Traction Progress - Graph NS Corridor
Traction Progress - Graph NS Corridor
Legend
Work Completed.
Viaduct (GSPD Ramp to P-42)
Third Rail & cable Bracket Total Installed % Progress
Bracket (No.):- 696 0%
APMC Station (ASS-TSS) Insulator (No.):- 356 251 71% Jivraj Station (ASS)
(20.01.2021) (25.03.2021)
87% work completed.
Third Rail (m) :- 1594.6 1135 71%
Note:- Here, Third Rail installation means completion of hanging only. (not includes splicing, coveering, EJ, MPA, PF installation)
1090m Third Rail Cover Fixing.
Note:- Here, Third Rail installation means completion of hanging only. (not includes splicing, coveering, EJ, MPA, PF installation)
Viaduct B/W SBRS-AEC (P-419 to P-442) (22.04.2021)
Third Rail & cable Bracket Total Installed % Progress
Bracket (No.):- 321 268 83%
Sabarmati RLY. Station(ASS- Insulator (No.):- 321 268 83% AEC Station(ASS-TSS)
TSS) (07.01.2021)
Third Rail (m):- 1605.5 1440 90%
Week Progress
Bracket:- Insulator:- Power Feed:- Third Rail:- — 33kV Bracket:- —
(22.07 to 29.07)
Week Progress
Bracket:- Insulator:- Power Feed:- Third Rail:- 238 33kV Bracket:- —
(22.07 to 29.07)