National BIM Guidelines FINAL Australia
National BIM Guidelines FINAL Australia
April 2017
Na onal BIM Guidelines and Case Studies for Infrastructure
Core Members
The Sustainable Built Environment Na onal Research Centre’s collabora on with our
partners is adding significant value to the effec veness and long‐term sustainability of
Australia’s built environment industry. This research would not have been possible
without the ongoing support of our industry, government and research partners:
2
Na onal BIM Guidelines and Case Studies for Infrastructure
Preface
The Sustainable Built Environment Na onal Research Centre and its predecessor, the
Coopera ve Research Centre for Construc on Innova on, has been commi ed to
leading the Australian property, design, construc on and asset management industry
in collabora ve research and innova on since 2001. We have been dedicated to
dissemina ng prac cal research outcomes to our industry, to improve business
prac ce and enhance the compe veness of our industry. Developing applied
technology and management solu ons, and sharing useful industry knowledge is
what our Centre is all about.
We look forward to your using the results of this applied research and working
together, transforming our industry in enhanced business prac ces, safety and
innova on.
3
Na onal BIM Guidelines and Case Studies for Infrastructure
Project Team
Professor Xiangyu Wang (Project Leader), Australasian Joint Research Centre for BIM, Cur n University
Professor Keith Hampson, Sustainable Built Environment Na onal Research Centre, Cur n University
Jun Wang, Research Assistant, Australasian Joint Research Centre for BIM, Cur n University
Wenchi Shou, Research Assistant, Australasian Joint Research Centre for BIM, Cur n University
Acknowledgement
Thanks to the following organisa ons for providing the BIM case studies
4
Na onal BIM Guidelines and Case Studies for Infrastructure
Executive Summary
To date, the level of BIM implementa on in Managing the development of a BIM model
the transport infrastructure sector is a few requires skills that are similar to managing
years behind that for ver cal building the real thing. BIM produc on is some mes
construc on. Compared with the building done by people who understand computer
sector, the provision of infrastructure technology but do not necessarily
usually involves physical and organisa onal understand how to manage the workflow
structures addressing society needs which into a BIM model from mul ple sources. In
are mainly owned and managed by order to improve the quality of BIM models,
governments. Almost all published BIM BIM model management requires more
guidelines/standards are targeted to the rigorous se ng of modelling guidelines, BIM
building sector. The purpose of this BIM roles and responsibili es, and BIM model
guideline is to promote the applica on of assessment.
BIM in infrastructure projects and to ensure
data fidelity and con nuity across the To bring together the informa on and
lifecycle of a project, thereby improving engage in BIM, effec ve and coordinated
quality and produc vity. collabora on is essen al. Two types of
collabora on workflows have been
Infrastructure in this guideline refers in developed, for individual discipline
par cular to main roads, highways, bridges modelling and cross‐disciplinary model
and tunnels, which each have their own design respec vely. In addi on, BIM
construc on methods and characteris cs. relevant issues are discussed such as
The experiences and inves ga on data from ownership, contractual implica ons and risk
the building sector are generally not profile.
relevant for infrastructure. This project has
iden fied and redefined 41 BIM uses in Five case studies were conducted to
infrastructure, which include 18 BIM uses in demonstrate the BIM capaci es in
the design stage, 11 in the construc on infrastructure projects: Upgrade of Great
stage and 12 in the opera onal stage. Eastern Highway (Australia), Moreton Bay
Regarding BIM model development, seven Rail project (Australia), Memorial Park
Levels of Detail (LODs) have been defined Underpass (New Zealand), Perth’s Light Rail
from LOD0 to LOD6. LOD0‐LOD4 come from Network (Australia) and Auckland City Rail
the CityGML standard and are useful in the Link (New Zealand).
infrastructure planning and design stages.
LOD5 and 6 are developed at the model
element level and used to support
infrastructure construc on and opera on.
5
Na onal BIM Guidelines and Case Studies for Infrastructure
Contents
Introduc on .................................................................................................................................... 10
1.1 What is BIM? ...................................................................................................................... 10
1.2 Purpose and scope ............................................................................................................ 11
1.3 Exis ng relevant guidelines ............................................................................................. 11
1.4 Terms and defini ons ....................................................................................................... 11
1.4.1 Industry Founda on Class (IFC) .................................................................................... 11
1.4.2 City Geography Markup Language (CityGML)............................................................... 12
1.4.3 Construc on Opera ons Building Informa on Exchange (COBie) ............................... 12
1.4.4 Level of Detail (LOD) ..................................................................................................... 12
1.4.5 Interoperability ............................................................................................................. 13
1.4.6 Model Element.............................................................................................................. 13
1.4.7 Model Element Author (MEA) ...................................................................................... 14
1.4.8 Request for Informa on (RFI) ....................................................................................... 13
6
Na onal BIM Guidelines and Case Studies for Infrastructure
7
Na onal BIM Guidelines and Case Studies for Infrastructure
BIM collabora on 42
5.1 BIM roles and responsibili es 42
5.1.1 BIM Project Manager 42
5.1.2 BIM Coordinator 42
5.1.3 Design BIM Manager 43
5.1.4 Construc on BIM Manager 44
5.2 Individual discipline modelling 46
5.3 Cross‐disciplinary model design 46
8
Na onal BIM Guidelines and Case Studies for Infrastructure
Case studies 53
7.1 Case Study 1: Upgrade of Great Eastern Highway, Western Australia 54
7.2 Case Study 2: Moreton Bay Rail Project, Queensland 58
7.3 Case Study 3: Memorial Park Underpass, New Zealand 65
7.4 Case Study 4: The Design of Perth’s Light Rail Network, Western Australia 74
7.5 Case Study 5: Auckland City Rail Link, New Zealand 80
References 96
9
1 Introduction
1.1 What is BIM?
1.2 Purpose and scope
In recent years, while BIM has become projects and to ensure data fidelity and
an important strategy in building con nuity across the lifecycle of a project
construc on to improve produc vity and improving quality and produc vity.
profitability, uses of BIM are just
beginning in infrastructure construc on. This BIM guideline focuses on four types
However, the applica on of BIM for of infrastructure: Main roads, Highways,
Infrastructure is rapidly accelera ng as Bridges and Tunnels. Also, it is used as a
owners and engineering servicereference guide to implement BIM for
providers increasingly recognise the infrastructure and provides BIM uses,
main elements with LOD (Level of Detail),
benefits of 3D modelling using intelligent
objects. modelling guidelines and model
assessment/quality control, BIM
The purpose of this BIM guideline is to collabora on, relevant issues and case
promote the use of BIM in infrastructure studies.
10
1.3 Existing relevant guidelines
A total of 42 guidelines from 10 countries for Infrastructure document, which
were collected and analysed (as shown in consists of both BIM Specifica ons and
Table 1). They were used as reference BIM Modelling and Collabora on
guides in the development of this Procedures.
Na onal BIM Guidelines and Case Studies
See the detailed list of each existing BIM guideline in Appendix A.
1.4 Terms and definitions
1.4.1 Industry Foundation Class (IFC)
The IFC specifica on is a neutral data format to with the Interna onal Standardiza on
describe, exchange and share informa on Organisa on ISO as ISO16739. The IFC
typically used within the building and facility specifica on is developed and maintained by
management industry sector. IFC is the buildingSMART Interna onal (h p://
interna onal standard for openBIM www.buildingsmart.org/ , formally known as
(openBIM is a universal approach to the Interna onal Alliance for Interoperability, IAI).
collabora ve design, realisa on, and opera on The official website to publish IFC and related
of buildings based on specifica ons is buildingsmart‐tech.org (h p://
open standards and workflows.) and registered www.buildingsmart‐tech.org/ ).
11
1.4.2 City Geography Markup Language (CityGML)
CityGML is an open data model and XML‐ CityGML is to reach a common defini on
based format for the storage and of the basic en es, a ributes, and
exchange of virtual 3D city models. It is rela ons of a 3D city model. This is
an applica on schema for the Geography especially important with respect to the
Markup Language version 3.1.1 (GML3), cost‐effec ve sustainable maintenance
the extendible interna onal standard for of 3D city models, allowing the reuse of
spa al data exchange issued by the Open the same data in different applica on
Geospa al Consor um (OGC) and the ISO fields.
TC211. The aim of the development of
1.4.3 Construction Operations Building Information Exchange (COBie)
1.4.4 Level of Detail (LOD)
In computer graphics, accoun ng for LOD provided. The LOD for a BIM model must
involves decreasing the complexity of a correspond to the needs of the modeller,
3D object representa on as it moves the project engineer, and the es mators
away from the viewer or according to and schedulers. LOD iden fies how much
other metrics such as object importance, informa on is known about a model
viewpoint‐rela ve speed or posi on. element at a given me. This
From a BIM perspec ve, LOD is a "informa on richness" grows as the
measure of the amount of informa on project comes closer to breaking ground.
12
1.4.5 Interoperability
1.4.6 Model Element
1.4.7 Model Element Author (MEA)
The Model Element Author is the party responsible for developing the content of a
specific Model Element to the LOD required for a par cular phase of the project.
1.4.8 Request for Information (RFI)
13
2 BIM uses in infrastructure
14
2.1 BIM uses in design stage
2.1.1 Site Analysis
2.1.2 Design Authoring
The design authoring purpose of the BIM add to the richness of informa on in a
uses is used to develop a Building model. Most audit and analysis tools can
Informa on Model based on criteria that be used for Design Review and
is important to the transla on of the Engineering Analysis BIM uses. Design
infrastructure’s design. Two groups of authoring tools are a first step towards
applica ons that are at the core of the BIM and the key is connec ng the 3D
BIM‐based design process are design model with a powerful database of
authoring tools and audit and analysis proper es, quan es, means and
tools. Authoring tools create models methods, costs and schedules.
while audit and analysis tools study or
2.1.3 Surface Analysis
The surface analysis purpose of BIM uses proposed design interven ons can be
is to generate detailed analysis of model assessed in terms of eleva on, slope,
objects such as the detailed volume aspect and hydrology, and cut and fill
analysis. All the analysis performed on calcula ons can also be made to balance
the exis ng Surface can also be earthworks requirements .
performed on proposed Surfaces. The
2.1.4 Land Survey
15
2.1.5 Performance Forecasting
The performance forecas ng of BIM uses life cycle cost of a facility. Scenario
is one of the largest and has the most forecas ng predicts performance of the
variance in its applica on from element facility during emergencies, such as fire,
to element. Within this purpose, detail accident and others. Temporal
analysis is conducted to predict future forecas ng predicts the performance of
performance of the facility and facility the facility over me to include building
elements. Some of the primary degrada on and the ming for element
performance factors that should be replacement. Together this purpose of
considered include financial, energy, BIM Uses examines mul ple facility
flow, scenario and temporal. Financial variables and predicts facility
forecas ng includes cost es ma on of performance.
first cost of construc on as well as the
2.1.6 Constructability Reviews
In this purpose of BIM uses, BIM is used exis ng systems related to construc on
for reviewing the building model and sequence, equipment access, completed
checking for coordina on and work and assembling difficult
buildability, along with plans and components. In this way, any
specifica on to determine misunderstandings can be reduced or
constructability of the project and cleared before ge ng out into the field,
coordinate with other project since all the important design details
par cipants. It can be used to enhance have been clarified.
2.1.7 Design Reviews
BIM is used to showcase the design to alterna ves and solve design and
the stakeholders, evaluate mee ng the constructability issues. If properly
program, and set criteria such as layout, executed, these reviews can resolve
sightlines, security, ergonomics and design issues by offering different
textures and colours, etc. Virtual mock‐ op ons by developing and evalua ng its
ups can be done in high detail even on a conceptual design alterna ves in that
part of the infrastructure, like a pier of a single model.
bridge, to quickly analyse design
16
2.1.8 Visualisation
As part of the communica on purpose of precise surface informa on, road and
BIM uses, using BIM to be er visualise a site designs and pipe network models.
facility is very powerful. BIM for Visualisa on is o en used to support
Infrastructure so ware maintains fidelity decision making about the facility's
between modelling, analysis and design or construc on as well as support
rendering applica ons in order to allow marke ng efforts. It can also include
for quick and accurate visual walkthroughs and schedule
representa ons of projects in a visualisa ons.
contextual environment by u lising
2.1.9 Design Changes
2.1.10 Design Evaluation
Using BIM tools, engineers can visually drainage, collec on and u lity networks
analyse designs beyond that which in real me is made possible with these
numeric values on a spreadsheet alone so ware tools. As project changes occur,
can communicate. Rota ng a design adjustments are made in the so ware
three‐dimensionally and performing and engineers can review the effects
automated clash detec on analysis for immediately.
17
2.1.11 Design Integration
This purpose of BIM uses is to quickly sketch early‐stage designs directly in that
consolidate different data files modelling environment or import
represen ng exis ng condi ons, such as detailed design informa on from Civil 3D
2D CAD, GIS, raster and 3D models, into a to easily create project visualisa ons and
single model. With the exis ng simula ons.
condi ons model in place, designers then
2.1.12 Quantity Take‐off
In this purpose of BIM uses, BIM is used and subject to change. In the
for coun ng or collec ng the amount of construc on phase, quan es become
specific facility elements. This purpose is more certain and in the opera ons
o en used as part of the es ma ng and phase, quan es of elements can be
cost forecas ng process. During the readily calculated.
design phase of a facility, quan es are
defined broadly, represented by a range
2.1.13 Cost Estimation
2.1.14 Code Validation
This purpose of BIM uses is implemented rooms. The purpose of func onality
to validate facility informa on. This valida on is to ensure that the facility is
includes purpose checking facility construc ble, maintainable, and usable.
informa on for accuracy to ensure that it Will the facility perform the purpose for
is logical and reasonable. The valida ng which it has been designed? Compliance
BIM uses fall into three primary areas: valida on confirms a facility's compliance
prescrip on, func onality and with codes and standards to include
compliance valida on. Prescrip on construc on codes, sustainability
valida on ensures that the facility has standards and others. Any me facility
the elements that were specified and informa on that was developed in
programmed within the facility including another process is checked for accuracy,
the primary element of facility spaces or it falls into the category of valida ng.
18
2.1.15 Structural Analysis
BIM data is u lised to determine the take place to create effec ve, efficient
behaviour of a given structural system. and construc ble structural systems. The
With the modelling, minimum required development of this informa on is the
standards for structural design and basis for what will be passed on to the
analysis are used for op misa on. Based digital fabrica on and construc on
on this analysis, further development system design phases.
and refinement of the structural design
2.1.16 Point Clouds
The term “Point Clouds” has been floated What we can use these resul ng point
around for a long me, but within the clouds for can vary from surface models
last few years there has been a deluge of for environmental studies, transporta on
technology advancements and drop in engineering, structural design, pipe
cost making the equipment to capture network modelling, to visualisa on. The
the built environment 3‐dimensionally an point cloud surveys have the advantages
economically viable op on for that they can be completed more
architecture, engineering and quickly, provide fully detailed coverage
construc on industries. There are many of the area and require fewer return
different methods for acquiring a point visits to pick up any missed details. This
cloud such as aerial LiDAR, mobile laser has great benefits in reducing the need
scanning, sonar and 3D photogrammetry. for trackside surveys.
2.1.17 Signal Sighting
The BIM approach has provided a major establish feasibility. An example of this is
opportunity to design and test the new the need to bring forward design of small
signalling proposals well ahead of a ‐parts fixing arrangements for overhead
scheme being on site. The 3D modelling line equipment close to cri cal signals,
has also focused a en on on areas where there is a risk of these elements
where early design focus is required to obscuring the signal.
19
2.1.18 Traffic Simulation
As the BIM advances to the broader out different scenarios regarding traffic
infrastructure space, this ability to pa erns to op mise design in real me.
automate the performance of This adds to the intelligent modelling
infrastructure design with traffic capabili es of Autodesk by taking the
simula on becomes really compelling. design, combining it with traffic data and
Programming provides the ability to test visualising it within a real‐world context.
2.2 BIM uses in the construction stage
2.2.1 Field Survey
Collec on and gathering of informa on The project team can leverage detailed
at the local level by conduc ng primary models built for trade coordina on or
surveys is called field survey. It is a basic other purposes and accurately lay out
procedure to understand the exis ng building systems in the field exactly as
surroundings. BIM and laser scanning can planned during the 3D model‐based
effec vely improve tradi onal survey coordina on process. BIM‐based
methods through accurately capturing construc on layout not only increases
detailed informa on about exis ng the level of layout precision, but also
condi ons and rapidly producing a 3D takes less manpower than tradi onal
model‐based representa on of the layout methods. This confidence and
exis ng environment for the project trust level is based on a reliance of the
team. accuracy of the BIM model.
2.2.2 Site Layout and Logistics
A site layout plan is a construc on plan facili es, hoarding details, signage and
prepared by the contractor as part of temporary services (i.e. electrical power,
their mobilisa on ac vi es before work ligh ng, water distribu on and drainage,
on site commences. The 3D model needs informa on and communica ons
to include: loca ons of cranes with radii technology installa ons, site security
and capaci es, site offices, welfare systems, etc.). With BIM and intelligent
facili es, off‐loading and storage areas, algorithms, a site layout scheme can be
sub‐contractor facili es, car parking, automa cally generated and dynamically
entrances, temporary roads, separate op mised.
pedestrian access, vehicle wheel washing
20
2.2.3 Virtual Scheduling and Work Planning
A tradi onal project schedule is based on resource collision, space collision and
a Gan chart and just shows the me collision. 4D simula on (3D models
sequence of each ac vity. It is hard to with the added dimension of me) is a
assess and evaluate the constructability powerful visualisa on and
of the schedule. With BIM, project communica on tool that can give a
managers can easily implement virtual project team, including the owner, a
project scheduling so as to eliminate be er understanding of project
collisions between ac vi es, such as milestones and construc on plans.
2.2.4 Construction Inspection
Building a new infrastructure project is a BIM implementa on, all the inspec on
complex process. Mistakes may not be and tes ng informa on are linked to a
discovered in a mely way through a 3D infrastructure model. Workers can
tradi onal approach which relies heavily easily get the right informa on at the
on personnel’s experience. In addi on, it right me at the right place. BIM can also
is me‐consuming to search for the right enable real me inspec on feedback so
informa on from tradi onal paper‐based as to record and track the inspec on
specifica ons and codes onsite. With progress.
2.2.5 Materials Management
21
2.2.6 Progress Tracking
Typical prac ce for progress tracking manual work that may impact the quality
mostly depends on foremen daily or of the progress es ma ons. BIM models
weekly reports which involve intensive integrated with laser scanning and
manual data collec on and entail mobile compu ng are being
frequent transcrip on or data entry implemented in the infrastructure
errors. These reports are then studied by industry and have shown big benefits for
field engineers and/or superintendents suppor ng progress tracking. When
along with 2D as‐planned drawings, combining 3D object recogni on
project specifica ons and construc on technology with schedule informa on
details to review the progress achieved into a combined 4D object oriented
by that date. A er that, they study the simula on, a project manager can
construc on schedule to iden fy the effec vely assess current construc on
work planned to be done by that date. progress and make mely decisions if a
This requires a significant amount of schedule delay appeared.
2.2.7 Quality Tracking and Reporting
BIM models provide quality assurance/ on a mobile device. A quality manager
quality control informa on for a quality can check the current status of all the
manager to help proac vely iden fy project quality issues and report to the
trends and minimise contractor risk. project manager. In addi on, in order to
Quality manager can create and improve the produc vity of a quality
automa cally distribute work‐to‐ check and reduce expensive rework, a
complete lists for trades and other quality checklist for each task can be
par es. A field quality check worker can embedded into a BIM model.
create and manage issues and checklists
2.2.8 Safety Planning and Control
Construc on safety and environmental contac ng the project coordinator. It is
plans must clearly describe how these difficult to iden fy and address all the
and other risks will be managed on each main safety hazards of the planned job.
project, what control measures will be BIM can provide a virtual construc on
used and how their effec veness will be pla orm and safety simula on
monitored and reviewed. Safe work environment for all the par es to
method statements are also required for develop a be er construc on safety
all work regarded as high risk plan. A BIM‐based safety plan can
construc on work, or prescribed ac vity. visually explain how the contractor
In the tradi onal process, the work intends to manage those safety risks to
method statements are firstly iden fied the contractors' own employees or
by the project coordinator through a subcontractors. In addi on, BIM‐based
preliminary project risk assessment. orienta on, introduc on, educa on and
Then, contractors may request a copy of supervision are possible ways to
this assessment to help in preparing their reinforce safety communica on by
own work method statements by visualisa on.
22
2.2.9 Cost Control
2.2.10 Equipment Management
Managing cost and revenue on type can be integrated into a BIM model,
equipment is cri cal to success in the such as maintenance schedules,
compe ve construc on market. BIM‐ complete service history and work
based construc on equipment arrangement. A project manager can
management can help a project manager develop a scien fic equipment
to schedule down me to fit project management scheme to improve and
workload. Status of every equipment ensure maximum u lisa on.
2.2.11 Digital Fabrication
A process that uses digi sed informa on minimum ambigui es and enough
to facilitate the fabrica on of informa on to fabricate with minimal
construc on materials or assemblies. waste. An informa on model could also
Some uses of digital fabrica on can be be used with suitable technologies to
seen in sheet metal fabrica on, assemble the fabricated parts into the
structural steel fabrica on, pipe cu ng, final assembly.
prototyping for design intent reviews,
etc. It assists in ensuring that the
downstream phase of manufacturing has
23
2.3 BIM uses in operation and maintenance stages
2.3.1 Maintenance Scheduling
2.3.2 System Analysis
2.3.3 Asset Management
24
2.3.4 Disaster Planning
2.3.5 Record Modelling
A process used to depict an accurate the capability to store more informa on,
representa on of the physical condi ons, the model contains a true depic on of
environment, and assets of a facility. The space with a link to informa on such as
record model should, as a minimum, serial codes, warran es and maintenance
contain informa on rela ng to the main history of all the components in the
architectural and MEP elements. facility. The record model also contains
Addi onal informa on including informa on linking pre‐build
equipment and space planning systems specifica on to as‐built specifica ons.
may be necessary if the owner intends to This allows the owner to monitor the
u lise the informa on. Furthermore, project rela ve to the specifica ons
with the con nuous upda ng and provided.
improvement of the record model and
2.3.6 Event Planning
The BIM operator has to put the Facility based checking data to FMS for
Management System (FMS) data into the maintenance inspec on, replacement of
system based on as‐built BIM data. When parts, space opera on & adjustment and
the object informa on has changed by renova on & expansion.
the space program, remodelling,
renova on and expansion etc., the BIM The BIM operator must input the final as‐
operator has to renew the BIM data. built BIM data to FMS and also has to
keep the original BIM data.
The BIM operator has to check and
monitor the facili es and input the BIM
25
2.3.7 Road/Rail Management
BIM road and rail infrastructure analyse current working condi ons of the
management solu ons help the user infrastructure, plan infrastructure
collect, maintain and analyse these improvements and plan future growth ‐
assets, delivering a central pla orm upon all the components necessary for
which they can plan, operate and effec ve railway and roadway asset
maintain an ever‐improving intelligent management. BIM data provides the
transporta on network. Included are the ability to collaborate and distribute
geospa al loca on of these assets, the geospa ally related data. BIM applica on
graphic representa on of these networks provides the technology framework
and their geospa al context in map form. needed for cost‐effec ve and efficient
This BIM solu on includes workflows to communica on involving geospa ally
build and manage infrastructure models, related informa on.
2.3.8 Transportation Management System
Planning, execu ng, monitoring and lifecycle. It allows users to quickly create
taking correc ve ac on across the en re and modify least‐cost shipment plans
transporta on lifecycle is cri cal in and loads that maximise capacity
today's complex and constrained u lisa on.
transporta on environment. This is why
manufacturers, retailers and logis cs Benefits from using BIM are overall cost
service providers choose BIM reduc on resul ng from transporta on
Transporta on Manager to effec vely op misa on, improved service levels and
manage their high‐volume, sophis cated customer sa sfac on, reduc on
transporta on networks. From order in damage‐in‐transit losses and the
management through customer service ability to enhance the reliability and
and financial se lement, BIM Manager efficiency of the distribu on network.
supports the en re transporta on
2.3.9 Traffic Volume Simulation
26
2.3.10 GIS Asset Tracking
The BIM helps you monitor the loca on ● Mobile asset tracking: real‐ me
and movement of objects in real me. loca on and status of vehicles,
Objects that can transmit their trains, trucks, ships, airplanes, and
geographic loca on via Global cargo containers
Posi oning Systems (GPS) or similar
technologies can be dynamically tracked ● Traffic control: traffic flow analysis
on a display map that can be shared via and real‐ me monitoring of traffic
the Internet or intranet. flow
Analy cal features enable users to With automa c vehicle loca on (AVL)
trigger an ac on based on an object's tracking and a GIS‐based display,
loca on rela ve to other geographic dispatchers can visually relate mobile
features, such as triggering an alert whenunit loca ons to des na on loca ons.
a vehicle or cargo moves out of its When live informa on or video feeds are
service area. incorporated into the map‐based display,
dispatchers can also keep an eye on the
BIM data support a diverse range of asset latest weather and traffic developments.
tracking applica ons such as
2.3.11 Water Mitigation and Planning
BIM can play an important role in most visible approach for flood
assessing the risk of communi es to mi ga on involves structural measures
flood events and the development and which include flood mi ga on dams,
implementa on of appropriate retarding basins, channel levees and
mi ga on measures to reduce the channel improvements.
severity and frequency of flooding. The
27
3 BIM model development
3.1 Transportation (main road, highway and railway)
Fig. 2: Representa ons of Transporta onComplex (from le to right: examples of road, track, rail,
and square) (source: Rheinmetall Defence Electronics).
28
Fig. 3: Example for the representa on of a Transporta onComplex in LOD2 in CityGML:
a road, which is the aggrega on of TrafficAreas and AuxiliaryTrafficAreas (source: City
of Solingen, IGG Uni Bonn).
In the coarsest LOD0 the Transporta onComplexes are just its centerline. In LOD2 to LOD4, it is further
modelled by line objects establishing a linear network. subdivided thema cally into TrafficAreas, which are
On this abstract level, path finding algorithms or similar used by transporta on, such as cars, trains, public
analyses can be executed. It also can be used to transport, airplanes, bicycles or pedestrians and in
generate schema c drawings and visualisa ons of the AuxiliaryTrafficAreas, which are of minor importance for
transport network. Since this abstract defini on of a transporta on purposes, for example road markings,
transporta on network does not contain explicit green spaces or flower tubs. The different
descrip ons of the transporta on objects, it may be a representa ons of a Transporta onComplex for each
task of the viewer applica on to generate the graphical LOD are illustrated in Fig.4 and Fig.5.
visualisa on, for example by using a library with style‐
defini ons (width, colour resp. texture) for each
transporta on object. Star ng from LOD1 a
Transporta onComplex provides an explicit surface
geometry, reflec ng the actual shape of the object, not
Fig. 4: Transporta onComplex in LOD0, 1, and 2‐4 Fig. 5: Transporta onComplex in LOD 2‐4: representa on of
(example shows part of a motorway) (source: a road with a complex cross‐sec on profile (example shows
Rheinmetall Defence Electronics). urban road) (source: Rheinmetall Defence Electronics).
29
3.2 Bridge model
The bridge model allows for the like rooms are dedicated to LOD4. To
representa on of the thema c, spa al cover the case of bridge models where
and visual aspects of bridges and bridge the topology does not sa sfy the
parts in four levels of detail, LOD 1 – 4 (as proper es of a solid (essen ally water
shown in Fig. 6). In analogy to the ghtness), a mul surface representa on
building model, the seman cal as well as is allowed. The line where the bridge
the geometrical richness increases from touches the terrain surface is
LOD1 (blocks model) to LOD3 represented by a Terrain Intersec on
(architectural model). Interior structures Curve, which is provided for each LOD.
Fig. 6: Bridge model in LOD1 – LOD4. (source: Karlsruhe Ins tute of Technology (KIT))
3.3 Tunnel model
The tunnel model supports the shown in Fig. 7). The thema c
representa on of thema c and spa al classifica on of tunnel surfaces is
aspects of tunnels and tunnel parts in illustrated in Fig. 8 for different types of
four levels of detail, LOD1 to LOD4 (as tunnel cross sec ons.
Fig. 7: Tunnel model in LOD1 – LOD4 (source: Karlsruhe Ins tute of Technology (KIT)).
30
In LOD1, a tunnel model consists of a simula ng disaster management or for
geometric representa on of the tunnel presen ng the light illumina on within a
volume. Op onally, Terrain Intersec on tunnel. The aggrega on of Hollow Spaces
Curve can be specified. These curves according to arbitrary, user defined
denote the exact posi on, where the criteria (e.g. for defining the hollow
terrain touches the 3D object. spaces corresponding to horizontal or
ver cal sec ons) is achieved by
The geometric representa on is refined employing the general grouping concept
in LOD2 by addi onal Surfaces and provided by CityGML. A Hollow Space
Curves. In LOD2 and higher LODs the may have the a ributes class, func on
outer structure of a tunnel can also be and usage. The class a ribute allows a
differen ated seman cally by the general classifica on of hollow spaces,
Boundary Surface and Tunnel e.g. commercial or private rooms, and
Installa on. A Boundary Surface is a part occurs only once. The func on a ribute
of the tunnel’s exterior shell with a is intended to express the main purpose
special func on like wall, roof, ground of the hollow space, e.g. control area,
plate, outer floor, outer ceiling. The installa on space, and storage space. The
Tunnel Installa on is used for tunnel a ribute usage can be used if the way
elements like outer stairs, strongly the object is actually used differs from
affec ng the outer appearance of a the func on. Both a ributes can occur
tunnel. mul ple mes.
In LOD3, the openings objects (doors and Spanning the different levels of detail,
windows) can be represented as the tunnel model differs in the
thema c objects. complexity and granularity of the
In LOD4, the highest level of resolu on, geometric representa on and the
also the interior of a tunnel, composed of thema c structuring of the model into
several Hollow Spaces, is represented in components with a special seman c
the tunnel model. This enlargement meaning. This is illustrated in Fig. 8,
allows a virtual accessibility of tunnels, showing the same tunnel in four different
e.g. for driving through a tunnel, for LODs.
31
3.4 LOD5 and LOD6 development
LOD0‐LOD4 which comes from CityGML LOD5: The Infrastructure Model Element is
standard is useful in infrastructure graphically represented within the Model
planning and design stages. However, it is as a specific system, object or assembly in
not suitable in construc on and opera on terms of size, shape, loca on, quan ty,
and maintenance stages. From the and orienta on with detailing, fabrica on,
lifecycle management perspec ve, it is assembly, and installa on informa on.
necessary to develop the further LOD, Non‐graphic informa on may also be
such as LOD5 for construc on stage and a ached to the Model Element.
LOD6 for opera on and maintenance
stage. LOD5 and LOD6 are developed LOD6: The Infrastructure Model Element is
based on Infrastructure Model Element a field verified representa on in terms of
level. Figs 9‐12 show the detailed model size, shape, loca on, quan ty, and
element for four different types of orienta on. Non‐graphic informa on may
infrastructure projects. also be a ached to the Model Elements.
Fig. 9: Model
elements for
road
32
Fig. 10: Model elements for bridge Fig. 11: Model elements for tunnel
33
4 BIM model management
Managing the development of the BIM model
requires skills that are similar to managing
the real thing. BIM produc on is done by
people who understand computer
technology but do not necessarily understand
how to manage the workflow into a BIM
model from mul ple sources. In order to
improve the quality of BIM models, BIM
model management requires se ng
modelling guidelines, BIM roles and
responsibili es, and BIM model assessment.
4.1 Modelling guidelines
4.1.1 BIM Element Modelling
In general, each element will be modelled element proper es are more generic and
according to its size, shape, loca on, orienta on approximate, but become more specific with
and quan ty. At the early stages of the project, increases in accuracy as the project progresses.
34
4.1.2 Model Orientation and Site Configuration
The origin point for the project should be and with reference to Australia Standard
clearly defined and drawn in the real Datum.
orienta on or spa al coordinate system
4.1.3 Model Division and Structure
Depending on the size of the building into separate building, zones and levels.
and / or the phasing for the project, it This should be agreed and documented
may be necessary to divide the model as early as possible.
4.1.4 Revision Management
The model will evolve rapidly during the should work with their respec ve BIM
project stages. Changes should be vendor to familiarise themselves with the
tracked and catalogued, especially when use of these so ware mechanisms so
the model crea on task is divided into a that design changes can be managed
few smaller packages and handled by more effec vely. The BIM coordinator for
different people. each discipline could play the role of
maintaining a register to record the
There are various so ware mechanisms latest informa on incorporated in the
to assist BIM users to manage and model.
monitor design changes. BIM users
4.2 BIM model assessment and quality control
Project teams should determine and of the model and data to various par es.
document their overall strategy for Each party contribu ng to the BIM model
quality control of the model. To ensure should have a responsible person to
model quality in every project phase and coordinate the model. This person, as
before informa on exchanges, part of the BIM team, should par cipate
procedures must be defined and in all major BIM ac vi es as required by
implemented. Each BIM created during the team. They should be responsible for
the lifecycle of a project must be pre‐ addressing issues that might arise with
planned considering model content, level keeping the model and data updated,
of detail, format and the party accurate, and comprehensive.
responsible for updates and distribu on
35
Quality control of deliverables must be Visual Check: Ensure there are no
accomplished at each major BIM ac vity unintended model components and the
such as design reviews, coordina on design intent has been followed by using
mee ngs or milestones. The standard of naviga on so ware
data quality should be established in the
planning process and agreed upon by the Interference Check: Detect problems in the
team. If a deliverable does not meet the model where two building components are
team’s standards, the reason why the clashing by a Conflict Detec on so ware
deliverable is lacking should be further Standards Check: Ensure that the model is
inves gated and prevented in the future. to the standards agreed upon by the team.
The deliverable needs to comply with
standards required by the owner and Element Valida on: Ensure that the
agreed upon by the project team. dataset has no undefined or incorrectly
defined elements
Each project team member should be
responsible for performing quality control Each party should designate a responsible
checks of their design, dataset and model party to make sure that the agreed upon
proper es before submi ng their process for quality control of models and
deliverables. Documenta on confirming data has been followed before accep ng
that a quality check was performed can be submi als and model revisions.
part of each submi al or BIM report. The
BIM Manager should be the one to confirm
quality of the model a er the revisions
were made.
36
BIM model quality assessment
37
4.2.1 Model Division and Structure
● Defining a file naming structure for all ● Iden fying and agreeing upon items
designers, contractor, subcontractors, such as the BIM and CAD standards,
and other project members content reference informa on, and the
version of IFC, etc.
● Describing and producing a diagram
how the models will be separated (e.g.
4.2.2 Model Delivery Schedule for Information Exchange
● Na ve file type
38
4.3 Electronic communication procedures
4.4 Interactive workspace
The project team should consider the co‐located?” If so, where is the loca on
physical environment it will need and what will be in that space? Will there
throughout the lifecycle of the project to be a BIM Trailer? If yes, where will it be
accommodate the necessary located and what will be in the space
collabora on, communica on, and such as computers, projectors, tables,
reviews that will improve the BIM Plan table configura on? Include any
decision making process. Describe how necessary informa on about workspaces
the project team will be located. on the project.
Consider ques ons like “will the team be
4.5 Technology infrastructure needs
The team should determine the requirements for hardware, so ware pla orms,
so ware licenses, networks, and modelling content for the project.
39
BIM simula on so ware is poten ally made by the authoring so ware and
revolu onary for construc on a aches cost, scheduling and other
management and contractors in informa on to it thus crea ng a tool for
par cular. This so ware takes the model achieving improved project delivery.
Computers / Hardware
Understanding hardware specifica ons ensure that this does not happen, choose
becomes valuable once informa on the hardware that is in the highest
begins to be shared between several demand and most appropriate for the
disciplines or organisa ons. It also majority of BIM Uses.
becomes valuable to ensure that the
downstream hardware is not less
powerful than the hardware used to
create the informa on. In order to
40
4.6 Revision management
The model will evolve rapidly during the project changes. BIM users should work with their
stages. Changes should be tracked and respec ve BIM vendor to familiarise themselves
catalogued, especially when the model crea on with the use of these so ware mechanisms so
task is divided into a few smaller packages and that design changes can be managed more
handled by different people. effec vely. The BIM coordinator for each
discipline could play the role of maintaining a
There are various so ware mechanisms to register to record the latest informa on
assist BIM users to manage and monitor design incorporated in the model.
41
5 BIM collaboration
5.1 BIM roles and responsibilities
5.1.1 The BIM Project Manager
BIM project should assign an individual to the ● Coordina ng BIM use on the project,
role of BIM project manager. This individual including quality control, access rights and
should have the appropriate level of relevant security
BIM experience required for the project
complexity and acquisi on delivery strategy. In ● Helping resolve design issues and change
general, responsibili es should include the control procedure
following: ● Managing and distribu ng digital outputs,
● Nego a ng, developing and enforcing the data transmission, and archiving.
BIM protocol
5.1.2 BIM Coordinator
All major technical disciplines/trades should ● Leading the technical discipline team BIM in
assign an individual to the role of lead BIM its documenta on and analysis efforts
technician to coordinate their work with the
en re Design/Construc on Team. These ● Coordina ng clash detec on and resolu on
individuals should have the relevant BIM ac vi es
experience required by the complexity of the ● Coordina ng internal and external BIM
project and should have, as a minimum, the training as required
following responsibili es for their discipline:
● Coordina ng trade items into the design
● Coordina ng technical discipline BIM BIM (depending on acquisi on).
development, standards, data
requirements, etc. as required with the plan)
design team BIM manager
42
5.1.3 Design BIM Manager
The design team should assign an individual to ● Liaising with design team, BIM and IT
the role of design team BIM manager. The managers to ensure so ware is installed and
individual should have sufficient BIM experience opera ng properly
for the size and complexity of the project and
should have relevant proficiency in the proposed ● Facilita ng BIM technical mee ngs with
BIM authoring and coordina on so ware. The discipline lead BIM coordinators
individual should serve as the main point of ● Determining the project BIM geo‐reference
contact with the BIM project manager and the point, and ensuring all technical discipline
design team for BIM related issues. In general, models are properly referenced to the point
responsibili es should include the following:
● Liaising with the client’s facili es
● Ensuring development and compliance with management department to determine
the approved design for BIM specific data and file exchange requirements
● Developing, coordina ng, publishing the ● Ensuring that the design deliverables
design plan and verifying that all necessary specified in the contract are provided in
configura ons required for the seamless conformance with the formats specified
integra on of design and construc on
model informa on have been implemented ● Ensuring informa on for facility
management (e.g. COBie), as required by
● Coordina ng team file management the BIM project brief, is provided for the
● Coordina ng the setup of shared file server contractor at nominated submi al
with design team IT staff. This should milestones
include interfacing with design team IT staff ● Ensuring proper BIM derived 2D informa on
to set up web portal, permissions, etc. for paper prin ng is provided as required
● Assembling composite design models for and that it conforms to the CAD/Drawing
coordina on mee ngs standards
● Facilita ng use of composite design models ● Coordina ng with the contractor to assure
in design coordina on/clash detec on the crea on of proper BIM final
mee ngs and providing detec on reports deliverables.
based on the iden fica on and resolu on of ● Aligning the requirements and deliverables
all hard and so collisions of different design team members
● Ensuring that BIM is used appropriately to irrespec ve of their contractual lineage, e.g.
test design requirements/criteria for IPD, EPC, DB
func onality
43
5.1.4 Construction BIM Manager
The construc on team should assign an ● Facilita ng use of composite trade models
individual to the role of construc on team BIM in construc on coordina on/clash
manager. This individual should have the detec on mee ngs and providing
appropriate level of relevant BIM experience detec on reports based on the
required for the project complexity and iden fica on and resolu on of all hard and
acquisi on delivery strategy. In general, so collisions
responsibili es should include the following:
● Communica ng with the design team,
● Taking overall responsibility for the coordina ng the data extrac on sets
construc on BIM model crea on and required by the construc on trades and
informa on developed during construc on ensuring that these requests are met
● Establishing so ware protocols for the ● Coordina ng with the design team to
construc on team for efficient delivery of facilitate the documenta on of design
project changes in the field and upda ng of the
BIM in a mely manner
● Ac ng as the main point of contact for BIM
and related issues between the ● Prior to approval and installa on, working
construc on team, subcontractors, the with Lead Fabrica on Modellers to
client, the design team and others as integrate 3D fabrica on models with the
required updated design model to ensure
compliance with design intent
● Where a contractor’s BIM Coordina on
Room is required by the project BIM brief, ● Coordina ng update of as‐built condi ons
providing specifica ons for it to the client in the final model deliverable
for approval. Ensuring that the
construc on team has necessary hardware ● Coordina ng with design team and
and BIM so ware properly installed and commissioning agent to ensure facility
accessible for project use management (e.g. COBie) informa on,
where required, is complete
● Where 4D BIM is required, ensuring
construc on sequencing and scheduling
ac vi es are integrated with the
construc on BIM
44
Table 2: Overview of responsibili es for BIM roles
5.3 Cross‐disciplinary model design
Project members should share their models possibili es of data loss or errors when sharing
with other project members at regular intervals different models. Issues that arose from the
for reference when they are developing their coordina on should be documented and
own single‐discipline model. At certain followed up.
milestones, models from different disciplines
should be subject to various coordina on Discrepancies discovered during the
processes, allowing involved par es to resolve coordina on process should be recorded,
poten al conflicts upfront and avoid costly managed, and communicated to relevant model
abor ve works and delays at the construc on owners through coordina on reports, including
stage. any specific loca on of interferences and
suggested resolu ons.
Prior to sharing, the data should be checked,
approved and validated as “fit for It is recommended that a revised version of the
coordina on”. The project team could leverage model should be frozen and signed‐off a er the
on the available so ware solu ons to perform issues iden fied during the coordina on
the coordina on effec vely. A common exercise have been resolved. A digital signature
(so ware) pla orm is recommended, to reduce can be considered to effect the protec on.
46
Example: Cross‐disciplinary model design in a road project
47
6 BIM relevant issues
6.1 Different BIM models
6.2 Duplication
Some firms may not be able to afford duplica on and creates the poten al for
BIM and therefore tradi onal drawings ambiguity. If, for example, the
will s ll have to be produced to manage contractual documents are in 2D but the
the downward supply chain. It is also project is designed in a BIM model –
likely that smaller contractors will not which will take precedence?
have access to the digital BIM model on‐
site. Further, most authori es require
tradi onal drawings for planning and
building regula on approval. This causes
48
6.3 Ownership
In most projects, ownership of the BIM algorithms and applicable engineering
model is likely to be retained by the principles. It is this informa on which the
owner of the building. However, system applies to enable the model of
ownership of the data contained within the building to be manipulated and
the BIM model itself is a separate issue. updated. Therefore design par cipants
Such data is likely to be wide‐ranging, will be required to depart much more
and contribu ons will come from a intellectual property on a BIM project
variety of different par cipants. For than they are tradi onally used to. The
example, there is likely to be design data, terms of any assignment or licensing of
cost data, design processes, tables, intellectual property rights will therefore
databases and graphical informa on. be of great concern to all design
Different laws will govern each of these par cipants. Increased integra on and
rights. Enhanced regard to intellectual collabora on also means that there will
property provisions is especially be complex layers of intellectual
important since the BIM model will not property, provided by different design
only show the results of patented par cipants, which will be difficult to
processes and designs, the BIM will iden fy and reverse engineer.
actually ‘know’ the building codes,
6.4 Designer's liability exposure
In a collabora ve BIM model many model, by modifying elements of the
par es contribute to the design. Crucial design affected by a change. These
details embedded in the design may be circumstances increase the poten al
provided not by design professionals, but liability exposure of design professionals
by specialty subcontractors or who use BIM collabora vely and risk
consultants. In addi on, BIM so ware is assuming overall model responsibility.
designed to react to changes in the
6.5 Professional terms of engagement
Terms of engagement for all of the contractual rela onship to work together
project team will need to be considered in order to deliver the project in the
and dra ed to reflect the collabora ve integrated and collabora ve spirit
nature of BIM and to ensure that required by BIM. Provisions on the input
responsibili es, du es and services are of data, limita on of liability and defining
aligned. Communica on and methods of the role of any BIM ‘model manager’ will
working will need to be outlined to also be crucial.
enable those who are not in a direct
49
6.6 Risk profile
The risk profile for construc on projects changes to policies and procedures. A
and project par cipants will change with balance will need to be struck between
use of a BIM model and a collabora ve, the need for fluid collabora on between
integrated approach. Measures will need par es on the one hand and the need to
to be taken to mi gate any increased precisely define responsibility to manage
areas of risk. This may require insurance, the changed risk profiles on the other.
indemni es, changes to contracts and/or
6.7 Mindset and approach
BIM will completely change the way that framework and incorporate the level of
designers approach the design process. detail required. More hours will be spent
The level of informa on contained within during the design and less in produc on.
a BIM model requires collabora on
between different par cipants at an
early stage to establish the ini al
6.8 Information technology
BIM places increased reliance upon be considered. The BIM model will be the
informa on technology. With this core of the project and just one error in it
reliance comes the need for specific can be very costly. Unlike the tradi onal
precau ons such as careful control of approach, with plans that can be checked
access rights and recording of audit trails. against one another, BIM plans are
Technical support facili es, firewall generated from the model and reflect
limita ons, bandwidth limits, corrup on the same data. This may allow small
of data and compa bility issues are miscalcula ons, which can later lead to
amongst the other concerns that need to big problems that are difficult to spot.
6.9 Cost
BIM models will require significant obtaining suitable bandwidth to handle
investment from those across the BIM data exchange. Given the level of
industry. There will be the direct cost of investment necessary, the industry will
the so ware and hardware but also take a cost benefit analysis to decide on
indirect costs such as training and adop on.
6.10 Owner
Owners are likely to pay for the owner stands to benefit most financially
opera on and management of the BIM, from BIM usage with both construc on
for example, appoin ng an informa on and opera onal savings.
or BIM model manager. However, the
50
6.11 Designers
Designers will have to spend significant collec ve design). However, designers
amounts on purchasing so ware, will benefit from advanced design
licences, hardware and training staff. features, such as clash deten on and
There will also be costs incurred from value engineering tools. BIM also has a
obtaining insurance (with poten ally proven track record as a marke ng tool,
high premiums given the collabora ve which provides a clear commercial
nature of BIM and increased risk of advantage in any bid process.
6.12 Contractors
In a collabora ve BIM model many model, by modifying elements of the
par es contribute to the design. Crucial design affected by a change. These
details embedded in the design may be circumstances increase the poten al
provided not by design professionals, but liability exposure of design professionals
by specialty subcontractors or who use BIM collabora vely and risk
consultants. In addi on, BIM so ware is assuming overall model responsibly.
designed to react to changes in the
6.13 Level of detail
Contractors are likely to want more more difficult to manage and operate.
detail included within the model so that Determining the balance of detail, and
clashes, delays and extensions of me how much reliance can be placed upon it,
will be avoided during construc on. will therefore be a crucial issue to be
However, with more detail added during nego ated between all project
the design phase, design costs will par cipants.
increase and the model will become
51
6.14 Contractual implications
Historically most contracts are bipar te become more appropriate. Payment
agreements. BIM has the poten al to mechanisms may also need to be
substan ally alter the rela onships changed to reflect the fact that BIM
between par es and blend their roles projects will become front loaded. Pain /
and responsibility. Risks will need to be gain mechanisms for collabora ng
allocated ra onally; based on the par cipants may also be favoured. The
benefits a party will be receiving from contract will also have to define the
BIM, the ability of the party to control status of the BIM model and deal with
the risks, and the ability to absorb risks post handover ma ers such as lifecycle
through insurance or some other means. management and data capture.
As par es journey along the path to fully
integrated BIM, bilateral contracts, with
BIM addendums or protocols, may
become unsuitable and collabora ve
mul party contracts could poten ally
6.15 Insurance / bond markets
Few insurance companies currently offer
BIM related products. The rarity of BIM
projects to date means that uncertain es
remain about its benefits and risks.
Insurers are likely to increasingly offer
BIM insurance policies but un l it is clear
what risks are involved premiums are
likely to be high. Uncertainty is also likely
to impact upon the bond market un l
BIM becomes more commonplace.
52
7 Case Studies
53
7.1 Case Study
Upgrade of Great Eastern Highway, Western Australia
7.1.1 Project Background
This case study describes the Great WA, Leighton Contractors and GHD as
Eastern Highway (GEH) upgrade, which the designer. This is a major access route
was delivered by the City East Alliance. between the Perth Domes c Airport and
The alliance partners were Main Roads the Graham Farmer Freeway.
7.1.2 Major Stakeholders
Main Roads WA ‐ Project (client), City Aboriginal Heritage, and European
East Alliance (MRWA, GHD, Leighton Heritage.
Contractors and NRW), Swan River Trust,
7.1.3 Project Description
54
7.1.4 BIM Tools
AutoCAD, AutoCAD Civil 3D, Navisworks, 12d and MX
7.1.5 BIM Technical Analysis (Pros)
BIM 3D, 4D and 5D modellings were 3D Coordina on
adopted in the virtual design and
Engineering Analysis
construc on of the project. In addi on,
other BIM uses were also applied in the Clash Deten on
project such as:
Product Master Data
Constructability Reviews
Field Survey
Traffic Impact Simula ons
7.1.6 BIM Technical Analysis (Cons)
The scope of project ended a er Addi onally, there is a very strong level
construc on and the maintenance was of interest to adopt other BIM uses
handled by another stakeholder. during opera on and maintenance of the
However, some areas of BIM uses could project, such as:
be improved and developed in the future
Road Management
during the construc on stage, such as :
Maintenance of Traffic
Field Design Changes
Geospa al Issue Tracking
Mobile Progress Claiming
Equipment Machine Control
Site Logis cs (JIT)
55
7.1.7 Process and Benefits
The screen shot of the Web Viewer below to view the current and planned works and
(Fig. 13) shows the project can be viewed on be er understand what will be occurring in
screen and acted as the “single point of their neighbourhood as this project has
truth” during the project’s construc on. The impacted hundreds of land holders and
Viewer is available to the public over the web business.
Fig. 13 Web‐based
Interface
The benefits in terms of accurate and current It has been synchronised on a monthly basis
visualisa on for Stakeholder Consulta on are with the 3D Navisworks model and updated
substan al. The project team have access via u lising the GIS and Navisworks Data (Fig 14
tablets and iPads to an enhanced Version below).
containing addi onal layers of informa on.
Fig. 14 Different
level of Details in
BIM
From the quality aspects, the construc on Fig. 15 illustrates the accurate informa on in
engineers were aware of where they should the model compared to the as‐built
not dig and the designer could physically see construc on.
the space and obstruc ons to design around.
56
Fig. 15
Comparison
of as‐built
versus as–
planned
7.1.8 Process Challenges
A few challenges were encountered in the project. They were required to be
project. These were: relocated
The limited project delivery meframe Maintaining access to all land owners and
required the construc on of the new road businesses for the length of the project
before all u li es could be relocated. As
such, cri cal construc on ac vi es such as High ini al investment and start‐up cost
earthworks cut and fill, retaining wall was a significant concern to the
construc on and street ligh ng installa on management team
had to occur in and around live services Loca on of exis ng u li es and buried
7.1.9 Conclusion
The project was completed successfully in The project has involved a total of 1.175
terms of cost, me and quality of works by million man hours with 0 lost me injury
applying numerous BIM uses in the project. (LTIFR =0). The project has achieved a na onal
Some areas of BIM uses were highlighted for HSE Award for the Leighton Group.
future use, par cularly during the construc on
and opera on stages.
Overall the project ran $7 million under the
targeted budget and 3 months ahead of the
Furthermore, it is worth no ng that the targeted comple on date, of which the total
construc on cost on Great Eastern Highway saving contributed to by the model was $24
for u lity reloca ons alone was about $8 million or equivalent to 14% of the total
million per kilometre, with reduc ons from project cost of $175 million.
the ini al es mates of about $2 million per
kilometre a ributable to efficiencies iden fied
in the model.
57
7.2 Case Study
Moreton Bay Rail Project, Queensland
7.2.1 Project Summary
The Queensland Transport and Main Australia and is also one of the fastest
Roads State Planning Program is based growing areas in Australia. Popula on
on analysis of current and future growth is expected to con nue over the
integrated passenger transport op ons. next 15 years which will cause a
Investment decisions must take into significant transporta on problem if the
account the challenges of distance in use of private cars grows at the same
order to deliver quality transport pace.
networks for a growing popula on. Use
Known as the Moreton Bay Rail (MBR),
of the Regional Queensland Passenger
work began in 2013 on an integrated
Transport Network Plan assists with the
public transport corridor for the region
iden fica on of appropriate network
with vehicle, cycle and pedestrian access.
services for designated regions.
The corridor includes a 12.6km double‐
The Moreton Bay region of Queensland is track rail line to provide a safe and
the third largest local government area in reliable transport network.
Currently over 80% of Moreton Bay residents travel to work in a private vehicle.
It is expected that nearly 6,000 people Council are co‐funding the $1.47billion
will use the Moreton Bay train daily. project to bring to frui on a visionary
Because MBR will significantly improve project that began through land
public transport in the area, it will acquisi on in the 1980s.
provide an incen ve for people to make
Finalisa on of alignment and sta on sites
the switch to public transport. Current
concluded with the design development
driving me is one hour from Kippa‐Ring
and crea on of the TrackStar Alliance in
to the CBD in Brisbane.
2013 to deliver the project. TrackStar
While rail service will be upgraded, an Alliance is an integrated infrastructure
addi onal effect is to reduce conges on delivery business that harnesses the skills
on the road network for journeys that of four business partners with
can’t be made using public transport. In Queensland Transport and Main Roads;
addi on the rail corridor provides a Hassell, Thiess, Aurecon and AECOM.
proven method to reduce carbon Each of the private sector partners
emissions; every full train equates to provides specific skills for this complex
removing 600 cars from the road project:
network.
● Contractor: Thiess
The MBR project is funded in part by the ● Architects & Urban Designers: Hassell
Na on Building Program of the Australian
Government. The Queensland ● Technical Services: Aurecon
Government and Moreton Bay Regional ● Engineers: AECOM
58
7.2.2 Project Overview
Location
The Moreton Bay Rail (MBR) project involves construc on of a new 12.6km dual heavy
track passenger rail line between Lawnton and Kippa‐Ring that includes six new railway
sta ons.
The integrated transport passenger rail corridor is located approximately 23 kilometres
north of the Brisbane CBD within the local government area of Moreton Bay Regional
Council. The corridor extends eastward from Petrie railway sta on (27.5 km by rail from
Central Sta on, Brisbane) to Anzac Avenue in Kippa‐Ring.
h ps://
www.moretonbay.qld.go
v.au/uploadedFiles/
common/projects/
moreton‐bay‐rail‐link/
MBRL‐Map.pdf
Key Features
● Rail corridor ● Road and rail bridges
The completed Moreton Bay Rail link MBR construc on includes 22 major
will be 12.6km of dual heavy track and bridge structures. In some loca ons,
structures. such as the Bruce Highway and Brays
Road in Murrumba Downs, a rail bridge
● Sta ons
will be built over the exis ng road. At
The six new sta ons: Kallangur, Kinsellas Road East a new road bridge
Murrumba Downs, Mango Hill, Mango has been built over the rail line.
Hill East (previously called Kinsellas
● Cycling and walking (paths and facili es)
Road), Rothwell and Kippa‐Ring. All
sta ons will provide full passenger MBR will provide an opportunity to up‐
services: 175m long side pla orms, grade user‐shared pedestrian and
walkways, cket offices, wai ng cycling links within the Moreton Bay
facili es, park and ride facili es and region specifically related to new rail
bus/train interchanges. sta on access.
59
Moving 371,000 cubic
metres of materials from the
Petrie sta on site. These
materials were re‐used at
other loca ons along the rail
corridor to build up the rail
embankment.
Cost
The $1.47billion required for the project is provided jointly by the Australian Government
($742million), Queensland Government ($300million) and Moreton Bay Regional Council
($105million). The Queensland Government, through Queensland Transport and Main Roads, is
delivering the project on behalf of the three funding partners. The Queensland Government has
also contributed land valued at $120million to the project.
Duration
● 2011: Develop detailed design, procurement for construc on and acquisi on of remaining
proper es
● 2012–2016: Preconstruc on ac vi es and construc on
● 2016: Finalise construc on and commence rail services (weather permi ng)
7.2.3 Design, Management and BIM
During the last 20 years different IT companies Designers for all phases of construc on
have invested in so ware to obtain integrated projects use a range of so ware with specific
environments for effec ve collabora on func ons. These occupa on specific so ware
between architects, engineers and contactors. preferences, as well as the organisa onal cycle
Development of these tools is based on the of ITC upgrades, are major drivers for the
premise that collabora on between all project global effort to provide a unified means of
par cipants through ITC will enhance informa on exchange within each
construc on process and increase work construc on project. Currently, integra ng 2D
efficiency. This focus has encouraged model‐ with approaches to 3D models is driving
based (3D) design solu ons including object‐ so ware development and project
oriented BIM environments. collabora on.
60
Table 3: Examples of the differences between the software used by the civil engineers at QTMR (string based) and
the architects at Hassell (object based).
61
√ √ √ √ 2D drawings
2000+
Station design is an essential ingredient in making public transport
attractive to users and the community – and getting the design for
each station right is a key priority for the Moreton Bay Rail project
team.
62
Benefits of BIM
● Iden fica on of incompa ble fixed 3D objects (clash detec on) in a working model
is more effec ve for project progress
The variety of processes and products that clash detec on) within Navisworks
are required in the construc on of the MBR Providing project consultants (project
means that problems will arise and managers, es mators, engineers,
solu ons need to be found. Building contractors) with a 3D model is a valuable
informa on modelling (BIM) is a solu on communica on tool. The value of clash
beneficial during the design stages. detec on analysis at an early stage assists
Revit and AutoCad, as authoring tools, with the evolu on of co‐ordinated project
create 3D models that are great problem documenta on.
solvers for clash detec on. This type of An important feature of the MBR transport
modelling means being able to see three corridor is the six new sta ons. Each
dimensional walls, floors, windows and sta on is strategically located to connect
columns which aids detailing and especially the rail corridor to their wider community
design changes. Because building objects with the aim of providing evidence of the
have been the focus of much of the BIM benefits of public transport. Each of the six
development during the last 15 years, sta ons will have a unique design to set it
architectural skills in BIM are the most within an urban growth precinct. BIM is
advanced. used by Hassell to design the sta ons and
The object based model design process integrate them into the road, rail, cycle and
flow for MBR is: pedestrian systems. At the same me
● Conceptual model in SketchUp efficiencies were obtained by standardising
elements of each of the sta ons such as
● Design development in Revit pla orm design, exterior sta on overhangs,
● Developing model returns to and ramps to parking areas.
SketchUp for visualisa on
● A con nuing itera ve process to
integrate changes into an acceptable
developed model
● Developed 3D model analysed (e.g.
63
A major shortcoming of Navisworks 3D providers, focused on compe ve advantage,
modelling is the lack of two‐way processing aim to be ahead of the pack with the latest IT
once the models are in Navisworks. This makes solu ons. These differences of purpose and
working with object based BIM solu ons risky organisa onal construc on management
(due to possible loss of data) for the project systems are converging with increasing use of
components that use models generated with increasingly effec ve 3D modelled construc on
string based so ware. The object based models solu ons.
also do not fit easily into the 12d string based
modelling pla orm preferred by QTMR.
As the client QTMR has the need to provide
safe public transport systems based on research
led standards that are embedded in their
opera ng and management systems. Private
h p://www.tmr.qld.gov.au/Projects/Featured‐projects/Moreton‐Bay‐Rail.aspx#projectplan.
64
7.3 Case Study
Memorial Park Underpass, New Zealand
7.3.1 Project Summary
65
The Australian and New Zealand Army Tonkin & Taylor and URS. The Memorial
Corps (ANZAC) formed in 1916 (troops Park Alliance deliverables are the three
from the First Australian Imperial Force lane underpass for NZTA and the
and 1st New Zealand Expedi onary Memorial Park on top of the underpass
Force) fought in Gallipoli. This major for MCH.
ba le is commemorated in both However three major constraints place
countries on 25 April, ANZAC DAY. The pressure on project delivery:
countries con nue to share memorials
and services. The Australian contribu on ● An 18 month deadline, ANZAC day
of AU$5 million is for a dedicated 25 April 2015 for WWI
Australian Memorial to be placed on the commemora on ceremonies
Ceremonial Plaza. ● Works are in the CBD of
Design and Construc on for the project is Wellington, New Zealand, a major
by The Memorial Park Alliance that earthquake zone
includes both government agencies, ● Significant heritage in the
NZTA and MCH and four private construc on site, over and above
providers: Downer, HEB Construc on, the War Memorials
7.3.2 Project Overview
The Na onal War Memorial Park and Underpass Project will result in an iconic interna onal War
Memorial in the city of Wellington, the capital of New Zealand.
Location
The underpass is a reinforced concrete structure approximately 180m long. The
structure will allow the 3 lanes of State Highway 1 to be placed underground from
Sussex St to Taranaki St, a main traffic route in the CBD of Wellington. Construc on
of the tunnel creates the needed ground level space to develop the Na onal War
Memorial Park especially an enlarged Ceremonial Plaza that will be built above the
underpass. At the same me the underpass is considered part of the Memorial
Precinct.
66
Key Features
● Surrounding roadworks for construc on of a basic box (slab,
walls, roof) using tradi onal
Diversion of Buckle Street, re‐design for
construc on methods; earthquake
entry and exit to tunnel, necessary
proofing.
temporary traffic, cycle and pedestrian
travel arrangements. ● Park
67
Cost
Duration
The New Zealand Parliament passed the Na onal War Memorial Park (Pukeahu)
Empowering Act 2012 to assist NZTA make the vision of a Na onal War Memorial
Precinct a reality inside a ght meframe of 18 months.
Designing and planning for construc on stormwater, water main, sewage, gas,
of the tunnel and the road diversion. electricity and telecommunica ons
pipes.
The first opera on on site was to divert a
sec on of State Highway 1 (Buckle In addi on, 6.5km of new pipes were
Street) to a temporary posi on enabling required (including new valves and steel
work on the underpass to begin. The pipe connected to the 100‐year‐old
major part of the diversion was to water main under Tory Street) to
remove, update or stabilise the maintain water table stability.
necessary city services that were located
underground where the trench was to be
dug. Examples of services: underground
68
● Phase 2. Dig the Trench: February 2013 – September 2013
The walls were necessary to create the Earth quake zones require specialised
construc on site for the tunnel. building methods. To ensure stability of
Temporary kingposts and mber walls the permanent retaining wall required
protected the ground and the workers in 558 anchors (each 13 metres long) to be
the trench. The wall was made up of 285 installed sideways into the ground. They
kingposts reaching 15 metres into the are ed into both the kingpost walls and
ground plus 14,381 mber posts slo ed sheet pile walls for added strength.
between the kingposts.
69
Australian Memorial
The Australian Memorial was designed centre) in its final res ng place. The
by Australian architectural firm Tonkin Crèche was built in 1914 for Mother
Zulaikha Greer. It features 15 columns Suzanne Aubert and has been recently
made from rugged red sandstone as placed on the New Zealand Historic
symbolic of the 'Red Centre' of Australia. Places Trust Register as the first purpose
The columns will be surrounded by built crèche in the country.
Australian eucalyptus trees, a typical
Australian landscape.
Re‐design and re‐surfacing of the
memorial area includes: terracing and
plan ng trees & shrubs; addi on of rock
features & sculptures including the
Australian s ck men; loca ng the Home
of Compassion Crèche (a child care
7.3.3 BIM Capability and Capacity
The Project Management team has the BIM environment based on the concept
responsibility of ensuring comple on of of 3D interoperable modelling.
the scope of the project as defined by Integra ng 3D modelling capability and
the clients ‐ New Zealand Transit Agency, capacity is the necessary founda on for
the New Zealand Ministry of Culture and comple ng the complex construc on
Heritage, Wellington City Council, and projects of the 21st century.
the Australian Office of War Memorials. In order to meet their obliga ons, a team
During the last 20 years, different IT of designers for specific phases and
companies have invested in so ware specific processes used a range of
development to enable effec ve so ware for dedicated project
collabora on between architects, components. To complete the scope of
engineers and contractors through an the project, within the site and me
integrated modelling process. constraints, the Memorial Park Alliance
Development of these tools is based on project team u lised 3D modelling for
the premise that collabora on between the design and management of some
all project par cipants through ICT will project components.
enhance the construc on process and This report focuses on the BIM
increase work efficiency. applica on to this brown field project,
Pla orm and so ware developers have specifically the applica on for
played a vital role in crea ng the evolving underground services.
70
Underground Services (water, telecommunica ons, gas and electricity)
Benefits of BIM
71
An example of a cri cal design resolu on
was to fit the tunnel between the fragile
100 year old horse shoe shaped brick and
mortar sewer and the other services
which were located over this structure.
Services for stormwater and
telecommunica ons had to remain under
the tunnel roof.
Challenges of Enabling BIM
● Public road and rail infrastructure project so ware interoperability
The Memorial Park Underpass project these problems, especially within the 18
has been designed and managed by 60 month project comple on deadline was
designers, construc on managers and dependent on ITC for design resolu on.
support staff. The construc on site
constraints were embedded in a number BIM technologies have been presented
of local community requirements: as a solu on to all problems within the
con nued use of the local primary construc on industry. However,
school; minimising disrup on of challenges remain. BIM has many
Wellington airport traffic; minimising defini ons (depending on occupa on
inconvenience for residents close to the and so ware claims) making transfer of
construc on site; as well as con nual 3D models on complex construc on
adapta on of local CBD traffic routes. All projects risky. While buildings are
of these constraints required a significant modelled in object based so ware,
amount of flexibility to deal with transport infrastructure design
unknown problems. The capacity to solve construc on models use string based
so ware.
72
Currently 12d is the standard modelling visualisa on for modelling the
system used by Australian and New replacement, removal and reloca on of
Zealand publicly funded transport the underground services (water, gas,
authori es. Many transport telecommunica ons, electrical) on this
infrastructure projects involve complex inner‐city iconic heritage
alignments to the curvature of earth’s project. However, integra ng their
surface (especially over long distances). model into the string based models of
Therefore it makes sense to use 3D other components of the infrastructure
modelling so ware that provides project was always ‘too difficult’.
visualisa on of geographic contours.
73
7.4 Case Study The Design of Perth’s Light Rail Network,
Western Australia
7.4.1 Project Summary
Metro Area Express, or MAX, is Perth’s the inten on of s mula ng revitalisa on
proposed 22 km light rail network that and new developments along the
will run from Mirrabooka in the north to proposed alignment.
the CBD, before spli ng into two Due to cri cal State budget pressures,
branches to Victoria Park Transfer the State Government has deferred the
Sta on in the east (via the Causeway) MAX Light Rail project for three years,
and to QEII Medical Centre in the west which will see overall comple on of the
(via West Perth). This visionary project project by late 2022.
will introduce a new era of public
transport in Perth, suppor ng the city’s The MAX Light Rail project is a
transforma on by providing a frequent, transforma onal project, and the State
high‐capacity service in the inner‐north Government is commi ed to delivering
and central west and eastern suburbs of the project in full. The revised meframe
Perth. will see a call for tenders in early‐2018,
construc on commencing in 2019, with
Essen ally a modern tram system using first services running by late 2022.
electric rail cars, the new light rail system
is quiet and efficient and will be built on BIM has been used in several ways on
exis ng streets but largely separated the MAX Light Rail project but mainly in
from general traffic. The project is a the design stage of the project at the
catalyst for city change, being moment.
coordinated with land‐use planning with
7.4.2 Major Stakeholders
The Integrated Services Team (IST) established for the project included AECOM, as
part of the Joint Venture and the Western Australia Department of Transport.
7.4.3 Project Description
The IST func oned in a collabora ve and innova ve way to successfully deliver the
Business Case including the following project disciplines; preliminary design (including
systems), traffic network opera ons modelling, environmental approvals and
sustainability, land use planning and stakeholder and community management.
7.4.4 Project Delivery Method
The proposed project delivery method is Design – Bid – Build. The State Government
has placed the project on hold.
74
75
7.4.5 BIM Tools and Uses
● Infrastructure So ware 12d model repor ng tool.
Provided the pla orm for the produc on of ● Traffic So ware: LinSig
the exis ng feature survey and the proposed Provided the pla orm for the Intersec on
road design model, including pla orms and traffic analysis.
retaining walls and the drainage assessment.
● Traffic So ware: SIDRA 6
● Autodesk AutoCAD Civil 3D
Provided the pla orm for the isolated
Provided the pla orm for the produc on of the intersec ons analysis.
exis ng in ground and above ground service
● Traffic So ware: STEM
model.
Provided the pla orm for the overall traffic
● Bentley Rail Track
Analysis and future traffic volume modelling.
Provided the pla orm for the produc on of the
● Traffic So ware: Commuter micro‐simula on
proposed rail design model.
Provided the pla orm for the overall traffic
● GIS So ware Esri
volume Analysis and future traffic volume
Provided the pla orm for the produc on of modelling.
mapping all of exis ng heritage, exis ng
environmental, building, exis ng services, and
proposed design.
● Clashes Detec on / MTO / 4d Sequencing using
Autodesk Navisworks
Provided the pla orm for the coordina on of
all models, review tools, clashes and cost
7.4.6 BIM Technical Analysis (Pros)
BIM uses were adopted only at the design stage of the project, such as:
76
7.4.7 BIM Model Development and Process
The details of the model could not clearly sensi veness of the project was
be defined by the LOD‐Specifica on as observed in the project, which all
the nature of the project is Civil employees were required to be bound to
infrastructure. Nevertheless, the LOD a cabinet confiden al agreement. There
Specifica on sec on G. “Building Site were some structured policies that only
works” could be used as a base for allowed approved users to access the
clarifying the details of the model. It informa on on the server and project
could be projected that most elements folders. The GIS web viewer had a user
modelled were at the average level of login with addi onal security to limit only
LOD 200. For elements that fell out of defined IP address access, allowing only
this parameter would be categorised access within predefined loca ons. The
under sec on G “fundamental LOD model was also audited regularly through
defini ons were applied”. an internal process to comply with the
The DoT or PTA is the owner of the defined quality systems.
model, the Intellectual property and the
method of informa on management in
crea ng the model. Yet, the poli cal
7.4.8 BIM Collaboration and Workflow
The proposed 22km light rail network condi ons required in the model
had a magnitude of exis ng informa on. development. It would iden fy areas or
Fig. 16 shows the overall BIM workflow. elements as posing risks to the project
The exis ng informa on could be and to be communicated clearly for
categorised into two main data sets, future risk mi ga on. The exis ng survey
namely, (a) physical data on the exis ng informa on data set was provided and
condi ons, and (b) spa al data on the synchronised in Infrastructure So ware
flows of exis ng vehicle and human 12d model. The survey informa on was
traffic condi ons. The physical exis ng exchanged with other so ware pla orms
informa on were derived from exis ng via Landxml. Landxml provided the
records and survey. The 22km nework common pla orm to exchange simple
was surveyed using a tradi onal method (non volumetric) informa on between
of feature survey and a laser scan pla orms.
method. Both survey methods provided
the informa on for the exis ng
77
Fig. 16 LRT BIM Workflow
The point cloud informa on data set was GIS data base. Bentley Subsurface
provided in Leica LAS format. The point u li es engineering so ware was
cloud data was processed using Autodesk adopted for crea ng and maintaining the
Recap to refine and index the point data form SUE. The data would be in the
informa on into the federated model shape file format and to be displayed in
and broken into key areas which required the project GIS view. Landxml was also
surface /volumetric model informa on used to categorise and provide the
physical/spa al/ visual data.
The exis ng u li es informa on data set
was obtained from mul ple asset and
government agencies. It included the GIS
asset records and spa al mapping
systems. ‘A.S.5488: Classifica on of
subsurface u lity informa on SUI’ was
applied to the exis ng u lity informa on
to provide a uniform data structure. The
processed informa on with the schema
from AS5488 was stored in the Ersi Shape
78
7.4.9 Conclusion
BIM has been used in several ways on the field construc on changes that are iden fied as
proposed MAX Light Rail project, including costly and provide challenges to the project
building intelligent databases of key project schedule and overall budget. Two dimensional
components and systems; overlaying of exis ng drawings were extracted from the BIM model,
services, rail, road, electrical system, 22km of which was developed with all of these factors in
point cloud laser scanning and civil/structural mind, for use in the business case.
elements to iden fy and eliminate conflicts (clash
detec on); and produc on of civil/structural
backgrounds. Virtual clash detec on eliminates
79
7.5 Case Study Auckland City Rail Link, New Zealand
7.5.1 Project Summary
The City Rail Link (CRL) will extend phase is to undertake preliminary design
Auckland’s passenger rail system past for use in procurement and detailed
Britomart to connect to the exis ng design of an Enabling Works package.
regional rail network at Mt Eden. The CRL will use twin 3.4km long tunnels
Britomart will become a through sta on up to 33 metres below the city centre
with new sta ons near Aotea Square and streets. It is es mated it will take five and
Karangahape Road, and a redeveloped a half years to build at a cost of NZ$2.5
sta on at Mount Eden. The current billion when inflated to 2024 prices.
7.5.2 Major Stakeholders
80
7.5.3 Project Description
Two new underground sta ons at Aotea of the construc on will be using a tunnel
(11m depth) and Karangahape Road boring machine (TBM), which is 7.5
(33m), will be developed and Mount metres in diameter. It will excavate
Eden Sta on will be redeveloped as about 1 million cubic meters of spoil.
illustrated in Fig. 17. It will involve cut Eighty‐eight subterranean proper es will
and cover construc on along Albert be affected and benefited by the tunnels.
Street and at Eden Terrace. The majority
7.5.4 Project Delivery Method
The project was a Reference Design Project, where Aurecon was engaged as the Principal
Technical Advisor. Future engagements are expected to be Design‐Build with Contractor
based design teams.
81
7.5.5 BIM Tools and Uses
At the design stage, six so ware packages were used. Table 5 shows the details
for the so ware.
Table 5: BIM tools
Update Release 2
Civil 3D 3D.DWG
AutoCAD .DWG
7.5.6 BIM Technical Analysis (Pros)
BIM uses were adopted only at the design stage of the project, such as:
82
7.5.7 BIM Technical Analysis (Cons)
● Public Informa on and Communica on ● Engineering Analysis
● Constructability Reviews ● Clash Detec on
● Traffic Impact Simula ons ● Quan ty Take‐off
● 3D Coordina on
7.5.8 BIM Model Development and Process
The aim is to see BIM used as the ● Enhance project quality and
primary drawing produc on environment workers’ safety on site
and not as a retrospec ve tool, so that All drawings which are relevant to
the func onality of BIM can be used to defining the project in terms of its
assist the design coordina on and physical envelope and spa al
op misa on. This will involve the coordina on will be produced in a 3D
establishment and execu on of CAD format with Building Informa on
collabora ve processes using 3D Modelling (BIM) capability. This includes
modelling tools, and the exchange and sta on and tunnel layouts, sta on and
coordina on of digital models to achieve tunnel building services, major
the following objec ves: equipment layouts, major sta on and
● Significantly reduce clashes between tunnel components, etc. Drawings which
the design intent of different are not relevant to this spa al aspect
systems (for example, hydraulic need not be developed to this standard
services and structural elements) to but where relevant shall be capable of
establish geometric presence and to being cross referenced or input as
pass the following benefits to the schedules to the overall BIM model.
design and construc on team: These excluded drawings may comprise
● Foster confidence in the design system architecture and schema cs,
intent reinforcement drawings, schedules,
explanatory notes, etc.
● Shorten construc on me
compared with tradi onal Overall, IP and ownership remain with
construc on processes the consultants put with an implied
● Minimise re‐work and license used by the client. The LOD for
varia ons during and the Reference Design Phase will be
construc on phases minimum LOD200.
83
7.5.9 BIM Roles and Responsibilities
Table 6 shows the BIM roles and responsibili es in the project.
Table 6: Roles and Responsibili es
7.5.10 BIM Collaboration and Workflow
Coordina on mee ngs were held weekly with model managers coordina ng their respec ve areas and
maintaining an issues or coordina on register that was tracked weekly with percentage completes, un l
they were closed out completely. Fig. 18 illustrates the workflow of the design stage.
Tuesday Thursday
Fig. 18 BIM Workflow
84
7.5.11 Conclusion
This is a large project, which will last for five and a half years and be built at a cost of $2.5
billion. The consultants were engaged with very li le defini on of what was required of BIM
for the project. The project has developed an interest into BIM uses in Public Informa on and
Communica on, and Constructability Reviews, which two methods could be improved further
in the design stage.
85
Appendix A – Existing BIM Guidelines
BIM guidelines
Country Organisa on Year Descrip on/Objec ve
& standards
Georgia Tech BIM This document will allow all stakeholders to weigh the
Requirements & importance of each requirement on a per‐project basis.
Georgia Tech
Guidelines for Through this collabora ve effort, a final project‐based set of
Facili es 2011
Architects, requirements and corresponding BIM Execu on Plan will be
Management
Engineers and issued based on what level of BIM proficiency necessary for a
Contractors given project.
USA
Indiana
BIM Guidelines &
University
Standards for
Architect's
Architects, 2012 Standards for AEC.
Office and
Engineers, and
Engineering
Contractors
Services
A achment G ‐ Standards for A/E project drawings. This includes CAD and BIM
University of
University of drawing standards, PDF requirements, and the schedule of
Washington
Washington CAD 2012 documents submi als for Owner’s compliance review. The A/E
Capital
and BIM may request a compliance review at any me during the
Projects Office
Standards Project .
86
University of Guidelines for design bid build contracts. This document
Southern California defines the Design and Construc on scope of work and
Facili es BIM Guidelines 2012 deliverables for using BIM on new USC construc on
Management projects, major renova ons and other projects as required
Services by USC, based on a Design Bid Build form of Contract.
Standards for design‐build projects. The LACCD BIM
Los Angeles Standards for Design‐Build Projects have been developed
Community College BIM Standard 2011 to define a process and establish requirements,
District procedures and protocol for the u lisa on of BIM in the
various stages of our design‐build projects.
USA Na onal Ins tute of NBIMS establishes standard defini ons for building
Building Science Na onal BIM informa on exchanges to support cri cal business
2012
buildingSMART Standard contexts using standard seman cs and ontologies…to be
alliance implemented in so ware
Associated General
The Contractor's to generally introduce the subject and provide an outline
Contractors of 2009
Guide to BIM of the “how‐to” for ge ng started
America
United States Air
Force Centre for
“ATTACHMENT
Engineering and the
F” – BIM 2012 Requirement for design‐build/firm fixed‐price contract
Environment Capital
Requirement
Investment
Management
87
The scope of this plan is to focus on the implementa on of BIM in
United States the U.S. Army Corps of Engineer's civil works and military
Roadmap for
Army Corps of 2012 construc on business processes, including the process for
Life‐Cycle BIM
Engineers working with the USACE Architectural Engineering Construc on
industry partners and so ware vendors
BIM
Standards for Design & Construc on Project developed to define
City of San Development
a process and establish requirements, procedures, and protocol
Antonio Capital Criteria and
for the u lisa on of BIM in the various stages of CoSA’s design
Improvements Standards for 2011
and construc on building projects elements and systems to use
Management Design &
as a tool to more efficiently manage, maintain, and renovate the
Services Construc on
facility for the life cycle of the building
Projects
The BIM guide considers the end‐use of the model for mul ple
client agencies, allowing qualified and authorized client agency
New York City
representa ves to review the ways in which the BIM may
Department of
BIM Guidelines 2012 facilitate their ongoing building opera on and maintenance
Design +
protocols, and tailor their agency requirement and standards to
Construc on
leverage the enhanced capabili es provide by BIM for building
O&M.
Professional
State of Texas, Service Guidelines and Standards for Architectural and Engineering
Texas Facili es Provider 2010 This document applies to all TFC projects contracted on or a er
Commission Guidelines and the Edit Date indicated in the header above.
Standards
GSFIC BIM
Georgia State The purpose of this guide is to aid Architects and Engineers (A/Es)
Guide 88
Financing and in their Building Informa on Modelling (BIM) efforts related to
Series 01: 2013
Investment design and construc on of GSFIC managed projects. This release –
Erhvervsstyrelsen
Det Digitale A guide made of 4 components: 3D CAD Manual, 3D Working
(Na onal Agency for
Denmark Byggeri (Digital 2007 Method, Project Agreement and Layer — and Object
Enterprise and
Construc on) Structures
Construc on)
Generalitat
Valenciana (Valencia
Spain FIDE Spanish
Regional
Government)
Yleiset
buildingSMART The guidelines mainly focuses on architecture and engineer
etomallivaa 2012
Finland design.
mukset
Finland Senate
Senaa Kiinteistot General opera onal procedures in BIM projects and detailed
Proper es:
(aka Senate 2007 general requirements of BIM models — focuses on the
BIM
Proper es) design phase
Requirements
Rijksgebouwendienst
A BIM Framework consis ng of seventeen orthogonal
(Ministry of the Rgd BIM
Netherlands 2012 dimensions that describe in general the Building Informa on
Interior and Standard
Modelling world cons tu ng a "Way of Thinking about BIM”
Kingdom Rela ons)
90
Appendix B – Existing BIM Tools
Tool Vendor Capabili es
1. Start by drawing lines and shapes, push and pull surfaces to turn them into 3D forms;
2. Changes to your model are reflected automa cally in Layout;
SketchUp
Trimble 3. Having the world’s biggest repository of free 3D models;
Pro
4. Massive plugins provide extra features such as sustainable analysis.
91
1. Edi ng complex models is faster and easier with “Direct sub‐object manipula on” and
“Thin‐wall shelling”;
2. Easier to create 2D drawings and illustra ons for every discipline in every nota on
system and visual style used around the world;
Rhino Rhinoceros 3. Rhino models can be accurate enough for and accessible to all the processes (e.g.
fabrica on, manufacturing, or construc on processes) involved in a design becoming a
reality;
4. Robust mesh import, export, crea on, and edi ng tools;
1. Design solu on: Mul ‐discipline 3D plant design, Intui ve 3D graphics, User‐friendly
interface, Local Customiza on;
2. Reduce business risk: Mul ‐discipline 3D plant design, Built‐in quality and compliance;
E3D AVEVA 3. Integra on: Built‐in quality and compliance, Integrated 3D, engineering and schema c
data;
4. High Performance: Integrated 3D, engineering and schema c data, High performance in
large networks.
1. A fully interac ve, color shaded 3D plant design environment, Hundreds of designers
can work concurrently on a project ;
2. Designers progressively create a highly intelligent 3D design by selec ng and posi oning
parametric components from an extensive catalogue;
3. Clash checking and configurable integrity checking rules ;
PDMS AVEVA 4. A configurable Status Management func on provides visual highligh ng and clear
repor ng of design maturity status of PDMS objects;
5. Highly configurable, automa c genera on of a wide range of reports and drawings
direct from the PDMS database ;
6. AVEVA PDMS is highly configurable and includes both a powerful programmable macro
language (PML) and a .NET API to customize the system and automate tasks.
92
1. 12d Model is a powerful terrain modelling, surveying and civil engineering so ware
package.
2. It allows quick and high quality produc on in a wide variety of projects including: Road
and Highways, Ports and Dredging, Land Development, Airport Infrastructure
Rail, Mining Infrastructure, Drainage, Sewer and U li es
Surveying, Oil and Gas, Construc on Rivers, Dams and Hydrology Environmental
3. Using 12d Model's screen menus and fast interac ve graphics, the user effortlessly
12D Model 12D
moves through a design.
4. With 12d Model's powerful design capabili es, difficult surveying and civil design tasks
can be easily visualised and completed.
5. 12d Model includes a powerful programming language, which allows users to build
their own op ons, from the extensive 12d Model programming library.
6. 12d Model has been specifically designed for easy use. It is ideal for use at all stages of
projects, and is par cularly useful for large route selec on and corridor studies.
93
Existing 4D Simulation Tools
Vendor Capabili es
1. Comprehend the full complexity of modern construc on projects during ini al planning
through the Virtual Construc on Model;
2. Improved constructability analysis and advanced planning and coordina on between
engineering office and site field office;
3. Design out unsafe construc on prac ces;
ConstructSim Bentley 4. Reduce me to create work packages while increasing accuracy;
5. Ability to match available labour to work packages;
6. Support Agile/Lean/WFP construc on methods;
7. Plan ahead to reduce construc on bo lenecks;
8. Reduce rework and out‐of‐sequence work;
9. Streamline turnover and commissioning planning.
1. Enable full round trip data synchroniza on (Import, Export, Synchronize To and From) to
facilitate work flows for both upstream and downstream delivery processes;
2. 4D spa al coordina on for sta c and dynamic analysis and conflict resolu on;
3. Deliver tradi onal project scheduling, repor ng, custom 4D anima on, advanced AVI
produc on;
Synchro Synchro
4. Provide EVA (earned value analysis) and cost loaded schedule for including variable cost
analysis for decision support and for planned and actual cost analysis;
5. Database module enables advanced systems integra on, reusable project and
component libraries, and support for the ever increasing data in the BIM model to
enterprise data management envisioned by the industry.
1. Loca ons are used to perform loca on‐based quan ty takeoff which is the input for
loca on‐based schedule planning;
2. Adop ng flow‐line scheduling to op mise the construc on schedule;
Vico Trimble 3. On‐site produc on control: Measuring work put in place by loca on and comparing
actuals to planned helps Supers see poten al conflicts far in advance;
4. 4D BIM scheduling movies makes it easy for audiences (Owners, trades, teams) to see
how the building will come together.
1. Plan, with comprehensive 3D process and resource planning tools to create and op mise
build‐to‐order and lean produc on manufacturing systems;
2. Simulate, with tools to virtually define and op mise manufacturing assets concurrently
DELMIA Dassault with manufacturing planning;
3. Operate an accurate virtual produc on system to track real‐ me produc on ac vi es,
perform schedule changes, launch new programs and introduce model changeovers, and
schedule maintenance opera ons.
1. Easily understood display of project status and construc on sequence via the 3D model
for monitoring cri cal tasks;
NET Player AVEVA 2. Simula on and review of construc on sequences in 4D;
3. Playback controls enable the user to start, stop, loop and step through the anima on;
4. Rrapid compila on of produc on or construc on progress and status reports.
94
Existing 5D Simulation Tools
Vendor Capabilities
1. Support 5D BIM using information from the model live-linked to user-defined rate
libraries and workbooks- all within the one program;
2. A networked environment allows instantaneous information sharing with others
working on the server;
CostX Exactal 3. Import of a multitude of drawing files and external rate information, and exports to a
variety of formats, taking interoperability to a new level;
4. Unique revision tool identifies changes and automatically updates quantities;
5. Use in-built templates to import model data or easily create Model Maps to
customize your BIM take-off.
95
References
96
References
97
26. Professional Service Provider Guidelines and 33. BoligBIM (BIM Manual), Boligprodusentene
Standards, Texas Facili es Commission: (Norwegian Home Builders Associa on):
Texas, USA. Available from: h p:// Norway. Available from: h p://
www. c.state.tx.us/divisions/facili es/prog/ boligprodusentene.no/ge ile.php/
construct/formsindex/01%20‐%202012%20A‐ Dokumenter/BIM‐manual%202.0%
E%20GUIDELINES.pdf 20Boligprodusentene.pdf
27. BIM Guidelines & Standards for ARCHITECTS 34. Statsbygg BIM Manual, Statsbygg: Norway.
and ENGINEERS Department of Available from: h p://www.statsbygg.no/
Administra on, Division of State Facili es: Files/publikasjoner/manualer/StatsbyggBIM‐
Wisconsin, USA. Available from: p:// manual‐ver1‐2‐1eng‐2013‐12‐17.pdf
doa p1380.wi.gov/master_spec/BIM% 35. Rgd BIM Standard, Rijksgebouwendienst
20Guidelines%20&%20Standards/BIM% (Ministry of the Interior and Kingdom
20Guidelines%20and%20Standards%20for% Rela ons): The Netherlands. Available from:
20AE%20%207‐1‐12%20Final%20DRAFT%207 h ps://www.rijksvastgoedbedrijf.nl/english/
‐26‐12.pdf documents/publica on/2014/07/08/rgd‐bim‐
28. BIM Guide, Georgia State Financing and standard‐v1.0.1‐en‐v1.0_2
Investment Commission: Georgia, USA. 36. BIM Standard for AEC industry in UK, AEC
Available from: h ps://gsfic.georgia.gov/ (UK) commi ee: UK. Available from: h ps://
sites/gsfic.georgia.gov/files/related_files/ aecuk.wordpress.com/documents/
document/GSFIC%20BIM%20Guide%205.pdf
37. AEC (UK) BIM Protocol: UK. Available from:
29. Det Digitale Byggeri (Digital Construc on), h ps://aecuk.wordpress.com/documents/
Erhvervsstyrelsen (Na onal Agency for
Enterprise and Construc on): Denmark. 38. Best Prac ce Guide for Professional
Available from: h p://www.h .dk/ Indemnity Insurance when using BIM,
fileadmin/templates/h /dokumenter/ Construc on Industry Council UK. Available
ar kler/Det_digitale_byggeri.pdf from: h p://cic.org.uk/publica ons/
30. VRG Formato Intercambio Datos Edificación 39. First Steps to BIM Competence: A Guide for
(Building Data Exchange Format), Generalitat Specialist Contractors, Specialist Engineering
Valenciana (Valencia Regional Government): Contractors' Group and BIM Academy at the
Spain. Available from: h p:// University of Northumbria: UK. Available
www.habitatge.gva.es/web/vivienda‐y‐ from: h ps://www.thebesa.com/
calidad‐en‐la‐edificacion/relacion‐de‐ media/1533/sec‐group‐bim‐updated‐
documentos‐reconocidos#DRD0106 2014.pdf
31. Yleiset etomallivaa mukset 2012, 40. Singapore BIM Guide, Building and
buildingSMART Finland: Finland. Available Construc on Authority: Singapore. Available
from: h ps://buildingsmart.fi/wp‐content/ from: h ps://www.corenet.gov.sg/
uploads/2016/11/ media/586132/Singapore‐BIM‐Guide_V2.pdf
YTV2012_Taydentava_liite_TATE_Prosessiohj 41. CORENET e‐submission System, Construc on
e.pdf and Real Estate NETwork: Singapore.
32. Senate Proper es: BIM Requirements, Available from: h ps://www.corenet.gov.sg/
Senaa Kiinteistot (Senate Proper es): general/corenet‐e‐submission‐system.aspx
Finland. Available from: h ps://
www.senaa .fi/en/senaa /senate‐
proper es
98
42. BIM Project Specifica on, The Hong Kong
Ins tute of Building Informa on Modelling:
Hong Kong. Available from: h p://
www.hkibim.org/wp‐content/
uploads/2011/08/HKIBIM_Specifica on‐Rev3
‐0.pdf
43. Na onal Building Informa on Model
Standard, Na onal Ins tute of Building
Sciences: Washington, DC, USA. Available
from: h ps://www.nibs.org/?
page=standards
44. Building Informa on Modelling: A Framework
for Collabora on. Construc on Law., 28: p. 5.
45. buildingSMART, (2008) Interna onal. Model ‐
Industry Founda on Classes (IFC). Available
from: h p://www.buildingsmart‐tech.org/
specifica ons/ifc‐overview
46. NBIMS 2007, Available from: h p://
www.wbdg.org/pdfs/NBIMSv1_p1.pdf.
47. Markku Kiviniemi, Kris ina Sulankivi, Kalle
Kähkönen, Tarja Mäkelä & Maija‐Leena
Merivirta (2011), BIM‐based Safety
Management and Communica on for
Building Construc on, VTT RESEARCH NOTES
2597.
48. BIM Project Execu on Planning Guide Version
2.0 (2010), Available from: H p://
www.engr.psu.edu/bim.
49. Gerhard Gröger, Thomas H. Kolbe, Claus
Nagel, Karl‐Heinz Häfele (2012), OGC City
Geography Markup Language (CityGML) En‐
coding Standard (version 2.0.0), Open
Geospa al Consor um, Available from:
h p://www.opengis.net/spec/citygml/2.0
50. Building Informa on Modelling, accessed:
23/08/2014. Available from: h ps://www.out
‐law.com/en/topics/projects‐‐construc on/
projects‐and‐procurement/building‐
informa on‐modelling/
99
Contact
Professor Xiangyu Wang
Email: xiangyu.wang@cur n.edu.au
Project Leader
Sustainable Built Environment Na onal
Research Centre
Cur n Director
Australasian Joint Research Centre
for Building Informa on Modelling
Cur n University
Kent Street Bentley WA 6102
GPO Box U1987 Perth WA 6845