Professional Documents
Culture Documents
RAPID-P0003-TRSA-CON-ITP-0001-0010 - ITP For Lighting System - R0
RAPID-P0003-TRSA-CON-ITP-0001-0010 - ITP For Lighting System - R0
RAPID-P0003-TRSA-CON-ITP-0001-0010 - ITP For Lighting System - R0
OWNER approval:
Name:
Date (DD-MMM-YY):
Signature:
Document Class: Z
Contract No: RAPID PROJECT PACKAGE 3 02260 Contractor’s Scope of Works are as following ( ): BY SUBSYSTEM
Contractor Name: TECNICAS REUNIDAS MALAYSIA SDN BHD
Subcontractor Name:
ITP Section No.: 1.0 BEFORE EXECUTION ( ), 2.0 DURING EXECUTION ( ), 3.0 AFTER EXECUTION ( )
ITP Section Scope of Inspection Inspection Record
Requirement and Inspection Form No.
Inspection/Test Stage Subcontractor Contractor Client
Acceptance Criteria Frequency
RAPID-P0003-TRSA-PMG-PRC-0001-
1.2 Calibration of Measuring and Control Equipment 0300 100% H H/R R Calibration Certificate
Material
1.3 Check Material Certificates PTS 33.64.10.10 100% H H/R R
Certificate
1.4 Materials Receiving on Site Free of Damage PTS 33.64.10.10 100% H W S/R 02260 CON-ROT-09
2.3 Light Panels Installed Properly According to Drawings AFC PTS 33.64.10.10 100% H S S N/A
2.5 Insulation and Continuity Test for Lighting Cable PTS 33.64.10.10 100% H W S 02260 CON-ELE-37
AWS D1.1
2.6 Welding Performed According to Procedure PTS 30.10.02.31 100% H S S N/A
Support´s Paint Touch Up Performed According to AWS D1.1
2.7 PTS 30.10.02.31 100% H S S N/A
Procedure
3.0 AFTER EXECUTION
3.1 Distribution Board and Light Panels Final Inspection PTS 33.64.10.10 100% H H W 02260 CON-ELE-24
02260 CON-ELE-25
3.2 Light /Light Receptacles Functional Test PTS 33.64.10.10 100% H H W
02260 CON-ELE-27
3.3 Light Illumination Level Test PTS 33.64.10.10 100% H H W 02260 CON-ELE-26
R : (Review) Document review 1. ITP Section Numbers for example but not to limited:
1.0 BEFORE EXCUTION
S = Surveillance of construction works and of tests / inspections performed 2.0 DURING EXECUTION
3.0 AFTER EXECUTION
W = Witness (Notification of authorized inspection Add other section (s) per Works in scope of work in the contract as necessary.
personnel required) 2. Scope of Inspection
Contractor QC : Construction / Supplies / Services Contractor.
H = Hold (Mandatory, do not proceed without PMC Site QC : Surveillance, Witness & testing of contractors work scopes
presence of authorized inspection personnel or 3. Painting Activities to be developed as per ITP-COA-001 - PAINTING
signed waiver)
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
TAG NUMBER: DESCRIPTION:
INCLUDED IN FOLDER: REPORT NUMBER:
BAR CODE:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
LOCATION :
No ROOM No / AREA PANEL NUMBER CIRCUIT NUMBER DESIGNATION VOLTAGE MEASUREMENT RECEPTACLE POLARITY ACCEPTED REJECTED REMARKS
Type: Manufacturer:
SIGNATURE:
PRINT NAME:
DATE:
No: CON-ROT-09
Rev.: 2
MATERIAL RECEIVING INSPECTION REPORT Date: --/--/----
Page:
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
TAG NUMBER: DESCRIPTION:
INCLUDED IN FOLDER: REPORT NUMBER:
BAR CODE:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms
that all these Tests have been performed according to them.
Supplier:
Originator:
INSPECTION RESULTS:
YES NO
( )
* - If YES, Report number should be included
REMARKS:
WITNESSED / REVIEWED BY: TR CONSTRUCTION SUPERVISOR TR QUALITY SUPERVISOR CLIENT (If required)
SIGNATURE:
PRINT NAME:
DATE:
No: CON-ELE-21
Rev.: 1
LIGHTING INSTALLATION INSPECTION CHECK LIST Date: 07/10/2015
Page: 1 of 1
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
3 Conform elevation of light as per the site condition and approved drawing
13 The exterior and street lighting fixtures is dust and splash proof type
The orientation of fixture is ensured the correction area is illuminated and not obscured by pipes /
14
or structures
17 Accessories complete
REMARKS:
WITNESSED / REVIEWED
SUBCONTRACTOR TR CONSTRUCTION SUPERVISOR TR QUALITY SUPERVISOR CLIENT (If Required)
BY:
SIGNATURE:
PRINT NAME:
DATE:
No: CON-ELE-23
LIGHT SWITCHES AND RECEPTACLE Rev.: 1
Date: 07/10/2015
INSTALLATION CHECK LIST Page: 1 of 1
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
TAG NUMBER: DESCRIPTION:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
REMARKS:
WITNESSED / REVIEWED
SUBCONTRACTOR TR CONSTRUCTION SUPERVISOR TR QUALITY SUPERVISOR CLIENT (If Required)
BY:
SIGNATURE:
PRINT NAME:
DATE:
No: 02260-CON-ELE-24
Rev.: 2
DISTRIBUTION/CONTROL BOARD & MISCELLANEOUS PANEL Date: 15/04/2016
Page: 1 of 2
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
TAG NUMBER: DESCRIPTION:
INCLUDED IN FOLDER: REPORT NUMBER:
BAR CODE:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms
that all these Tests have been performed according to them.
NAME PLATE
Ensure safety devices are in good condition, equipment are de-energized and safe LOTO and work
1
permit controls were accepted
3 Check equipment is correctly mounted and located in accordance with layout drawings
5 Check Entire assembly including auxilary devices for any apparent damage or missing parts
Check ratings and labelling of circuit components (circuit breakers, switches, contactors…) are
7
correct as per drawings
11 Visualy check bus bar for possibly misalightment, splice bolting, isolators, etc
Verify that all external operating mechanisms are functional and that all mechanical interlocks are
12
correct and operative
15 Verify CTs/VTs name plates values conform to vendor and project drawings
20 Check spare holes in the enclosure have been properly plugged with suitable Ex rating caps
23 Check for cleanliness of Panel Free of debris, left tools and wiring pieces
REMARKS:
No: 02260-CON-ELE-24
Rev.: 2
DISTRIBUTION/CONTROL BOARD & MISCELLANEOUS PANEL Date: 15/04/2016
Page: 2 of 2
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
TAG NUMBER: DESCRIPTION:
INCLUDED IN FOLDER: REPORT NUMBER:
BAR CODE:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms
that all these Tests have been performed according to them.
TEST EQUIPMENT
CONTINUITY TEST
BUS-BAR
TEST CONFIGURATION:
L1 L2 L3 N E
PASS / FAIL
BUS-BAR
TEST VOLTAGE:_________V
L1-L2/L3/N/E L2-L1/L3/N/E L3-L1/L2/N/E N-L1/L2/L3/E E-L1/L2/L3/N
REMARKS:
WITNESSED / TR CONSTRUCTION
SUBCONTRACTOR TR QUALITY SUPERVISOR CLIENT (If required)
REVIEWED BY: SUPERVISOR
SIGNATURE:
PRINT NAME:
DATE:
No: CON-ELE-25
Rev.: 1
LIGHTING FUNCTIONAL TEST Date: 07/10/2015
Page: 1 of 1
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
LOCALIZATION ROOM Nº / AREA PANEL NUMBER CIRCUIT NUMBER DESIGNATION ACCEPTED REJECTED
REMARKS:
SIGNATURE:
PRINT NAME:
DATE:
No: CON-ELE-26
Rev.: 1
LIGHTING ILLUMINATION LEVEL TEST Date: 07/10/2015
Page: 1 of 1
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
TYPE: MANUFACTURER:
MIN. ILLUMINATION
MEASURE LOCATION (ATTACH LEVEL
LOCALIZATION TYPE OF LAMP (ACCORDING ACCEPTED REJECTED
MARKED DRAWING) ILLUMINATION
ESPECIFICATIONS)
REMARKS:
SIGNATURE:
PRINT NAME:
DATE:
No: CON-ELE-37
INSULATION RESISTANCE TEST REPORT FOR POWER CABLES Rev.: 1
Date: 07/10/2015
(After Installation) Page: 1 of 1
PROJECT: SUBCONTRACTOR:
SYSTEM/SUBSYSTEM: DRAWING:
TAG NUMBER: DESCRIPTION:
INCLUDED IN FOLDER: REPORT NUMBER:
BAR CODE:
This certificate does not exempt the Subcontractor from the Terms of the Contract, Project Specifications or Quality Procedures but confirms that all these Tests have been performed according to them.
Voltage to be appied according to project specifications: Duration: 1 min. Minimum value allowed as per project specification: MΩ
Phase R
Phase S
Phase T
Neutral
Ground
TEST EQUIPMENT
EQUIPMENT NAME,
MANUFACTURER AND MODEL:
SERIAL NUMBER:
CALIBRATION
CERTIFICATION No:
CALIBRATION DATE
(FROM-TO):
REMARKS:
SIGNATURE:
PRINT NAME:
DATE: