Projects

Orapa Diamond Mine (January 2005 – November 2005)


Incidences: none

Project Type Project Estimated Actual Cost on Estimated Actual total


Cost completion project time: project time:
HME Plant R 56 456 000.00 R43 667 000.00 14 months 10 Months
workshop (South African
Rand equivalent)

Orapa Diamond Mine (February 2006 – January 2008)


Incidences: two Minor

Project Type Project Estimated Actual Cost on Estimated Actual total


Cost completion project time:: project time
15km conveyor R 780 487 000.00 R 614 202 000.00 2 years 1 year
extension plus (South African 6 months 11 months
DMS Crushing Rand equivalent)
Plant

Orapa Diamond Mine (April 2009 – June 2009)


Incidences: none

Project Type Project Estimated Actual Cost on Estimated Actual total


Cost completion project time:: project time
TMM PLANT R 6 320 000.00 R 5 434 000.00 3 months 2 months
WASHBAY (South African
Rand equivalent)

HARMONY GOLD MINE (March 2016 – September 2019)


Projects

Project Type Project Estimated Actual Cost on Estimated Actual total


Cost completion project time:: project time
Flotation tanks R 400 500 000.00 R326 560 000.00 3 years 2 years
and refinery 6 months
plant
Projects

Chart Title

450,000,000
400500000
400,000,000
326560000

350,000,000

300,000,000
Axis Title

250,000,000

200,000,000
73940000
150,000,000
1 2 3

100,000,000 0.5
varience
2.5 1 -1
50,000,000 Actual
3 0
Estimated
0

Axis Title
Cost Time Incidences

-50,000,000

Axis Title

Estimated Actual varience