Eleventh Plan 2007-12 : Summary of Proposals

MNRE
Rs. in crore

GRID-INTERACTIVE & DISTRIBUTED/ OFF-GRID RENEWABLE POWER 3,925.00

GRID-INTERACTIVE RENEWABLE POWER 1800.00


OFF-GRID/DISTRIBUTED RENEWABLE POWER 2100.00
PERFORMANCE TESTING 25.00

RENEWABLE ENERGY FOR RURAL APPLICATIONS 2,250.00

RENEWABLE ENERGY FOR URBAN,


INDUSTRIAL & COMMERCIAL APPLICATIONS 685.00

RESEARCH, DESIGN & DEVELOPMENT 1,500.00

SUPPORTING PROGRAMMES
SPILL-OVER LIABILITIES OF 10th PLAN 2,100.00

DOMESTIC BUDGETARY SUPPORT/ PLAN OUTLAY 10,460.00

1
Proposal for 11th Plan for
Grid-interactive Renewable Power
MNRE

Programme Component Physical Target Proposed Outlay


for 11th Plan for 11th Plan
(in MW) (Rs. in crore)
Wind Power 10500 75
(for demo only)
Small Hydro Power 1400 700

Biomass Power 1200 600


Co-generation 500 200
Urban Waste to Energy 200 150
Industrial Waste to Energy 200 75
Total 14000 1800

2
Proposal for 11th Plan for
Distributed/Off-Grid Renewable Power MNRE

Programme Component Physical Target Proposed outlay


for 11th Plan for 11th Plan
(in MWe) (Rs. in crore)

Wind/Hybrid Power 950 1900


Small Hydro Power
Bio Power

Solar Power (grid/ off-grid) 50 200

Total 1000 2100

3
Proposal for 11th Plan for
Renewable Energy for Rural Applications
MNRE
Programme Component Physical Target Proposed Outlay
for 11th Plan for 11th Plan
(Rs. in crore )
For remote villages/ hamlets –
Remote Village Lighting 9000 villages/hamlets 650.00

Village Energy Security Test Projects 1000 villages 225.00

Common component for cooking/ 10000 villages/ hamlets 900.00


supplementary motive power
For all villages
Solar thermal systems - flat plate 15 lakh m2 200.00
- concentrating 1 lakh m2 25.00
Family Type biogas plants 20 lakh plants 250.00

Total 2250.00

4
Proposal for 11th Plan for Renewable Energy
for Urban, Industrial & Commercial Applications
MNRE
Programme Component 11th Plan Physical Target Proposed 11th Plan
Outlay
(Rs. in crore )
Solar thermal systems/ devices
- water heating @ Rs.1550/m2 9.50 million m2 *375.00
- drying @ Rs.1250/m2 0. 25 million m2 31.25
-other (steam generation) @ Rs.2500/m2 0. 25 million m2 62.50
- instl./prog. Support @ Rs.200/m2) - *50.00
- mun. corpns. – incentive 10 nos. 10.00
Energy-efficient buildings 50 lakh sq.m. floor area 50.00

Akshay Urja Shops 2000 nos. 55.00

Cities 100 nos. 50.00


with RPOs

Total 683.75
~ 684.00

*Subsidy / incentive for only 2.5 million m2 targeted during first 2 years of the Plan
5
Propsal for 11th Plan for
Research, Design & Development
MNRE
Programme Component Proposed outlay for 11th Plan
(Rs. in crore )
Bio-Energy 150.00
Solar Energy 360.00
Wind Energy 200.00
Small Hydro Power 50.00
New Technology 400.00
Solar Energy Centre 40.00
C-WET 40.00
NIRE 40.00
Others (TIFAD/ NETCOF/ Standards & Testing/ 182.00
Resource Assessment, etc.)

Total 1462.00
~1500.00

6
Proposal for 11th Plan for
Support Programmes
MNRE
Programme Component Proposed Outlay for 11th Plan
(Rs. in crore )
Information and Publicity 290.00
Extension for RE systems 250.00
Monitoring and Evaluation 10.00
Plan Secretariat 50.00
IREDA 250.00
Supports to State Governments 50.00
Support to Industry 1000.00
10th Plan spill over liabilities 100.00
Others- IR, HRD & Training 100.00

Total 2100.00