Professional Documents
Culture Documents
Role of PMP Atlas in Design Flood Estimation. M. Raghuram Director
Role of PMP Atlas in Design Flood Estimation. M. Raghuram Director
M. Raghuram
Director
Presentation Outline
Introduction
Methods of PMP Estimation
Data Requirements in PMP Studies
PMP atlases and Details
Usage of PMP Atlas
Example & Case Studies
Guidelines in using PMP Atlas
#2
Design Flood
Based on the type of Water Resources Structure and down stream
impacts, BIS specifies the design flood .
Basin Response Function
UG
Design
Flood (SPF/PMF/
Return Period Flood)
Design Storm (SPS/PMP/
Return Period Storm)
Isopluvial Maps of Different Return Periods
5
SPS & PMP Analysis
#6
Definitions of SPS & PMP
The Standard Project Storm is the one, which is reasonably
capable of occurring over the basin under consideration and
is generally the heaviest rain storm, which has occurred in
the region of the basin during the period of rainfall records.
#7
PMP Estimation - Methods
Methods
Physical Method
Local Storm Method
Transposition Method
PMP for 1, 2, 3 Days
#9
PMP Estimation - Data & Subjectivity
Severe Rainstorm Data and their Synoptic Situation
Daily Rainfall Data for the concerned Period
Isohyetal Pattern of the storms
Persisting Dew Point Temperature during Storm Period
Highest persisting Dew point data at project location
Topography
Storm Transposition
SRRG Data for Temporal Distribution
#11
Estimation of PMP Storm Area Approach
PMP Estimation (Physical Method)
Definition of PMP
Data Procurement
It is defined as the theoretically the greatest depth of precipitation for a given
duration that is physically possible over a given size storm area at a particular
Daily Rainfall Data Dew Point Data Hourly Rainfall Data
geographical location at a certain time of year.
Rainstorm Analysis Time Distribution
Analysis
Storm
Methods of estimation
Transposition Heavy Rain spells
1. Storm model approach
Isohytel Maps Average Percent
2. Maximization and transposition of actual storms.
Time Distribution
3. Use of generalized depth-area-duration data
( 6,12, 24, 48, 72
Depth‐ Duration analyses
4. Statistical of extreme rainfalls
Depth‐Area‐ Hours)
(DD) Duration (DAD)
Clock Hour
Standard Project Strom (SPS) Correction
Strom Maximization
Moisture Adjustment Factor (MAF)
PMP for 1, 2, 3 Days
Grid Point PMP
#12
Depth Area Duration (DAD) Analysis
#13
Prepared PMP Atlases
In 1997, PMP Atlases were prepared for
• Chambal, Betwa, Sone and Mahi basin.
• Godavari and other east flowing rivers.
• Cauveri and other east flowing rivers
• Mahanadi and adjoining river basin.
• Narmada, Tapi, Sabarmati, Banas and Luni River
Systems and Rivers of Saurashstra and Kutch Region.
• West Flowing Rivers of Western Ghats
In 2007, PMP Atlases were prepared for
• Indus basin
• Krishna Basin
Updating of PMP Atlas
Preparation of New PMP atlases for
#15
PMP Atlas - Deliverables
Documentation of all rainstorms affecting the basins
Grid PMP depths at 1o X 1o grid points for each of the basins and
Maps
Area reduction factors for conversion of point PMP depths into areal
depths
#16
Deliverables - Contd.,
Estimation of point PMP for the durations of 1, 2 and 3-day storms
based on Hershfield’s method and preparation of PMP maps
Estimation of 2.33, 5, 10, 25, 50, 100, 500, 1,000, 5,000, 10,000
year return period rainfall for all stations
Clock-hour correction
Maps showing the snow fed areas and rain fed areas.
#17
Godavari Basin Study
#18
Salient Features of Godavari Basin
Godavari is the third largest river basin in India extending over an
area of 3,12,812 sq. km.
#21
List of Analyzed Storms
#22
Storm Centre Location Map
#23
Synoptic Situation of Severe Storms
#24
Tracks of Severe Storms
#25
Isohyetal Map of 27th June, 1914 Storm (1 Day)
26
DAD Curve of 25-27 June, 1914 Storm
#27
MMF of Severe Storms
#28
Sub Basin wise PMP Estimation
#29
Sub Basin Map
Sub Basin wise PMP Estimation
SPS depths for 1, 2 and 3 - Day durations are read from the
relevant Enevelop DAD curve and values are tabulated for different
areas
The relavant PMP (insitu) values are estimated using SPS values
and the MMFs of the concerned storms
#31
Sub Basin wise PMP Estimation
The SPS and PMP values of Upper Godavari Sub Basin
#32
PMP Estimation at Grid Points
#33
PMP Estimation at Grid Points
#34
Estimation Procedure
#35
SPS and PMP depths at Grid Points
Envelope Depth Area Duration Curve (1‐Day)
600
WRD‐1, WRD‐2, WRD‐3
500
Precipitation in mm
400
300
200
100
0
0 10 20 30 40 50
Area in 1000 sq. km.
#36
Grid PMP – 1 Day Duration for 1, 000 sq km
#37
Estimation of Time Distribution
#38
Time Distribution
#39
Statistical Estimates of PMP
#40
PMP by Statistical approach
#41
PMP by Statistical approach
#42
Usage of PMP Atlas
#43
Usage of PMP Atlas
Ideally suited for projects with small and medium size drainage
areas with Catchments with one of the grid points close to its
centre
#45
Example Problem
#46
Problem
Average value of one day PMP = 460 mm
Envelop DAD Curve of Sub Basin
Area (sqkm) SPS (mm)
MAF at the Project Location 1.18
4000 376
5000 356 The PMP value 438.8 mm
4205 371.9
Transposing Isohytel Map
Transposable Storms for the Project Site
Storm Centre Storm Peak
18 July 2000 Paoni 407
12 July, 1994 Chandur Railway 468
27 June, 1914 Parbhani 401
Transposed Storm Depth at the Project
Storm Centre Transposed depth
18 July 2000 Paoni 338
12 July, 1994 Chandur Railway 222
27 June, 1914 Parbhani 274
MAF for the 18 July, 2000 storm at Project 1.24
PMP value for the Project 419 mm
Statistical Method
1 day PMP read from Spatial Pattern Map is 470 mm
Areal Reduction for project CA is 0.85
The PMP value for the CA is 400 mm
Case Studies
#53
Case Study – Sukta Project, MP
Sukta Project – Grid Point PMP
Grid Point PMP
104M‐2 452
104M‐3 479
103U‐1 451
103U‐2 475
Mean 464
Grid Points- Critical Storms
The critical storms and MAF vary from grid point to grid point yielding
descrete values at grid points
This variabilty from Grid Point to Grid Point restricts its utilisation for large
catchmnets
#56
Sukta Project – DAD curve of 15 Sep 1998 Gharadengri
SPS 472
MAF 1.02
PMP 481
#57
www.rmsi.com
www.rmsi.com
www.rmsi.com
www.rmsi.com
Sukta Project – Isohyetal Map
Method PMP Value
(mm)
Grid Point PMP 464
DAD Curve 481
Detailed Storm Study 478
Bansujara Project - MP
#63
Areal Rainfall by DAD curve Vs Isohyetal map
#65
Bansujara Project - Grid Points
#66
RRB Project, Narmada River
#67
RRB Project – Transposed Storm
#68
RRB Project – Transposed Storm at CG of total CA
#69
RRB Project – Transposed Storm at CG of Basania CA
#70
RRB Project – SPS values for different storm Positions
PMP values are computed considering the above SPS avlues and MAF as
1.21
#71
RRB Project – Grid Points
#72
Case Studies
If elongation ratio is less than 1.5 and one of the grid point is close
to centre of catchment, grid Point SPS/PMS values can be used for
catchments up to 500 sqkm
#74
The PMP atlases are comprehensive data banks
which will be useful not only for quick assessment
of design storm for a small or medium catchments
but also for detailed project specific storm
studies.
Thank You
#75
www.rmsi.com