Code: LEM-COM-PR01-F05

LAMBERTELECTROMEC Edition 1
Effective date :
Method statement 07/06/2012

A- General Info: LEM-MS-EKO TOWER 2-001 FOR SPLIT TYPE UNIT


INSTALLATION.

Activity Name and Type: Split type unit  Electrical  Mechanical


 Telecom  Low Current
installation
Activity Description: Split type unit installation

Activity Trade: Mechanical


Activity Briefing: Installation of Split type unit in accordance with the contract documents and
approved shop drawings.

Method Statement Objectives: To enumerate the practical steps that will be involved in the
installation of split type unit with necessary accessories.

B- Resources Requirements
Position of Personnel Required Main Tools Requirements
1. Team leader (Site Engineer/Supervisor)
2. Foremen.
Drilling machine, hammer, sprit level, measuring
3. Technicians.
tape, scaffold, ladder, power extension, tool box.
4. Technical helper.

C-References
Mechanical Specification
Approved Shop drawings
Approved Material Submittals
Project Health & Safety Regulations

D-Safety Guidelines
All workers will attend daily safety induction session before starting work
All workers should put on the appropriate Personal Protective Equipments (PPEs) such as cover-all, Helmet and
safety boots.
All equipment’s shall be tagged and checked before using.
Housekeeping shall be done before and after working to remain cleanliness in the area.
Code: LEM-COM-PR01-F05
LAMBERTELECTROMEC Edition 1
Effective date :
Method statement 07/06/2012

E-Responsibilities
The Project Manager is over all responsible for planning, control, monitoring and
executing the project in accordance with the contract documents, specifications, and Local Authority
regulations.

Site Mechanical Engineer is responsible to check and ensure the conformity of mechanical installations with
project Standards and Local Authority regulations. He is also responsible to ensure that the inspection and
testing are done as per approved quality control procedure/documents.

The Project Engineer is responsible to carry out the work as per approved shop drawings and method
statements. He is also responsible for the inspection and testing of mechanical installations as per approved
inspection and test plan. He is directly responsible for the timely executions of all aspect of work in coordination
with the other trades involved in the project.

The Site QA/QC is responsible:


a. To ensure that Material complies with approved Material Submittals.
b. To carry out Inspection of all Installations.
c. To ensure that installations are being tested where needed.
d. To generate non-conformances and ensure corrective action is taken when required.
e. To notify the responsible Quality Manager of all non-conformances.
f. To create an Inspection Plan in liaison with the Project engineers.
g. To coordinate with the Main Contractor/Consultant or Client to ensure timely inspection of the job.
h. Produce all reports and documentation that might be required by his/her Manager.
Code: LEM-COM-PR01-F05
LAMBERTELECTROMEC Edition 1
Effective date :
Method statement 07/06/2012

F-Installation Instructions

1. Arrange all required materials, accessories and tools at work area before commencing work.
2. Hold the mounting plate against the wall where the location of the indoor unit.
3. Use a sprit level to make sure the plate is both horizontally and vertically square.
4. Drill holes into the wall at the appropriate spots to affix the plate to the wall, Secure the plate to the wall
with tapping screws.
5. Install the indoor unit as stated on shop drawing.
6. Installation of the remote control unit in suitable place where is not splashed by water.
7. Install the outdoor unit with isolator rubber as stated on shop drawing.
8. Connect the pipes between the indoor and outdoor unit.
9. Connect the control cable between the indoor and outdoor unit.
10. Connect the AC drain to nearest floor drain as per shop drawing.
11. Make the necessary power connection.
12. After completion of works send request for inspection to the consultant through the main contractor.

House Keeping & Logistics

At the close of each working day, all material surpluses to requirements, and general items of scrap or debris,
will be removed from the work-face in order to maintain a clear and clean working environment.
Storage of all materials, plant, equipment, tools etc is not to impede access or egress to and from work areas.
Code: LEM-COM-PR01-F05
LAMBERTELECTROMEC Edition 1
Effective date :
Method statement 07/06/2012

Developed by : Mohammad Laham Signature : Date :

Checked by : Pierrot Almawi Signature : Date :