Professional Documents
Culture Documents
1.00 PCC For RCC (1:1.5:3) 3,150.77
1.00 PCC For RCC (1:1.5:3) 3,150.77
1.00 PCC For RCC (1:1.5:3) 3,150.77
Plinth to FF
Column 121.00
Beam 115.68
Slab 472.41
Staircase 64.84
FF to SF
Column 121.00
Beam 115.68
Slab 472.41
Staircase 64.84
SF to Roof
Column 99.00
Beam 101.73
Slab 387.99
Balcony 279.73
13.00 DOOR
4' * 8' 32.00
2.5' X 7' 140.00
3' X 7' 147.00
sliding door 96.00
UNIT
CFT
KG
CFT
CFT
KG V % Steel
14.38 1.50 1,693.83
12.46 3.00 2,934.19
2.31 3.00 543.49
17.65 2.50 3,463.68
37.74 1.50 4,444.00
3.67 1.50 432.39
13,511.59 KG
CFT
2,767.14 3,689.52 3,074.60
449.79 1,349.37 562.24
KG
CFT
NOs
KG
CFT
NOs
KG
CFT
NOs
d V
0.25 108.00
CFT 0.25 9.06
SFT 0.25 32.90
SFT 0.33 362.21
SFT
SFT
CFT
KG
CFT
CFT
CFT
KG
CFT
NOs
SFT 3,351.56
3,005.32
3,016.60
9,373.48
5,434.48
KG
CFT
SFT
CFT
KG
CFT
NOs
FT
FT
150000
0
756862.1
334336.05
1073744
448845
1161996.37415891
376689.4
130000
326975
476533.35
400000
490000
150480
72000
67600
522450
234372.6
226186.8
203840
1847475
172800
114400
44000
60000
25000
52200
9918785.67415891
347157.498595562
446345.355337151
10712288.5280916
1071228.85280916
11783517.3809008
1,17,00,000
S.No. Materials and Works Quantity Unit Rate Total
A Preparation
A1 Excavation/ Filling LS 150000
B civil works -structure, brick works and plaster works 0
B1 OPC Cement 44521.3 kg 17 756862.1
B2 PPC Cement 22289.07 kg 15 334336.05
B3 Bricks 67109 no. 16 1073744
B4 Sand 3903 cuft 115 448845
B5 Rebar (rod) 13,511.59 kg 86 1161996.37415891
B6 Aggregate 3275.56 cuft 115 376689.4
C Doors and windows
C1 Door Chaukush 33 sqft 6000 198000
G Labour cost
G1 civil works Labour cost 4347 sqft 425 1847475
K Total Direct Construction Cost 6347947.924159
Electrical Work LS 250000
Senitory Work LS 450000
Total Cost 7047947.924159
Overhead and other cost 10% 704794.7924159
Grand Total Cost 7752742.716575
Final Total cost 77,00,000