PROCESS CHART

Process : Sheet Metal Working

Company : Uday Metal Works

Chart Begins : 10 Sheets of Metal in Store

Chart Ends : Completed Sheets Delivered to the Store

Charted by : Group 7 Date : 15/09/2020

DISTANCE | TIME SYMBOL EXPLANATION

10 Sheets Of Metal

30 mtrs Taken/Transfer To Cutting


Department

20 mins Machine is busy

5 mins Sheet loaded on machine

4*10 mins Sheet Cut from one Side

Repeat for 4
sides
3*8 mins Sheet unloaded and reloaded
4 for cutting from another
side

5 mins Sheet Unloaded from


Cutting machine
20 mtrs Taken/ Transfer to
Inspection Department

15 mins Dimensions Check during


inspection

20 mtrs Taken/Transfer to Bending


Department

4*10 mins Hole drilled at one corner of


Repeat for 4 the sheet
corners

40 mins Bending sheets from all the


4 sides

40 mtrs Taken/Transfer to Store

Sheets stored in Store

SUMMARY
SYMBOLS FREQUENCY TIME|DISTANCE
2 -------------------|-----------------

4 -----------------| 110 mtrs

15 154 mins |-----------------

1 15 mins |-----------------

1 20 mins |-----------------
MULTIPLE ACTIVITY CHART
Process : Facing and Centering of a shaft

Chart Begins : Shaft to be faced and centered lying near the machine

Chart Ends : Faced and Centered shaft kept aside near the machine

Charted by : Group 7 Date : 16/09/2020

TIME
SCALE WORKMEN MACHINE
DESCRIPTION T S DESCRIPTION T S
0
Lode Job 0.15 Idle 0.15

0.15
Secure Job 0.05 Idle 0.05
0.20
Depress cycle on switch 0.05 Idle 0.05
0.25 Idle 1.60 Facing and centering on Auto cycle 1.60
of the machine

1.85
Idle 0.05 Jaws to open out to release Job 0.05
1.90
Collect Job from the Jaws 0.05 Idle 0.05
1.95
Job aside 0.05 Idle 0.05
2.00
SUMMARY

SUBJECT CYCLE TIME


Workmen (MINS)

Machine 2.00
TIME WORKED PER CYCLE(MINS) PERCENTAGE UTILISATION
0.35 17.5%
1.65 82.5%