INSPECTION PHASE 4
Date: _______________
Registration Number: _______________
1. Description
A. Phase 4 consists of selected items to be inspected every 150-hours and 300-hours or 24 calendar
months, whichever occurs first. NOTE: 150 hour items are also listed in Phase B. When performing
Phases 1 through 4 as one operation, duplicated items do not need to be performed twice.
B. Inspection items are given in the sequence of the zone in which the inspection is completed. A
description of the inspection, as well as the Item Code Number are supplied for cross-reference to
section 5-10-01. Frequently, tasks give more information about each inspection. These tasks are
found in the individual chapters of this manual.
C. The right portion of each page gives space for the mechanic's and inspector's initials and remarks.
You can use copies of these pages as a checklist while you complete the tasks in this Inspection
Phase.
2. General Inspection Criteria
A. As you complete each of the inspection tasks in this Inspection Phase, examine the adjacent area
while access is available to find conditions that need more maintenance.
B. If it is necessary to replace a component or to make a change to a system while you complete a
task, do the task again before the system or component is returned to service.
C. (Phase) Inspection Kits are available for some Inspection Phase Documents. They supply
consumable materials used to complete the inspection item(s) given for the interval. Refer to the
Model 500 Illustrated Parts Catalog, Introduction, Phase Inspection Kit List to find applicable part
numbers.
B211003 Flow Control Shutoff and Check Valves - Perform oper- ENG
ational test (Parker Hannifin/Janitrol Check valves that
have a serial number lower than 4AD39 and that do not
have a serial number suffix B). Task 21-10-00-711
B324006 Main Gear Wheel Brakes - Check wear, refer to vendor 720, 730
manual for criteria. Task 32-40-00-212
D361001 Bleed air peri-seals connectors - Replace the peri-seals 410, 420
in the connectors immediately downstream from the en-
gine bleed air ports. Task 36-10-00-900
A361001 Bleed Air Flexible Connector - Perform Detailed Inspec- 410, 420
tion Task 36-10-00-220
C783001 Thrust Reverser Pivot Points Lubrication (WC-393 Non- 410, 420
Aerosol Spray Lubrication Method) Task 78-30-00-640
B783002 Thrust Reversers - Perform operational test. Task 78-30- AUX, 311,
00-710 312
C783002 Lubricate the Thrust Reverser Guide Rods (D-5100NS 410, 420
Aerosol Spray Lubrication Method) Task 78-30-00-641