Professional Documents
Culture Documents
37-Contractual Risk of Building Information Modeling Toward A Standardized Legal Framework For Design-Bid-Build Project
37-Contractual Risk of Building Information Modeling Toward A Standardized Legal Framework For Design-Bid-Build Project
Abdur Rehman Nasir, Ph.D. 3; and Muhammad Sohail Anwar Malik, Ph.D. 4
Abstract: Building information modeling (BIM) is an encouraging development in the architecture, engineering, construction, and oper-
ations (AECO) industry due to its data-rich digital representation of building components. Although BIM is technically mature, its legal and
contractual systems are yet to be standardized. Motivated by this need, the current study has developed a framework for legal and contractual
risks within BIM. In this study, 14 significant risks were identified from 10 published taxonomies, and five standard and three custom BIM
contracts were reviewed to assess their coverage and check their redressal strategies. On the basis of the triangulation of information gathered
from published contracts, expert opinion, and custom manuscripts, mitigation strategies for the legal risks were proposed and formalized into
a contractual framework designed for a design-bid-build delivery system. This study contributes to the body of knowledge and practice
by helping the AECO community understand the current level of legal and contractual maturity of BIM, and by stimulating the technological
and legal fraternities to sufficiently deliberate the contractual uncertainties in order to facilitate the uptake of BIM in the AECO industry.
DOI: 10.1061/(ASCE)CO.1943-7862.0001617. © 2019 American Society of Civil Engineers.
Author keywords: Building information modeling; Legal risk; Contractual framework; Standard contract; Custom contract manuscripts;
Design-bid-build.
the unavailability of universal contractual guidelines, which drops there is a complete lack of BIM contractual framework for projects
the overall efficiency because of the reduction of BIM deliverables procured against a design-bid-build (DBB) system of delivery.
to noncontractual items in projects (Olatunji and Akanmu 2014). The question arises: why focus on BIM contractual framework
Although some contractors choose to implement BIM on a vol- for DBB? The answer is that not only DBB performs better in cost,
untary basis (Kumar et al. 2017), a well-structured, balanced, and due to its use of competitive bidding, than DB, which clearly has a
clear set of contractual guidelines will help boost the BIM value better schedule (Minchin et al. 2013) and claims (Hashem et al.
proposition (Eadie et al. 2015). Moreover, a recent study on BIM 2018) performance, but DBB is also a widely utilized option as
adoption in China also emphasizes the development of a clear set of almost 52% of total projects are procured through it (Duggan
BIM guidelines (Herr and Fischer 2018). and Patel 2013). In addition, DBB is a preferred system of procure-
The development of such guidelines is driven by the need to ment for public projects due to better productivity and fewer
address legal risks regarding the creation, usage, and manage- cost changes (Park and Kwak 2017), and the owner’s desire to
ment of BIM-associated information. Depending on the usage of maintain control over the project (Ibbs et al. 2003). However, the
BIM among project stakeholders, specific contractual guidelines focus of this paper is not to compare DBB and DB per se but only to
and provisions will be needed to cope with the lack of predis- point toward the gap in literature by which the existing contractual
posed strategies and outdated contracts (Kuiper and Holzer 2013). systems mostly prefer to operate inside DB regime of project
Responding to this demand, various contract documents have been delivery.
developed to manage BIM and its related information. Presently, To address the gap in literature and respond to the mounting
five contracting systems that incorporate BIM are available in the challenge of a dedicated contracting system for BIM in the context
industry: ConsensusDOC 301 BIM Addendum (ConsensusDOCS of the DBB project delivery method, this study identified potential
2008), Architects Engineers and Contractors BIM Protocol (AEC legal problems in BIM implementation from the point of view of
2012), American Institute of Architects E203 (AIA 2013), Con- prime stakeholders. On the basis of the content analysis of syn-
struction Industry Council BIM Protocol (CIC 2013), and Chartered thesized literature, the significant legal problems were highlighted.
Institute of Builders, Time and Cost Management Contract (CIOB Further, using a triangulation approach that included existing con-
2015). tracting systems, expert opinion from AECO practitioners, and cus-
ConsensusDOCS 301 BIM Addendum is the oldest of the stan- tom manuscripts, a standardized legal framework was developed
dard contract documents. The developers of this system, acknowl- for seamless induction of BIM in mainstream contracts. The find-
edging the longer, wider, and deeper penetration of traditional ings of this research will contribute to the body of knowledge by
contracts in the industry, tried to expand the existing forms of providing a detailed analysis of existing contracting systems, legal
agreement instead of drafting a whole new set of documents for risks of BIM implementation, and dedicated contractual provisions
BIM. Lowe and Muncey (2009) concluded that inadequate change- of such an implementation. The contribution to industry is in the
management culture of the construction industry may result in fur- form of a functional and applicable contracting system that ad-
ther problems if the entirely new contracting regime is introduced. dresses all the identified legal risks associated with the implemen-
Further, AEC (2012) released AEC BIM Protocol version 2.0 as an tation of BIM in the AECO industry.
improvement over version 1.0. This contract document urges the
use of best practices. The American Institute of Architects drafted
Review and Synthesis of Existing Research
E203 as an integrated project delivery (IPD) contract that can be
used as an addendum to existing general conditions for traditional A comprehensive review was performed to study and critique the
delivery methods (AIA 2013). Similarly, the Construction Industry existing publications relevant to the selected topic. To do so, a two-
Council BIM Protocol makes the minimum changes necessary to stage review was conducted in which the legal risks of BIM were
the pre-existing contractual arrangements for BIM in construction studied initially using a total of 10 published taxonomies. Each re-
projects (CIC 2013). This contractual system is limited to the search taxonomy was studied in detail and the relative impact of
design-build (DB) project delivery method. Furthermore, the time each risk was identified through a two-step content analysis. In
and cost management contract is an improvement over the Contract the first step, the relative frequency of appearance of each legal risk
for Complex Projects by CIOB (2015). was noted, and in the second step its qualitative assessment was
Upon detailed study, it is found that these contracts do not performed to place it into one of three impact categories: high (H),
sufficiently cater to various risks and uncertainties involved in medium (M), and low (L). Then in the second stage of the review,
BIM-based project delivery (Al-Shammari 2014), which opens a the five existing contractual systems were studied.
space for custom manuscript contracts (Abdirad 2015). These cus-
tom contracts are based on best practices and exclusively developed
Legal Risks of BIM
for a limited scope of application, but they are rarely known and do
not justify generalization. Thus, there are still many unclear legal Existing research has discussed the advantages and challenges
requirements for the contract structure and policy and for the con- of BIM in greater detail (Newton and Chileshe 2012; Bryde
tractual relationships and obligations associated with the BIM et al. 2013; Migilinskas et al. 2013). The uncertainties associated
model and security (Chong et al. 2017). with BIM implementation have been categorized into technical,
It should be noted that the technical risks of BIM actively feed into force the necessary mechanism to ensure that every party is liable
its legal uncertainty, and therefore addressing the latter will result in for its data entry. Keeping that in view, Alwash et al. (2017) rated it
the resolution of former (Olatunji 2011; Manderson et al. 2015). as a medium (M) risk. And further, Arensman and Ozbek (2012)
Following the first stage of literature review, a total of 14 legal categorized it as a low (L) risk because it was chronologically pre-
risks were identified from the relevant articles, and their description sented at the end. On the other hand, Manderson et al. (2015) and
was formalized, as given in Table 1. Kuiper and Holzer (2013) did not discuss this risk at all. Similarly,
To determine the implication and magnitude of these risks, a all other risks were synthesized from the literature using such a
two-step content analysis, as previously explained, was performed detailed process, and great care was taken in interpretation of the
using quantitative and qualitative assessment of identified legal literature.
risks. For quantitative analysis, the frequency of appearance was Although Pareto analysis, also known as the 80=20 rule, has
used, and qualitative analysis was based on the impact of these risks been used in the past as a screening strategy to eliminate the less
in the views of authors of selected articles (Newton and Chileshe impactful factors (Ullah et al. 2017), in order to conduct a holistic
2012; Bryde et al. 2013; Migilinskas et al. 2013; Siddiqui et al. analysis the current study did not opt to eliminate any identified
2016; Ullah et al. 2016). The subjectivity in interpretation of results risk, regardless of the resulting lower total score. It is pertinent that
and conclusions of published studies cannot be eliminated, and the total score is a linear product of cumulative frequency and over-
therefore its responsibility is entirely assumed by the authors of this all impact, which is derived by converting the qualitative scale into
paper. However, to objectively understand the version of published a numerical scale based on the weighted average of impact from
studies, the papers were read multiple times and the literal as well each paper.
as the figurative connotation of the content was evaluated. For ex- As presented in Table 2, the risk of intellectual property is the
ample, the risk of cost compensation has high impact (H) according most common in working with BIM and has been treated as having
to Chong et al. (2017) because it had a mean value of 1.11 with an a high impact in 80% of reviewed papers. It has been reported by
average mean of 0.64. But according to Eadie et al. (2015), it has a many authors, such as Fan (2013) and Olatunji (2015). Researchers
low impact because it was ranked at 13th position in the top 16 have yet to decide on the model ownership, and the literature is
LR7 H M L M L M H 7 M 3 21
LR8 H — — M H — — M — H 5 H 4.2 21
LR9 M M — L H — L M M — 7 M 2.7 19.1
LR10 M M M — M — — L M — 6 M 2.6 15.9
LR11 M — — M M — — — M M 5 M 3 15
LR12 — H L — — L — — M — 4 M 2.5 10
LR13 — L — M — M — — — M 4 M 2.5 10
LR14 — — M — L — — M M — 10 M 2.3 6.9
Note: H = high risk; M = medium risk; and L = low risk.
inconclusive on the party that possesses the intellectual claim over A summary of the content analysis of contract documents points
the BIM model. After the risk of model ownership, the issue of to the fact that ConsensusDOCS BIM Addendum, despite being the
professional liability is most prominent. Design consultants stand oldest, briefly discusses more risks than others but does not specify
liable for the design contributions of others, including default any contractual provisions for conditions of the contract and legal
changes by software (Arensman and Ozbek 2012; Manderson et al. validation of design. Further, AEC BIM Protocol released its latest
2015). version, 2.0, in 2012, which encourages use of best practices for
Further, BIM contractual frameworks need to define the mod- ownership of data and model management difficulties. However,
eling products and the information that will be available for review the best practices are subject to the level of BIM implementation,
and distribution. Also, it should clearly state how BIM will work which is quite limited.
under different project delivery methods (Manderson et al. 2015). The AIA E203 BIM addendum covers fewer risks, overlooking
Researchers and industry professionals have repeatedly discussed major issues like professional liability that is described by other
the interoperability issues. When software tools are not working BIM contracts. Similarly, CIC BIM Protocol, by proposing to apply
smoothly, potential issues can arise (Olatunji 2015). Further, owing best practices, gives generic information. It instructs to appoint a
to its innovative organizational structure, BIM requires new roles BIM manager and has a specimen for a BIM management plan. But
and responsibilities. Research has reported that a new set of pro- it remains silent on various issues such as standard of care, cost
fessional services involved in BIM protocols are yet to standardize compensation, and legal validation of design. Finally, CIOB Time
(Olatunji 2011). and Cost Management Contract is the latest document that has in-
Because BIM is a fully digital system, the shift from traditional corporated BIM. It discusses how the contract will help in the case
documents to e-communication has caused concerns over data that a separate BIM contractor is appointed. But it, too, does not
security. Ensuring that data is well protected against loss, its control address the cost compensation, conditions of contract, and data
access and any possible financial losses in case of a breach are security of the BIM model. Nevertheless, it encourages the use of
major concerns (Manderson et al. 2015). But all this is not going a mutually developed model management protocol. If stakeholders
to come free of charge. As BIM requires a new set of professional do not devise one, then AIA G202 BIM management protocol takes
skills and initial cost, its cost compensation should be discussed, precedence (CIOB 2015).
deliberated, and resolved. Since there do not exist precise contracts As provided in Table 3, a quantitative synthesis of several
for BIM, it is still unclear how the participants will be compensated
risks responded to by each contracting system out of the total
for the added cost (Chien et al. 2014). Also, the BIM product de-
identified risks reveals that ConsensusDOCS 301 BIM Addendum
livery and criteria for model building are not standardized. BIM
has the maximum coverage of 79%, followed by CIOB Time
stakeholders are obligated to use sensible professional judgment
and Cost Management Contract and CIC BIM Protocol with
to prevent any loss (Alwash et al. 2017).
coverage of 71%. On the other hand, E203-2013 and AEC BIM
Protocol have the minimum coverage of 57%. The strength of
Contracting Systems of BIM existing systems is their coverage of the copyright or intellectual
As previously explained, five contract documents are currently property issue, which is discussed by all of them. It is regarded
available in the industry that incorporate some of the legal that ownership of the model shall remain with the party who
risks of BIM. These documents are ConsensusDOCS 301 BIM develops it. A license must be issued to any other party using it.
Addendum (ConsensusDOCS 2008), AEC BIM Protocol (AEC Similarly, issues such as interoperability are briefly discussed,
2012), AIA E203 (AIA 2013), CIC BIM Protocol (CIC 2013), and a common data environment is recommended for smooth
and CIOB Time and Cost Management Contract (CIOB 2015). work. This clause can be used for improving software compatibil-
These systems provide a foundation for research and development ity, as discussed by the BIM addenda. However, various other
as well as the adoption of a standardized contracting system risks are not addressed by all the systems; for example, the risks
for BIM implementation. Using the identified risks, provided in of condition of contract and admissibility of electronic-based
Table 1, it is synthesized that these systems respond to some risks documents protocols are either partly addressed or not addressed
quite adequately but tend to forgo others. at all.
It can be concluded that none of the available contract docu- has been put to ensure a scientifically sound and conveniently rep-
ments encompasses all the risks of BIM reported in the recent stud- licable methodology. The details are explained in the subsequent
ies of legal implications of BIM and addressed in the preliminary sections.
contractual framework developed by Chong et al. (2017). Fur-
thermore, necessary remedies regarding the judicial precedence
of the contract along with the legal validation of design and risk Initial Study
allocation are not provided anywhere in the literature. This gap jus- Initially, a broad set of recent studies was analyzed to find the
tifies the need for standard contract documents, data security, and research gap. The latest published articles on information and com-
incorporation of new roles and responsibilities (Herr and Fischer munication technology (ICT) and on automation in civil engineer-
2018). ing and construction were consulted, which guided the way toward
the current state of development of BIM attributes. When the basics
of recent literature on BIM were analyzed, a gap in research was
Research Methodology found in the form of weak contractual support for a full-fledged
implementation of BIM, even though this technology is gaining
To sufficiently meet the set objectives, this study follows a four- a good reputation in the market. However, because its contractual
stage research methodology, as shown in Fig. 1. Maximum effort obligations are not yet met, project participants are voluntarily
Published
Research Identification of Legal Risks
Downloaded from ascelibrary.org by ECOLE DE TECHNOLOGIE SUPERIEURE on 11/20/20. Copyright ASCE. For personal use only; all rights reserved.
Literature
Review
Contract
Risk Mitigation Strategies Systems
Custom
Development of
Contracts
Questionnaire
Collection
& Analysis
Data
Data Data
Collection Analysis
Triangulation
Development
Framework
Development of
Limitations &
Contractual
Recommendations Framework
implementing BIM (Kumar et al. 2017). Considering this limita- list of only 37 papers. In the second-level screening, these papers
tion, a research statement was developed regarding necessary con- were analyzed in detail to identify the ones purely discussing the
tracts for BIM. As per this statement, the current study proposes a legal risks and offering a risk taxonomy. In response to this exer-
well-structured and balanced contractual framework for managing cise, irrelevant papers were eliminated and content analysis of
the legal uncertainties of BIM implementation in construction proj- the remaining 10 papers was carried out to identify legal risks,
ects procured through DBB, which will result in a smooth induction as previously described and presented in Table 2. In a separate ac-
of BIM into the AECO industry. tivity, five standard contracting systems were studied in detail to
find the mitigation strategies and best practices to manage the iden-
Literature Review tified risks, as given in Table 3. Finally, the past research was
synthesized.
To cover as much recent literature as possible, an inverted pyramid
approach was adopted under which many papers were consulted
Data Collection and Analysis
initially and screening was performed in the later stages to identify
the most relevant papers. To do this, research papers were searched On the basis of the detailed synthesis, risk mitigation strategies
online using Science Direct, Taylor & Francis Online, Emerald identified from the past research and contract documents were
Insight, ASCE, Google Scholar, and Scopus libraries, with the incorporated into a questionnaire survey that was distributed to
keywords BIM, Contracts, and Legal Risks. practitioners to incorporate expert opinion. The questionnaire had
Initially, a total of 79 research papers were retrieved. A first- two sections. In the first section, the demographic information of
level screening was performed by carefully reading the abstracts the respondents was solicited, including their personal and profes-
and conclusions of these papers. As a result, papers not dealing sional details such as experience, organizational position in the
with contractual and legal risks were filtered, resulting in a short project, and country of practice. The second section had 14
LR3 Modeling deliverable and sharing shall be discussed in BIM execution plan. 43.33
Modeling deliverable shall be specified by the client. Noneditable versions of model shall be shared. 22.00
Modelling deliverable shall be specified by the A/E. Construction-ready BIM model shall be transmitted to constructor. 22.00
Apply best practices. 10.67
LR4 Common file format to be developed in BIM execution plan. 44.67
The A/E shall provide common data environment. 30.00
Apply best practices. 24.00
LR5 Client will appoint information manager who shall develop BIM execution plan and chair BIM execution plan meetings. 41.33
BIM manager shall be appointed. 26.00
The A/E shall prepare a BIM execution plan. 22.00
Apply best practices. 9.33
LR6 Project data shall be saved on network servers with monitored access. 46.00
Each superseded file shall be saved and its log shall be maintained. 26.67
Apply best practices. 26.00
LR7 Client will bear the additional cost. 42.67
Apply best practices. 26.00
Consultant (A/E) will bear the additional cost. 20.00
Contractor will bear the additional cost. 7.33
LR8 Contractual framework shall be incorporated into an addendum of standard contract document. 43.33
All remedies of contractual risks shall develop a BIM standard. 28.00
Apply best practices. 28.00
LR9 All parties are responsible for their data input duty. 43.33
Spearin doctrine shall govern (and parties shall not be responsible for faulty data provided by other). 27.33
Contractor shall be appreciated to render professional services with reasonable judgment to prevent loss. 16.00
Apply best practices. 12.67
LR10 Digital data should be treated as a part of contract document. 48.67
Apply best practices. 17.33
Hard data governs over soft data. 16.00
2D drawings shall be plotted to be presented in court or local administration. 15.33
LR11 BIM model shall be maintained by the A/E in accordance with BIM protocol that shall be prepared by stakeholders. 33.33
Parties shall prepare a BIM execution plan with mutual understanding. 32.00
The A/E is responsible for model management. 22.00
Apply best practices. 10.67
LR12 Noneditable version to be produced that can be presented in local administration. 41.33
Drawings can be extracted in accordance with BIM protocol. 26.67
Apply best practices. 18.00
2D drawings shall be plotted to be presented in court or local administration. 12.67
LR13 Common software shall be decided in BIM execution plan. 56.00
Apply best practices. 24.67
Project team member shall have no liability in case of incompatibility. 16.00
LR14 If BIM is used, then this addendum shall govern. 57.33
Apply best practices. 40.00
Legal validation of design (LR12) requires the plotting of draw- (41.33%) and that such drawings can be extracted in accordance
ings. Two out of five contract systems discuss this issue and pro- with BIM protocol and execution plan (26.67%).
pose the solution in the form of plotting of drawings. Custom Software compatibility risk (LR13) is discussed by all standard
contracts emphasize the responsibility of the A/E for the legal val- and custom contracts. It is the A/E’s responsibility to suggest a
idation of design. Survey results state that a noneditable version common software to manage this issue. Custom contracts suggest
must be produced that can be presented in local administration specified software if the A/E does not dictate one. Survey results
LR11 same party. Seven risks have been shared by all the stakeholders,
LR1 LR12 and therefore not a single party will be exclusively liable for their
LR13 mitigation, such as the risk of conditions of the contract (LR3),
which will be mitigated by an elaborate BIM execution plan to
LR2 be developed by all the stakeholders and managed by the A/E. Sim-
ilarly, the risk of data interoperability (LR4) will be mitigated by
identifying a common software in the BIM execution plan, also
covering lack of software compatibility (LR13).
Furthermore, four risks will be mitigated by the contract frame-
Fig. 3. Proposed contractual framework.
work itself because not a particular party owns them as they exist
purely due to nonexistence of a standardized contracting system for
BIM. For example, risk of data security (LR6) is managed in such a
validate the AEC (2012) clause that common software shall be de- way that the data will be saved on system networks with monitored
cided in the BIM execution plan (56.00%). access. Similarly, risk of unclear BIM standards (LR8) will be
Risk of legislation and judicial precedence (LR14) was catered mitigated by sufficient description of all risks and declaration of
in the same pattern by all standard and published contracts by sug- their owners by the proposed framework. Further, for the risk of
gesting that an addendum shall be specified for BIM and will be admissibility of electronic-based documents (LR10), the contrac-
applicable if BIM is used. More than half the survey respondents tual framework suggests that such documents, including digitally
agreed and stated that if BIM is used, then this addendum shall stamped models, will be treated as part of contract documents.
govern (57.33%). However, the hard data will govern over the soft data. Lastly, for
legal validation of design (LR12), the contractual framework sug-
gests that 2D drawings can be presented in local administration for
Proposed Contractual Framework validation. A summary of proposed framework with respect to all
legal risks and their most preferred mitigation strategies is given
Using the data collected through various syntheses and surveys, in Table 6.
a contractual framework for DBB is proposed. The framework uses It should be noted that these mitigation strategies echo the best
three dimensions of information in the form of published contracts, of the survey response along with standard and custom contracts
survey response, and custom contract manuscripts to provide the manuscripts. Although they are discussed separately, they can be
information triangulation. Owing to the integrated nature of BIM, incorporated into a streamlined system that although it may not pro-
the roles and responsibilities of various stakeholders seem to over- duce an ideal framework, ensures practicability as well as legal ro-
lap, as shown in Fig. 3. It is argued in the literature that the overlap bustness by assigning proper roles and responsibilities to relevant
of responsibilities, although it may seem confusing to relevant entities. For example, the A/E acts as a pivotal body for all major
stakeholders, ensures a better, effective redressal of risks and con- risks. It has copyright over data so all other major risks are also
tractual relationships (Porwal and Hewage 2013). borne by it. Beside devising a BIM execution plan on the directions
equate and will help in resolving the legal risk of BIM. Another nition, a standard contractual and legal framework may still ensure
senior BIM researcher, as well as encouraging the sound basis of better implementation of BIM without demanding repetitive efforts
the proposed framework, suggested that more depth was needed by to configure contracting systems.
incorporating more legal risks into the framework. The industry In light of recommendations from the experts and limitations of
professional suggested that issues like the employer’s information this research in its scope and details, research efforts are encour-
requirement (EIR) and the data drop should be incorporated into the aged toward operationalizing the proposed framework by formulat-
framework. Thus, the proposed framework may act as a point of ing a robust system of roles, rights, and privileges that ensures data
departure in the face of these suggestions, to stimulate future re- privacy and security. Once it has been operationalized, enhance-
search that must focus not only on enhancing the structure and con- ments can be made by directly incorporating the stance of client
tents of the proposed framework but also on operationalizing its organizations. Further, issues such as EIR and data drop must be
clauses and observing their value addition. sufficiently addressed either through BIM protocol or execution
plan. The structure and mechanics of the BIM execution plan,
which has been emphasized by the proposed contractual frame-
Conclusions work, has not been discussed in this paper. Future research focusing
on the development of a detailed BIM execution plan will tactically
BIM is gaining a significant reputation in the AECO industry, and and operationally help in providing a standardized contractual
its rate of adoption has substantially increased. A detailed review of framework for BIM implementation in the AECO industry.
the published literature highlights that the legal risks of BIM should
be mitigated through predisposed strategies. Several contract docu-
ments discuss legal risks associated with BIM but do not cover all Data Availability Statement
of them. This study explored 14 legal risks of BIM through liter-
ature review and found that intellectual property, professional All data generated or analyzed during this study are included in the
liability, cost compensation, and data interoperability are the most published paper. Information about the Journal’s data-sharing pol-
significant risks. An analysis of recently published contract sys- icy can be found here: http://ascelibrary.org/doi/10.1061/(ASCE)
tems, expert opinion, and custom contracts in light of legal risks CO.1943-7862.0001263.
resulted in the identification of risk owners and possible mitigation
strategies. These strategies were then incorporated into a contrac-
tual framework that was discussed with industry professionals as Acknowledgments
well as academic researchers for further improvement.
The proposed framework operates within the DBB project de- The authors extend their special gratitude to all the industrial
livery method for easy and smooth implementation of BIM. It can practitioners who responded to the survey and contributed their va-
become part of any existing DBB contract by being issued as an luable input in the proposed framework. Also, we thank the editor
addendum, which reduces the effort of formulating a new set of and reviewers who provided constructive feedback that helped im-
contract documents. Furthermore, this study discusses the owner prove the contents of this paper.
of the BIM execution plan and how this plan will operate; either
the plan is devised by the stakeholders from scratch, or an already
published plan can be used. With all that done, a complete set of
Supplemental Data
contract documents is obtained that will help in execution of BIM Survey data is available online in the ASCE Library (www
to its fullest. Thus, the contribution of this study is twofold: it iden- .ascelibrary.org).
tifies the critical legal risks that must be managed for smooth in-
duction of BIM in construction projects, and it provides a stepping
stone in the form of a contract framework toward the standardiza- References
tion of a contractual system for implementing BIM in the AECO
industry. This study will inspire AECO community to devise a pan- Abdirad, H. 2015. “Advancing in building information modeling (BIM)
acea for the contractual uncertainties of BIM in AECO projects. contracting: Trends in the AEC/FM industry.” Accessed January 16,
It is pertinent to note that this paper takes an inside view of the 2018. https://aecuk.files.wordpress.com/2012/09/aecukbimprotocol-v2
knowledge gap, and as a result, it offers a contractual and legal -0.pdf.
framework for implementing BIM in construction projects deliv- AEC (Architects Engineers and Contractors). 2012. AEC (UK) BIM
protocol. London: AEC.
ered through the traditional DBB system. Larger, nonoperational
Ahmad, Z., M. J. Thaheem, and A. Maqsoom. 2018. “Building information
legal and technical risks surfaced due to the advent of BIM—such modeling as a risk transformer: An evolutionary insight into the project
as the practice of A/E by untrained and nonlicensed individuals, uncertainty.” Autom. Constr. 92: 103–119. https://doi.org/10.1016/j
involuntary data fudging, and data drop due to the n-tier distributed .autcon.2018.03.032.
architecture of cloud-based data repositories—are beyond the AIA (American Institute of Architects). 2013. “Document E203—2013
scope of this paper. Although an extreme scenario, there is a logical building information modeling and digital data exhibit.” Accessed
Arensman, D. B., and M. E. Ozbek. 2012. “Building information modeling to qualitative research, 178–183. Thousand Oaks, CA: SAGE
and potential legal issues.” Int. J. Constr. Educ. Res. 8 (2): 146–156. Publications.
https://doi.org/10.1080/15578771.2011.617808. Gerges, M., S. Austin, M. Mayouf, O. Ahiakwo, M. Jaeger, A. Saad, and
Azhar, S. 2011. “Building information modeling (BIM): Trends, benefits, T. E. Gohary. 2017. “An investigation into the implementation of
risks, and challenges for the AEC industry.” Leadersh. Manage. building information modeling in the Middle East.” J. Inf. Technol.
Eng. 11 (3): 241–252. https://doi.org/10.1061/(ASCE)LM.1943-5630 Constr. 22 (1): 1–15.
.0000127. Gu, N., and K. London. 2010. “Understanding and facilitating BIM
Azhar, S., A. Behringer, A. Sattineni, and T. Mqsood. 2012. “BIM adoption in the AEC industry.” Autom. Constr. 19 (8): 988–999. https://
for facilitating construction safety planning and management at job- doi.org/10.1016/j.autcon.2010.09.002.
sites.” In Proc., CIB-W099 Int. Conf. on Modelling and Building Safety. Hale, D. R., P. P. Shrestha, G. E. Gibson Jr., and G. Migliaccio. 2009.
Glasgow, UK: Glasgow Caledonian Univ. “Empirical comparison of design/build and design/bid/build project
Azhar, S., M. Khalfan, and T. Maqsood. 2015. “Building information mod- delivery methods.” J. Constr. Eng. Manage. 135 (7): 579–587. https://
elling (BIM): Now and beyond.” Constr. Econ. Build. 12 (4): 15–28. doi.org/10.1061/(ASCE)CO.1943-7862.0000017.
https://doi.org/10.5130/AJCEB.v12i4.3032. Hashem, M., M. S. Mehany, G. Bashettiyavar, B. Esmaeili, and G. Gad.
Azhar, S., A. Nadeem, J. Y. Mok, and B. H. Leung. 2008. “Building 2018. “Claims and project performance between traditional and alter-
information modeling (BIM): A new paradigm for visual interactive native project delivery methods.” J. Leg. Aff. Dispute Resolut. Eng.
modeling and simulation for construction projects.” In Proc., 1st Int. Constr. 10 (3): 04518017. https://doi.org/10.1061/(ASCE)LA.1943
-4170.0000266.
Conf. on Construction in Developing Countries. Karachi, Pakistan:
Herr, C. M., and T. Fischer. 2018. “BIM adoption across the Chinese AEC
NED Univ. of Engineering and Technology.
industries: An extended BIM adoption model.” J. Comput. Des. Eng., in
Barison, M. B., and E. T. Santos. 2010. “An overview of BIM specialists.”
press. https://doi.org/10.1016/j.jcde.2018.06.001.
In Proc., Computing in Civil and Building Engineering, ICCCBE2010
Ibbs, C. W., Y. H. Kwak, T. Ng, and A. M. Odabasi. 2003. “Project delivery
141. Nottingham, UK: Univ. of Nottingham.
systems and project change: Quantitative analysis.” J. Constr. Eng.
Barlish, K., and K. Sullivan. 2012. “How to measure the benefits of
Manage. 129 (4): 382–387. https://doi.org/10.1061/(ASCE)0733-9364
BIM—A case study approach.” Autom. Constr. 24: 149–159. https://doi
(2003)129:4(382).
.org/10.1016/j.autcon.2012.02.008.
Jung, W., and G. Lee. 2015. “The status of BIM adoption on six conti-
Bryde, D., M. Broquetas, and J. M. Volm. 2013. “The project benefits of
nents.” In Proc., Int. Conf. on Civil and Building Engineering (ICCBE).
building information modelling (BIM).” Int. J. Project Manage. 31 (7):
Ankara, Turkey: World Academy of Science, Engineering and
971–980. https://doi.org/10.1016/j.ijproman.2012.12.001.
Technology.
Bunni, N. G. 2013. The FIDIC forms of contract. New York: Wiley.
Kuiper, I., and D. Holzer. 2013. “Rethinking the contractual context for
Chen, H.-M., K. C. Chang, and T. H. Lin. 2016. “A cloud-based system building information modelling (BIM) in the Australian built environ-
framework for performing online viewing, storage, and analysis on big ment industry.” Constr. Econ. Build. 13 (4): 1–17. https://doi.org/10
data of massive BIMs.” Autom. Constr. 71: 34–48. https://doi.org/10 .5130/AJCEB.v13i4.3630.
.1016/j.autcon.2016.03.002. Kumar, B., H. Cai, and M. Hastak. 2017. “An assessment of benefits of
Chien, K.-F., Z. H. Wu, and S. C. Huang. 2014. “Identifying and assessing using BIM on an infrastructure project.” In Proc., Int. Conf. on Sustain-
critical risk factors for BIM projects: Empirical study.” Autom. Constr. able Infrastructure 2017. Reston, VA: ASCE.
45: 1–15. https://doi.org/10.1016/j.autcon.2014.04.012. Lowe, R. H., and J. M. Muncey. 2009. “ConsensusDOCS 301 BIM
Chong, H.-Y., S. L. Fan, M. Sutrisna, S. H. Hsieh, and C. M. Tsai. 2017. addendum.” Constr. Law 29 (1): 1–9.
“Preliminary contractual framework for BIM-enabled projects.” Luthra, A. 2010. “Implementation of building information modeling in
J. Constr. Eng. Manage. 143 (7): 04017025. https://doi.org/10.1061 architectural firms in India.” M.S. thesis, Purdue Univ.
/(ASCE)CO.1943-7862.0001278. Manderson, A., M. Jefferies, and G. Brewer. 2015. “Building information
CIC (Construction Industry Council). 2013. “Building information modelling and standardised construction contracts: A content analysis
model (BIM) protocol.” In Proc., CIC/BIM Pro. London: Construction of the GC21 contract.” Constr. Econ. Build. 15 (3): 72–84. https://doi
Industry Council. .org/10.5130/AJCEB.v15i3.4608.
CIOB (Chartered Institute of Building). 2015. Time and cost management McAdam, B. 2010. “Building information modelling: The UK legal
contract. Bracknell, UK: Chartered Institute of Building. context.” Int. J. Law Built Environ. 2 (3): 246–259. https://doi.org/10
ConsensusDOCS. 2008. “ConsensusDOCS 301.” In Proc., Building Infor- .1108/17561451011087337.
mation Modeling (BIM) Addendum. Arlington, VA: ConsensusDocs. Migilinskas, D., V. Popov, V. Juocevicius, and L. Ustinovichius. 2013.
Ding, Z., J. Zuo, J. Wu, and J. Y. Wang. 2015. “Key factors for the BIM “The benefits, obstacles and problems of practical BIM implementa-
adoption by architects: A China study.” Eng. Constr. Archit. Manage. tion.” Procedia Eng. 57: 767–774. https://doi.org/10.1016/j.proeng
22 (6): 732–748. https://doi.org/10.1108/ECAM-04-2015-0053. .2013.04.097.
Duggan, T., and D. Patel. 2013. Design-build project delivery market Mihindu, S., and Y. Arayici. 2008. “Digital construction through BIM sys-
share and market size report. Norwell, MA: RCD/RSMeans Market tems will drive the re-engineering of construction business practices.”
Intelligence. In Proc., Visualisation, 2008 Int. Conf. New York: IEEE.
Eadie, R., T. McLernon, and A. Patton. 2015. “An investigation into the Minchin, R. E. Jr, X. Li, R. R. Issa, and G. G. Vargas. 2013. “Comparison
legal issues relating to Building Information Modelling (BIM).” of cost and time performance of design-build and design-bid-build
In Proc., RICS COBRA AUBEA 2015. London: Royal Institution of delivery systems in Florida.” J. Constr. Eng. Manage. 139 (10):
Chartered Surveyors. 04013007. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000746.