Professional Documents
Culture Documents
Part - A Earth Works: 102 (2) Cubic Meter Surplus Common Excavation #REF!
Part - A Earth Works: 102 (2) Cubic Meter Surplus Common Excavation #REF!
Part - A Earth Works: 102 (2) Cubic Meter Surplus Common Excavation #REF!
Equipment Requirement
Quantites Equipment Activity
Type of Equipment No. of unit
Required (m2) Output (m2/day) Duration (days)
Road Grader 1 #REF! 2400.00 #REF!
Water Truck 1 #REF! 8000.00 #REF!
Quantites Equipment Activity
Type of Equipment No. of unit
Required (m3) Output (m3/day) Duration (days)
Road Roller 2 #REF! 320.00 #REF!
Materials Total -
5.66666666666667 6
0.833333333333333 1
5.66666666666667 6
56
5.04394666666667 5
5.5 6
4,888.39
44,484.35
4,888.39
2,444.20
14,984.08
40.00
1,686,727.18 8%
27,156,269.30
PART - D. DRAINAGE AND SLOPE PROTECTION
ITEM No.: 500(1) UNIT: l.m.
DESCRIPTION: REINFORCED CONCRETE CULVERT PIPE QUANTITY: 220
1,213,359.40
-
28
PART - E. MISCELLANEOUS
ITEM No.: 604(2) Station: 5+811 to 5+914 UNIT: Linear Meter
DESCRIPTION: FENCING (CHAIN LINK FENCE FABRIC) QUANTITY: 103.00
Equipment Requirement
No. of unit Quantities Equipment Activity
Type of Equipment
Required (pcs.) Output (pcs./day) Duration (days)
Stake truck 1 100.00 14 7.00
Equipment Total -
B. Labor:
Labor Total -
C. Materials:
Field Office/(7m x 9m School Facility) 1 lot 945,000.00 945,000.00
Field Office Supplies 1 lot 3,000.00 3,000.00
School Supplies 1 lot 50,000.00 50,000.00
Office Table 2 pcs. 3,000.00 6,000.00
Chairs (monoblock w/ arm rest) 6 pcs. 600.00 3,600.00
Conference Table w/ chairs 1 pc. 12,000.00 12,000.00
Electric Fan 3 units. 1,500.00 4,500.00
Steelbed w/ uratex foam, beddings and pillows 1 pc. 5,000.00 5,000.00
Two burner stove (standard) w/ LPG tank 1 set 3,500.00 3,500.00
Kitchen utensils 1 set 2,000.00 2,000.00
Water dispenser 1 set 5,000.00 5,000.00
Digital Camera 1 pc. 16,335.00 16,335.00
Printer (color, all in one, ink economical) 1 unit 7,000.00 7,000.00
Laptop Computer (Intel Core i7 or Higher) 2 units. 65,000.00 130,000.00
Materials Total 1,192,935.00
#REF!
#REF!
#REF!
#REF!
95,434.80 0%
1,336,087.20
PART - E. MISCELLANEOUS
ITEM No.: SPL 1 UNIT:
DESCRIPTION: MOBILIZATION/DEMOBILIZATION QUANTITY:
REMARKS
2=1 mobilization + 1 demobilization
Low Bed Trailer Truck
Low Bed Trailer Truck
Low Bed Trailer Truck
Low Bed Trailer Truck
Low Bed Trailer Truck
Low Bed Trailer Truck
Low Bed Trailer Truck
Self Transport
Low Bed Trailer Truck
Low Bed Trailer Truck
Low Bed Trailer Truck
Self Transport
Self Transport
Cargo Truck
Cargo Truck
Cargo Truck
Cargo Truck
Cargo Truck
Cargo Truck
Self Transport
Cargo Truck
AMOUNT
413,100.00
159,488.00
413,100.00
413,100.00
49,572.00
49,572.00
462,672.00
462,672.00
Name of Project: Construction of Flume Type Drainage Canal
Manpower
Contractor's
Item No Description Quantity Equipment Materials Direct Cost OCM Profit Taxes Total Cost Unit Cost
Labor Amount
1 General Requirements 1.00 - 9,840.00 9,840.00 30,500.00 40,340.00 6,051.00 4,034.00 2,521.25 52,946.25 52,946.25
103 (1) a Excavation for Structure, Demolition works, Clearing of 287.70 140,260.00 27,900.00 27,900.00 - 168,160.00 25,224.00 16,816.00 10,510.00 220,710.00 767.15
404(1) a Reinforcing Steel 14247.93 7,000.00 182,000.00 182,000.00 611,013.06 800,013.06 120,001.96 80,001.31 50,000.82 1,050,017.15 73.70
405(1) a1 Structural Concrete 100.70 6,540.00 113,280.00 113,280.00 380,205.00 500,025.00 75,003.75 50,002.50 31,251.56 656,282.81 6,517.21
153,800.00 333,020.00 333,020.00 1,021,718.06 1,508,538.06 226,280.71 150,853.81 94,283.63 1,979,956.21
Total 153,800.00 333,020.00 333,020.00 1,021,718.06 1,508,538.06 226,280.71 150,853.81 94,283.63 1,979,956.2
A. MATERIALS:
B. EQUIPMENT (POL):
C. LABOR:
MAN-DAYS = 9
ITEM 405 - STRUCTURAL CONCRETE
QUANTITY = 19.00 CU.M
A. MATERIALS:
C. LABOR:
A. MATERIALS:
B. EQUIPMENT (POL):
C. LABOR:
I LABOR
No. of
Description Person No. of Day Daily Rate Amount (Php)
Construction Foreman 1 4 480.00 1,920.00
Laborers 6 4 330.00 7,920.00
Sub-Total 9,840.00
II EQUIPMENT
No. of
Description Units No. of Day Daily Rate Amount (Php)
Sub-Total 0.00
III GENERAL
A. MATERIALS:
B. EQUIPMENT (POL):
none
C. LABOR:
A. MATERIALS:
C. LABOR:
Original POW Estimated Test Min. No. of Sample Test Total Test Test Amount of
Item No. Description Unit REMARKS
Quantity Direct Cost (P) Required Test Req'd. Requirements Required Unit Cost Test
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
= (4)/(8) x (7) = (9) x (10)
PART C - EARTHWORKS
100 Clearing and Grubbing ha. #REF! IR 1 whole area 1 #REF! #REF!
101 Removal of Stuctures and Obstruction ls. IR 1 whole area 1 #REF! #REF!
102 Roadway Excavation (Surplus Unclassified) cu.m. IR 1 #REF! #REF! (IR) if materials are surplus excavation
P 1 for every 1500 cu m. #REF! #REF! Apply (P) test if unsuitable excavation
103 Structure Excavation cu.m. G 1 #REF! #REF!
#REF! P 1 for every 1500 cu m. #REF! #REF! if materials are to be incorporated in the work
C 1 #REF! #REF!
104 Embankment cu.m. G 1 #REF! #REF!
P 1 for every 1500 cu m. #REF! #REF!
#REF!
C 1 #REF! #REF!
FDT 3 for every 500 sq.m. #REF! #REF! Layer placed not exceeding 200mm in loose measurement
105 Sub-Grade Preparation sq.m G 1 #REF! #REF!
P 1 for every 1500 cu m. #REF! #REF! subgrade thickness of 200mm
#REF!
C 1 #REF! #REF!
FDT 3 for every 500 sq.m. #REF! #REF! 3 FDT Test per set
PART D - SUBBASE & BASE COURSE
200 Aggregate Sub Base Coarse cu.m. G 1 #REF! #REF!
for every 300 cu m.
P 1 #REF! #REF!
C 1 #REF! #REF!
#REF! for every 1500 cu m.
Q1 1 #REF!
CBR 1 for every 2500 cum #REF! #REF!
FDT 3 for every 500 sq.m. #REF! #REF! 3-FDT @ every 150mm/layer of subbase coarse
PART E - SURFACE COURSE
311 Portland Cement Concrete Pavement cu.m.
a.)Cement bags PEC 1 for every delivery -
Project Engineer Certificate or Mill Certificate
#REF! MC
Qc 1 for every 2000 bags #REF! apply Qc if source is questionable or per concrete trial mix result
b.) Fine Aggregates Q4 1 for every 1500 cu m. #REF! apply Q3 test, if source not yet tested
#REF!
G 1 for every 75 cu m. #REF! Additional test (G) if delivered materials are inconsistent
c.) Coarse Aggregates Q6 1 for every 1500 cu m. #REF! apply Q5 test, if source not yet tested
#REF!
G 1 for every 75 cu m. #REF! Additional test (G) if delivered materials are inconsistent
d.) Water PEC 1 for the whole work Inspection Report or Qw if source is questionable
Qw 1 for the whole work
e.)Joint Filler PEC -
#REF! 1 for every Inspection Report or Mill Test Certificate
MC
f.)Steel Bars Q7 1 for every 10000 kg #REF! #REF! Dowels
#REF!
MC for every delivery
g.)Concrete Ft or Ct 3 for every 75 cu.m #REF! 3 beam or cylinder samples per set for 75 cu.m or batch day
#REF!
St 1 for every batch/day Per batch if consistency is questionable
h.) Concrete Pavement sq.m Tc 5 per km/lane core drilling and compression test
407 Concrete Structures
404 Reinforicng Steel works kgs. #REF! Q7 1 for every 10000 kg #REF! #REF! 1 sample per size
405 Structural Concrete cu.m.
a.)Cement # of bags Qc 1 for every 2000 bags #REF! #REF! apply Qc if source is questionable
#REF!
MC 1 for every delivery
b.) Fine Aggregates cu.m. Q4 1 for every 1500 cu m. #REF! apply Q3 test, if source not yet tested
#REF!
G 1 for every 75 cu m. #REF! Additional test (G) if delivered materials are inconsistent
c.) Coarse Aggregates cu.m. Q6 1 for every 1500 cu m. #REF! apply Q5 test, if source not yet tested
#REF!
G 1 for every 75 cu m. #REF! Additional test (G) if delivered materials are inconsistent
d.) Water PEC 1
DETAILED ESTIMATES
I LABOR
No. of
Description Person No. of Day Daily Rate Amount (Php)
Construction Foreman 1 10 480.00 4,800.00
Laborers 7 10 330.00 23,100.00
Sub-Total 27,900.00
II EQUIPMENT
No. of
Description Units No. of Day Daily Rate Amount (Php)
Back hoe w/ breaker 1 10 10,500.00 105,000.00
Dumptruck 1 10 1,250.00 12,500.00
Fuel 320 ltr 43.00 13,760.00
Lubricants, Spare parts & others (lumpsum) 2,500.00
FOLS 6,500.00
0
Sub-Total 0.00
I LABOR
No. of
Description Person No. of Day Daily Rate Amount (Php)
Construction Foreman 1 35 480.00 16,800.00
Steelmen 7 35 400.00 98,000.00
Laborers 6 35 320.00 67,200.00
Sub-Total 182,000.00
II EQUIPMENT
No. of
Description Units No. of Day Daily Rate Amount (Php)
Bar Cutter 1 35 100.00 3,500.00
Bar Bender 1 35 100.00 3,500.00
Handtools -
Sub-Total 7,000.00
III MATERIALS
Sub-Total 611,013.06
I LABOR
No. of
Description Person No. of Day Daily Rate Amount (Php)
Construction Foreman 1 12 480.00 5,760.00
Masons 4 12 400.00 19,200.00
Carpenter 4 12 400.00 19,200.00
Laborers 18 12 320.00 69,120.00
Sub-Total 113,280.00
II EQUIPMENT
No. of
Description Units No. of Day Daily Rate Amount (Php)
Concrete mixer 1 12 270.00 3,240.00
Concrete vibrator 1 12 150.00 1,800.00
FOLS 1,500.00
Sub-Total 6,540.00
III MATERIALS
Sub-Total 380,205.00