Work Pending.

Legend
Work Completed.
Viaduct (GSPD Ramp to P-42)
Third Rail & cable Bracket Total Installed % Progress
Bracket (No.):- 696 0%

Insulator (No.):- 696 0% APMC Station (ASS-TSS)


(20.01.2021)
GSPD Ramp
87% work completed.
Third Rail (m) :- 3124.5 0%

33kV cable Brackets (No.):- 2604 1080 41%

Week Progress Bracket:-


— Insulator:- — Power Feed:- Third Rail:- — 33kV Bracket:- —
(22.07 to 29.07)

Viaduct B/W APMC-JVRJ (P-43 to CP-69) (08.04.2021)


Third Rail & cable Bracket Total Installed % Progress
Bracket (No.):- 356 251 71%

APMC Station (ASS-TSS) Insulator (No.):- 356 251 71% Jivraj Station (ASS)
(20.01.2021) (25.03.2021)
87% work completed.
Third Rail (m) :- 1594.6 1135 71%

33kV cable Brackets (No.):- 1329 1299 98%

Week Progress Bracket:-


— Insulator:- Power Feed:- Third Rail:- — 33kV Bracket:- —
(22.07 to 29.07)

Note:- Here, Third Rail installation means completion of hanging only. (not includes splicing, coveering, EJ, MPA, PF installation)
1090m Third Rail Cover Fixing.

Note:- Here, Third Rail installation means completion of hanging only. (not includes splicing, coveering, EJ, MPA, PF installation)
Viaduct B/W SBRS-AEC (P-419 to P-442) (22.04.2021)
Third Rail & cable Bracket Total Installed % Progress
Bracket (No.):- 321 268 83%

Sabarmati RLY. Station(ASS- Insulator (No.):- 321 268 83% AEC Station(ASS-TSS)
TSS) (07.01.2021)
Third Rail (m):- 1605.5 1440 90%

33kV cable Brackets (No.):- 1338 1338 100.00%

Week Progress
Bracket:- Insulator:- Power Feed:- Third Rail:- — 33kV Bracket:- —
(22.07 to 29.07)

48 Splicing, 8 MPA and 8 EJ installed in last week.

Viaduct B/W AEC-SMMS (P-443 to P-479) (22.04.2021)


Third Rail & cable Bracket Total Installed % Progress
Bracket (No.):- 550 550 100%

Insulator (No.):- 550 395 72% Sabarmati Metro


AEC Station(ASS-TSS)
Station(ASS)
(07.01.2021)
(24.05.2021)
Third Rail (m):- 2302 2302 100%

33kV cable Brackets (No.):- 1919 1919 100.00%

Week Progress
Bracket:- Insulator:- Power Feed:- Third Rail:- 238 33kV Bracket:- —
(22.07 to 29.07)

Viaduct B/W SMMS-MTRS (P-480 to PP-518) (15.06.2021)


Third Rail & cable Bracket Total Installed % Progress
Bracket (No.):- 510 0%

Sabarmati MetroNote:- Here, Third Rail installation means completion


Insulator (No.):-of hanging only. (not includes splicing,
510coveering, EJ, MPA, PF installation)
0% Motera Stadium
Station(ASS) Station(ASS-TSS)
(24.05.2021)