BANBAN SITINJAK, ST
Jl. Mc.kenzie block F No. 19
Gunung Bahagia 76114 Balikpapan
Hp: +6282155480810
E-mail Address: sitinjak.banban@gmail.com

OBJECTIVES

I am willing to give total support the organization that I am in, with the experience and capability that
I have, in order to achieve organization’s goals and create mutual benefits.

PERSONAL DATA

Place, date of birth : Hutagalung, October 16, 1982


Marital Status : Married
Hobbies : Writing, Reading, Football and Travelling
Personalities : Honest, responsible and high dedication
Height & Weight : 178 Cm & 80 Kg
Nationality : Indonesian
Language : Indonesia & English

EDUCATIONAL BACKGROUND

University : Uniba, Mechanical Engineering (2014)


Polytechnic : Polytechnic Negeri Medan, Mechanical Engineering (2003)
Senior High School : SMK Swasta Immanuel, Medan (2000)
Junior High School : SMP Swasta Panca Karsa, Medan (1997)
Elementary School : SD Inpres Hutagalung, North Sumatra (1994)
SPECIAL AWARDS

• May 28, 2013


1st winner for Poster competition” Appreciated by TOTAL E&P Indonesie at CPU.

• August 26, 2012


2nd winner for Cermat application” Appreciated by TOTAL E&P Indonesie.

• July 26, 2012


1st winner for Cermat application” Appreciated by TOTAL E&P Indonesie.

• July 26, 2003


“Appreciation Certificate” Appreciated by Politeknik Negeri Medan.

• November 21, 2002


“The 3rd winner of “due like activity” presentation: Conducted by Politeknik Negeri Medan.

ISTRUCTOR/TRAINER

• March 31, 2010


As an instructor of lifting operation by using Crawler Crane
“Conducted by PT.Meindo Elang Indah. (Certified)

• May 20, 2009


As an instructor of lifting operation by using Crawler Crane and Job Risk Assessment / Job Site
Analysis “Conducted by PT.Meindo Elang Indah. (Certified)
Page 2 of 6

TRAINING AND COURSES

• October 26, 2012


Basic first aid Conducted by TOTAL E&P Indonesie. (Certified)

• September 30, 2012 ( 4 years valid)


Basic fire fighting Conducted by TOTAL E&P Indonesie. (Certified)

• August 8, 2012
Risk awareness & prevention Conducted by TOTAL E&P Indonesie. (Certified)

• October 19, 2012


Respect for Environment (Production/ drilling / projects) Conducted by TOTAL E&P Indonesie.
(Certified)

• July 9-13, 2012


Scaffolding inspector Certification Conducted by TOTAL E&P Indonesie. (Certified)

• September 30, 2011


Fire fighting training Conducted by TOTAL E&P Indonesie. (Certified)

• September 29, 2011


HUET & Sea Survival conducted by PT. Bumi Liputan Pusaka. ( 4 years valid) (Certified)

• March 22, 2010


Sea Survival training conducted by INTERCOACH Safety Training. (Certified)

• Juny 20, 2009


Cermat/Anomaly training conducted by PT. Meindo Elang Indah. (Certified)
• March 18, 2009
Basic Safety Training “Conducted by PT. Meindo Elang Indah . (Certified)

• April 12, 2008


“Lifting and Job risk Assessment Training” conducted by PT. Meindo Elang Indah (Instructor is
Mr. Richard Kieller). (Certified)

• June 14, 2007


“Work Permit Training conducted by PT. Meindo Elang Indah, Trainer is Gerick Vincent. (Certified)

• March 16, 2007 – April 18, 2007


“TOEFL Preparation Class” conducted by Perhimpunan Persahabatan Indonesia – Amerika (PPIA).

• February 5, 2007 – March 12, 2007


“English Course Conversation Class” conducted by Perhimpunan Persahabatan Indonesia –
Amerika (PPIA). (Certified)

• May 26, 2001


“Course of Computer” conducted by Lembaga Pendidikan Medan Business Computer. (Certified)

• October 26, 1998 – January 26, 1999


“Pendidikan System Ganda “Organized by Top Car Service in Medan. (Certified)

PROFICIENCY AND SKILLS

• METHOD & PROCEDURES CONSTRUCTION ENGINEERING (ONSHORE AND OFFSHORE)


• INSTRUCTOR ( LIFTING CALCULATION BY USING CRAWLER CRANE & JOB RISK ASSESSMENT)
• ISOMETRIC AND STRUCTURE DRAWING
• AUTOCAD 2D & 3D
• MICROSOFT OFFICE
• MICROSOFT PROJECT
Page 3 of 6

• MICROSOFT POWER POINT-PRESENTATION


• PRECOMMISSIONING
• KNOWLEDGE OF PIPING MATERIALS (PIPES, FITTING, FLANGES, STEEL PROFILES, ETC.) AND CONSUMABLES
(WELDING ROADS, GAS, ETC.) KNOWLEDGE OF THE DIFFERENT MATERIALS TO BE WELDED FOR PIPING AND
STRUCTURAL STEEL, SUCH AS CARBON STEEL, STAINLESS STEEL, DUPLEX, GALVANIZED, ETC. KNOWLEDGE OF
WELDING AND NDT TECHNIQUES, PROCEDURES (E.G., WPS, PQR) AND EQUIPMENT
• KNOWLEDGE OF THE MAIN APPLICABLE INDUSTRY MATERIALS INTERNATIONAL STANDARDS AND CODES (SUCH
AS ASME, API, ASTM AND JIS) AND ABILITY TO ANALYZE CLIENTS SPECIFICATIONS AND STANDARDS.
• KNOWLEDGE OF PIPING/STRUCTURAL BASIC TERMINOLOGY AND RULES
• ABILITY TO MANAGE THE RESOLUTION OF ENGINEERING NON CONFORMITY (NCR) AT SITE SUPPORTING
CONSTRUCTION AND / OR FABRICATION ACTIVITIES EFFECTIVELY INTERFACING PROJECT TEAM, CLIENT AND
VENDOR
• STAAD. PRO V8I

WORK EXPERIENCES

1. 13 March 2021 – 30 April 2021: Field Engineer at PT. Wahana Sarana Jati

Project :Engineering, procurement and Construction (EPC)


OF Lawe-Lawe Facilities
Location : Mahakam area, East Kalimantan, Indonesia RDMP RU-V BALIKPAPAN
Client : Hutama Karya and Pertamina RDMP
Duties & responsibilities:
• Weekly Meeting with Client.
• Technical review of detailed Engineering, construction and installation.
➢ Preparing the Alignment sheet Drawing
➢ Preparing Method statement
➢ Preparing welding map.
➢ Preparing of lifting arrangement on Site.
➢ Prepare all engineering document project

2. January 2020 – September 2020 : Management Representatives at PT. Caleb Technology


Balikpapan Branch
Job & Responsibilities
➢ Internal and external coordination (client)
➢ Searching for tender and others opportunities
➢ Manage all requirement to improve office in Balikpapan
➢ Calculate BOQ for tender
➢ Evaluate tender document
3. April 2018 – December 2019 : Project Manager at PT. Sarana Sealing Indonesia

Job & Responsibilities


➢ Managing budget, HR, and project schedule for 16.623 Dia Inch Piping
➢ Managing and facilitate project planning, daily meeting, reviews, make project related
meetings
➢ Review and make progress report on the project to fit within specified time limits, and
inform project progress to customers and other departments to reduce unwanted risk and
constrain
➢ Understanding process documents as applicable including process descriptions, process
data sheets, PFD, P and ID

4. June 2016 – Maret 2018 : Engineer PT. Bahana Cipta Internusa

Work for TOTAL E&P INDONESIE PROJECT


➢ Checked drawing that prepared by Drafter
➢ Prepare drawing of tank
➢ Prepare work procedure for tank construction
➢ Prepare lifting calculation
➢ Prepare as built drawing
Page 4 of 6

5. December 2014 –February 2015: PWK Senior Supervisor of PT. Inconis


Salvage operation
Departement : Task force of salvage operation
Location : CPU/SPU/NPU (Offshore)
Client : TOTAL E&P INDONESIE
• Duties & responsibilities:
➢ To supervise anchoring job for Barge and AHT
➢ To supervise the salvaging of grounded Liputan 16 Barge
➢ To supervise the salvaging of sunk Danielle Nicole Barge (28-12-14 till 4-2-15)
➢ To check the completeness of marine spread document and personnel
➢ To supervise the diver activities
➢ Responsible for HSSE on the Barge

6. June 2014 – May 2015: PWK Senior Supervisor of PT. Inconis


Structure and Pipelines repair and installation.
Departement : ENG/CST/PWK
Location : CPU/SPU/NPU (Offshore and Onshore)
Client : TOTAL E&P INDONESIE
• Duties & responsibilities:
➢ To conduct tool box meeting and safety talk.
➢ Open and close work permit.
➢ To ensure that the Safety, health and environment are implemented on site.
➢ To ensure the progress of project is running according to approved schedules
➢ Supervising and ensuring that all construction is executed based on Approved engineering
drawing and procedure.
➢ Check of CTR work permit and meeting permit with FO (CPU and SPU)
➢ Coordination with other entity
➢ Coordination with PWK field supervisor
➢ To supervise and Check Crane Anchor Barge position based on approved Anchor Barge
Drawing
➢ Check the completeness of the Tug boat Crews
➢ Responsible for HSSE on the Barge

7. October 2011 – May 2014: PWK Senior Supervisor of Kopkar Sucofindo/PT. Birutiga Utama
Structure and Pipelines repair and installation.
Departement : ENG/CST/PWK
Location : Handil/CPU/SPU (Offshore and Onshore)
Client : TOTAL E&P INDONESIE
• Duties & responsibilities:
➢ To conduct tool box meeting and safety talk.
➢ Open and close work permit.
➢ To ensure that the Safety, health and environment are implemented on site.
➢ To ensure the progress of project is running according to approved schedules
➢ Supervising and ensuring that all construction is executed based on Approved engineering
drawing and procedure.
➢ Check of CTR work permit and meeting permit with FO (CPU and SPU)
➢ Coordination with other entity
➢ Coordination with PWK filed supervisor
➢ Check Crane Anchor Barge position based on approved Anchor Barge Drawing
➢ Check the completeness of the Tug boat Crews
➢ Responsible for HSSE on the Barge

8. October 2010 – October 2011: PWK Supervisor of PT. Supraco


Structure and Pipelines repair and installation.
Departement : ENG/CST/PWK
Location : Handil (Onshore)
Client : TOTAL E&P INDONESIE
• Duties & responsibilities:
Page 5 of 6

➢ To conduct tool box meeting and safety talk.


➢ Open and close work permit.
➢ To ensure that the Safety, health and environment are implemented on site.
➢ To ensure the progress of project is running according to approved schedules
➢ Supervising and ensuring that all construction is executed based on Approved engineering
drawing.
➢ Responsible for HSSE on the Barge

9. November 2009 – September 2010: Piping Precommissioning Staff of PT. Meindo Elang Indah
Structure and Piping installation to existing facilities (Tie In works)
Project : Peciko 7 – EPC 1
Location : BSP Peciko 7 Area
Client : TOTAL E&P INDONESIE
• Precommissioning
➢ Prepare test package document, flushing, hydrotest, draining & drying, Gross leak test and
reinstatement.

10. June 2009 – October 2009: Site Engineer of PT. Meindo Elang Indah
The Engineering, Procurement, Supply, Handil 12” Pipeline river crossing replacement and
installation to existing facilities (Tie In works)
Project : Handil 12” Pipeline River Crossing Replacement Contract No. 4500006619
Location : Mahakam area, East Kalimantan, Indonesia (offshore)
Client : TOTAL PWK/ENG.
Duties & responsibilities:
• Weekly Meeting with Client.
• Technical review of detailed Engineering, construction and installation.
➢ Preparing the Pipeline Isometric Drawing
➢ Preparing the Structure Drawing
➢ To prepare anchoring position drawing
➢ Preparing of procedures and other technical documentation.
➢ Preparing of Job Site Analysis/Job Risk assessment.
➢ Preparing of lifting arrangement on Site.
➢ Ensuring that the pipeline is installed is as per Engineering design drawing.
➢ Preparing the as built drawing.

11. April 2008 – May 2009: Site Engineer of PT. Meindo Elang Indah
The Engineering, Procurement, Supply and Construction of Hook up/interface installation and
Connection to Existing Facilities (Tie In)
Project : Tunu Field Development Project – Phase 11 Contract TP11S / EPSC3
Location : Mahakam area, East Kalimantan, Indonesia (offshore)
Client : TOTAL E&P INDONESIE

Duties & responsibilities:


• Technical review of detailed Engineering, construction and installation.
➢ Preparing of procedures and other technical documentation.
➢ Preparing Job Site Analysis/Job Risk assessment.
➢ Preparing the Structure Drawing.
➢ Prepare Barge positioning drawing
➢ Preparing of lifting arrangement on onshore and Site.
➢ Ensuring that the construction on site is as per Engineering design drawing.
➢ Preparing the as built drawing.

12. April 2007 – March 2008 : Method Engineer of PT. Meindo Elang Indah
The Engineering, Procurement, Supply and Construction, Sand backfilling in swampy area,
permanent Jetty and Pipeline Connection to Existing Facilities (Early Tie In)
Project : Tunu Field Development Project – Phase 11 Contract TP11S / EPSC7
Location : Mahakam area, East Kalimantan, Indonesia
Client : TOTAL E&P INDONESIE
Page 6 of 6

Duties & responsibilities:


• Technical review of detailed Engineering, construction and installation.
➢ Preparing of procedures and other technical documentation.
➢ Preparing of Job Site Analysis/Job Risk assessment.
➢ Preparing of anchoring drawing layout for work Barge.
➢ Preparing of shop drawing of GTS X Etip-1 Platform.
➢ Ensuring that the construction of permanent Jetty is as per Engineering design drawing.

13. September 2005 – December 2006: Ass. Method & Procedure Const. Engineering of PT.
Kaliraya Sari
The Engineering, Procurement, Supply and Construction of GTS’s and Connection to Existing
Facilities
Project : Tunu Field Development Project –Contract TP10 / EPSC
Location : Mahakam area, East Kalimantan, Indonesia (offshore and Onshore)
Client : TOTAL E&P INDONESIE

Duties & responsibilities:


• Technical review of detailed Engineering, construction and installation.
➢ Preparing of Job Site Analysis/Job Risk assessment.
➢ Preparing of procedures lifting arrangement and lifting plan on yard (onshore) and site.
• As team of Load Out, Sea Fastening, and GTS deck Installation, i.e. GTS Ax, GTS Kx, GTS Lx, and
GTS Ix.

I certified that, to the best of my knowledge and belief, my curriculum vitae is correctly described.

Best regards,

BANBAN SITINJAK, ST
0821 5548 0810
WORK EXPEREINCED
TRAINING CERTIFICATES
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

TEPI WASTE MANAGEMENT

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-27759


Completion Date : 05 October 2015
Valid Until : October 2019
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

SHALLOW GAS INTRODUCTION

Head of Well Construction Divsion

Certificate Number : WCI/WLC/SGEL/15-24650


Completion Date : 12 September 2015
Valid Until : September 2020
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

SOP 06-301 PERSONAL PROTECTIVE EQUIPMENT

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-11286


Completion Date : 03 December 2014
Valid Until : December 2018
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

SOP 06-301 PERSONAL PROTECTIVE EQUIPMENT

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-11286


Completion Date : 03 December 2014
Valid Until : December 2018
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

SOP 06-610 MCU & FITNESS TO WORK

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-11293


Completion Date : 03 December 2014
Valid Until : December 2018
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

MAESTRO MODULE #1 (GENERAL OVERVIEW)

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-00162


Completion Date : 13 December 2014
Valid Until : December 2018
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

HAND AND PORTABLE POWER TOOLS

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-23641


Completion Date : 05 September 2015
Valid Until : September 2019
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

SOP 03-004 ENTRY INTO CONFINED SPACES

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-11291


Completion Date : 03 December 2014
Valid Until : December 2018
CERTIFICATE OF COMPLETION
This is to certify that
Banban SITINJAK

Has completed and passed the online training module

SOP 10-101 CERMAT REPORTING

Head of Health, Safety, and Environment (HSE) Division

Certificate Number : HSE/SPLMS/2012-15552


Completion Date : 09 February 2015
Valid Until : February 2019