Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Cable and Conduit Seal To be reviewed and approved prior to electrical work at
1.1
Installation Procedure
SAIC-P-3004 SAIC-P-3004 RH RH jobsite.
Cable Splicer Certification and Job Clearance Cards (JCC's) to be issued prior to
1.3
Project Job Clearance Cards
SAIC-P-3210 SAIC-P-3210 RH RH commencement of MV Cable termination work.
RECEIVING
2.0
INSPECTION
Transformer Accessories
Material Receiving
2.5
Visual Inspection
SAIC-P-3918 SAIC-P-3918 H W See GENERAL NOTES for typical accessories.
Dry Xfmr LV ≤500 kVA
Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Transformer Accessories
Material Receiving
2.6
Visual Inspection
SAIC-P-3919 SAIC-P-3919 H W See GENERAL NOTES for typical accessories.
Dry Xfmr MV or ≥501 kVA
Transformer
Jobsite Acceptance Test
In accordance with transformer manufacturer's
2.7 (Continuity and Insulation SATR-P-3907 SATR-P-3907 H W instructions.
Resistance Testing)
Dry Xfmr LV and ≤500 kVA
Transformer
Jobsite Acceptance Test
In accordance with transformer manufacturer's
2.8 (Continuity and Insulation SATR-P-3908 SATR-P-3908 H W instructions.
Resistance Testing)
Dry Xfmr MV or ≥501 kVA
3.0 INSTALLATION
Transformer Assembly,
Installation & Identification SA PID shall be notified on start of this activity for each
3.2
Visual Inspection
SAIC-P-3920 SAIC-P-3920 H W MV transformer, and each LV transformer area.
Dry Xfmr LV ≤500 kVA
Transformer Assembly,
Installation & Identification SA PID shall be notified on start of this activity for each
3.3
Visual Inspection
SAIC-P-3921 SAIC-P-3921 W S MV transformer, and each LV transformer area.
Dry Xfmr MV or ≥501 kVA
Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4.0 PRE-COMMISSIONING
Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Power Cable Termination SA PID shall be notified on start of this activity for each
4.5
Torque Testing
SATR-P-3209 SATR-P-3209 H W MV transformer, and each LV transformer area.
Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
Accessories include metering, control, protective relaying cabinets & devices, automatic or manual tap changers, MV bushings, current transformers, voltage transformers, surge arrestors &
6
capacitors, winding leads, rain shields, rodent screens, dust filters, bus bar, post insulators, secondary neutral strapping, cable crimp terminals, mechanical fasteners, and grounding pads and posts.
LEGEND
Dry Type Transformers (Low Voltage and Medium Voltage) SATIP-P-121-01 MP 30-Apr-13 Electrical
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO