Professional Documents
Culture Documents
002881-r-001 - A - Site Visit Report - 21jul15
002881-r-001 - A - Site Visit Report - 21jul15
002881-r-001 - A - Site Visit Report - 21jul15
Vietnam
Structural Inspection and Assessment
Visual Structural Inspection Report
Date: 21-07-2015
002881-r-001
CAI MEP INTERNATIONAL TERMINAL, VIETNAM
STRUCTURAL INSPECTION AND ASSESSMENT
VISUAL STRUCTURAL INSPECTION REPORT
Client
Author
Name: Van Thawng Lian
Direct line: 6294 3033
E-mail: van.thawnglian@dmc.nl
Address: 51 Changi Business Park Central 2, #07-12, The Signature, Singapore 486066
Telephone +65 62943033 / www.dmc.nl / projects.dmc@dmc.nl
002881-p-0001 Rev. A
21-07-2015
2 / 19
Index
1 Introduction...............................................................................................4
1.1 Project Background .......................................................................................... 4
1.2 Cai Mep International Terminal ........................................................................ 4
1.3 Incident and Initial Observations ..................................................................... 6
1.4 Scope, Objective and Purpose ......................................................................... 7
2 Site Visit and Visual Structural Inspection.............................................8
2.1 Areas of Focus .................................................................................................. 8
2.2 Inspections and Activities ................................................................................ 8
2.3 Data Gathering................................................................................................... 8
3 Observations and Assessments .............................................................9
3.1 Global Structural Damages............................................................................... 9
3.2 Local Damages Sustained at Block 5 .............................................................13
4 Summary, Conclusions and Recommendations .................................19
002881-p-0001 Rev. A
21-07-2015
3 / 19
1 Introduction
Delta Marine Consultants Singapore Pte.Ltd, further referred to as DMC, has been appointed
by Charles Taylor Adjusting (Marine), further referred to as Client, to provide consultancy
services for structural inspection and damage assessment sustained on the wharf structure
during a collision by a vessel at Cai Mep International Terminal, further referred to as CMIT,
in Vietnam.
Cai Mep International Terminal Co., Ltd. (CMIT) was established on January 26, 2007 as a
joint venture between the Vietnam-based Saigon Port, Vietnam National Shipping Lines and
APM Terminals BV. The CMIT terminal is lying along the Cai Mep River, with the close
deviation from the main sailing route. It is approximately 80km away from Ho Chi Minh City,
and approximately 50km from main manufacturing areas in Binh Duong Province, Dong Nai
Province and others. Location of CMIT is shown in Figure 1-1.
002881-p-0001 Rev. A
21-07-2015
4 / 19
Figure 1-2 show the terminal layout including the 600m long berth. The berth, having 16.5m minimum
water depth alongside, has been designed to cater maximum vessel size of 160,000 DWT.
The 600m berth is structurally design and constructed as a combination of 100m long 6 blocks, as
shown on Figure 1-3 (refer to as-built drawing CMIT/BT/C/ABC/003 Rev 1 in Appendix A). Adjacent
blocks are physically connected by means of shear key along reinforced concrete deck, refer to Figure
1-4. Collision with the vessel occurred at Block 5.
APPROXIMATE POINT OF
COLLISION
002881-p-0001 Rev. A
21-07-2015
5 / 19
Figure 1-4: Expansion Joint between Adjacent Blocks
Based on CMIT’s Incident Report dated 1 July 2015, M/V Vessel CMA CGM DON PASCUALE collided
with the Berth at Block 5 at 13:01 on 1 July 2015, while attempting to berth. The vessel was observed
approaching the berth in almost perpendicular direction just before it’s bow was in contact with cope
line of Block 5 of the berth structure.
The vessel bow and hull were in direct contact with reinforced concrete structural elements and piles,
without berthing on the provided fenders. Thus the damages were limited to structural elements of Block
5 berth and not to the mooring bollards and fenders. Figure 1-5 shows layout of initial observations of
the collided area and damages. Preliminary survey (ref. Vietcontrol’s report No. 1506-CMIT) by
Vietcontrol reported that:
Damages observed on concrete deck and beam where the vessel had in direct contact with
vessel bow;
3 nos. steel piles below the front crane beam are cut out completely from the beam;
1 no. reinforced concrete spun pile at the second row was seriously damaged;
No visible damages observed on other nearby piles.
002881-p-0001 Rev. A
21-07-2015
6 / 19
Figure 1-5: Collided Location Layout on Block 5 (by CMIT)
The work scope in Stage I ‘Visual Structural Inspection’ to the berth structure included a site visit by
DMC personnel to perform visual structural inspection of the damages sustained on the berth structure,
to gather relevant as-built and design information and liaising with other underwater diving surveyors
and ultrasonic test team on site.
The main objective of site visual inspection is visually assess the extent of damage in the context of
structural integrity and to identify further studies and works. It does not include analysing the lead up
and cause to this incident.
This report compiles and presents observations during the site visual inspection, preliminary
assessment and recommendations for the next course of actions.
002881-p-0001 Rev. A
21-07-2015
7 / 19
2 Site Visit and Visual Structural Inspection
DMC has visited CMIT on 13 and 14 July 2015, and carried out on-site visual inspections above and
under deck.
The two (2) main concerns focused during the visual structural inspections were:
1) Global deformation or damages - to identify and assess if the incident sustained any structural
damages to other parts of the berth structure other than initially identified; and
2) Extend of local damages – to assess damages sustained at the area in direct contact with the
vessel.
Activities carried out during the 2 days site visit are outlined below:
Day 1 (13 July 2015):
Meeting and discussion with other surveyors appointed by CMIT (ultrasonic test, deck
survey, underwater diving inspection)
Above deck visual inspection
Under deck visual inspection
Data gathering
002881-p-0001 Rev. A
21-07-2015
8 / 19
3 Observations and Assessments
In order to identify if the Block 5 berth has sustained deformations and structural cracks or damages,
the following above deck visual inspections were performed:
1) Any misalignment of berth front faces (refer to Figures 3-1 and 3-2);
3) Any misalignment of joint between adjacent blocks (refer to Figures 3-7 and 3-8)
4) Any visible cracks on front and rear crane beams (refer to Figure 3-5). Considering the fact that
pairs of steel tubular racker piles were designed and provided under the rear crane beam, which
would function as lateral strong point for the global berth structure, it is envisaged any potential
damages or cracks if caused by the impact of vessel to be more significant on this beam
compared to others.
No visible misalignment of the Block 5 berth structure in reference to adjacent Blocks 4 and
6 was observed;
The observations above, in general, indicated that no globally sustained deformation or damages on
the berth structure caused by the vessel collision. This lead to conclude that the assessment shall be
focused on local damages sustained at the berth front where the vessel collision occured.
However, above observations shall be confirmed by the ultrasonic test results and above deck survey
reports later.
Figure 3-1: Berth Face at Blocks 5 and 4 Joint– No misalignment was observed
002881-p-0001 Rev. A
21-07-2015
9 / 19
Figure 3-2: Berth Face at Blocks 5 and 6 Joint– No misalignment was observed
Figure 3-3: Front Crane Rail Recess at Blocks 5 and 4 Interface– No misalignment was observed
002881-p-0001 Rev. A
21-07-2015
10 / 19
Figure 3-4: Rear Crane Rail Recess at Blocks 5 and 4 Interface– No misalignment was observed
Figure 3-5: Rear Crane Rail Recess at Blocks 5 and 6 Interface– No misalignment was observed nor
visible cracks along the beam.
002881-p-0001 Rev. A
21-07-2015
11 / 19
Figure 3-6: Front Crane Rail Recess at Blocks 5 and 6 Interface– No misalignment was observed
Figure 3-7: Joint between Blocks 4 and 5– No fresh damages or gap was observed
002881-p-0001 Rev. A
21-07-2015
12 / 19
Figure 3-8: Joint between Blocks 5 and 6 – No fresh damages or gap observed
The local damages reported by Vietcontrol are described in Section 1.3. The following paragraphs
summarized additional visual observations made during DMC’s site visit and review of the as-built
drawings.
Figure 3-9 shows piling layout of part of Block 5 where the vessel collided with. It appeared that the
vessel bow hit the 500mm thick reinforced concrete deck slab at it’s front face between Gridlines 04m
and 05, while the bulbous bow crushed the frontal panel of beam at Grid 05 where mooring hooks were
provided, then the 3 nos. steel piles supporting front crane beam at Grids 04m-j, 05-j and 05m-j and
further hitting pile at Grid 05-i. It is noted from as-built drawings and the visual inspection that piles a
long Grids ‘j’ (front crane beam), ‘e’ (rear crane beam) and ‘09’ are steel tubular piles and the rest
reinforced concrete spun piles. Reference shall be made to as-built drawing CMIT/BT/C/ABC/008 for
overall piling layout and pile sizes of Block 5 berth structure.
Figure 3-9: Piling Layout of Block 5 At Damaged Area (ref. Drawing No. CMIT/BT/C/ABC/008)
002881-p-0001 Rev. A
21-07-2015
14 / 19
Figure 3-10: Detached Steel Tubular Pile at Grid 04m-j
Figure 3-11: Damaged Steel Tubular Piles at Grid 05-j and 05m-j
002881-p-0001 Rev. A
21-07-2015
15 / 19
Figure 3-12: Damaged RC Spun Pile at Grid 05-i
Figure 3-13: Damages of 500mm Thick Deck Where Vessel Bow Contacted (View towards Block 6)
002881-p-0001 Rev. A
21-07-2015
16 / 19
Figure 3-14: Damaged Slab and Crane Beam - A View from Sea towards Shore
Figure 3-15: Concrete Deck Surface Directly above Damaged Pile at Grid 05-i: No visible fresh crack
or damage was observed.
002881-p-0001 Rev. A
21-07-2015
17 / 19
Figure 3-16: Damaged Reinforced Concrete Mooring Hook Panel
Figure 3-17: Area Identified for Ultrasonic Tests and Underwater Diving Survey (by Others)
002881-p-0001 Rev. A
21-07-2015
18 / 19
4 Summary, Conclusions and Recommendations
No globally sustained damages and deformation were observed, i.e. Block 5 is aligned well with
adjacent Blocks 4 and 5. This observation shall be confirmed with the deck survey report in a
later stage.
Local damages sustained by reinforced concrete slab and beam at the berth front face are
found to be critical, which could affect structural integrity of the berth structure subject to the
extent of invisible damages sustained. Extent of such damages on these members and nearby
structural elements shall be checked and confirmed with ultrasonic test performed by others,
and structural capacity shall be analysed and checked, taken into account the damage
conditions;
A total of 4 piles were found fully damaged and required to be replace for the design operation.
Conditions and integrity of the nearby piles shall be checked and confirmed with ultrasonic test
results and underwater diving survey.
Structural capacity of the berth structure for interim operations outlined below, shall be carefully
analysed and assessed, after establishing the extent of local damages sustained:
o Moving the STS crane over damaged area;
o Using mooring hooks and fenders at Grids 03 and 06 which are adjacent to the
damaged area; and
o Operating of STS Crane in vicinity of the damaged area (how close the crane can be
operated).
13
002881-p-0001 Rev. A
21-07-2015
19 / 19