already been
covered in the bidding conference, which was already held. Apart from fairness, you are ensuring that
your requirements are understood. Another benefit of sending out a revised RFQ would be receiving
back more viable bids from other vendors. Option B. May sound reasonable, but it’s better to send a
revised (RFP) instead of sending only the required information.
Question: 34
Correct
Explanation
The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources
is referred to as scope creep. Change is inevitable, so the project manager must perform all changes
through the Integrated Change Control process to avoid scope creep caused by uncontrolled changes.
Question: 35
Correct
$160,000
$170,000
$100,000
Explanation
BAC = 400,000 (given), AC= 340,000 (given), CPI = 0.80 (given), The Estimate to Completion (ETC)
equation = EAC – AC, EAC = BAC/CPI = 400,000/0.80 = 500,000. ETC = 500,000 – 340,000 = 160,000.
Question: 36
Correct
Facilitation
Interviews
Focus Groups
Explanation
In the Define Scope process, an interpersonal and team skill that is used is facilitation. It is used in
workshops and working sessions with key stakeholders, and each stakeholder may have different
expectations or areas of expertise, which can be beneficial. Facilitation then can help obtain a cross-
functional and common understanding among the stakeholders concerning project deliverables and any
project or product boundaries. [Planning] [PMBOK 6th edition, Page 145 ]
Question: 37
Correct
Don’t add the new requirements, as the work has been examined and accepted by the
stakeholders
Explanation
The change control board (CCB) have been approved the new requirement, so the project manager
should first update the change log then Update the affected baselines and inform the appropriate
stakeholders .
Your lead engineer estimates that one of the activities will most
likely require 50 weeks to complete. It could be completed in 40
weeks if all goes well, but it could take 180 weeks in the worst
case. What duration will you put into your schedule for this
activity if you do not want any scenario to weigh more than any of
the others?
90 weeks
45 weeks
70 weeks
140 weeks
Explanation
In this scenario, you do not want any scenario to weigh more than any of the others. so, In this scenario,
we will use ( Triangular distributions ). Triangular distributions equation = (P+M+O)/3. (50+40+180)/3 =
90 weeks
Question: 39
Correct
Control Schedule
Explanation
The Change requests are processed according to the change management plan and the process
for
managing change on the project by the project manager, CCB, or an assigned team member. As a result,
changes may be approved, deferred, or rejected. Approved change requests will be implemented through
the Direct and Manage Project Work process. Deferred or rejected change requests are communicated
to the person or group requesting the change.
Question: 40
Correct
Compromise
Force
Avoid
Withdrawal
Explanation
A compromise requires searching for options that bring some degree to satisfaction to all parties in order
to temporarily or partially resolve the conflict. This would be the best way to handle the current situation
as the difference of time zone is not under the control of anyone.[PMBOK 6th edition, Page 349]
Question: 41
Correct
Control Quality
Control Scope
Validate Scope
Explanation
You are in the Validate Scope process. Validate Scope is the process of formalizing acceptance of the
completed project deliverables. One of the inputs in the Validate scope process is Verified deliverables
that are completed and checked for correctness through the Control Quality process. Formal acceptance
occurs after quality control activities are performed.[PMBOK 6th edition, Page 164]
Question: 42
Correct
Two team members were arguing and fighting with each other
about how to do an activity on the project so as a response for
that, the project manager separated the two team members into
two separate groups. What conflict resolution technique did the
Project manager use in this situation?
Withdrawal
Smoothing
Compromising
Collaborating
Explanation
Withdrawal means avoiding. Conflict is avoided by moving them to different groups.
Question: 43
Correct
Communicate ground rules and ensure they are followed in all the meetings
Explanation
The project kick-off meeting is usually associated with the end of planning and the start of executing. Its
purpose is
to communicate the objectives of the project, gain the commitment of the team for the project,
and explain the roles and
responsibilities of each stakeholder.[PMBOK 6th edition, Page 86]
Question: 44
Correct
Explanation
Ignoring the key stakeholders and Escalate this issue to the sponsor will not resolve the differences. The
Best option is Meet with the key stakeholder separately to resolve the differences.
Question: 45
Correct
Explanation
Get the total for the actual costs by adding the $120,000 and $70, 000 for the Activity A and Activity B. •
Total actual cost = $120,000 + $70,000 = $190,000 • EV = % of work completed * PV Total EV = 40 % *
300,000 + 30%*200,000= $ 180,000. CPI = EV/AC = 180,000/190,000= 0.94 (over budget.
Question: 46
Correct
Management reserves
Contingency reserves
Cost baseline
Explanation
Management reserves are an amount of the project budget withheld for management control purposes
and are reserved for unforeseen work that is within scope of the project. Management reserves are
intended to address the unknown unknowns that can affect a project. The management reserve is not
Question: 47
Correct
The business case documents the business needs and the cost-
benefit analysis that justifies the project. Which of the following
best describes the responsibility of the project manager within
the Project business case?
The project manager may make recommendations to keep the project business case in
alignment with the goals and objectives of the organization.
Explanation
The project manager does not update or modify the business documents since they are not project
documents; however, the project manager may make recommendations to keep the project business
case in alignment with the goals and objectives of the organization. [PMBOK 6th edition, Page 78]
Question: 48 Correct
Explanation
Grouping risks into categories can lead to the development of more effective risk responses by focusing
attention and
effort on the areas of highest risk exposure, or by developing generic risk responses to
address groups of related risks.[PMBOK 6th edition, Page 425]
Question: 49
Correct
You are in the process of finalizing all activities for the project,
phase, or contract. Which of the following tools can be used to
improve the metrics of the organization by comparing what was
initially planned and the end result?
Variance analysis
Regression analysis
Document analysis
Explanation
Variance analysis can be used to improve the metrics of the organization by comparing what was initially
planned and the end result.[PMBOK 6th edition, Page 126]
Question: 50
Correct
Explanation
The most important element that should the team consider while creating the probability and impact
matrix is the Possible effects on the objectives of the project by taking the highest priority level
regardless
Question: 51
Correct
Historical Information
Business case
Explanation
Historical Information. Documents and data on prior projects including project files, records,
correspondence, closed
contracts, and closed projects.[PMBOK 6th edition, Page 708]
Question: 52
Correct
Define scope
Collect requirements
Identify stakeholders
Explanation
The keyword in this question is ( included in the project and which should not ) The project scope
statement is the main output form define scope process. The project scope statement is the description
of the project scope, major deliverables, assumptions, and constraints. The project scope statement
documents the entire scope, including project and product scope. It describes the project’s deliverables in
detail. It also provides a common understanding of the project scope among project stakeholders. It may
contain explicit scope exclusions that can assist in managing stakeholder expectations. [PMBOK 6th
edition, Page 154]
Question: 53
Correct
Acquisition skills.
Explanation
An interpersonal and team skill that can be used for Acquire Resources process is negotiation. Many
projects need to negotiate for required resources. The project manager need
to negotiate with:
**
Functional managers. Ensure that the project receives the best resources possible in the required
timeframe
and until their responsibilities are complete.
** Other project management teams within the
performing organization. Appropriately assign or share scarce
or specialized resources.
** External
organizations and suppliers. Provide appropriate, scarce, specialized, qualified, certified, or other
specific
team or physical resources. Special consideration should be given to external negotiating policies,
practices, processes, guidelines, legal, and other such criteria. PMBOK 6th Page, 332
Question: 54
Correct
Replan task B's start date so it begins after the completion of task A .
Explanation
The relation between task A and B is ( FS ) and the task A is delayed , so the project manager should
focus on Crashing task A and start task B at the planned time so that the deadline is unchanged. option (
Fast track task B and immediately begin work. ) not correct because Resources for task B have limited
availability. option ( Fast track task A and move task B’s start date. ) not correct because the deadline will
change. option ( Replan task B's start date so it begins after the completion of task A . ) not correct
because the deadline will change.
Question: 55
Correct
Risk mitigation
Risk avoidance
Risk Transference
Implement the changes as they are being asked for by a key stakeholder
Explanation
Any changes being asked for or requested to any approved plan need to be formally reviewed by the
Change Control Board. Note: triple constraints' is already done because in the questions he mentioned
that the Project Management Plan and the Scope baseline will be updated.
Question: 58
Correct
Ignore the customer since the product was already accepted by him
Explanation
Validate Scope process is the process of obtaining the stakeholder`s formal acceptance of the completed
project scope and associated deliverables. Verifying the project scope includes reviewing deliverables to
ensure that each is completed satisfactorily.[PMBOK 6th edition, Page 163]
Question: 59
Correct
Explanation
The histogram is one of Data representation techniques that can be used for the Control quality Process
that can demonstrate the number of defects by source or by component. Control Quality to analyze and
examine product defects (errors). (Mange Quality) to analyze and examine the issues related to the
process not to deliverables defects. [PMBOK 6th edition, Page 305 ]
Question: 60
Correct
You are in the Close Project or Phase process and have reviewed
the contracting documents to help you assess available
documentation, allow identifying lessons learned and knowledge
sharing for future projects. What is the name of the tool and
technique you will use to perform this activity?
Document analysis.
Regression analysis
Trend analysis
Explanation
Customer satisfaction is an important part of modern quality management.
Remember, customer
satisfaction is about making sure that the people who are paying for
the end product are happy with what
they get. But the way that you make sure that your
customers are happy is by meeting their needs - and
you do that by ensuring the product
the team builds meets the customer’s requirements. That’s what
quality management is
all about, and it’s an important reason that you do quality management.
Question: 63
Correct
Forcing
Smoothing
Compromise
Withdrawal
Explanation
Forcing means putting your foot down and making a decision. One person wins, one person loses, and
that’s the end of that.
muForce/direct. Pushing one’s viewpoint at the expense of others; offering only
win-lose solutions, usually enforced
through a power position to resolve an emergency. This approach
often results to a win-lose situation.[PMBOK 6th edition, Page 349]
Question: 64
Correct
Scope Management
Explanation
Proactively working with project stakeholders and resolving their issues related to project stakeholder
engagement.[PMBOK 6th edition, Page 505]
Question: 66
Correct
Requirements documentation
Project charter
Explanation
The statement enables the project team to perform more detailed planning, guides the project team’s
work during execution, and provides the baseline for evaluating whether requests for changes or
additional work are contained within or outside the project’s boundaries. [PMBOK 6th edition, Page 154]
Interactive communication.
Pull communication.
Explanation
Interactive communication is the best communication method to maintain and improve relationships with
the stakeholders
Question: 68
Correct
Process flow
Matrix diagrams
Mind mapping
Explanation
When flowcharts are used to represent the steps in a process, they are sometimes called process flows
or process flow diagrams and they can be used for process improvement as well as identifying where
quality defects can occur or where to incorporate quality checks. [PMBOK 6th edition, Page 284]
Question: 69
Correct
Explanation
Enterprise environmental factors and Organizational process assets are inputs in develop project charter.
[PMBOK 6th edition, Page 75]
Question: 70
Correct
Project charter
Requirements documentation
Business case.
Explanation
The project charter is an important input in close project or phase process and documents the project
success criteria, the approval requirements, and who will sign off on the project. [PMBOK 6th edition,
Page 124]
To deal with risks that are passively accepted and/or unidentified risks once it occurs.
Explanation
For the PMP Real Exam, a workaround is an unplanned response the Project Manager needs to take to
deal with emerging risks and risks that are passively accepted as the risk response during project
execution.
a workaround is used for unidentified risks or risks that are passively accepted (note: risks that
are accepted actively will be dealt with a Fallback).
Question: 72
Correct
Explanation
Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans,
tracking identified
risks, identifying and analyzing new risks, and evaluating risk process effectiveness
throughout the project. One of the techniques in this process is Risk reviews. Risk reviews are scheduled
regularly and should examine and document the effectiveness of risk responses in dealing with overall
project risk and with identified individual project risks. Risk reviews may also result in identification of new
individual project risks, (including secondary risks that arise from agreed-upon risk responses),
reassessment of current risks, the closing of risks that are outdated, issues that have arisen as the result
of risks that have occurred, and identification of lessons to be learned for implementation in ongoing
phases in the current project or in similar projects in the future. The risk review may be conducted as part
of a periodic project status meeting or a dedicated risk review meeting may be held, as specified in the
risk management plan. [PMBOK 6th edition, Page 453, 457]
Question: 73 Correct
Risk reassessment
Reserve analysis
Risk Audit
Explanation
Technical performance analysis is a data analysis tool and technique in Monitor Risks. Its purpose is
comparing technical performance to the schedule of technical achievement. It requires the definition of
objective, quantifiable measures of technical performance to help compare actual results against targets.
Example of these measures are weight, transaction times, number of delivered defects, or storage
capacity. The deviation can help indicate the possible impact of threats or opportunities.[PMBOK 6th
edition, Page 456]
Question: 74 Correct
You have found as you Monitor Risks that some risks have not
been closed, and some secondary risks have occurred but have
not been documented. You decide you should—
Conduct an audit
Explanation
Meetings are a tool and technique in Monitor Risks. These meetings can include risk reviews. They are
scheduled regularly to evaluate the effectiveness of risk responses in dealing with both overall and
individual risks. These reviews may identify new risks, identify secondary risks, reassess existing risks,
close outdated risks, close issues from risks that have occurred, and identify lessons learned.[PMBOK
6th edition, Page 457]
Question: 75
Correct
Performance reviews
Audits
Explanation
These reviews are a tool and technique in the Control Procurements process under data analysis, which
includes measure, control, and analyze quality, resources, schedule, and cost performance against that
in the agreement. These reviews also include identifying work packages that already are behind
schedule, over or under budget, or have resource or quality issues. Inspections and audits, are specified
in the contract and are required by the buyer to verify compliance in the seller’s work processes or
deliverables; they also are a tool and technique in this process. A status review meeting, answer d, is an
informal session to discuss performance to date. [PMBOK 6th edition, Page 498]
Question: 76
Correct
Explanation
Monitor Risks is the process of monitoring the implementation of agreed-upon risk response plans,
tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness
throughout the project. The Risk management plan,Risk register,Risk report and Work performance
reports are inputs in this process. [PMBOK 6th edition, Page 453]
Question: 77
Correct
Influencing skills
Negotiations
Explanation
In the Implement Risk Responses process, interpersonal skills are a tool and technique. Within it,
influencing is suggested. Some risk response actions may be owned by a stakeholder who is not part of
the project team. These stakeholders tend to have competing demands for their time, and the same
applies to project team member working on more than one project and working in a matrix structure. The
project manager or the person responsible for the project’s risk management activities then uses
influencing to encourage risk owners to take action.[PMBOK 6th edition, Page 451]
Question: 78
Correct
Influencing
Sensitivity analysis
Question: 80
Correct
Workaround
Change Request
Explanation
When risk is identified, the next step is to perform qualitative analysis of the risk that is analyze the risk
before response is planned.
Question: 81
Correct
Prompt list
Checklists
Hierarchical charts
Risk report
Explanation
A prompt list is a predetermined list of risk categories that might give rise to individual project risks and
that could also
act as sources of overall project risk. The prompt list can be used as a framework to aid
the project team in idea generation
when using risk identification techniques. The risk categories in the
lowest level of the risk breakdown structure can be
used as a prompt list for individual project risks. Some
common strategic frameworks are more suitable for identifying
sources of overall project risk, for example
PESTLE (political, economic, social, technological, legal, environmental), TECOP
(technical,
environmental, commercial, operational, political), or VUCA (volatility, uncertainty, complexity, ambiguity).
[PMBOK 6th edition, Page 416]
Question: 82 Correct
Problem Solving
Forcing
Withdrawal
Smoothing
Explanation
Since the Project manager discussed with the team members and then took a decision, this is an
example of problem-solving. If without discussing he would have straight away went for 3rd party solution
then it was forcing
Question: 83 Correct
Withdrawal
Forcing
Smoothing
Explanation
COMPROMISE IS THE 2ND BETTER CONFLICT RESOLUTION TECHNIQUE. THE 1ST IS PROBLEM-
SOLVING.
Question: 84
Correct
Question: 85
Correct
Meet the project team to assess the impact , then negotiate with the functional manager to
assign a new team member
Update the schedule baseline to incorporate the delay that will cause because this situation
Explanation
The project manager should meet the project team to assess the impact. Since the project manager is
working in a matrix organization, the project manager should use his skills such as negotiation with the
functional manager, to assign a new team member if he needs the team member to assign.
The sender
The receiver
Explanation
The delivery of the information is the responsibility of Both the sender and the receiver.
Question: 87
Correct
Status report
Performance report
Explanation
A status report communicates stasis. It shows what is true at a certain time. A progress report
communicates time. It shows what's happened (and even might preview what's going to happen)
Question: 88
Correct
Stakeholder Analysis
Explanation
Communication Management Plan.This Plan provides information such as frequency of communication ,
type of communication , who is responsible for communication.
Question: 89
Correct
Review the communication management plan and validate why you did not get this
information through it.
Hold a meeting with the sponsor and discuss this info with him.
Hold a meeting with your team and inform them about what will happen.
Hold a meeting with stakeholders and discuss this information openly with them
Explanation
Keyword ( you do not have the information that your project will be canceled) so the PM should Review
the communication management plan because this plan contains the Information to be communicated
and the Person or groups who will receive the information. [PMBOK 6th edition, Page 377]
Question: 90
Correct
Active listening
Cultural awareness
Political awareness
Explanation
Active listening. Techniques of active listening involve acknowledging, clarifying and confirming,
understanding, and removing barriers that adversely affect comprehension.[PMBOK 6th edition, Page
386]
Question: 91
Correct
Manage Quality
Control Quality
Validate Scope
Explanation
Plan Quality Management: Identifying the quality standards that are relevant to the project and
determining how to meet them.
Plan Quality Management—The process of identifying quality
requirements and/or standards for the project
and its deliverables, and documenting how the project will
demonstrate compliance with quality requirements and/
or standards.[PMBOK 6th edition, Page 271]
Question: 92
Correct
Control Quality
Control Scope
Validate Scope
Explanation
Control Quality is concerned with comparing the work results with the quality requirements to ensure the
result is acceptable.[PMBOK 6th edition, Page 272]
Question: 93
Correct
Ask the customer if the key feature can wait for the next release.
Explanation
Keyword ( key feature requested by the customer is missing from the requirements ) . To Add the key
feature in the final product, the project manager should Perform a change request to take the approval
from CCB. Very important question fro reall exam.
Project charter
Explanation
The statement of work (SOW) for each procurement is developed from the project scope baseline and
defines only
that portion of the project scope that is to be included within the related contract. The SOW
describes the procurement
item in sufficient detail to allow prospective sellers to determine if they are
capable of providing the products, services,
or results. Sufficient detail can vary based on the nature of
the item, the needs of the buyer, or the expected contract
form. The information included in a SOW can
include specifications, quantity desired, quality levels, performance data, period
of performance, work
location, and other requirements. The statement of work (SOW) is an important inputs in control
procurement process and is a part of Procurement documentation. [PMBOK 6th edition, Page 477, 496 ]
Question: 95 Correct
Statement of work
Explanation
The buyer project manager should refer to the Statement of work because it contains the description of
the procurement item, Specifications, quality requirements, and performance metrics Description of
collateral services required Acceptance methods and criteria Performance data and other reports
required Quality Period and place of performance Currency and payment schedule Warranty.[PMBOK
6th edition, Page 481]
Question: 96
Correct
If the project manager was asked to start the project based on the
project charter, what is the next step?
Determine Budget
Explanation
Kickoff meeting happens after the Project Management Plan is approved by sponsor/management.
Before doing anything else, we have to determine how will we plan for each knowledge area (Develop
Project Management Plan)
Question: 97
Correct
kick-off meeting
Identify stakeholders
Question: 98
Correct
Explanation
The best course of action is to meet the sponsor to discuss customer complains.
Question: 99 Correct
Explanation
To maintain the spirit and performance of the team without any negative impact, you should Conduct a
meeting with the 12 members and select 4 randomly. Very Important question for PMP real Exam.
Question: 100
Correct
Explanation
Perform Quantitative Risk Analysis is the process of numerically analyzing the combined effect of
identified individual
project risks and other sources of uncertainty on overall project objectives. The key
benefit of this process is that it
quantifies overall project risk exposure, and it can also provide additional
quantitative risk information to support risk
response planning. [PMBOK 6th edition, Page 428]
Question: 101
Correct
Control Quality
Manage Quality
Validate Scope
Explanation
A very important question for PMP real exam. You are in the validate scope process, and one of the key
inputs in this process is verified deliverables. Verified deliverables are output from the control quality
process. So, the correct answer is Control quality process. [PMBOK 6th edition, Page 164]
Question: 102
Correct
Stakeholder analysis
Explanation
To prevent this situation, the project manager should identify all the stakeholders that can impact the
project.
Start the meeting on time and conduct a separate meeting with stakeholders who did not
attend.
Start the meeting on time and gain commitment from the attending stakeholders
Explanation
A very important question for the real PMP exam. As you know, the project manager who is present the
implementation strategy during the meeting. and the sponsor who is present the organization strategy
and project goals. Both the project manager and sponsor are the key stakeholders and will attend the
meeting, so the meeting will start on time and gain commitment from the attending stakeholders then
conduct a separate meeting with stakeholders who did not attend. Postpone and cancel the meeting will
delay the project, so it's not good options.
Question: 104
Correct
This approved change will be verified for the correct implementation of the defect fix in
quality control
Explanation
All approved changes for any defect fixes must be verified in quality control for their correct
implementations. Root cause analysis was done before the change approval then the next step is to
validate scope for customer approval. ( PMBOK 6th Edition, Page 301 )
Question: 105
Correct
You are the new project manager who has never managed a
project before. You receive your first project and are preparing to
begin your role. Which of the following will help you to improve
your chances of success?
Configuration management.
Stakeholder inputs
Explanation
Because you have no experience, you will have to look at the experience of others. This information is
captured in the historical records from previous projects and Lessons learned repository.
Question: 106
Correct
Requirement documentation
Explanation
Question: 107
Correct
Explanation
Ground rules, defined in the team charter are established to set clear expectations regarding acceptable
behaviour by the project team members. SO the project manager should Escalate ground rule to comply
bt team members and remain on topic and do not interrupt each other.
Question: 108
Correct
Training
Explanation
As a project manager, to motivate your project team to finish the project early, you should conduct the
recognition and rewards system.
Question: 109
Correct
Explanation
Knowing the differences between the types of organizational structures is necessary to answer this
question correctly.
Understanding your role as a project manager in different organizational structures
plays an important part in your project
management responsibilities and the decisions you have to make.
The project manager's role in a weak matrix
organization is part-time and done as part of another job and
not a designated job role like a coordinator. In such an
organization, the project manager's authority over
resources is low, and it is the functional manager who takes on the
responsibility of managing resources.
Therefore, if you need additional staff for your project, you will be operating under
the constraint that
hiring staff is typically done by the functional managers who are responsible for most of the project
resources. (PMBOK Guide) – Sixth Edition, Page(s) 47
Question: 110
Correct
Schedule compression
Fast tracking
Resource leveling
Explanation
ne of the tools and techniques associated with the Control Schedule process is schedule compression.
One type of
schedule compression technique is crashing. Crashing involves adding resources to activity
on the critical path to
shorten the duration. The payment of overtime as described in the question is an
example of crashing. The schedule
compression technique of crashing is being used in this scenario to
bring the schedule back into alignment with the plan.(PMBOK Guide) – Sixth Edition, Page(s) 228
Question: 111
Correct
Explanation
The scenario implies the project manager is performing the Control Procurements process. The lessons
learned register
could be updated as an output of this process. Capturing lessons learned to enable
continuous improvement should
happen on every project so that the knowledge gained is converted into
actions. Taking proactive steps can help project
managers avoid past mistakes on future projects.
Updating the lessons learned register to include more time and
resources for the vetting of suppliers will
serve as a reminder for future projects. This action represents a proactive
measure that ensures the
lessons learned are incorporated into future projects.(PMBOK Guide) – Sixth Edition,Page(s) 500
Question: 112
Correct
Explanation
The communications management plan is a component of the project management plan that describes
Question: 115
Correct
You are the project manager of a project. The project you are
managing has experienced quality issues, which were the fault of
one of the suppliers. Much of the rework the supplier has billed
for in the final invoice of $20,000 was created by their quality
issues; therefore, you arrived at a revised amount of $18,000 to
be paid. You sent the payment of $18,000 along with your
justification, but the supplier reinvoiced with a balance due of
$2,000. What is your best course of action now?
Contact the legal team about pursuing legal action against the supplier
Ignore the supplier's second invoice and consider your payment of $18,000 payment in full
Explanation
Question: 116
Correct
Develop the hardware with a predictive life cycle and use an adaptive life cycle for the
software
Both the hardware and software should have their scope defined during initial project
planning
Both the hardware and software should have their scope defined iteratively
Develop the software with a predictive life cycle and use an adaptive life cycle for the
hardware
Explanation
The question describes a project which is utilizing a hybrid development life cycle. A hybrid development
Question: 117
Correct
Change requests
Question: 118
Correct
Assess external and internal influences that may impact project strategy
Question: 119
Correct
Explanation
Quantitative risk analysis is a reliable method to assess overall project risk which is performed by
assigning cost impacts to identified risks. However quantitative risk analysis is not required for all projects
nor is it always possible. The use of quantitative risk analysis depends on the availability of numeric data
that can be assigned to project risks as well as specialized expertise. In addition, quantitative risk
analysis is costly and typically takes more time to complete than
qualitative risk analysis. Individual
Any stakeholder
Project team
Project sponsor
Project manager
Explanation
Changes may be requested by any stakeholder involved with the project and may occur at any time
throughout the
project life cycle. The project manager, the project sponsor, and the project team are all
project stakeholders and
therefore, can request changes.(PMBOK Guide) – Sixth Edition, Page(s) 115
Question: 122
Correct
Explanation
The scenario requires documenting the problems identified and the actions taken in order to track
progress and ensure a
resolution is reached.The purpose of the issue log is to record and track issues
that surface during the project lifecycle. This document is first
created as an output of the Direct and
Manage Project Work process and is then used as input in many project
processes and updated as a
result of the monitoring and control activities throughout the life of the project.(PMBOK Guide) – Sixth
Edition, Page(s) 351, 96
Question: 123
Correct
Explanation
The question implies that the Implement Risk Responses process was triggered and completed in this
scenario. The risk
register should be updated to reflect any changes to the previously agreed-upon risk
responses for individual project
risks that are subsequently applied as a result of the Implement Risk
Responses process. In this scenario, the risk status
will likely need to be updated in the risk register
along with any identified risks associated with the secondary vendor.
Therefore, among the available
choices, updating the risk register is what the project manager should do first.(PMBOK Guide) – Sixth
Edition, Page(s) 452, 417
Question: 124
Correct
Explanation
The business needs to be satisfied with the execution of the project are a significant component of the
project charter
and should always be included. Although each of the other answer choices is important to
the successful completion of
the project, none are available to be included in the project charter during
the Initiating phase of a project.(PMBOK Guide) – Sixth Edition, Page(s) 77, 81
Question: 125
Correct
Benchmarking
Risk register
Explanation
The question implies that the Plan Quality Management process is underway and the cost of quality
(COQ) is a data
analysis technique that may be used in this process. The optimal COQ reflects the
appropriate balance for investing in
the cost of prevention and appraisal (cost of conformance) to avoid
failure costs (cost of nonconformance). The project
manager should use the COQ data analysis
technique in the scenario described by the question.(PMBOK Guide) – Sixth Edition, Page(s) 282, 283
Question: 126
Correct
Give rewards to team members who meet their performance goals at the end of the project
Explanation
Recognition and reward systems are determined during the Plan Resource Management process. While
managing the
project team, the project manager makes reward decisions and implements them as part of
the team development
process. Unless the need arises to change the recognition plan, a project
manager should adhere to the project plan.
Since the work of creating a recognition and reward system
should have already been done, the project manager's best
approach would be to consult the resource
management plan.(PMBOK Guide) – Sixth Edition, Page(s) 319, 341-342
Question: 127
Correct
Explanation
Implementation of risk responses may result in a change request to the cost and schedule baselines or
other
components of the project management plan. In the scenario described, as a result of implementing
the risk response
plan, the original timeline is no longer valid, and the schedule baseline needs to be
updated. If the contingency reserve
was sufficient to accommodate the delay caused by changing
vendors, you could just update the schedule to utilize the
contingency reserve without a need to update
the schedule baseline. However, the question states that the contingency
reserves are inadequate to
meet the schedule objective. Since there are insufficient scheduling reserves, a new
schedule baseline
must be established. An update to any baseline after it has been established during project planning
requires an approved change request. Therefore, of the available options, submitting a change request is
what you
should do next.(PMBOK Guide) – Sixth Edition, Page(s) 451
Question: 128
Correct
Explanation
The question suggests that the Plan Cost Management process is being performed, which is the process
of defining how
the project costs will be estimated, budgeted, managed, monitored, and controlled. The
project charter provides the
preapproved financial resources from which the detailed project costs are
developed. The project charter also defines the
project approval requirements that will influence the
management of the project costs. Therefore, you should review the
project charter to see if there are any
preapproved financial resources from which the detailed project costs can be
developed.(PMBOK Guide)
– Sixth Edition,, Page(s) 236
Question: 129
Correct
0.625
1.25
1.667
Explanation
The question is asking about the efficiency that must be maintained to complete the project within the
estimate at
completion (EAC) rather than the original budget at completion (BAC). The formula required
for this calculation is TCPI =
(BAC - EV) / (EAC - AC). The BAC is the initial project budget which is
$20,000. The project's current earned value (EV)
is $15,000, which is calculated by multiplying the actual
percent complete (75% or 0.75) by the BAC ($20,000). The EAC
is the new budget of $25,000, and the
actual cost (AC) is $17,000. Following are the detailed calculations for the correct
answer to this
question:
BAC = $20,000
EV = 0.75 * $20,000 = $15,000
EAC = $25,000
AC = $17,000
Therefore:
TCPI
= (BAC - EV) / (EAC - AC) = ($20,000 - $15,000) / ($25,000 - $17,000) = $5,000 / $8,000 = 0.625
Question: 130
Correct
Explanation
The question indicates that the Close Project or Phase process is being carried out. The business case is
used to
determine if the expected outcomes from the economic feasibility study used to justify the project
occurred. The business
case is the document that the project manager should review in this case.
(PMBOK Guide) – Sixth Edition, Page(s) 125
Question: 131
Correct
Explanation
The quality management plan is a subsidiary of the project management plan.The question indicates that
the quality standards of the project deliverable must be updated to meet new regulatory requirements.
Quality standards are a component of the quality management plan. The quality management plan is a
component of the project management plan. If changes that impact any of the components of the project
Question: 132
Correct
Explanation
In this scenario, there is a dispute in the claim, and
direct negotiations between your company and the
vendor have been unsuccessful. Whenever a settlement cannot be
achieved through negotiation, some
form of alternative dispute resolution (ADR) including mediation or arbitration should
be explored. Claims
administration, such as ADR, can be used as a tool or technique during the Control Procurements
process. Of the choices provided, seeking alternative dispute resolution is the best thing for you to do in
this situation and
is, therefore, the best answer to the question asked.(PMBOK Guide) – Sixth Edition,
Page(s) 498
The quality management plan to ensure it was followed for these last few houses
The requirements management plan to ensure all the requirements are met
The performance measurements baseline to ensure determine how the project performed
Explanation
Even though some components of the project management plan may be of more obvious importance, all
components of
the project management plan are required as inputs to project closure. There were
obvious quality and requirements
issues on this project, but the project manager will need to review all
aspects of the project and not just the obvious
problem areas. Hence, all components of the project
management plan are needed to close the project. In addition to the
project management plan and
baselines, the project manager will also need to review many, if not all, of the project
documents and
business documents. If nothing else, all of these documents will need to be marked as final versions
during the Close Project or Phase process. In this scenario, all of the answer choices are correct,
however, reviewing the
project management plan provides the most comprehensive answer, and is,
therefore, the best answer to the questions
asked.(PMBOK Guide) – Sixth Edition, Page(s) 124
Question: 134
Correct
Explanation
As a project manager, you have the responsibility to ensure that all change requests are reviewed and
analyzed using
the Perform Integrated Change Control process established for the project. As part of this
process, the decisions made
on the change requests should be communicated to the request owner or
group. In the scenario, the decision has been
made (the change request has been approved); therefore,
the decision should be communicated to the relevant
stakeholders. Typically, the decisions are
communicated in accordance with the guidelines specified in the project's
communications management
plan which establishes how, when, and by whom information about the project will be
administered and
disseminated.(PMBOK Guide) – Sixth Edition, Page(s) 120
Explanation
For small projects, there is usually one team that performs the planning and the execution. In this case,
the kick-off
meeting occurs shortly after initiation, in the Planning Process Group, because the team is
involved in planning. Based
on the scenario described, the project you are managing is small, implying
planning has just begun. Therefore, neither
the project management plan nor the project scope statement
has been created. Of the two remaining choices, providing
the approved project charter is more
appropriate than providing a business case because the approved project charter
contains more specific
information about the project, including the project's key deliverables, milestones, and the roles
and
responsibilities of stakeholders.(PMBOK Guide) – Sixth Edition, Page(s) 53, 81, 86, 561
Verified deliverables
Scope Baseline
Explanation
The question describes the project team reviewing the inputs to the Define Scope process to develop the
scope
statement. The inputs to the Define Scope process are the project charter, the project
management plan, enterprise
environmental factors, organizational process assets, and project
documents. The risk register is a project document that
may influence the scope statement by describing
specific risk response strategies that affect the project scope, such as
reducing or changing project and
product scope to avoid or mitigate risk. Therefore, of all the options presented, the risk
register is the
document that the team will need to review to develop the scope statement.(PMBOK Guide) – Sixth
Edition, Page(s) 152
Question: 137
Correct
Bid documents
Business documents
Procurement strategy
Explanation
The question suggests that the project management process of Plan Procurement Management is being
conducted. One
output of the Plan Procurement Management process is bid documents. Bid documents
are all documents used to solicit
information, quotations, or proposals from prospective sellers. Bid
documents would include the request for information
(RFI), request for quotation (RFQ), and request for
proposal (RFP). These documents are structured to facilitate an
accurate and complete response from
each prospective seller and to facilitate the easy evaluation of the responses. The
project team is
creating bid documents in the situation described by the question.(PMBOK Guide) – Sixth Edition,
Page(s) 477, 699
Question: 138
Correct
Project schedule
Issue log
Explanation
The question implies that the project manager is conducting the Control Resources process. One of the
project
documents that serves as an input to the Control Resources process is the physical resource
assignments. The physical
resource assignments describe the expected resource utilization along with
details such as type, amount, location, and
whether the resource is internal to the organization or
outsourced.The project schedule shows the resources that are needed, when they are needed, and the
location where they are needed. The project schedule does not describe the expected resource utilization
along with details
such as type, amount, location.(PMBOK Guide) – Sixth Edition, Page(s) 354
Question: 139
Correct
Developing contingency plan and Introduce the stakeholder to the project sponsor
Explanation
A new stakeholder has been identified, and a new 'significant' risk has been brought to the attention of
the project manager. What is the 'first' thing the project manager should do? Of the answer choices
provided, adding the new risk to the risk register should be the 'first' thing the project manager does.
Once the risk is recorded, the subsequent steps of risk analysis and risk response planning should take
priority in order to determine the most appropriate actions to address this potential threat. After the threat
to the project has been addressed the project manager can add the stakeholder to the stakeholder
register and continue the steps of the Identify Stakeholder process such as stakeholder analysis.
(PMBOK Guide) – Sixth Edition, Page(s) 96
Question: 140
Correct
Approve the request as the project manager has authority to decide for the group
Approve the request as the project sponsor has the final say
Explanation
The description provided by the question indicates that the Perform Integrated Change Control process is
underway. One
of the tools and techniques associated with the Perform Integrated Change Control
process is decision making.
Decision-making techniques include voting which can take the form of
unanimity, majority, or plurality to decide whether
to accept, defer, or reject a change request. The project
management plan establishes the criteria for which change
requests are approved, rejected, or deferred.
Therefore, the project manager should consult the project management
plan in order to determine the
approved decision-making technique in this scenario.
Note, that the change management plan is the
specific component of the project management plan that establishes the
change control board and
documents the extent of its authority. However, the change management plan was not listed as
an
answer choice. Since the change management plan is a subsidiary of the project management plan,
consulting the
project management plan is the best response.(PMBOK Guide) – Sixth Edition, Page(s)
113, 115, 119
Question: 141
Correct
Explanation
The question states that the stakeholder engagement plan is being created, which suggests that the Plan
Stakeholder
Engagement process is being performed. Root cause analysis, which typically utilizes
Ishikawa diagrams, is a data
analysis technique that is commonly used during the Plan Stakeholder
Engagement process to identify underlying
reasons for the level of support of project stakeholders in
order to select the appropriate strategy to improve their level of
engagement. Among the available
choices, only an Ishikawa diagram can provide insight into the reason for the
stakeholder's resistance to
the project and is, therefore, the best answer to the question asked.(PMBOK Guide) – Sixth Edition,
Page(s) 521
Question: 142
Correct
Use brainstorming to generate and collect multiple ideas related to project requirements
Hold a focus group to learn about stakeholder expectations and attitudes about the project
Explanation
The question suggests that the project manager is performing the Collect Requirements process, which
is the process of
determining, documenting, and managing stakeholder needs and requirements to meet
project objectives. In support of
this process, the project manager will need to employ data gathering
techniques to elicit feedback from the stakeholders
to determine their needs and requirements. The
question suggests that the project manager needs to use a data
gathering technique where the
responses will remain confidential. An interview is a formal or informal approach to elicit
information from
stakeholders by talking to them directly. Of the available choices, conducting interviews is the best tool
for the project manager to use to obtain confidential information.(PMBOK Guide) – Sixth Edition, Page(s)
142
Question: 143
Correct
Explanation
The project is in its executing phase. Loss of the key project team member during the project execution
would negatively
affect the project performance, typically leading to the schedule to be extended or the
budget to be exceeded. Ideally, the
project manager would want to immediately acquire another team
member with the same level of skills and experience
as the one that became unavailable. However, this
option is not given as an answer choice. Therefore, the only viable
alternative among the choices given is
to submit a change request to update the project management plan, specifically
the Resource
Management Plan and other project documents such as roles description and project staff assignments,
to
reflect the changes in the staffing and propose a potential solution.The change management plan is a
subsidiary plan of the project management plan. It provides direction to manage the
change control
process and documents the roles and responsibilities of the change control board (CCB) if one is used on
the project.(PMBOK Guide) – Sixth Edition, Page(s) 350
Question: 144
Correct
Explanation
The purpose of a kick-off meeting is to communicate the objectives of the project, gain the commitment of
the team for
the project, and explain the roles and responsibilities of each stakeholder. Multiphase
projects will typically include a kickoff
meeting at the beginning of each phase. Had the project manager
conducted a kick-off meeting at the start of the
second phase, the phase objectives would have been
made clear to the stakeholders, and the confusion about
stakeholder roles and responsibilities could
have been reduced or avoided.(PMBOK Guide) – Sixth Edition Page(s) 86
Question: 145
Correct
Control Procurements
Control Quality
Explanation
Approved change requests are an output of the Perform Integrated Change Control process. Once the
change request
has been approved, the Perform Integrated Change Control process is complete, and
there is nothing more that needs to
be done in this process pertaining to the approved change request.
The approved change requests are then
implemented through the Direct and Manage Project Work
process. In the case of a defect repair, once the repair has
been completed, the Control Quality process
is performed to verify the repair has been correctly done. In case of the
modifications to the terms and
conditions of the contract, the change request is implemented as part of the Control
Procurements
process. Therefore, of the available choices, the Perform Integrated Change Control process is the least
likely to be conducted at this point in the scenario.(PMBOK Guide) – Sixth Edition, Page(s) 113, 496, 92-
93, 301
Question: 146
Correct
Management reserves
Contingency reserves
cost baseline
Question: 147
Correct
Meetings
Make-or-buy analysis
Bidder conferences
Market research
Explanation
The scenario implies you are carrying out the Plan Procurement Management process. Research alone
Question: 148
Correct
Distribute the report as part of the Monitor and Control Project Work process
Explanation
Work performance reports are the output of the Monitor and Control Project Work process. These reports
are then
circulated to the project stakeholders through the Manage Communications process as defined
in the communications
management plan. Examples of work performance reports include status reports
Explanation
The communications management plan describes how, when, and by whom information about the project
will be distributed. However, the communications management plan is not listed as an answer choice.
The communications management plan is a subsidiary of the project management plan. Therefore, of the
available choices,
the project management plan is the best source of information on how the report
should be disseminated.(PMBOK Guide) – Sixth Edition, Page(s) 127-128, 377
Question: 151
Correct
Create the project charter, create stakeholder register, Develop the project management
plan ,Conduct the kick-off meeting
Create the project charter,Perform stakeholder analysis, Conduct the kick-off meeting
,Develop the project management plan
Create the project charter , Define Scope, Collect Requirements ,Create WBS ,Define
activities
Create the project charter, Plan scope management, Collect Requirements, Define Scope
,Create WBS
Explanation
The sequence 'Create the project charter, create stakeholder register, Develop the project management
plan, Conduct the kick-off meeting ' is the only option with the correct action sequence before project
execution starts.
Question: 152
Correct
Cause-and-effect diagrams
Explanation
A cost-benefit analysis can be used to determine the point where investing in additional
prevention/appraisal costs is neither beneficial nor cost-effective. A cost-benefit analysis of each quality
activity
compares the cost of the quality step to the expected benefits. This analysis can help the project
manager determine if
the planned quality activities are cost-effective. Therefore, performing a cost-
benefit analysis could have determined that
doing extensive testing to ensure zero escaped defects in
the product would have caused the project to be over budget
and behind schedule and, therefore, might
have prevented the problem from occurring.(PMBOK Guide) – Sixth Edition,Page(s) 282
Question: 153
Correct
Explanation
Activity attributes extend the description of the activity by identifying multiple components associated with
each activity. Activity attributes Document the number and roles of people needed to complete the work
along with the skill level, such as junior, senior. Activity attributes provide the primary data source for use
in estimating team and physical resources required for each activity on the activity list. Examples of
attributes
include resource requirements, imposed dates, activity location, assumptions, and constraints.
(PMBOK Guide) – Sixth Edition, Page(s) 322
Question: 155
Correct
WBS dictionary
Resource levelling
Question: 156
Correct
Influencing
Leadership
Emotional intelligence
Forcing
Explanation
Because project managers often have little or no direct authority over team members in a matrix
environment, their ability to influence stakeholders on a timely basis is critical to project success. Key
influencing skills include Ability to be persuasive. The project manager should effectively negotiate and
influence others who are in a position to provide the required team and physical resources for the project.
(PMBOK Guide) – Sixth Edition, Page(s) 330 , 350
Appraisal Costs
Prevention Costs
Explanation
The cost regarding defects identified in the surveys may be considered external failure costs in the COQ
model and can have extensive cost implications for the organization. PMBOK 6th edition. page,303
Question: 158
Correct
Explanation
The team member identified the risk then complete the analysis ( a high impact but a low chance of
occurrence) . Since the chance of occurance is low , so the best answer is Accept the risk and plan to
use the contingency reserve. option ( Assess and monitor the risk, and develop a risk response strategy.
) incorrect because the risk already analyzed.
Question: 160
Correct
ِAn activity not on the critical path will be delayed by 4 days and it
has a float of 5 days. How many days is the total float?
1 DAY
2 DAY
0 DAY
3 DAY
Explanation
The total float ( 5-4=1 )
Register the risk and establish a procedure in the change management plan to handle those
changes.
Notify the sponsor about this and risk for a large budget for any contingency.
Inform the procurement manager and risk procurement to handle this with these vendors
directly.
Set a maximum price that cannot be exceeded for the extent of the project.
Explanation
Keyword ( afraid - precautions ) The project manager should Register the risk and establish a procedure
in the change management plan to handle those changes.
Statement of work
Business case
Requirements documentation
Explanation
Very important questions for PMP real exam. Statement of Work ( SOW ) is the correct answer
Question: 163
Correct
Smoothing
Compromising
Collaborating
Explanation
The Keyword ( postpone ) in this situation, the project manager decided to postpone the discussion with
the team members until the meeting ends. its an example of Withdrawal. Very important question for
PMP real exam
Question: 164
Correct
Control Quality
Manage Quality
Control Procurements
Question: 165
Correct
Scope statement.
Explanation
SOW as part of agreement and important Input to Develop project Charter. SOW Describes Product,
service ,result ,and key delivrables.
Explanation
A very important question for PMP REAL EXAM. The project manager should Implement the response
plan due to a strike by the team members that causing delays in an important component delivery.
Question: 167
Correct
Wait for the new financial year to make any changes in product advancements
Calculate the ROI to decide if it makes sense to proceed with the project
Calculate the expected monetary value (EMV), to make necessary recommendations to the
organization
Explanation
Perform a cost-benefit analysis of the business case to illustrate the benefits of implementing the project
Question: 168
Correct
Requirements documentation.
Explanation
PMBOK 6th edition Page, 157 ..... The project manager is creating a work breakdown structure (WBS)
and one of the project documents that can be considered as inputs for this process is Requirements
documentation. Detailed requirements describe how individual requirements meet the business need for
the project. option ( Detailed activity list. ) is not correct because this is output from define activity process
on schedule management and we are currently in scope management .
Question: 171
Correct
Project charter
Explanation
The Project charter includes the Assigned project manager, responsibility, and authority level. PMBOK
6th Page, 81
Question: 172
Correct
in your project, SPI is 0.8 , CPI 1.2 . You analyzed the baseline
and decided to return the schedule back to meet the customer
plan. You will:
Explanation
SPI=0.8 so the project is behind schedule. CPI 1.2 so the project is under budget, so you can hire more
resources ( crashing ) to meet the customer plan.
Explanation
There are 3 paths in this network diagram are as follows A-B-C-D & A-B-E-D & A-E-D. Since paths A-B-
C-D & A-B-E-D are the longest paths with zero float for all of the activities, it represents the critical path.
Question: 174
Correct
For a project, PV=$20, AC=$30, and only 80% of the work has
been completed. What is The earned value ( EV)?
$24
$25
$26
Explanation
EV= The planned value of all the work completed (earned) to a point in time, usually the data date,
without reference to actual costs.
EV = Sum of the planned value of completed work = 0.8*20=16
Question: 175
Correct
214
216
213
Explanation
EAC=AC+BAC-EV. AC=$ 30, PV=$20 EV= The planned value of all the work completed (earned) to a
point in time, usually the data date, without reference to actual costs.
EV = Sum of the planned value of
completed work = 0.8*20=16.
SO EAC=30+200-16=214
Question: 176
Correct
-14
-17
-20
-25
Explanation
VAC=BAC-EAC. BAC=$200, EAC= AC+BAC-EV . AC=$30, PV=20
EV= The planned value of all the
work completed (earned) to a point in time, usually the data date, without reference to actual costs.
EV =
Sum of the planned value of completed work = 0.8*20=16.
SO EAC= 30+200-16=214. SO VAC=200-
214=-14
$90
$100
$95
$105
Explanation
ETC=EAC-AC. EAC=BAC/CPI= 200/0.8=250. SO ETC=250-160=90
Question: 178
Correct
Conduct kick-off meeting to inform and engage stakeholders and gain commitment
Explanation
Obtain project charter approval from the sponsor, in order to formalize the authority assigned to the
project manager and gain commitment and acceptance for the project. The project charter provides the
project manager with the authority to apply organizational resources to project activities.PMBOK 6th
Page, 75
Question: 179
Correct
Explanation
Refer to PMP Exam Outline in the Closing Process Group Task 6:Archive project documents and
materials using generally accepted practices in order to comply with statutory requirements, for potential
use in future projects, and audits.
Question: 180
Correct
You are in the close project or phase process of the project. You
finalize all activities across all the project management process
groups to formally complete the phase or project. The customer
is very happy about the project deliverables. The project manager
ready to manage a new project. As a project manager, what
should you do before leaving the project?
Verify that project deliverables conform to the quality standards established in the quality
management plan
Measure project performance to identify and quantify any variances and corrective actions
Question: 182
Correct
Explanation
Issue a change request and Adding more resources to activity A are strongly related. If we add more
resource we may need to update cost baseline so need a change request. But the question said activity
A has a limited budget in order not to delay activity B, we should raise change request to update cost
baseline in order to add more resources. Also no need to escalate to senior manager as this should be
the last step. .
Mitigation
Transference
Acceptance
Avoidance
Explanation
The correct answer is (Mitigation ) if you rent Alternative equipment, you just make a temporary solution
to reduce the probability of occurrence and/or impact of a threat. Not avoidance because the renting will
not eliminate the risk.
Assume that it is too late and continue the closing process without a project charter
Explanation
The sponsor or initiator of the project is responsible to establish (approve and issue) the charter and can
take the help of the project manager to develop it. The project charter is an important input in the close
project or phase process to document the project success criteria, the approval requirements, and who
will sign off on the project. PMBOK 6th page, 124
Question: 185
Correct
Assume you are in the closing phase and deliver the product to
the customer. The project team has a proposal to enhance the
final characteristics of the product. As a project manager, what
should you do next?
Explanation
The project manager should be proactive and the first step is to discuss the proposal with the customer
as these features will enhance the final characteristics of the product.
Question: 186
Correct
Explanation
the Resource management plan and cost baseline. are inputs in the plan risk response process. The
resource management plan is used to help
determine how resources allocated to agreed-upon risk
responses will be coordinated with other project resources. The cost baseline has information on the
contingency fund that is
allocated to respond to risks.PMBOK 6th edition page 439
Risk categorization
Audits
Explanation
Risk categories. Provide a means for grouping individual project risks. A common way to structure risk
categories
is with a risk breakdown structure (RBS), which is a hierarchical representation of potential
sources of risk. An RBS helps the project team consider the full range of sources from which individual
project risks may arise. This can be useful when identifying risks or when categorizing identified risks.
Grouping risks into categories can lead to the development of more effective risk responses by focusing
attention and effort on the areas of highest risk exposure, or by developing generic risk responses to
address groups of related risks.
PMBOK 6th Edition Page ( 405, 425 )
Question: 188
Correct
You are a new project manager who has recently assigned in the
executing phase. You found no RAM on the project.
To which
document you refer to know who is responsible for implementing
work package:
WBS
Resource Calendar
Stakeholder Register
Explanation
The WBS dictionary is a document that provides detailed deliverable, activity, and scheduling
information
about each component in the WBS. The WBS dictionary is a document that supports the WBS. Most
of
the information included in the WBS dictionary is created by other processes and added to this document
at a
later stage. Information in the WBS dictionary may include but is not limited to:
Code of account
identifier,
Description of work,
Assumptions and constraints,
Responsible organization/ Individual who
responsible for implementing the work package.
Schedule milestones,
Associated schedule activities,
Resources required,
Cost estimates,
Quality requirements,
Acceptance criteria,
Technical references,
and
Agreement information.
PMBOK 6th Edition, Page 162
Question: 189
Correct
Validate Scope
Explanation
If changes occur during the Control Quality process that may impact any of the components of the project
management plan or project documents, the project manager should submit a change request. Change
requests are processed for review and disposition through the Perform Integrated Change Control
process. PMBOK 6th edition, Page 306
Question: 190
Correct
Project team development and the improvement of the team skill level
Explanation
The evaluation of a team’s effectiveness may include indicators such as:
Improvements in skills that
Question: 191
Correct
Explanation
Keyword (a large number of staff members located globally and a quick turnaround is required. )
Questionnaires and surveys are written sets of questions designed to quickly
accumulate information
from a large number of respondents. Questionnaires and/or surveys are most appropriate
with varied
audiences, when a quick turnaround is needed, when respondents are geographically dispersed, and
where statistical analysis could be appropriate. PMBok 6th edition page 143
Question: 192
Correct
Bring the vendor to meet the control quality department and follow the quality procedures
Directing the Quality Department to reject all materials related to the vendor
Explanation
A very important question for PMP real exam. The project manager should be proactive and manage the
conflict between the quality control department and the vendor. so, the project manager should bring the
vendor to meet the control quality department and follow the quality procedures.
Question: 193
Correct
Explanation
The stakeholder register includes the assessment information. Major requirements, expectations, the
potential for influencing project outcomes, and the
phase of the project life cycle where the stakeholder
has the most influence or impact. PMBOK 6th Edition Page, 514
Question: 194
Correct
Explanation
Question: 195
Correct
Project charter
Issue log
Risk register
Explanation
Since the project team is aware of the monsoons will happen on a yearly basis, therefore it should be
recorded in the project charter.
Review the change management plan and follow the established process for processing
change requests.
Meet with the change control board members individually and try to persuade them to
approve the change request.
Approve the change request. As the project manager, you should use expert judgment to
decide what is best for the project.
Explanation
Change requests should be processed according to the change management plan, which defines the
process for
managing changes to the project, including the process for submitting, evaluating and
implementing change requests.PMBOK 6th edition Page, 120
Question: 197
Correct
Explanation
The WBS is a component of the scope baseline. An approved change request is required ti update any of
the project baselines including their components.