Satip P 121 01 Rev 7 MP

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 7

SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13 Note: For Maintain Potential

31-Mar-13 Note: For Maintain Potential Projects usage only.


SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Cable and Conduit Seal To be reviewed and approved prior to electrical work at
1.1
Installation Procedure
SAIC-P-3004 SAIC-P-3004 RH RH jobsite.

Cable Termination and Splicing


1.2 Special Work Procedure SAIC-P-3223 SAIC-P-3223 RH RH
Document Review

Cable Splicer Certification and Job Clearance Cards (JCC's) to be issued prior to
1.3
Project Job Clearance Cards
SAIC-P-3210 SAIC-P-3210 RH RH commencement of MV Cable termination work.

RECEIVING
2.0
INSPECTION

Dry Xfmr LV ≤500 kVA


2.1 Storage, Handling, and Preservation SAIC-P-3918 SAIC-P-3918 I S Weekly inspection by Contractor QC
Visual Inspection

Dry Xfmr MV or ≥501 kVA


2.2 Storage, Handling, and Preservation SAIC-P-3919 SAIC-P-3919 I S Weekly inspection by Contractor QC
Visual Inspection

Dry Xfmr LV ≤500 kVA


"S"- Aramco supply material
2.3 Material Receiving SAIC-P-3918 SAIC-P-3918 H S/W "W"- Contractor supply material
Visual Inspection

Dry Xfmr MV or ≥501 kVA


2.4 Material Receiving SAIC-P-3919 SAIC-P-3919 H W
Visual Inspection

Transformer Accessories
Material Receiving
2.5
Visual Inspection
SAIC-P-3918 SAIC-P-3918 H W See GENERAL NOTES for typical accessories.
Dry Xfmr LV ≤500 kVA

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13 Note: For Maintain Potential Projects usage only.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Transformer Accessories
Material Receiving
2.6
Visual Inspection
SAIC-P-3919 SAIC-P-3919 H W See GENERAL NOTES for typical accessories.
Dry Xfmr MV or ≥501 kVA

Transformer
Jobsite Acceptance Test
In accordance with transformer manufacturer's
2.7 (Continuity and Insulation SATR-P-3907 SATR-P-3907 H W instructions.
Resistance Testing)
Dry Xfmr LV and ≤500 kVA

Transformer
Jobsite Acceptance Test
In accordance with transformer manufacturer's
2.8 (Continuity and Insulation SATR-P-3908 SATR-P-3908 H W instructions.
Resistance Testing)
Dry Xfmr MV or ≥501 kVA

3.0 INSTALLATION

See SATIP-P-111-01 Grounding and Bonding


SATIP-P-104-07 B/G Conduit, and Duct Bank
Transformer Grounding As applicable.
3.1
Visual Inspection
See Remarks See Remarks H W
SA PID shall be notified on start of this activity for each
MV transformer, and each LV transformer area.

Transformer Assembly,
Installation & Identification SA PID shall be notified on start of this activity for each
3.2
Visual Inspection
SAIC-P-3920 SAIC-P-3920 H W MV transformer, and each LV transformer area.
Dry Xfmr LV ≤500 kVA

Transformer Assembly,
Installation & Identification SA PID shall be notified on start of this activity for each
3.3
Visual Inspection
SAIC-P-3921 SAIC-P-3921 W S MV transformer, and each LV transformer area.
Dry Xfmr MV or ≥501 kVA

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13 Note: For Maintain Potential Projects usage only.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

See SATIP-P-104-03 Cable Tray


SATIP-P-104-05 A/G Conduit
SATIP-P-104-07 B/G Conduit
SATIP-P-111-01 Grounding and Bonding
Conduit, and/or Cable Tray
SATIP-P-116-10 MV Cablebus
3.4 Installation & Identification See Remarks See Remarks W S SATIP-P-116-12 LV Cablebus
Visual Inspection
As applicable

SA PID shall be notified on start of this activity for each


MV transformer, and each LV transformer area.

See SATIP-P-104-01 LV Cable


SATIP-P-104-02 MV Cable
Cable Pulling / Laying
3.5
Visual Inspection
See Remarks See Remarks W S
SA PID shall be notified on start of this activity for each
MV transformer, and each LV transformer area.

See SATIP-P-104-01 LV Cable


SATIP-P-104-02 MV Cable and
Cable Gland Installation, Cable Dressing,
SATIP-P-111-01 Grounding and Bonding
3.6 Identification, & Termination Visual See Remarks See Remarks W S
Inspection
SA PID shall be notified on start of this activity for each
MV transformer, and each LV transformer area.

4.0 PRE-COMMISSIONING

See SATIP-P-104-01 LV Cable


SATIP-P-104-02 MV Cable
Cable Continuity SATIP-P-116-10 MV Cablebus
4.1 and Insulation Testing See Remarks See Remarks W S SATIP-P-116-12 LV Cablebus
(Installed Cablebus or Cable)
SA PID shall be notified on start of this activity for each
MV transformer, and each LV transformer area.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13 Note: For Maintain Potential Projects usage only.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

See SATIP-P-114-01 Protective Relaying as applicable.

May include high-potential withstand testing - in


accordance with transformer manufacturer's instructions.
Pre-energization Testing
4.2 (Installed Transformer) SATR-P-3907 SATR-P-3907 H W
Dry Xfmr LV ≤500 kVA
Hold point prior to transformer energization.

SA PID shall be notified on start of this activity for each


MV transformer, and each LV transformer area.

See SATIP-P-114-01 Protective Relaying as applicable.


May include high-potential withstand testing - in
accordance with transformer manufacturer's instructions.
Pre-energization Testing
4.3 (Installed Transformer) SATR-P-3908 SATR-P-3908 H W Hold point prior to transformer energization.
Dry Xfmr MV or ≥501 kVA
SA PID shall be notified on start of this activity for each
MV transformer, and each LV transformer area.

MV Cable SA PID shall be notified on start of this activity for each


High-Potential MV transformer.
4.4
Withstand Testing
SATR-P-3210 SATR-P-3210 H W
(Installed Cable) Hold point prior to transformer energization.

Power Cable Termination SA PID shall be notified on start of this activity for each
4.5
Torque Testing
SATR-P-3209 SATR-P-3209 H W MV transformer, and each LV transformer area.

Dry Xfmr LV ≤501 kVA In accordance with transformer manufacturer's


Pre-energization instructions.
4.6
Visual Inspection
SAIC-P-3920 EIL H W
for Energization Certificate Hold point prior to transformer energization.

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13 Note: For Maintain Potential Projects usage only.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Dry Xfmr MV or ≥501 kVA In accordance with transformer manufacturer's


Pre-energization instructions.
4.7
Visual Inspection
SAIC-P-3921 EIL H W
for Energization Certificate Hold point prior to transformer energization.

See SATIP-P-111-01 Grounding and Bonding.

Coordinate with energization of transformer source


and load equipment such as:
SATIP-P-116-01 MV Switchgear
Transformer Pre-energization
Energization SATIP-P-116-02 MV MCC's
4.8 Quality Document Review EIL
Certificate RH RH SATIP-P-116-03 LV Switchgear
and Energization Certificate
SATIP-P-116-04 LV MCC's
SATIP-P-116-05 Switchracks and Distribution Racks
SATIP-P-116-07 LV Panelboards and Switchboards

Hold point prior to transformer energization.

Energized Dry Xfmr LV ≤500 kVA In accordance with transformer manufacturer's


No Load, Functional, Thermal instructions.
4.9
Load (Hot Spot) Testing, and
SATR-P-3907 SATR-P-3907 H H
Protection Testing Hold point prior to PMCC / MCC.

Energized Dry Xfmr MV or ≥501 kVA In accordance with transformer manufacturer's


No Load, Functional, Thermal instructions.
4.10
Load (Hot Spot) Testing, and
SATR-P-3908 SATR-P-3908 H H
Protection Testing Hold point prior to PMCC / MCC.

Energized Transformer Remote See SATIP-J-900-01 Instrument Loop Checking


4.11
Indication and Alarm Testing
See Remarks See Remarks H H as applicable

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13 Note: For Maintain Potential Projects usage only.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

See SATIP-P-111-01 Grounding and Bonding


Coordinate with energization of transformer source
Energized Dry Xfmr LV ≤500 kVA
4.12
Final Inspection
SAIC-P-3920 EIL H H and load equipment.

Hold point prior to PMCC or MCC.

See SATIP-P-111-01 Grounding and Bonding


Coordinate with energization of transformer source
Energized Dry Xfmr MV or ≥501 kVA
4.13
Final Inspection
SAIC-P-3921 EIL H H and load equipment.

Hold point prior to PMCC or MCC.

Review FEIL and all associated Quality Records.


Energized Transformer
PMCC
4.14 Quality Document Review FEIL RH RH
MCC Hold point prior to electrical service (by voltage level)
and Mechanical Completion Certificate
completion certification.

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

Accessories include metering, control, protective relaying cabinets & devices, automatic or manual tap changers, MV bushings, current transformers, voltage transformers, surge arrestors &
6
capacitors, winding leads, rain shields, rodent screens, dust filters, bus bar, post insulators, secondary neutral strapping, cable crimp terminals, mechanical fasteners, and grounding pads and posts.

LEGEND

H Hold Point for QC Inspection/ Test R Review of Documents

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - MARCH 2013) Rev 7 31-Mar-13 Note: For Maintain Potential Projects usage only.
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

W Witness Inspection/Test RH Review and Approval of Documents


S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use

You might also like