Download as pdf or txt
Download as pdf or txt
You are on page 1of 276

 

SPECIFICATIONS  
FOR 
Construction of Interior work at NBCC Centre 
3rd floor, OKHLA, New Delhi 
 
(SECTION B&C) 

CLIENT 
 
 
 
 
 
 
Pharmacy Council of India 
Combined Councils Building 
Kotla Road,    
Aiwan‐E‐Ghalib Marg 
NEW DELHI‐110002 

Project Management and Construction
 
 
NSL 
2nd Floor, Local Shopping Centre, 
East Kidwai Nagar,  
New Delhi 110023 
 
SPECIFCATIONS: Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi

 
 

INDEX 
 
 
 
 
 
1. SECTION B : SPECIFICATIONS 
a. SECTION B1: SPECIFICATIONS INTERIOR WORKS 
b. SECTION B2: SPECIFICATIONS ELECTRICAL WORKS 
c. SECTION B3: SPECIFICATIONS HVAC 
d. SECTION B4: SPECIFICATIONS FIRE AND PLUMBING WORKS 
2. SECTION C: LIST OF APPROVED MAKES 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

NSL 
PMC CONSULTANT     
SPECIFCATIONS: Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi

 
 
 
 
 
 
 
 
 
SECTION‐B 
 
SPECIFICATIONS 
FOR THE  
Construction of Interior work at NBCC Centre 
3rd floor, OKHLA, New Delhi  
 
 
 
 
 
 
 

NSL 
PMC CONSULTANT     
SPECIFCATIONS: Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi

 
 
 
 

SPECIFICATIONS COMMON FOR ALL SECTIONS 
 
The work in general shall be carried out as per CPWD Specifications, for Civil work 
specifications 2016 shall be followed and for electrical work CPWD specifications 2016 
shall be followed with latest amendments along with relevant IS codes with latest 
amendments. Where the same are not applicable the work shall be carried out as per 
specifications mentioned in this volume with best engineering practice in the industry. 
This is applicable for all type of work covered in the scope of this contract whether it is 
interior, civil, electrical, furniture,CCTV, Access Control, BMS, HVAC, IT, Networking 
firefighting, EPBAX etc. etc. 

NSL 
PMC CONSULTANT     
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
 
       
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

SPECIFICATIONS FOR INTERIOR WORKS 
SECTION B1 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

NSL 
PMC CONSULTANT A1
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
 
 
Technical Specifications ‐ Interior Work 
 
    PREAMBLE TO BILL OF QUANTITIES 
 
RATES TO INCLUDE:  
Rates quoted shall be for the items completed in all respect at all floors/heights/levels including all 
taxes,  octroi, duties and levies transportation, loading and unloading  and the cost of all materials, 
fittings,  fixtures,  all  labour  for  all  the  operations  as  detailed  in  the    specifications  and  contract 
conditions. Apart from other factors mentioned in the specifications and contract conditions, rates 
quoted for the items in this schedule shall also include the following:  
 
1. GENERAL:  
1.1 Whether mentioned or not in the Bill of Quantities, all works are to be carried out as per the 
drawings, designs, catalogues and or instructions of NBCC Engineer‐IN‐Charge of the work. Nothing 
extra shall be paid over the quoted rates for not understanding the designs etc. before hand.  
1.2 Sample of all works/items shall be got approved from the Engineer in Charge before taking the 
mass production in hand and nothing shall be paid for the cost of samples.  
1.3 Any incidental work required to complete the item and not specifically covered in the item as 
mentioned in Bill of Quantities shall be completed at no extra cost.  
1.4  Unless  otherwise  specified  all  exposed  surfaces  of  wood/wooden  mouldings  and  plywood  of 
loose  furniture/items  tops  shall  be  finished  in  at  least  two  coats  of  melamine  polish,  including 
staining to match the shades of laminates etc.  
1.5  Rates  for  carpeting  shall  include  for  fixing  of  Aluminium  grippers  over  the  junction  of  carpet 
and/or marble stone flooring.  
1.6 All laminates for furniture items shall be 1.0 mm thick in Satin finish, colour texture and shade 
as per the schemes given by the Architects.  
1.7  Unless  otherwise  specified,  all  inner  surfaces,  sides  and  under  sides  of  furniture  items, 
drawers/cabinets shall be polished/Painted flat oil painted as directed by Architects.  
1.8  All  exposed  edges  of  plywood/block  boards  shall  be  finished  with  teak  wood  lippings  5  mm 
thick of profile as per  detail and Melamine polished unless  otherwise specified and no extra cost 
shall be paid.  
1.9 All furniture items shall be delivered at site packed in polythene sheets. 
1.10: All the  necessary approvals to be taken before the start of the work 
1.11 All approvals taken in one go, and not in piece meal 
1.12  Articles which has high lead time of delivery has to be given priority and necessary approval 
to be taken within 15 days of award of work. To avoid any delay in project. 
1.13  Furniture will be approved only after mock‐up 
1.14 Contractor has to furnish shop drawing and take necessary approval from Engineer in charge, 
before starting the work 
1.15  Its  responsibility  of  Contractor  to  take  necessary  approval  and  has  to  furnish  the  approvals 
received from from NBCC, of articles used, during or after the construction, as and when asked 
1.17    any  deviation  in  quantity  and    new  item/substitute  has  to  be  notified  well  in  advance,  and 
necessary approval to be taken from the competent authority 
1.18  After  the  award  of  the  work,  appointed  contractors,  has  to  submit,  details  of  deadline  and 
time line and has to adhere to it, for approvals and completions of the project. 
1.19  Contractor  will  submit  weekly  report  on  project,  on  work  completed  in  previous  week  and 
work which will be done in the next week 

NSL 
PMC CONSULTANT A2
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
 
 
2. WOOD WORKS:  
2.1 Wherever ply is mentioned it will mean ply wood.  
2.2 All Board/Ply will be of BWP Type.  
 
3. HARDWARE:  
3.1  Necessary  handles,  tower  bolts,  ball  catchers,  stoppers,  hinges,  brass/GI  screws,  nails,  locks, 
sliding  rails,  nut  and  bolts  etc.  shall  be  provided  by  the  Contractor  which  shall  be  out  of  the  
approved make of these materials annexed in the technical specifications/approved by Architects. 
  
4. PAINTING AND PO LISHING:  
4.1  All  finishes,  shade  of  colours,  texture  of  fabrics  including  all  surfaces  of  finishes  like  POP, 
painting,  lamination,  panelling,  stitching  joints  in  upholstery,  all  polishing  shall  be  as  per  the 
satisfaction of the Architects/Engineer in Charge 
4.2  Thoroughly  brushing  the surface  to  be  finished,  free  from  mortar  dropping  and  other  foreign 
matter including preparing the surface and sand papering to give an even surface.  
4.3 For painting and polishing items – on all kinds of wood and wood based surfaces 
4.4 All painting work to be completed with at least one coat of the primer along with two or more 
coats of the  paint as per the Technical Specification, till desired finish is achieved, Manufacturer’s 
specification and to the satisfaction of the  Architects/ Engineer in Charge.  
4.5 All the polishing works to be completed with at least two coats of the polish of the approved 
make  as  pr  the  list  of  approved  manufacturers  and  to  the  full  satisfaction  of  the  Architects/ 
Engineer in Charge.  
 
5. GLASS WORKS:  
5.1  The  edges  of  glass  tops  for  tables  wherever  shown  shall  be  beveled  as  per  approval  of  the 
Architects.  
6.1  Rates  shall  include  Aluminium  grippers  as  directed.  Rates  shall  include  laying  of  carpet  to 
required shape with piles in one direction including all wastage, Rate quoted shall be applicable to 
skirting and steps and net area of laid carpet only shall be measured and paid.  
 
6. FALSE CEILING 
 
6.1 Gypboard and G.I. Framework 
 
6.1.1 Scope of work 
 
The work envisaged under these specifications refer to supplying and fixing in position false ceiling 
at any floor, any location and at any height. 
 
a)  Providing and fixing suspended G.I. frame work of specified width as mentioned in 
drawings 
 
b)  Providing and fixing one layer of 12.5 mm gypboard over this frame work. 
 
c)  Jointing the board flush, applying two coats of primer suitable for gypboard and two 
coats of acrylic emulation matt finish paint of approved shade and make. 
 

NSL 
PMC CONSULTANT A3
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
d)  Making necessary cut out for light fitting, A.C. grills diffusers and other necessities. 
The work shall include horizontal, vertical and inclined surfaces depending upon the 
various requirements. 
 
6.1.2 Material 
 
G.I. Frame work: 
 
The system consists of G.I. frame work suspended from the soffit of the RCC ceiling. The following 
G.I. components shall be used for grid work (or) as specified in the drawing. 
 
1.  Ceiling section of 80X26X0.5 mm 
2.  Perimeter channel of 20X27X20X0.5mm 
3.  Intermediate channels of 15X45X0.9mm 
4.  Ceiling angel of 25X10X0.55mm 
5.  Connecting clips of 2.64 mm dia. 
6.  Soffit cleat 22X37mm 
7.  Anchor fasteners 6 mm 
 
All the G.I. components shall be of standard approved make. 
The G.I. grid work system shall be suspended from the soffit of RCC ceiling using anchor fasteners 
of 6mm of approved type and make and connected to soffit cleats and ceiling angle by means of 
necessary nuts, bolts and washers etc. 
 
Gyp Board 
 
Gyp  Board  of  plain  series  12.5  mm  manufactured  by  India  gypsum  shall  be  used.  The  Gyp  board 
shall conform to IS 2095. The longitudinal edge of the Gyp board shall be of tapered / square edges, 
so  as  to  have  flush  joints  while  fixing.  Handling  and  transporting  of  Gyp  board  shall  be  done 
carefully and as recommended by the manufactures. The board should always be kept in a dry an d 
covered place sheltered from rain and to avoid dampness from flow, they should be supported on 
wooden battens which should not be more than 45cm apart on a flat surface. The material shall be 
stacked  in  piles  of  smaller  heights  and  should  not  be  stacked  on  edges.  Gyp  board  which  have 
deformed due to poor stacking should not be used. 
 
Insulation  
 
Perimeter channels are levelled at the required position of the finished ceiling line and fixed to the 
wall  at  610  mm  centre  with  the  screws  and  nylon  plugs.  The  remaining  G.I.  grid  component  are 
installed to form a regular grid suspended from the soffit of RCC slab using soffit cleats ceiling angle 
and anchor fasteners as specified. Extra frame for various cut outs of different shapes, light fittings, 
AC grills, diffusers, smoke detectors and other necessities have to be provided frame work has to 
be made with perimeter channel of specified size and shall be suitably supported. The line and level 
of  the grid work  has  to  be  checked  for  perfection  and  prior clearance of  the  grid work  has  to  be 
checked for perfection and prior clearance of the grid work has to be obtained from the Engineer‐
in‐charge before the placement of Gyp board. 
 
The Gyp board are fixed with bound edges at right angles to ceiling section with all joints staggered. 
All joints of Gyp board has to be fixed on ceiling section. The Gyp boards are screwed to the ceiling 

NSL 
PMC CONSULTANT A4
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
section and perimeter channels with Gyp board dry wall screws with joints staggered. Spotting of 
screws  and  jointing  are  then  carried  out  according  to  India  Gypsum  recommendations  to  give  a 
flush and smooth joint.  
 
Necessary door openings of hinged type of suitable sizes has to be provided with a suitable frame 
work for control valves and for access above false ceiling / AC duct boxing at not extra cost. Joints 
at horizontal, vertical and inclined surfaces shall be suitably strengthened with additional G.I. frame 
work as required. 
 
Finally the boards are jointed and finished so as to have a flush look which includes fling and finish 
gin the tapered and square edges of the board with a jointing compound, paper tape and two coats 
of primer suitable for gyp board (all as per recommended practices of Indian Gypsum). Then, the 
finished Gyp board has to be painted with 2 coats of acrylic emulsion matt finish paint of approved 
color and make. 
 
The  rate  shall  includes  providing  all  materials,  erecting,  suspending,  G.I.  grid  work,  jointing  the 
boards, providing required cut outs and open able doors and painting including providing necessary 
fittings  and  fixtures  etc.  complete  as  per  the  specifications  and  all  other  activities  related  to  the 
completion of the above job. 
 
Details of A.C. grills, diffusers, recessed type electrical fittings to be erected in false ceiling will be as 
per specifications and as shown in drawings.  
 
The scope of works includes fixing with screws, fixtures etc. the recessed electrical light fittings in 
the grid work of false ceiling/ boxing, Marine plywood (6mm thick)/special G.I. sections, if required, 
shall  also  be  provided  at  no  extra  cost.  The  rate  quoted  shall  include  all  the  above  mentioned 
activities related to the completion of the above job. 
 
6.2 Grid Ceiling (Gypsum anhydrous Ceiling)  
 
The false ceiling mainly will be consisting of 2’ – 0” x 2’ – 0” grid system. To avoid partial grid (less 
than  2’  –  0”  x  2’  –  0”)  at  the  ends,  a  band  of  uniform  size  Gypsum  Board  false  ceiling  may  be 
provided along the periphery. The size of the  
 
6.3 Mineral Fiber tile false ceiling 
 
False  ceiling  tiles  will  be  of  Fine  Fissured  type  High  NRC  tiles  of size  595  x  595mm  and  minimum 
15mm  thick  manufactured  from  high  density  Glass  wool  with  the  visible  surface  be  batch  pre 
painted.  The  system  should  have  sound  Absorption  NRC  value  of  0.7  .Tiles  should  withstand  a 
permanent ambient RH up to 95% without sagging, The light reflectance of the tiles should not be 
less  than  83%.Providing  and  fixing pre  coated (Exposed  portion  only)  Grid  system  in  600x600mm 
module which includes providing and fixing wall angle along the perimeter of the room with help of 
nylon sleeves and wooden screws at 300mm centers. Then suspending the main tee of size from 
the soffit with help of soffit deat,rawl plugs and wire rod with Leveling spring dip at 1200mm c/c. 
1200mm Cross Tee is then interlocked into the pre‐Cut slots in the main Tees at 600mm centres in 
direction perpendicular to the main Tee to make a grid of 600x1200mm.Finally 600mm Cross tees 
are  then  interlocked  into  the  pre‐cut  slots  in  to  the  1200mm  tees  at  1200mm  centres  and  in 
direction parallel to the main tee. Cross Tees having length more than 600mm are to be supported 
independently. Tiles of size 595x595mm shall be placed into the grid size. 

NSL 
PMC CONSULTANT A5
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
 
7. PARTITIONS AND PANELLING  
7.1  Quoted  rate  shall  include  labour/materials  required  to  fix  the  sub‐frame  to  the  wall  with  GI 
Sections  (‘L’/  ‘U’)  shape  clamp  with  adequate  screws  and  repairing  the  portion  damaged  while 
putting the gutties. etc. and making good the same.  
7.2 Quoted rate shall be inclusive of making provisions for electrical conduits and switch boxes and 
time required while coordinating with other Contractors for the final finishing of the work.  
7.3  The  partition  frame  work  shall  be  provided  upto  the  RCC  slabs  at  top  but  measurement  for 
payment shall be of partition upto false ceiling and frame /support of partition above false ceiling 
shall be carried out within the quoted rate for which no extra shall be paid.  
7.4  All  electrical  works  shall  be  got  carried  out  through  licensed  “A”  class  Electrical  Contractor 
having experience of similar work and duly approved by Architects/ Engineer in Charge. The work 
shall be executed as per specifications and strictly in keeping with relevant IS code and rules and 
regulations of authorities.  
7.5 All work/materials will be as per good engineering practice.  
7.6 Wherever glass is mentioned it will be clear float glass.  
7.7 Glass wool of Twiga make of 50mm thk of density 32Kg/cubic meter to be used between in 75 
mm thk partition and 100 mm thk glass wool for 125 mm partition 
 
8. WOOD WORK AND JOINERY:  
8.1 PLY WOOD:  
Ply wood shall be BWP quality phenol bonded as per relevant Indian Standard Specifications with 
commercial or decorative facing as required. These shall be obtained from approved sources and 
thickness shall be as shown in drawings.  
8.2 BLOCK BOARDS:  
Block  board  shall  be  Grade‐I  exterior  grade  bonded  with  BWP  type  synthetic  phenol  bonded 
adhesives. These shall be of the required thickness and type and obtained from approved sources. 
8.3 LAMINATE (ESD Electrostatic Dissipative laminate):  
Laminates  where  specified  shall  be  of  approved  brand  type,  texture  and  thickness  and 
manufacturer as per IS:2046‐95.  
Fixing of laminates shall be done as per best trade practices and strictly as per printed instructions 
of  the  manufacturers  using  phenol  Formaldehyde  Synthetic  Resin  adhesive  of  approved  make. 
Unless otherwise indicated laminated shall be 1.5 mm thick of approved make. 
Laminates property  
  
8.4 JOINERY:  
All  details  shall  conform  to  the  drawings,  but  all  measurements  shall  be  checked  at  site.  The 
scantlings  shall  be  accurately  planned  and  finished  smooth  to  hold  full  dimensions  shown  in  the 
drawings after finishing and rebates, rounding’s and mouldings made before they are framed. No 
patching  or  plugging  of  any  kind  shall  be  prepared  and  got  approved  by  the  Engineer  before 
proceeding with bulk manufacture.  
 
9. IRONMONGERY:  
 
9.1  This  section  shall  cover  all  finish  hardware,  latches,  locks  and  other  fittings  and  fixtures  etc., 
used  in  wood  doors.  All  finish  hardware  shall  be  well  made,  reasonably  smooth,  and  free  sharp 
edges  and  corners  flaws  and  other  defects  and  shall  be  as  per  relevant  Indian  Standard  Code. 
Unless otherwise required all finish hardware shall be polished brass.  

NSL 
PMC CONSULTANT A6
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
9.2 All hardware shall be of approved make and shall be specifically got approved by the Engineer 
before  ordering.  No  fittings  and  fixtures  shall  be  fixed  before  all  major  work  is  over.  While  fixing 
correct handling of fixtures shall be ensured.  
9.3 All finish hardware shall be fixed by skilled carpenters experienced in this work. Work shall be 
done as per manufacturer’s printed instructions and to the satisfaction of the Engineer.  
9.4  All  hardware  fixed  to  respective  locations  shall  be  adequately  protected  from  damage  and 
splashes of mortars and paints by covering suitably with Jute clothes/Black PVC sheet till handling 
over  of  the  work  to  the  Engineer/Owner  to  his  satisfaction.  The  finished  hardware  shall  be 
absolutely clean without any foreign materials and fully showing original finish in its best condition.  
 
 
 
 
10. Vitrified Tile Flooring, Dado / Skirting / Facia 
 
Materials: 
 
Vitrified Tiles: The tiles shall be of approved make as mentioned in the approved makes and shall 
generally  conform  to  the  approved  standards.  They  shall  be  flat  and  true  to  shape,  free  from 
cracks, crazing spots, chipped edges and corners. Unless otherwise specified, the nominal sizes of 
tiles shall be as under: 
 
The tiles shall be square or rectangular of nominal sizes such as: 600 x 600 mm; 800 x 800 mm or 
drawings or as directed by the Engineer‐in‐ Charge. Thickness shall be as per recommendations of 
the approved manufacturers. 
 
Technical specifications of the tiles shall be generally conforming to the following standards: 
 
Technical Specifications for Glazed Vitrified Tiles/Digital 
 
NO  PROPERTY   EXPECTED STANDARDS 
1.   Deviation in length   (+/‐) 0.6% 
2.   Straightness of sides   (+/‐) 0.5% 
3.   Rectangularity   (+/‐) 0.6% 
4.   Surface flatness   (+/‐) 0.5% 
5.   Water absorption   < 0.50% 
6.   Mohs. Hardness   > 6 
7.   Flexural strength   > 27 N / mm2 
8.  Abrasion resistance   Class V 
9.  Skid resistance (friction coefficient)  > 0.4
10.  Glossiness   Min. 85% reflections 
 
The  tiles  shall  conform  to  the  relevant  standards  in  all  respects.  Samples  of  tiles  shall  be  got 
approved from the Engineer‐in‐charge before bulk procurement for incorporation in the work. 
 
Preparation of Surface for Flooring: 
 
Following procedure shall be followed: 
 

NSL 
PMC CONSULTANT A7
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
Sub grade concrete or RCC slab or side brick wall / or plastered surfaces on which tiles are to be laid 
shall be cleaned, wetted and mopped. 
 
Mortar and bedding: Cement mortar for bedding shall be prepared of mix 1:4, to a consistent paste 
and  shall  conform  to  the  specification  for  materials;  preparations  etc.  as  specified  under  cement 
mortar.  The  amount  of  water  added  while  preparing  mortar  shall  be  the  minimum  necessary  to 
give sufficient plasticity for laying. Care shall be taken in preparation of the mortar to ensure that 
there are no hard lumps that would interfere with even bedding of the tiles. Before spreading the 
mortar  bed  the  base  shall  be  cleaned  off  all  dirt,  scum  or  laitance  and  loose  materials  and  well 
wetted without forming any pools of water on the surface. The mortar of specified proportion and 
thickness  shall  then  be  evenly  and  smoothly  spread  over  the  base  by  use  of  screed  battens  to 
proper level or slope. 
 
Once the mix is prepared, no further water be added and the same shall be used within one hour of 
adding water. Apply on an average 20 mm thick bedding of mortar over an area of 1 sqm. at a time 
over surface of the area for laying tiles, in proper level and allowed to harden sufficiently to offer a 
fairly good cushion for the tiles to set. 
 
Laying of Tiles for Flooring: 
 
The  tiling  work  shall  be  done  as  per  the  pattern  shown  in  the  drawing  or  as  directed  by  the 
Engineer‐in‐Charge. As a general practice laying of tiles shall be commenced from the centre of the 
area and advanced towards the walls. Cut tiles, if any, shall be laid along wall with necessary border 
pattern as shown / directed by the Engineer‐in‐ Charge. Tiling work shall be completed by pressing 
tiles  firmly  into  place  along  the  wall  /  floor.  A  white  cement  slurry  to  the  back  of  the  tile  to  be 
applied to ensure proper and full bedding. The tiles shall be laid on the bedding mortar when it is 
still plastic but has become sufficiently stiff to offer a fairly firm cushion for the tiles. 
 
Tiles, which are fixed on the flooring adjoining the wall, shall be so arranged that the surface on the 
round edge tiles shall correspond to the skirting or dado. Press gently the tile with wooden mallet 
for even adherence at the back of the tile. Do not use an iron hammer or some heavy material to 
press the tile. 
 
The edges of the tiles shall be smeared with neat white cement slurry and fixed in this grout one 
after  the  other,  each  tile  being  well  pressed  and  gently  tapped  with  a  wooden  mallet  till  it  is 
properly bedded and in level with the adjoining tiles. There shall be no hollows in bed or joints. The 
joints  shall  be  kept  as  close  as  possible  and  in  straight  line.  Unless  otherwise  specified,  joint‐less 
tiling shall be done butting the tiles with each other. If joint is specified, the same shall not exceed 
1.00  mm.  in  width.  The  joint  shall  be  grouted  with  white  /  matching  colour  cement  slurry.  After 
fixing the tiles, finally  in an even plane or slope, the flooring shall be covered with wet sand and 
allowed undisturbed for 14 days. 
 
Fixing Tiles for Dado & Skirting / Facia: 
 
The fixing of tiles on wall surfaces shall be done only after completing fixing of the tiles on the floor. 
Following procedure shall be followed: 
 
The  back  of  tiles  shall  be  cleaned  off  and  covered  with  layer  of  approved  adhesive  with  proper 
toweling as per manufacturer’s recommendations. 

NSL 
PMC CONSULTANT A8
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
 
The edges of the tiles shall be smeared with the adhesive and fixed on the wall one after the other, 
each tile being well pressed and gently tapped with a wooden mallet till it is properly fixed in level 
with  the  adjoining  tiles.  There  shall  be  no  hollows  on  the  back  or  in  joints.  Unless  otherwise 
specified,  joint‐less  tiling  shall  be  done  butting  the  tiles  with  each  other.  If  joint  is  specified,  the 
same shall not exceed 1.00 mm. in width. The joint shall be grouted with approved adhesive. The 
joints shall be kept in straight line or as per the approved pattern. 
 
While fixing tiles in dado / skirting work, care shall be taken to break the joints vertically. The top 
line  shall  be  touched  up  neatly  with  the  rest  of  the  plaster  above.  If  doors,  windows  or  other 
openings are located within the dado area, the corners, sills, jambs etc. shall be provided with true 
right  angles  without  any  specials.  The  contractor  will  not  be  entitled  to  any  extra  claims  on  this 
account for cutting of tiles if required. 
 
The fixing shall be done from bottom of wall to upward without  any hollows in the bed of joints. 
Each tile shall be as close as possible to one adjoining. All tiles faces shall be in one vertical plane. 
 
Grouting of Joints in Floor / Skirting / Dado: 
 
The  joints,  if  specified,  shall  be  cleaned  off  and  all  dust  and  loose  particles  removed.  Joints  shall 
then  be  filled  with  approved  adhesive  like  BAL‐ENDURA  or  equivalent  grouts.  After  finishing  the 
grouting process, after 15 minute, wipe off excess grout with a damp sponge and polish the tiles 
with a soft & dry cloth for a clean surface. 
 
The Finished work shall not sound hollow when tapped with a wooden mallet. 
 
Cleaning: 
 
As  directed  by  the  Engineer‐in‐Charge,  the  tiles  shall  be  cleaned  by  mild  acid  (However, 
Hydrofluoric acid and its derivatives should not be used). After the tiles have been laid in a room or 
the days fixing work is completed, the surplus cement grout / adhesive that may have come out of 
the joints shall be cleaned off before it sets. The dado / skirting shall be thoroughly cleaned. In the 
case of flooring, once the floor has set, the floor shall be carefully washed clean and dried. When 
drying,  the  floor  shall  be  covered  with  oil  free  dry  sawdust.  It  shall  be  removed  only  after 
completion of the construction work and just before the floor is used. 
 
Cleaning Agents for Vitrified Tiles: 
 
Vitrified  tiles  are  resistant  to  all  chemicals  (except  hydrofluoric  acid  and  its  derivatives),  hence 
commercially available detergents and cleaning agents can also be used for regular maintenance. 
Any spills and stains must be removed immediately. If left dry they may leave stains, which may be 
difficult to remove completely. 
 
 

NSL 
PMC CONSULTANT A9
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
 
11. GRANITE SLAB FLOORING AND CLADDING 
 
11.1 General 
 
11.1.1 Description 
 
This section covers the requirements for providing and fixing of granite stone to external walls of 
buildings including pins, cramps and filling of joints with mortar. 
 
11.1.2 Applicable Codes and Standards 
 
The codes and standards generally applicable to the work of this section are listed herein after :‐ 
 
IS:757  Wrought  Aluminium  and  Aluminium  Alloys,  sheet  and  stripe  (for  general  engineering 
purposes) 
IS:4101 Stone Facing – Part‐I 
 
The following clauses are intended to amplify the requirements of the reference documents listed 
above and the contractor shall comply with these clauses. 
 
11.2 Materials 
 
11.2.1 Granite Stone Slabs 
 
The slabs shall be of the required colour and shade and of textures as description of the item. The 
stone  slabs  shall  be  hard,  sound,  durable  and  tough,  free  from  cracks,  decay  and  weathering. 
Before  starting  the  work  the  contractor  shall  get  the  samples  of  stone  slabs  approved  by  the 
Engineer‐in‐Charge. 
 
The stone slabs shall be machine cut to the requisite thickness along planes parallel to the natural 
bed  of  the  stone  and  shall  be  of  uniform  size  if  required.  The  thickness  of  the  slabs  shall  be 
minimum 35 mm or as specified in the description of the item with a permissible tolerance of +3 
percent. 
 
11.2.2 Mortar 
 
Mortar for (fixing and filling of joints hall be as specified. 
 
11.2.3 Pins 
 
Pins shall be of gunmetal 35 mm long and 6 mm diameter or as specified. Their samples shall be got 
approved by the Engineer‐in‐Charge and kept at site. 
 
11.2.4 Cramps 
 
The material of cramps shall have high resistance to corrosion under conditions of dampness and 
against the chemical action of mortar of concrete. The cramps shall be of the material specified in 
the item of work. 

NSL 
PMC CONSULTANT A 10
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
 
11.3 Laying 
 
The stone slabs shall be fixed with mortar in position without the use of chips or underpinning of 
any  sort.  Where  so  desired,  the  adjoining  stones  shall  be  secured  by  means  of  pins.  Further  the 
stone shall be secured to  the backing by means of cramps.  The clamps shall be spaced not more 
than 60 mm apart and shall be provided as directed by the Engineer‐in‐Charge. 
 
Cramps shall be attached to the sides and/or top and bottom and/or sides top sand bottom. The 
actual  number  of  cramps  and  their  sections  shall  be  as  per  requirements  of  design  of  carry  the 
loads. 
 
Where  cramps  are  used  to  hold  the  unit  in  position  only,  the  facing  shall  be  provided  with  a 
continuous support on which the stones shall rest at the ground level and other storey levels, the 
support  being  in  the  form  of  projection  from  or  recess  into  the  concrete  floor  slab,  or  a  beam 
between  the  columns  of  a  metal angle  attached  to  the  floor  slab  or  beams.  These  supports shall 
preferably be of vertical interval not more than 3.5 apart and also over the heads of all openings. 
Such supports shall also be provided where there is transition from thin facing below to thick facing 
above. 
 
Alternatively cramps may be used to hold the units in position in addition to supporting the units 
thus transferring the weight of the units to the backing. Such cramps shall be properly designed as 
per IS:4101 (Part‐1). The pins and cramps shall be laid in cement mortar 1:2 (1 cement : 2 coarse 
sand) 
 
The walls shall be carried up  truly plumb. All courses shall be  laid truly horizontal and all vertical 
joints truly vertical. The stone shall break joints on the face for atleast half the height of the course, 
unless otherwise shown in the drawings. The stone shall be in regular courses as per drawing and 
all  stones  shall  be  of  the  same  height  unless  otherwise  specified.  In  case  of  reinforced  cement 
concrete backing, the cramps shall be fixed to concrete while laying, at the requisite positions. 
 
11.4 Joints 
 
The joints shall be done with cement mortar 1:3 (1 cement : 3 coarse sand). All joints shall be full of 
mortar. Special care shall be taken to see that the grounding for cladding work as full of mortar. If 
any  hollow  groundings  are  detected  by  tapping  the  face  stones,  there  shall  be  taken  out  and 
replayed. The thickness of joints shall be as small as possible, not exceeding 5 mm. For close but 
jointed  facing,  the  thickness  shall  not  be  exceed  1.5  mm.  The  fine  joint  shall  be  uniform 
throughout. 
 
Where joint filler or compound is to be used, the joints shall be raked to a depth of at least 25 mm 
after the mortar in the joints has set sufficiently and the filler or compound applied. The joints may 
be subsequently finished with mortar suited to the appearance of work. It is preferable to use joint 
sealing compounds when the facings are exposed to heavy rainfall and winds and their selections 
would depend upon local experience and availability of joints sealing. 
 
11.5 Other Details 
 

NSL 
PMC CONSULTANT A 11
SPECIFICATION: Interiors Pharmacy Council of INDIA, at 3rd Floor, NBCC Center, OKHLA, New Delhi
11.5.1 Pointing 
 
All  exposed  joints  shall  be  pointed  with  mortar  as  specified.  The  pointing  when  finished  shall  be 
sunk from face of the stone by 5 mm or as specified. The depth of mortar in pointing work shall not 
be less than 15 mm. 
 
11.5.2 Curing 
 
Stone cladding work shall be pointed with mortar as specified. The pointing when finished shall be 
sunk from face of the stone by 5 mm or as specified. The depth of mortar in pointing work shall not 
be less than 15 mm. 
 
11.5.3 Protection 
 
Green  work  shall  be  protected  from  rain  by  suitable  covering.  The  work  shall  also  be  suitably 
protected from damage, mortar dropping and rain during construction. 
 
11.5.4 Scaffolding 
 
Double  scaffolding  having  two  sets  of  vertical  supports  shall  be  provided.  The  supports  shall  be 
sound and strong, tied together with horizontal pieces over which scaffolding planks shall be fixed. 
 
 

NSL 
PMC CONSULTANT A 12
SPECIFICATIONS: ELECTRICAL Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi
 
 
 
 
 
 
 
 
 

 
 
 
SPECIFICATIONS FOR ELECTRICAL WORKS 
SECTION B2 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Date: 14‐04‐2017 
                   
PMC: NSL
SPECIFICATIONS: ELECTRICAL Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi
INDEX  

S.no.  TITLE  Page no. 


1  PREAMBLE TO BILL/ SCHEDULE OF QUANTITIES   E1‐E3 
2  ELECTRICAL GENERAL PROVISIONS  E4‐E25 
3  CONDUIT SYSTEM, CABLE TRAY, CABLE LADDER AND  E26‐E34 
TRUNKING INSTALLATION 
4  EARTHING SYSTEM   E35‐E40 
5  PANELBOARDS  E41‐E56 
6  WIRES AND CABLES  E57‐67 
7  WIRING DEVICES  E68‐E76 
8  CIRCUIT BREAKER  E77‐E84 
9  FIRE DETECTION   E85‐ E92 
10  LAN  E93‐ E100 
11  UPS  E101 ‐ E117 
12  WATER LEAKAGE AND RODENT CONTROL  E118 – E123 
13  ACCESS CONTROL  & CCTV  E124 – E142 
14  AUDIO VIDEO SYSTEM  E143 – E150 
     
     
 
 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

PMC: NSL
SPECIFICATIONS: PTB Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

                                                                             SECTION VI 
PREAMBLE TO BILL/ SCHEDULE OF QUANTITIES 
 
A. Tender shall be on the basis of item rates which shall include the cost of materials, 
labour,  all  taxes,  duties  and  all  other  services  required  for  the  complete 
installation,  testing  and  commissioning  in  accordance  with  the  relevant  NEC/IER 
and  code  in  practice  including  the  fees  if  any  and  expenditure  for  factory 
inspection  together  with  the  liabilities  and  obligations  as  detailed  in  the  general 
conditions of contract.  It will also be the responsibility of the bidder to obtain all 
types  of  sanctions  etc  like  power/light  connections  and  the  drawings  etc  if  any, 
required by the concerned local authorities. 
 
B. Prices shall remain firm and free from variation due to rise and fall in the cost of 
materials  and  labour  or  any  other  price  variation  whatsoever  whether  during 
extended period of completion, if any. 
 
C. Item rates shall remain valid for any variation in the estimated quantities given in 
schedule of quantities. 
 
D. In  order  to  facilitate  the  technical  scrutiny  of  the  various  quotations,  the  bidder 
must  supply  with  their  quotations  detailed  technical  particulars  make  catalogues 
and  erection  drawings  for  various  items  under  different  parts  specified  in  the 
schedule of quantities. 
 
E. The  drawing  and  specifications  lay  down  minimum  standard  of  equipment  and 
workmanship  and  the  deviations.    In  the  absence  of  any  deviations,  it  will  be 
deemed that the bidder is fully satisfied with the intents of the specifications and 
drawings  and  their  compliance  with  the  statutory  and  fire  insurance  provisions 
including local codes, where the drawings and specifications conflict, the stringiest 
shall apply. 
 
F. All  equipments  and  the  installations  shall  be  tested  as  specified  and  a  test 
certificate in the prescribed form as required by the local supply authorities shall 
be furnished. 
 
G. The  entire  installation  shall  be  guaranteed  against  defective  materials  or 
workmanship for a period of 12 months from the date of the installation certified 
by  the  Consultant  and  taken  over by the Client.  During the guarantee period all 
the defects shall be rectified by the contract free of cost. 
 
H. The  successful  bidder  shall  submit  the  shop  drawings  to  the  Consultant  for 
approval prior to start the work.  The approval of these drawings will be general 
and will not absolve the contractor of the responsibility of the correctness of these 

PMC: NSL E1
SPECIFICATIONS: PTB Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

drawings.    At  least  6  copies  of  the  approved  drawings  shall  be  supplied  to  the 
Consultant  for  their  distribution  to  the  various  agencies  at  site  at  no  cost  to  the 
Client. 
 
I. The  position  of  distribution  boards  and  switchboards  may  require  some  minor 
adjustments  due  to  either  site  requirements  or  change  in  structural  layout.    All 
such  changes  from  the  position,  shown  in  the  drawings,  shall  be  required  to  be 
incorporated  without  any  extra  payment  or  deduction  for  change  in  length  of 
wiring etc. 
 
J. The bidders must see the site conditions and take all the aforesaid and foregoing 
factors while quoting the rates, as no extra payment will be allowed on any ground 
arising out of or relating to the aforesaid and foregoing. 
 
K. In  single  phase  (230  V)  A.C.  supply  system  circuit  wires  of  same  phase  shall  be 
drawn in same conduit.  For 3 phase, 4 wire wiring system wires of different colour 
shall be used and for insulated neutral only black colour wire shall be used. 
 
L. The  bidder  shall  include  in  his  rates  for  painting  with  three  coats  of  synthetic 
enamel  paint  to  match  the  surroundings  or  as  directed  by  the  Consultant  for  all 
steel structure used for works at no extra cost. 
 
M. The successful bidder shall supply completion drawings of the entire installation on 
tracing cloth as well as three prints of each drawing showing the complete wiring 
diagram as executed at site drawn to scale approved by the Consultant after the 
completion of work but before completion certificate is given by the Consultant. 
 
N. After laying and jointing the cables shall be subject to necessary tests as stipulated 
in IS: 5959 (Part‐I): 1970. 
 
O. As  more  than  one  make  is  mentioned,  prior  approval  of  particular  make  for  use 
shall be obtained from the Consultant.  All samples of all electric fittings and other 
accessories shall be approved by the Consultant prior to their installation. 
 
P. No alteration whatsoever is to be made to the text of quantities of this schedule of 
quantities, unless such alteration is authorized in writing by  the Consultant.  Any 
such alteration or addition shall, unless authorized in writing, be disregarded when 
tender documents are considered. 
 
Q. Any error in description or in quantity or omission of items from the contract shall 
not  vitiate  this  contract  but  shall  be  corrected  and  demand  to  be  a  variation 
required by the Consultants. 
 

PMC: NSL E2
SPECIFICATIONS: PTB Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

R. All measurements shall be taken in accordance with the Indian Standard Electrical 
Installation  in  buildings  method  of  measurements  of  IS:  5908:1970,  unless 
otherwise specified. 
 
S. The  contractor  shall  provide,  within  one  month  after  completion  of  the  work  or 
along with the final bill, three sets of manuals properly bound which shall contain 
the following information: 
 
1. Description of installation items using main items of equipments. 
2. Description  of  all  equipments  and  system  operation  with  trouble  shooting 
manuals. 
3. Line  diagram  of  each  system  including  main  feature  of  equipments  and  showing 
method of setting controls. 
4. Method of fault finding, routine, adjustment and wiring diagram. 
5. Description  of  routine  maintenance,  oil  and  greasing  points  and  recommended 
lubricants. 
6. Manufacturer service manuals for all equipments. 
7. Spares reference manuals. 
 
T. The contractor shall provide the following at no extra cost to the Client. 
 
1. Danger Notice Boards 
2. Treatment  for  electric  shock  giving  details  of  FIRST  AID  TREATMENT  with  chart 
diagrams (mounted in suitable frame). 
3. Line wiring diagrams of the electrical system mounted in suitable frame. 
 
U. The  contractor  will  remove  all  the  debris  and  surplus  earth  from  work  site 
(belonging to his work) free of cost. 
 
 
 
END OF SECTION 
 
 

PMC: NSL E3
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

ELECTRICAL GENERAL PROVISIONS 
 
PART 1 – GENERAL 
 
1.01 WORK DESCRIPTION 
 
A. The  scope  of  works  for  all  electrical  works  and  systems  comprises  engineering,  supply,  delivery, 
installation, testing and commissioning, handover, training, maintenance and warranty all as described or 
reasonably  implied  in  the  Contract.  The  Contractor  is  obliged  to  provide  fully  functioning  works  and 
systems  in  conformance  with  the  requirements  of  the  Contract.  In  the  event  certain  items  are  not  fully 
described or indicated in the Contract, but deemed essential by the Engineer for the performance of the 
works and systems then the provision of such items shall form part of the Contractors scope of works at 
no additional cost to the Owner. 
 
B. The Contractor shall be responsible to co‐ordinate the equipment and services and shall produce properly 
co‐ordinated  shop  drawings  to  demonstrate  the  installation  comply  with  the  performance  requirement 
with shop drawing, calculations and details. 
 
A. Shop  drawings  shall  take  into  account  actual  measurement  and  setting  out  dimensions/levels 
obtained  and  determined  by  the  Contractor  on  site,  actual  equipment/material  used,  actual  routing  of 
services, co‐ordination with all installation, and site conditions/constraints. This specification is intended 
to cover installation, testing and commissioning of LV Panels and associated equipment/ materials, panels, 
etc. 
 
1.02 SCOPE OF WORK: 
 
A. The Electrical and ELV installation shall generally include the following: 
1. Common Services: 
a. Liaison  with  the  local  supply  Authority  to  obtain  and  coordinate  provision  of  incoming 
electricity supply. 
b. Installation, testing & commissioning of MV system including incoming electricity supply, 
consumer  main  MV  switchboard,  cabling  to  component  MV  switchboards,  cabling  to  power 
transformer, power transformers and associated accessories to SEB requirement and arrange SEB 
acceptance upon completed. 
c. Supply,  installation,  testing  &  commissioning  of  telephone  system  including  incoming 
telephone  lines,  component  telephone  distribution  panel  at  each  level,  interconnecting  cablings 
and associated accessories. 
d. To provide telephone cabling as specified on the drawings. 
e. Complete central earthing systems for connection with component electrical systems. 
 
2. Internal Services 
a. Complete LV distribution system including main LV switchboard, automatic power factor 
correction devices, sub‐boards and distribution boards, UPS and associated distribution main and 
sub‐main cabling and associated accessories. 
b. Complete lighting and power installation including all final circuiting work and associated 
accessories. 
c. Normal and emergency lighting supply and installation and associated accessories. 
d. Complete earthing system. 

PMC: NSL E4
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

e. Complete lightning protection system and associated accessories. 
f. Complete telephone cabling system and associated accessories. 
g. Complete wiring work to external/landscape and public area architectural/special lighting 
and dimming systems and associated accessories. 
h. Complete cable support system for future structure cabling system and associate works. 
i. Miscellaneous  works  like  providing  and  fixing  of  rubber  mats,  fire  buckets,  first  aid  box, 
fire extinguishers, etc. 
j. All associated interfacing power supply work to other mechanical installations. 
k. All  interfacing  works  with  the  Building  Management  System  for  remote  control  and 
monitoring. 
l. All associated interfacing works with other M&E installations. 
m. Other  works  as  shown  on  the  Drawings  and  described  elsewhere  in  the  Contract 
documents. 
 
B. The item rate shall remain valid for variation to any extent of the estimated quantities given in the 
Schedule of Quantities. 
 
C. All equipment shall be of the class most suitable for working under the conditions specified and 
shall withstand the atmospheric conditions without deterioration. 
 
D. Minor  civil  work  is  included  in  the  contractor’s  scope  of  work.  Further,  the  responsibility  of 
coordination with the civil and other contracting agencies ensuring completion of turnkey contract rests 
with the contractor. 
 
E. Contractor shall co‐ordinate with all other agencies working at site for interconnection and safety 
aspects. 
 
F. Also the Contractor shall furnish back up combined guarantee minimum for 1 year from the date 
of successful commissioning from the manufacturer.  In case there is any defect, the free replacement of 
any part or in whole will be made immediately at no extra cost to Owner. 
 
1.03 FEE, PERMITS & TESTS: 
 
A. The contractor shall obtain all sanctions and permits required for the above said works from all 
the  relevant  authorities.  All  actual  fees  payable  in  this  regard  will  be  reimbursed  against 
receipt/documentary proof (evidence). On completion of the work, the Contractor shall obtain N.O.C from 
concerned authorities including SEB, Chief Electrical Inspectorate, of State. The original of the same shall 
be delivered to the Owner through Consultants. 
 
B. The Owner shall have full power regarding the equipments/ materials get tested by authorized/ 
recognized  independent  agency  at  the  contractor’s  expense  in  order  to  prove  their  soundness  and 
adequacy. The contractor will rectify the defects/ suggestions pointed out by independent agency through 
Owner at contractor’s expense. 
 
C. The installation shall comply in all respects with the requirements of Indian Electricity Act 1910, 
Indian Electricity Rules (IER) 1956 and other related Laws and Regulations (for F.F. etc.) as amended up to 
date, there under and special requirements, if any, of the State Electricity Boards etc. The contractor shall 
be  liable  to  furnish  the  list  of  authorized  licensed  persons/  employed/  deputed  to  carry  out  the  works/ 
perform the assigned duties to fulfill the requirement of Rule No.3 of IER 1956 as amended up to date. 

PMC: NSL E5
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
1.04 CODES & STANDARDS: 
 
A. The design, manufacture, inspection, testing and performance shall comply with all the currently 
applicable  statutes,  safety  codes,  relevant  Bureau  of  Indian  Standards  (BIS),  British  Standards  (BS), 
International  Electro  Technical  Commission  (IEC)  publication,  NEMA  &  VDE  Standards  amended  up  to 
date. 
 
B. The design engineering, manufacturing and the installation shall be in accordance with established 
codes, sound engineering, practices and specifications. Further, the same shall conform to the statutory 
regulations applicable in the country.  Contractor shall obtain all approvals from statutory authorities, e.g. 
Electrical  inspector,  SEB  or  any  other  agency  as  applicable  before  commissioning  of  electrical  system  if 
required.   
 
C. Some of the relevant Indian and British Standards are listed below. 
 
1. Indian Electricity Act. 
2. Indian Electricity Rules. 
3. Factory Act. 
 
Any  other  standard  may  be  followed  provided  it  is  equivalent  or  more  stringent  than  the  standards 
specified above. 
 
In case of any deviation/conflict of this specification with the codes & standards, the following order of 
precedence shall govern 
 
1. Engineer’s decision. 
2. Local codes of practice 
3. Drawings. 
4. Specifications 
5. International standards & requirements. 
 
1.05 DESIGN: 
 
A. The design and workmanship shall be in accordance with the best engineering practices, to ensure 
satisfactory performance and service life. The equipment offered by the contractor shall be complete in all 
respects.  Any  materials  or  accessories,  which  may  not  have  been  specifically  mentioned,  but  which  are 
usual  and  necessary  for  the  completion  of  the  system  and  satisfactory  &  trouble  free  operation  and 
maintenance  of  the  equipment  shall  be  provided  without  any  extra  cost  to  the  Owner.  This  shall  also 
include spares for commissioning of the equipment. 
 
B. This specification defines the basic guidelines to develop a suitable electrical system as necessary 
for the Complex.  All data required in this regard shall be taken in to consideration to develop a detailed 
engineering for the system.  Site conditions as applicable are mentioned elsewhere. 
 
C. Compliance with these specifications and/or approval of any of the Contractor’s documents shall 
in no case relieve the Contractor of his contractual obligations. 
 

PMC: NSL E6
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

D. All  work  to  be  performed  and  supplies  to  be  made  as  a  part  of  contract  shall  require  specific 
approval/review of Owner or his authorized representative 
 
E. The  engineering  activities  shall  comprise  the  submission  for  approval  of  the  following  from 
Consultants/Owner 
 
1.06 BIDDER SHALL BE RESPONSIBLE FOR: 
 
1. Detailed  co‐ordination  with  other  services,  shop  drawings  for  various  electrical  layouts  such  as 
equipment  layout,  cabling  layouts,  earthing  layouts,  including  equipment  installation  and  cable 
termination details etc. prior to start of work. 
2. Preparation of bill of materials for electrical works. 
3. Protection co‐ordination drawings/ tables for complete power system. 
4. Shop inspection and testing procedures. 
5. Field‐testing and commissioning procedures. 
6. Preparation of as built drawings. 
 
Bidder shall also be responsible for: 
Any  other  work/activity  which  is  not  listed  above,  however  is  necessary  for  completeness  of 
electrical system 
Bidder shall clearly understand and quote accordingly: 
To ensure that all clauses given in this part of the specifications shall also apply to all other electrical 
works of other segments. The bidder shall bring to the notice of the Owner the differences, if any, 
and  get  the  same  clarified  failing  which  the  Owner  may  impose  the  more  stringent  of  the 
specification/ clauses at the sole risk and costs of the contractor. 
 
 
 
1.07 DATE OF COMMENCEMENT AND COMPLETION PERIOD: 
 
A. The  contractor  shall  be  allowed  admittance  to  the  site  on  the  date  of  commencement  as 
described  in  the  General  Conditions  and  he  shall  thereupon  and  forthwith  begin  the  works  and  shall 
regularly proceed with and complete the same on or before the date of completion subject, nevertheless 
to the provisions for the extension of time. The time being the essence of the contract, the Contractor will 
adhere  to  the  time,  progress  chart  and  project  schedule  and  will  give  proportional  output/progress  in 
proportional time  
 
1.08 SCHEDULE AND MANNER OF OPERATIONS: 
 
A. Time being the essence of this Contract, the Contractor will be expected to furnish all labour and 
materials  in  sufficient  quantities  and  at  appropriate  times,  expedite  and  schedule  the  work  as  required 
and so manage the operation that the work will be completed within the time stated in the Contract.   
 
1.09 PROJECT SCHEDULE: 
 
A. The contractor will have to submit a detailed project schedule. 
 
1 For various items of works to be carried out by him. 
 

PMC: NSL E7
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

2 For various associated works to be carried out by other agencies. 
 
so  that  the  work  gets  completed  with  in  the  contractual  completion  time.    This  schedule  shall  be 
submitted  by  the  contractor  in  Microsoft  project  software  format.  The  contractor  shall  follow  this 
schedule  meticulously  and  shall  also  coordinate/  follow  up  with  other  agencies  to  expedite  the  works 
associated  with  his  own  work.  Liquidity  damages  clause  will  become  applicable  for  any  delay  in 
completion of the work. 
 
B. The contractor will submit within 7 days of the award of work, a detailed schedule of program of 
work. 
 
C. No  additional  payment  will  be  made  to  the  contractor  for  any  multiple  shift  work  or  other 
incentive methods contemplated by him in his work schedules even though the time schedule is approved 
by the Consultant/Engineer‐in‐Charge. 
 
1.010 DESIGN CONDITIONS: 
 
A. Design  ambient:  45  Deg.  C  maximum  dry  bulb  temperature  &  2  Deg.  C  minimum  dry  bulb 
temperature 
B. Altitude: 300 m above sea level 
C. Relative Humidity: 98% maximum 
D. Site Environment: Normal.  
 
1.10 COORDINATION OF WORK  
 
A. Contract  documents  establish  scope,  materials  and  quality  but  are  not  detailed  installation 
instruction.  
 
B. Coordinate work with related trades and furnish, in writing, any information necessary to permit 
the work of related trades to be installed satisfactorily and with the least possible conflict or delay. 
 
C. The  drawings  show  the  general  arrangement  of  equipment  and  appurtenances.  Follow  these 
drawings as closely as the actual construction and the work of other divisions will permit. Provide off‐sets, 
fittings, and accessories which may be required but not shown on the drawings. Investigate the site, and 
review drawings of other divisions to determine conditions affecting the work, and provide such work and 
accessories as may be required to accommodate such conditions. 
 
D. The locations of thermostats, switches, panels and other equipment indicated on the drawings are 
approximately correct. Exercise particular caution with reference to the location of panels, thermostats, 
switches,  etc.,  and  have  the  precise  and  definite  locations  accepted  by  the  Engineer  before  proceeding 
with the installation. 
 
E. The  drawings  show  only  the  general  run  of  services  and  approximate  location  of 
equipment,  outlets,  panels,  etc.  Any  significant  changes  in  location  of  equipment,  outlets,  panels,  etc., 
necessary in order to meet field conditions shall be brought to the determine attention of the Engineer for 
review  before  such  alterations  are  made.  Modifications  shall  be  made  at  no  additional  cost  to  the 
Contract. 
 

PMC: NSL E8
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

F. Carefully  check  space  requirements  with  other  division  works  to ensure that equipment 


can be installed in the space allotted. 
 
G. Wherever  work  interconnects  with  work  amongst  different  installation,  coordinate  with 
other  trades  to  insure  that  they  have  the  information  necessary  so  that  the  Contractor  may  properly 
install the necessary connections and equipment. Identify items requiring access in order that the Ceiling 
Trade will know where to install access doors and panels. 
 
H. Consult amongst installation so that, wherever possible, motor controls and distribution 
equipment are of the same manufacturer. 
 
I. Furnish  and  set  sleeves  for  passage  of  risers  through  structural  masonry  and  concrete 
walls  and  floors  and  elsewhere  as  required  for  the  proper  protection  of  each  riser  passing  through 
building surfaces. 
 
J. Provide  fire  stopping  around  all  pipes,  conduits,  ducts,  sleeves,  etc,  which  pass  through 
fire compartments. 
 
K. Provide  required  supports  and  hangers  for  equipment  suitably  so  as  not  to  exceed 
allowable loading of structures. 
 
L. Wherever the work is of sufficient complexity, prepare additional detail drawings to scale 
to  coordinate  the  work  with  the  work  of  other  trades.  Detailed  work  shall  be  clearly  identified  on  the 
drawings  as  to  the  area  to  which  it  applies.  Submit  these  drawings  to  the  Engineer  for  review.  At 
completion include a set of these drawings with each set of record drawings. 
 
M. Coordinate with the local utility companies/authorities for their requirements for service 
connections  and  provide  all  necessary  provisions,  grounding,  materials,  equipment,  labor,  testing,  and 
appurtenances. 
 
N. Before  commencing  works,  examine  adjoining  works  on  which  this  work  is  in  any  way 
affected and report conditions which prevent performance of the works. Become thoroughly familiar with 
actual existing conditions to which connections must be made or which must be changed or altered. 
 
W. The  Contractor  is  responsible  to  any  modifications  required  due  to  service  not  properly 
coordinated.   

 
1.11 ELECTRICAL POWER SUPPLY INTERFACES 
 
A. The Contractor shall provide power supply points/isolators at certain designated locations 
within the development for all mechanical and electrical installations as indicated on the drawings.  It is 
the  responsibility  of  the  Contractor  to  coordinate  and  make  connections  to  these  power  supply 
points/isolators and to provide all the necessary ‘down‐stream’ power supply distribution board/network 
to the mechanical system’s control panels, equipment, sensors, field devices, etc. 
  
1.12 BUILDING MANAGEMENT SYSTEM AND INTERFACES 
 

PMC: NSL E9
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

A.  The Contractor shall co‐ordinate the mechanical system and equipment to interface with the Building 
Management System in accordance with the point schedules specified on the Drawings. All necessary 
interfacing works shall be included in the Contract. 
1.13 CENTRAL CONTROL ROOM INTERFACES 
 
A.  The Contractor shall include the supply and installation of a custom‐built control console of proprietary 
make in the Fire Command Centre and each building component’s Security Room to integrate all control 
panels, mimic panels, and central equipment of the following systems: 
1. Building Management system 
2. Security  systems,  including  CCTV,  access  control,  door  monitoring,  watchman  tour,  panic  alarm 
system, etc. 
3. Fire Alarm and Detection system 
4. Ventilation Control Panel for all emergency operation fans/systems 
5. Lift system 
6. Escalator system 
7. Fireman Intercom system 
8. Fire Protection Pumps Control Panel 
9. Fireman’s Override Control Panel 
10. Public Address and Emergency Evacuation Announcement systems 
11. MATV System 
12. all other systems to be housed inside the Fire Command Centre/Security Room 
 
1.14 INTERFACING WITH ALL SERVICES AND SYSTEMS 
 
A. General 
1. The Contractor shall provide all necessary provisions for interfacing amongst installation, services, 
and  equipment.  All  necessary  sensors,  current/voltage  transformers,  voltage‐free  contacts,  relays, 
auxiliary  contacts,  terminals,  transducers,  etc.  for  interfacing  works  shall  be  provided  by  the 
Contractor. 
2. All control/monitoring wiring from sensors, equipment, and components for the interfacing shall 
be terminated at a separate interfacing compartment located at the respective equipment/system’s 
switchboard  or  control  panel.  The  interfacing  compartment  shall  be  completed  with  all  necessary 
connectors, terminals, and with proper identifications to allow interfacing works to be easily carried 
out.  The  compartment  shall  clearly  indicate  “Extra  Low  Voltage  Cable  Only.  No  Power  Cable 
Connection”.  Where  there  is  no  equipment/system  switchboard  or  control  panel  involved,  the 
Contractor  shall  provide  separate  interfacing  panels  with  provisions  same  as  the  interfacing 
compartment as described above. The locations of the switchboard/control panels and the interfacing 
panels shall be properly coordinated. 
3. For every control panel and each module of the switchboard, at least five (5) spare terminals shall 
be provided for future interfacing works. 
4. Wiring  and  cables  for  interfacing  with  the  fire  alarm  system  and  other  fire  protection  and  life 
safety systems shall be fire rated to comply with Civil Defense’s requirements. 
5. Unless  otherwise  specified  or  shown  on  the  Drawings,  interfacing  wiring  from  Fire  Alarm  and 
Building  Management  systems  shall  be  provided  and  terminated  at  the  terminals  of  the  interfacing 
compartments  or  panels  by  the  Fire  Alarm  System  and  Building  Management  System  installation 
respectively. The Contractor shall co‐ordinate the current and voltage requirements for the interfacing 
works/provisions.  The  type  of  provisions  for  interfacing  signals  shall  be as follows, unless otherwise 
specified: 

PMC: NSL E 10
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

6. Digital inputs and outputs           :  voltage‐free dry contact 
7. Analog inputs and outputs  :  4 – 20 mA or 0 – 10 mV 
8. All the interface provisions shall be DC operated and rated not more than 50 mA. 
9. For  interfacing  works  between  Fire  Alarm  System  and  Building  Management  System,  the 
Contractor  shall  provide  the  Fire  alarm  installation  with  interface  wiring  and  terminate  them  at  the 
Building Management System’s interfacing compartments or panels.  
10. The Contractor shall provide and make all power cable connections from mechanical equipment, 
local control panels, and distribution boards to the electrical isolators or power points (including cable 
termination) provided under Division 16 works. Location of power supply isolators and power points 
shall be properly coordinated. 
11. In  addition  to  the  interfacing  requirements  shown  on  the  Drawings,  interfacing  provisions  as 
described below shall also be provided and included in the Contract. 
 
B.  Electrical Installation 
1. The Electrical Installation  shall provide the following: 
a. Isolators  and  power  points  (fused  spur  units)  for  all  mechanical  equipment  and 
systems. Where shown on the Drawings, the Electrical installation shall include direct power cable 
connections to the mechanical system’s main motor control centres. 
b. Earthing  terminal  in  the  Fire  Command  Centre  and  all  other  plant  rooms  for 
supplementary equipotential bonding of mechanical equipment and systems. 
c. Power  failure  signal  to  the  Lift  System  (including  wiring  terminations  into  the  Lift 
interfacing  panel  in  the  Lift  Motor  Room),  Fire  Alarm  System  and  the  Building  Management 
System. 
d. Electrical  bonding  of  all  roof  equipment  and  external  metal  cladding  including 
provisions and connection of bonding cables. 
e. Fuel  main  storage  tank  and  day  tank  High/Low  level  alarm  signals  to  the  Building 
Management System. 
f. Emergency  power  supplies  to  Building  Management  System  (including  all  field 
panels), Fire Alarm System, car parking system, and all security systems. 
g. Emergency power supplies to all fire shutters, smoke shutters/curtains, and automatic 
doors. 
h. Power point in each toilet for the plumbing installation (for connection to automatic 
sanitary sensors and flush valve under the Plumbing and Sanitary installation). 
2. Power  supply  to  variable  air  volume  (VAV)  boxes  and  the  ACMV  system’s  control 
components/sensors shall however be provided under the ACMV installation from the corresponding 
equipment motor control panel. 
 
1.15 EXAMINATION OF SITE  
 
A. Prior  to  the  submitting  of  bids,  visit  the  project  site  and  become  familiar  with  all 
conditions affecting the proposed installation and make provisions as to the cost thereof. 
 
B. The Contract Documents do not make representations regarding the character or extent 
of  the  sub‐soils,  water  levels,  existing  structural,  mechanical and electrical installations, above or below 
ground,  or  other  sub‐surface  conditions  which  may  be  encountered  during  the  work,  based  on 
examination of the site or other information. Failure to examine the drawings or other information does 
not relieve the Contractor of responsibility for satisfactorily completion of the work. 
 
1.16 EXCAVATION AND BACKFILL  

PMC: NSL E 11
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
A. Where  ever  required  provide  trenches  details,  duly  approved  by  the  consultant  with  all 
relevant section etc. as per IS codes to the Civil contractor, minimum before 1 month of laying the pipes, 
etc.  Co  ordinate  with  the  civil  contractor  during  the  excavation,  and  ensure  that  the  excavation  and 
backfilling is being properly done as per requirement. 
 
B. Where  ever  it  is  asked  by  the  Owner/  consultant  for  providing  trenches  in  contractor’s 
scope. It is deemed that the cost of the pipe is inclusive of trench digging and backfilling. The following 
points needs to be taken care of while making the trenches. 
 
C. The  trench  shall  be  of  widths  necessary  for  the  proper  execution  of  the  work.  Grade 
bottom of the trenches accurately to provide uniform bearing and support the work on undisturbed soil at 
every point along its entire length. Except where rock is encountered, do not excavate below the depths 
indicated.  Where  rock  excavations  are  required,  excavate  rock  to  a  minimum  over  depth  of  four  inches 
below the trench depths indicated on the drawings or required. Backfill over depths in the rock excavation 
and  unauthorized  over  depths  with  loose,  granular,  moist  earth,  thoroughly  machine  tamped  to  a 
compaction level of at least 95% to standard proctor density or 75% relative density or as specified by the 
Engineer. Wherever unstable soil that is incapable of properly supporting the work is encountered in the 
bottom  of  the  trench,  remove  soil  to  a  depth  required and backfill the trench to the proper grade with 
coarse sand, fine gravel or other suitable material. 
 
D. Excavate  trenches  for  utilities  that  will  provide  the  following  minimum  depths  of  cover 
from existing grade or from indicated finished grade as required by local authorities. 
 
E. Trenches should not be placed within 3 meters of foundation or soil surfaces which must 
be resist horizontal forces. 
 
F. Do not backfill until all required tests have been performed and installation observed by 
the Engineer. Comply with the requirements of other sections of the specifications. Backfill shall consist of 
non‐expansive soil with limited porosity. Deposit in 15 cm layers and thoroughly and carefully tamp until 
the work has a cover of not less than 30 cm. Backfill and tamp remainder of trench at 30 cm intervals until 
complete. Uniformly grade the finished surface. 
 
1.17 CUTTING AND PATCHING  
 
A. All kinds of cutting and repairing of brick Walls or Partitions, etc. for the proper routing of 
pipe, shall be in the scope of the contractor. However, cutting and repairing of RCC wall, or ceiling shall be 
in the scope of civil contractor. 
B. Where cutting, channeling, chasing or drilling of floors, walls, partitions, ceilings or other 
surfaces  is  necessary  for  the  proper  installation,  support  or  anchorage  of  conduit  or  other  equipment, 
layout  the  work  carefully  in  advance.  Repair  any  damage  to  the  building,  piping,  equipment  or  defaced 
finish  plaster,  woodwork,  metalwork,  etc.,  using  skilled  trade  people  of  the  trades  required  at  no 
additional cost to the Contract. 
 
C. Provide  slots,  chases,  openings  and  recesses  through  floors,  walls,  ceilings,  and  roofs  as 
required.  Where  these  openings  are  not  provided,  provide  cutting  and  patching  to  accommodate 
penetrations at no additional cost to the Contract. 
 
1.18 SEALING OF PENETRATIONS 

PMC: NSL E 12
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
A. Air Tight Seals 
 
1. All  penetrations  through  the  building  fabric  subject  to  suction  or  pressurization  shall  be  sealed 
airtight. 
 
B. Holes in Roof 
 
1. Roof  penetrations  for  passage  of  conduits  or  circular  PVC  and  PVC  Cables  shall  be  sealed 
watertight using a flexible polypropylene conical sleeve manufacturer to seal the cable to the roof 
structure, regardless of the roof profile. 
 
2. All sharp metal edges, which may come in contact with the cable, shall be suitably bushed. 
 
C. Fire Rated Penetrations 
 
1. Where services penetrate any fire rated barrier, the Contractor shall seal the penetration with the 
use of an appropriate material to ensure the integrity of the fire barrier. 
 
2. The Contractor shall seal the cable enclosures through fire rated barriers to ensure the integrity 
and rating of the fire barrier. 
 
D. Acoustic Penetrations 
 
1. Where services penetrate acoustic barriers, sealant shall be supplied and installed to maintain the 
acoustic separation at least equal to the barrier penetration. 
 
1.19 MOUNTING HEIGHTS 
 
A. Verify exact locations and mounting heights with the Engineer before installation. 
 
1.20 SUPPORTS  
 
A. Support  work  in  accordance  with  the  best  industry  practice.  Provide  supports,  hangers, 
auxiliary structural members and supplemental hardware required for support of the work. 
 
B. Provide  supporting  frames  or  racks  extending  from  floor  slab  to  ceiling  slab  for  work 
indicated  as  being  supported  from  walls  where  the  walls  are  incapable  of  supporting  the  weight.  In 
particular, provide such frames or racks in electric closets and equipment room. 
 
C. Provide  supporting  frames  or  racks  for  equipment  which  is  installed  in  a  free  standing 
position. 
 
D. Supporting  frames  or  racks  shall  be  of  standard  angle,  standard  channel  or  specialty 
support  system  steel  members,  rigidly  bolted  or  welded  together  and  adequately  braced  to  form  a 
substantial structure. Racks shall be of ample size to assure a workmanlike arrangement of all equipment 
mounted on them. 
 

PMC: NSL E 13
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

E. Adequate  support  of  equipment  (including  outlet,  pull  and  junction  boxes  and  fittings) 
shall not depend on ducts, pipe, electric conduits, raceways, or cables for support. 
 
F. Equipment shall not rest on or depend for support on suspended ceiling media (tiles, lath, 
plaster,  as  well  as  splinters,  runners,  bars  and  the  like  in  the  plane  of  the  ceiling).  Provide  independent 
support of equipment. Do not attach to supports provided for ductwork, piping or work of other trades. 
 
G. Provide  required  supports  and  hangers  for  equipment  so  that  loading  will  not  exceed 
allowable  loading  of  structure.  Equipment  and  supports  shall  not  come  in  contact  with  work  of  other 
trades. 
 
1.21 FASTENINGS  
A. Fasten equipment to building in accordance with the best industry practice. 
 
B. Where weight applied to the attachment points is 45 kg or less, conform to the following 
as a minimum: 
1.  Wood  :  Wood screws 
2.  Concrete and solid masonry :  Dash Fastener of appropriate ratings ‐HILTI/FISHER  
3.  Solid metal  :  Machine screws in tapped holes or with welded studs 
 
C. Where weight applied to the building attachment points exceeds 45 kg,  but is 135 kg or 
less, conform to the following as a minimum: 
 
1. At concrete slabs provide 60 cm x 60 cm x 13 cm steel fishplates on top with through bolts. Fishplate 
assemblies shall be chased in and grouted flush with the top slabs screed line, where no fill is to 
be applied. 
 
2. At steel decking or sub‐floor for all fastenings, provide through bolts and threaded rods. The tops of 
bolts and rods shall be set at least one inch below the top fill screed line and grouted in. Suitable 
washers  shall  be  used  under  bolt  heads  or  nuts.  In  cases  where  the  decking  or  sub‐floor 
manufacturer produces specialty hangers to work with his decking or sub‐floor such hangers shall 
be provided. 
 
D. Where weight applied to building attachment points exceeds 135 kg, coordinate with and 
obtain the approval of Engineer and conform to the following as a minimum: 
 
1.  Provide suitable auxiliary channel or angle iron bridging between building structural steel 
elements to establish fastening points. Bridging members shall suitably weld or clamped to 
building steel. Provide threaded rods or bolts to attach to bridging members. 
E. For items which are shown as being ceiling mounted at locations where fastening to the 
building  construction  element  above  is  not  possible,  provide  suitable  auxiliary  channel  or  angle  iron 
bridging tying to the building structural elements. 
 
F. Wall mounted equipment may be directly secured to wall by means of steel bolts. Groups 
or arrays of equipment may be mounted on adequately sized steel angles, channels, or bars.  
 
 
 
1.22 IDENTIFICATION  

PMC: NSL E 14
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
A. Identify  equipment  with  permanently  attached  black  phenolic  nameplates  with  13  mm 
high white engraved lettering. Identification shall include equipment name or load served as appropriate. 
Nameplates  shall  be  attached  with  cadmium  plated  screws;  peel  and  stick  tape  or  glue  on  type 
nameplates is unacceptable. 
 
B. Services runs shall be properly identified as per the requirements in the Contract. 
 
C. See individual section for additional identification requirements. 
 
1.23 PROHIBITED LABELS AND IDENTIFICATIONS 
 
A. In all public areas, tenant areas, and similar locations within the project, the inclusion or 
installation  of  any  equipment  or  assembly  which  bears  on  any  surface  any  name,  trademark,  or  other 
insignia which is intended to identify the manufacturer, the vendor, or other source(s) from which such 
object has been obtained, is prohibited. 
 
B. Required  test  lab  certification  labels  shall  not  be  removed  nor  shall  identification 
specifically required under the various technical sections of the Specifications be removed. 
 
1.24 EQUIPMENT PADS AND ANCHOR BOLTS 
 
A. Provide  all  details  with  proper  sections  for  the  equipment  pads  and  anchor.  The 
equipment  pads  casting  and  making  provision  for anchor fastening shall be as per the final UNALTERED 
drawing  duly  approved  by  the  consultant,  shall  be  in  the  scope  of  Civil  contractor.  However,  the 
Contractor shall ensure the proper coordination with the civil contractor. 
 
B. All equipment pads for all vibrating equipments shall have cork vibration pads sandwiched 
between the finish surface and the bottom surface of required thickness suggested by the civil consultant, 
to ensure that the minimum vibration can travel below. 
 
C. Provide  galvanized  anchor  bolts  for  all  equipment  placed  on  concrete  equipment  pads, 
inertia  blocks,  or  on  concrete  slabs.  Provide  bolts  of  the  size  and  number  recommended  by  the 
manufacturer  of  the  equipment  and  locate  by  means  of  suitable  templates.  Equipment  installed  on 
vibration  isolators  shall  be  secured  to  the  isolator.  Secure  the  isolator  to  the  floor,  pad,  or  support  as 
recommended by the vibration isolation manufacturer. 
 
D. Where  equipment  is  mounted  on  gypsum  board  partitions,  the  mounting  screws  shall 
pass  through  the  gypsum  board  and  securely  attach  to  the  partition  studs.  As  an  attached  to  15  cm 
square,  galvanized  metal  back  plates  which  are  attached  to  the  gypsum  board  with  an  approved  non‐
flammable adhesive. Toggle bolts installed in gypsum board partitions are not acceptable. 
1.25 MISCELLANEOUS: 
 
A. A  site  order  book  will  be  maintained  at  site,  which  will  be  in  the  custody  of  the  Owner,  or  his 
representative and all instructions given to the contractor will be recorded in the site order book and the 
same has to be signed by the contractor to comply with the instructions given therein. 
 

PMC: NSL E 15
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

B. After  completion  of  the  work  the  whole  installation  shall  be  tested  by  the  contractor  in  the 
presence  of  the  Consultant/Engineer‐in‐Charge.    The  tests  shall  comply  the  following  I.E.E.  Regulations 
and shall be submitted along with the final bill: 
 
1. The  result  of  the  insulation  test  shall  comply  with  the  I.E.E.  Regulations  1101  to  1108A  and 
1008B as may be applicable. 
2. Test shall be carried out to ascertain that all the non‐linked SP switches have been connected 
to the phase conductor. 
3. The continuity test of the earthing system shall comply with I.E.E. Regulations 1108 to 1109 to 
the latest addition. 
C. If the result of the above tests does not comply with the I.E.E. Regulations, the contractor shall be 
bound to rectify the faults so that the required results are obtained. 
 
D. The  contractor  shall  be  responsible  to  provide  all  the  necessary  testing  instruments,  such  as 
megger insulation tester, earth tester multi‐meter, AVO meter etc for carrying out the above tests. 
 
E. The work will not be considered as complete and taken over by the Owner till all the components 
of  the  work  after  being  completed  at  site  in  all  respects  have  been  inspected/  tested  by  the 
Consultant/Owner to his entire satisfaction and a completion certificate issued by the Owner/Consultant 
to this effect. 
 
F. Shop drawing for electrical work e.g. equipment, cable earthing and conduit layout for all systems 
shall be prepared by the contractor and got approved before starting of the work. 
 
G. At  the  completion  of  the  work  and  before  issuance  of  certificate  of  virtual  completion,  the 
contractor  shall  submit  6  sets  of  drawing  and  two  tracing  of  each  drawing  to  Owner  of  each  layout 
drawings drawn at approved. 
 
H. Contractor’s Superintendence: 
1. The contractor shall provide all necessary superintendence during the execution of the works and 
as long thereafter as the engineer may consider necessary. The contractor or his competent and 
authorized agent or representative approved of in writing by the owner/ Engineer (which approval 
may at any time be withdrawn) is to be constantly on the works and shall give his whole time to 
the superintendence of the same. Such authorized agent or representative shall receive on behalf 
of the contractor, directions and instructions from the Engineer‐in‐charge or his representative. 
2. The contractor shall provide detailed organization of the execution team deployed for the works 
with names and CV’s, of all key staff before the commencement of work and get it approved of in 
writing  by  the  Owner/  Consultant.  Contact  telephone  or  pager  numbers  for  emergency  and/or 
twenty‐four (24) hour call shall also be included. 
3. If  in  any  case  of  withdrawal  of  any  worker/  technician/Engineer  from  the  execution  team,  the 
replacement  of  the  same  shall  be  done  with  equivalent  qualification,  and  shall  be  approved  in 
writing by the Owner/ Consultant. 
 
PART 2 – PROUCT, TESTING & COMMISIONING 
 
2.01 DESIGN CRITERIA 
 
A. Electrical Details for Incoming Supply: 
 

PMC: NSL E 16
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

1. Supply Voltage: as approved by SEB 
2. Fault Level (Sym.) at supply point (Designated): MVA (to be confirmed from State Electricity Board 
by Bidder). 
3. Neutral: Grounded 
4. Voltage Regulations: + 10% 
5. Frequency Regulations: + 3% 
6. Combined Regulations: + 10% 
 
B. LT Power Distribution System: 
 
1. Voltage: 415 V 
2. Frequency: 50 Hz 
3. Neutral: Grounded 
4. Short  Circuit  Fault  withstand  capacity:  20  to  50  KA  for  1  sec.,  as  per  BOQ  and 
specifications 
 
C. Control supply for Electrical System: 
 
The various supply voltage to be used in the control panels for the main equipment shall be as under: 
1. Spring charge motor: 230 V AC or 24 V DC (Universal Motor) 
2. Closing/ Trip Coil: 24 V DC 
3. Alarm/ Indication/ Relays: 24 V DC 
4. Heaters: 230 V AC  
 
D. Painting of Panels: 
 
  Powder coating of approved shade as per Specification. (Refer clause of painting) 
E. Painting of Cable Trays and Structural steel: 
 
   Powder coating of approved shade as per Specification. (Refer clause of painting) 
 
F. Cable Details: 
 
1. LT Control Cables: Copper conductor armoured PVC insulated 1.1 KV grade. 
2. LT Power Cables: Aluminium conductor armoured XLPE insulated.  
3. Grounding Conductors: Copper/ G.I. as specifications and BOQ 
 
G. Accuracy Class of Meters: 
 
1. Revenue Meters: Class‐I or as approved by SEB 
2. Ammeters, Voltmeters & Other Instruments: Digital Type 
 
2.02 DRAWINGS: 
 
A. The  list  of  drawings  is  enclosed  along  with  this  specification.  These  drawings  are  meant  to  give 
general idea to bidder regarding the nature of work covered by these specifications. 
 

PMC: NSL E 17
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

B. Any information/data shown/not shown in these drawings shall not relieve the contractor of his 
responsibility  to  carry  out  the  work  as  per  the  specifications.  Additional  information  required  by  the 
bidder for successfully completing the work shall be obtained by him. 
 
2.03 SHOP DRAWINGS: 
 
A. The contractor shall prepare detailed coordinated electrical shop drawing indicating Panel layout, 
with other relevant services and submit to the Consultant for approval or the Engineer‐in‐Charge before 
commencing the work. The shop drawings shall indicate all setting out details and physical dimensions of 
all components with wiring and cable details including system operating write up in the system i.e. Control 
and  Relay  Panel  and  fixing  details  for  the  above  mentioned  work.    All  work  shall  be  carried  out  on  the 
approval  of  these  drawings.  However,  approval  of  these  drawings  do  not  relieve  the  contractor  of  his 
responsibility  for  providing  maintenance  free  and  full  proof  system  including  any  missing 
component/accessories to meet with the intent of the specifications. Contractor will submit 2 (two) prints 
for preliminary approval and finally 6 (six) prints for distribution. 
 
2.04 MANUFACTURER’S INSTRUCTIONS: 
 
A. Where manufacturers have furnished specific instructions, relating to the material/equipments to 
be  used  on  this  job,  covering  points  not  specifically  mentioned  in  this  document,  manufacturer’s 
instructions should be followed. 
2.05 COMPLETION DOCUMENTS AND DRAWINGS: 
 
A. Three copies of operation manuals/catalogues of all standard equipment are to be furnished by 
the contractor immediately after commissioning of plant. 
 
B. Three copies of write up on preventive maintenance, trouble shooting and operating instructions 
of  the  system  along  with  as‐built  drawings  are  to  be  supplied  by  the  Contractor  at  the  time  of 
commissioning. 
 
C. On  completion  of  the  work  in  all  respects,  the  Contractor  shall  supply  five  portfolios               
(300x450 mm), each containing complete set of drawings on approved scale, clearly indicating complete 
layouts, location; wiring and sequencing of automatic controls, location of all concealed wiring and other 
services.    Each  portfolio  shall  also  contain  consolidated  control  diagrams  and  technical  literature  on  all 
controls.    The  Contractor  shall  frame  under  glass,  in  the  Panel  rooms,  one  set  of  these  consolidated 
control diagrams. 
 
2.06 MATERIALS AND EQUIPMENT: 
 
All the materials and equipments shall be of the approved make and design. Unless otherwise called for 
any approval by Owner’s Engineer‐in‐Charge, only the best quality materials and equipment shall be used. 
 
A. Space Heaters: 
Suitable number of adequately rated heaters thermostatically controlled with On‐Off switch and fuse shall 
be  provided  to  prevent  condensation  in  any  panel  compartment.    The  heaters  shall  be  installed  in  the 
lower  portion  of  the  compartment  and  electrical  connections  shall  be  made  from  below  the  heaters  to 
minimize  deterioration  of  supply  wire  insulation.    The  heaters  shall  be  suitable  to  maintain  the 
compartment temperature to prevent condensation. 
 

PMC: NSL E 18
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

B. Fungi static Varnish: 
Besides the space heaters, special moisture and fungus resistant varnish shall be applied on parts, which 
may  be  subjected  or  predisposed  to  the  formation  of  fungi  due  to  the  presence  or  deposit  of  nutrient 
substances.  The varnish shall not be applied to any surface of part where the treatment will interfere with 
the  operation  or  performance  of  the  equipment.    Such  surfaces  or  parts  shall  be  protected  against  the 
application of the varnish. 
 
C. Ventilation Opening: 
In order to ensure adequate ventilation, compartments shall have ventilation openings provided with fine 
wire mesh of brass to prevent the entry of insects and to reduce to a minimum the entry of dirt and dust.  
Outdoor compartment openings shall be provided with shutter type blinds. 
 
D. Degree of Protection: 
The  enclosures  of  the  control  cabinet,  junction  boxes  and  marshalling  boxes,  panels.  etc  to  be  installed 
shall provide degree of protection as detailed her under. 
1. Installed indoor        :  IP‐55 
2. Installed indoor in air‐conditioned area  :  IP‐31 
3. Installed in covered area      :  IP‐42 
4. Installed indoor in non air‐conditioned area where possibility of entry of water is limited :IP‐41 
5. For LT Switchgear (AC and DC distribution boards) :IP‐42 
 
The degree of protection shall be in accordance with IS: 13947 (Part –I) IEC‐947 (Part –I). Type test report 
for degree of protection test, on each type of the box shall be submitted for approval. 
 
E. Rating plates, Name plates and Labels: 
LV  panel  and  auxiliary  items  installed  in  the  building  is  to  permanently  attach  to  it  in  a  conspicuous 
position.  A  rating  plate  of  non‐corrosive  material  with  engraved  manufacturer’s  name,  year  of 
manufacture,  equipment  name,  type  or  serial  number  together  with  details  of  loading  conditions  of 
equipment  in  question  has  been  designed  to  operate  and  such  diagram  plates  as  may  require  by  the 
owner. The rating plate of each equipment shall be in accordance to IEC requirement. 
All such nameplates, instruction plates, rating plates shall be bilingual with Hindi inscription first followed 
by English. Alternatively two separate plates on with Hindi and another with English inscriptions may be 
provided. 
 
F. Design Improvements: 
The bidder shall note that the equipment offered to him in the bid only shall be accepted for supply. 
If  for  any  reason,  contractor  wished  to  deviate  from  specification,  prior  permission  from  owner/ 
consultant shall be sought. 
If  any  change  is  agreed  upon  and  that  if  affects  the  price  and  schedule  of  completion,  the  parties  shall 
agree  in  writing  as  to  the  extent  of  any  change  in  the  price  and/  or  schedule  of  completion  before  the 
contractor  proceeds  with  the  change.  Following  such  arrangements,  the  provision  thereof,  shall  be 
deemed to have been amended accordingly in the specification. 
 
G. Quality Assurance Programme: 
To  ensure  that  the  equipment  and  services  under  the  scope  of  this  Contract  whether  manufactured  or 
performed within the Contractor’s works or at his sub‐contractor’s premises or at the Owner’s site or at 
any  other  place  of  work  are  in  accordance  with  the  specifications,  the  Contractor  shall  adopt  suitable 
quality  assurance  program  to  control  such  activities  at  all  points  necessary.    Such  programme  shall  be 

PMC: NSL E 19
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

outlined by the Contractor and shall be finally accepted by the Owner after discussions before the award 
of Contract.  A quality assurance programme of the contractor shall generally cover the following: 
1. His  organization  structure  for  the  management  and  implementation  of  the  proposed  quality 
assurance programme. 
 
2. Documentation control system. 
 
3. Qualification data for bidder’s key personnel. 
 
4. The  procedure  for  purchases  of  materials,  parts  components  and  selection  of  sub‐contractor’s 
services including vendor analysis, source inspection, incoming raw material inspection, verification of 
material purchases etc. 
 
5. System for shop manufacturing and site erection controls including process controls and fabrication 
and assembly control. 
 
6. Control of non‐conforming items and system for corrective actions. 
 
7. Inspection and test procedure both for manufacture and field activities. 
 
8. Control of calibration and testing of measuring instruments and field activities. 
 
9. System for indication and appraisal of is inspection status. 
 
10. System for authorizing release of manufactured product to the Owner. 
 
11. System for maintenance of records. 
 
12. System for handling storage and delivery and. 
 
The Owner or his duly authorized representative reserves the right to carry out quality audit and quality 
surveillance  of  the  system  and  procedure  of  the  Contractor  /  his  Vendor’s  quality  management  and 
control activities. 
 
H. Quality Assurance Documents 
The Contractor shall be required to submit the following Quality Assurance Documents within three weeks 
after dispatch of the equipment. 
 
1. All  Non‐Destructive  Examination  procedures,  stress  relief  and  weld  repair  procedure  actually  used 
during fabrication and reports including radiography interpretation reports. 
 
2. Welder and welding operator qualification certificates. 
 
3. Welder’s  identification  list,  listing  welder’s  and  welding  operator’s  qualification  procedure  and 
welding identification symbols. 
4. Raw material test reports on components as specified by the specification and / or agreed to in the 
quality plan. 
 
5. Stress relief time temperature charts/oil impregnation time temperature charts. 

PMC: NSL E 20
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
6. Factory  test  results  for  testing  required  as  per  applicable  codes/mutually  agreed  quality 
plan/standards referred in the technical specification. 
 
7. The quality plan with verification of various customer inspection points (CIP) as mutually and methods 
used to verify the inspection and testing points in the quality plan were performed satisfactory. 
 
2.07 INSPECTION, TESTING AND INSPECTION CERTIFICATES: 
 
A. The Owner and the Consultant or duly authorized representative shall have at all reasonable times 
free  access  to  the  Contractor’s  premises  or  works  and  shall  have  the  power  at  all  reasonable  times  to 
inspect and examine the materials and workmanship of the works during its manufacture or erection, if 
part  of  the  works  is  being  manufactured  or assembled at other premises or works, the Contractor shall 
obtain  permission  to  inspect  as  if  the  works  were  manufactured  or  assembled  on  the  Contractor’s  own 
premises or works.  Inspection may be made at any stage of manufacture, dispatch or at site at the option 
of the Owner and the equipment if found unsatisfactory due to bad workmanship or quality, material is 
liable to be rejected. 
 
B. All equipment being supplied shall conform to type tests and shall be subject to routine tests in 
accordance  with  requirements  stipulated  under  respective  sections.    Bidder  shall  submit  the  type  tests 
reports for approval. The Contractor shall intimate the Owner/Consultant the detailed programme about 
the tests at least three (3) weeks in advance in case of domestic supplies.  If for any item type test were 
pending payment would be made on successful completion of type/routine test(s) actually carried out as 
per Consultant/Owner instructions. 
 
C. The  Contractor  shall  give  the  Consultant/Owner  thirty  (30)  days  written  notice  of  any  material 
being  ready  for  testing.    Such  tests  shall  be  to  the  Contractor’s  account.    The  Consultant/Owner  unless 
witnessing of the tests is virtually waived will attend such tests within thirty (30) days of the date of which 
the  equipment  is  notified  as  being  ready  for  test/inspection,  failing  which  the  Contractor  may  proceed 
with the test which shall be deemed to have been made in the presence of Owner/Consultant and he shall 
forthwith forward to the Consultant duly certified copies of tests in triplicate. 
 
D. The Consultant/Owner shall within fifteen (15) days from the date of inspection as defined shall 
inform  in  writing  to  the  Contractor  of  any  objection  to  any  drawings  and  all  or  any  equipment  and 
workmanship which in his opinion is not in accordance with the Contract.  The Contractor shall give due 
consideration to such objections and make the necessary modifications accordingly. 
 
E. When the factory tests have been completed at the Contractor’s or Sub‐contractor’s works, the 
Consultant/Owner shall issue a certificate to this effect within fifteen (15) days after completion of tests 
but if the tests are not witnessed by the Consultant/Owner, the certificate shall be issued within fifteen 
(15) days of receipt of the Contractor’s Test certificate by the Consultant/Owner.  Failure of the issue such 
a certificate shall not prevent the Contractor from proceeding with the works.  The completion of these 
tests or the issue of the certificate shall not bind the Owner to accept the equipment should, it, on further 
tests after erection, is found not to comply with the Specification.  The equipment shall be dispatched to 
site only after approval of test reports and issuance of MICC by the Owner. 
 
F. For tests whether at the premises or at the works of the Contractor or of any Sub‐Contractor, the 
Contractor except where otherwise specified shall provide free of charge such items as labor, materials, 
electricity, fuel, water, stores, apparatus and instruments as may be required by Owner/Consultant or this 

PMC: NSL E 21
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

authorized  representative  to  carry  out  effectively  such  tests  of  the  equipment  in  accordance  with  the 
Specification. 
 
G. The  inspection  by  Owner/Consultant  and  issue  of  Inspection  Certificate  thereon  shall  in  no  way 
limit  the  liabilities  and  responsibilities  of  the  Contractor  in  respect  of  the  agreed  quality  assurance 
programme forming a part of the Contract. 
 
H. The  Consultant/Owner  will  have  the  right  of  having  at  his  own  expenses  any  other  tests(s)  of 
reasonable  nature  carried  out  at  Contractor’s  premises  or  at  site  or  in  any  other  place  in  addition  of 
aforesaid type and routine tests to satisfy that the material comply with the specifications. 
 
I. The  Owner/Consultant  reserves  the  right  for  getting  any  field  tests  not  specified  in  respective 
sections  of  the  technical  specification  conducted  on  the  completely  assembled  equipment  at  site.    The 
testing equipments for these tests shall be provided by the Contractor. 
 
2.08 TESTS: 
 
A. Charging (Pre‐commissioning tests): 
 
On  completion  of  erection  of  the  equipment  and  before  charging,  each  item  of  the  equipment  shall  be 
thoroughly  cleaned  and  then  inspected  jointly  by  the  Owner/Consultant  and  the  Contractor  for 
correctness  and  completeness  of  installation  and  acceptability  for  charging,  leading  to  initial  pre‐
commissioning tests at Site.  The pre‐commissioning tests to be performed as per relevant I.S. / vendor/ 
bidder submittal and as included in the Contractor’s quality assurance programme. 
 
B. Commissioning Tests: 
1. The  available  instrumentation  and  control  equipment  will  be  used  during  such  tests  and  the 
Contractor  will  calibrate  all  such  measuring  equipment  and  devices  as  far  as  practicable.    However, 
unmeasurable parameters shall be taken into account in a reasonable manner by the Contractor for 
the requirement of these tests.  The tests will be conducted at the specified load points and as near 
the  specified  cycle  condition  as  practicable.    The  Contractor  will  apply  proper  corrections  in 
calculation, to take into account conditions which do not correspond to the specified conditions. 
 
2. All instruments, tools and tackles required for the successful completion of the Commissioning Tests 
shall be provided by the Contractor, free of cost. 
 
3. Pre‐commissioning  test  shall  be  carried  out  as  per  relevant  IS  and/or  as  specified  in  the  relevant 
clause. 
 
4. The Contractor shall be responsible for obtaining statutory clearances from the concerned authorities 
for  commissioning  of  the  equipment.    However  necessary  fee  shall  be  reimburse  by  Owner  on 
production of requisite documents. 
 
2.09 PACKAGING: 
 
A. All  the  equipments  shall  be  suitably  protected,  coated,  covered  or  boxed and crated to prevent 
damage  or  deterioration  during  transit,  handling  and  storage  at  Site  till  the  time  of  erection.    While 
packing  all  the  materials,  the  limitation  from  the  point  of  view  of  availability  of  Railway 
wagon/truck/trailer sizes in India should be taken account of the Contractor shall be responsible for any 

PMC: NSL E 22
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

loss  or  damage  during  transportation,  handling  and  storage  due  to  improper  packing.    Any  demurrage, 
wharfage and other such charges claimed by the transporters, railways etc. shall be to the account of the 
Contractor.    Owner  takes  no  responsibility  of  the  availability  of  any  special  packaging/transporting 
arrangement. 
 
2.1 PROTECTION: 
 
A. All  coated  surfaces  shall  be  protected  against  abrasion,  impact,  discoloration  and  any  other 
damages.    All  exposed  threaded  portions  shall  be  suitably  protected  with  either  a  metallic  or  a  non‐
metallic protecting device.  All ends of all valves and piping and conduit equipment connections shall be 
properly  sealed  with  suitable  devices  to  protect  them  from  damage.    The  parts  which  are  likely  to  get 
rusted, due to exposure to weather should also be properly treated and protected in a suitable manner. 
 
2.2 FINISHING OF METAL SURFACES: 
A. General: 
All metal surfaces shall be subjected to treatment for anti‐corrosion protection.  All ferrous surfaces for 
external use unless otherwise stated elsewhere in the specification or specifically agreed, shall be hot‐dip 
galvanized  after  fabrication.    High  tensile  steel  nuts  and  bolts  and  spring  washers  shall  be  electro 
galvanize.    All  steel  conductors  used  for  earthing/grounding  (above  ground  level)  shall  be  galvanized 
according to IS: 2629. 
 
B. Painting: 
1. All sheet steel work shall be degreased, pickled, and phosphated in accordance with the IS‐6005 
“Code  of  practice  for  Phosphating  iron  and  sheet”.    All  surfaces,  which  will  not  be  easily  accessible 
after  shop  assembly,  shall  beforehand  be  treated  and  protected  for  the  life  of  the  equipment.    The 
surfaces,  which  are  to  be  finished  painted  after  installation  or  require  corrosion  protection  until 
installation, shall be shop painted with at least two coats of primer.  Oil, grease, dirt and swab shall be 
thoroughly  removed  by  emulsion  cleaning.    Rust  and  scale  shall  be  removed  by  pickling  with  dilute 
acid followed by washing with running water, rinsing with slightly alkaline hot water and drying. 
 
2. After Phosphating, thorough rinsing shall be carried out with clean water followed by final rinsing 
with  dilute  dichromate  solution  and  oven  drying.    The  phosphate  coating  shall  be  sealed  with 
application  of  two  coats  of  ready  mixed,  stoving  type  zinc  chromate  primer.    The  first  coat  may  be 
“flash dried” while the second coat shall be stoved. 
 
3. Powder coating/electrostatic painting of approved shade shall be applied. 
 
4. The exterior color of the paint shall be as per   IS‐5 or as approved by Consultant.  A small quantity 
of  finishing  paint  shall  be  supplied  for  minor  touching  up  required  at  site  after  installation  of  the 
equipments, if required. 
 
5. In case the Bidder proposes to follow his own standard surface finish and protection procedures 
or  any  other  established  painting  procedures  like  electrostatic  painting  etc.  the  procedure  shall  be 
submitted along with the Bids for Owner’s review and approval. 
 
2.3 HANDLING, STORAGE AND INSTALLATION: 
 
A. In accordance with the specific installation instructions as shown on manufacturer’s drawings or 
as directed by the Owner or his representative, the Contractor shall unload, store, erect, install, wire, test 

PMC: NSL E 23
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

and place into commercial use all the equipment included in the contract.  Equipment shall be installed in 
a neat, workmanlike manner so that it is level, plumb, square and properly aligned and oriented. 
 
B. Contractor shall follow the unloading and transporting procedure at site, as well as storing, testing 
and commissioning of the various equipment being procured by him separately.  Contractor shall unload, 
transport,  store,  erect,  test  and  commission  the  equipment  as  per  instructions  of  the  manufacturer’s 
Engineer(s) and shall extend full co‐operation to them. 
 
C. In  case  of  any  doubt/misunderstanding  as  to  the  correct  interpretation  of  manufacturer’s 
drawings  or  instructions,  necessary  clarifications  shall  be  obtained  form  the  Owner/Consultant.  
Contractor  shall  be  held  responsible  for  any  damage  to  the  equipment  consequent  for  not  following 
manufacturer’s drawings/instructions correctly. 
 
D. Where assemblies are supplied in more than the one section, Contractor shall make all necessary 
connections  between  sections.        All  components  shall  be  protected  against  damage  during  unloading, 
transportation,  storage,  installation,  testing  and  commissioning.    Any  equipment  damaged  due  to 
negligence or carelessness or otherwise shall be replaced by the Contractor at his own expense. 
 
E. The Contractor shall submit to the Owner every week, a report detailing all the receipts during the 
weeks.    However,  the  Contractor  shall  be  solely  responsible  for  any  shortages  or  damages  in  transit, 
handling and/or in storage and erection of the equipment at Site.  Any demurrage, wharfage and other 
such charges claimed by the transporters, railways etc. shall be to the account of the Contractor. 
 
F. The  Contractor  shall  be  fully  responsible  for  the  equipment/material  until  the  same  is  handed 
over tot he Owner in an operating condition after commissioning.  Contractor shall be responsible for the 
maintenance  of  the  equipment/material  while  in  storage  as  well  as  after  erection  until  taken  over  by 
Owner, as well as protection of the same against theft, element of nature, corrosion, damages etc. 
 
G. The  Contractor  shall  be  responsible  for  making  suitable  indoor  storage  facilities,  to  store  all 
equipment, which require indoor storage. 
 
H. The words ‘erection’ and ‘installation’ used in the specification are synonymous. 
 
I. Exposed  live  parts  shall  be  placed  high  enough  above  ground  to  meet  the  requirements  of 
electrical and other statutory safety codes. 
 
J. The  minimum  phase  to  earth,  phase  to  phase  and  section  clearance  along  with  other  technical 
parameters for the various voltage levels shall be maintained as per relevant IS. 
 
2.4 PROTECTIVE GUARDS 
 
A. Suitable  guards  shall  be  provided  for  protection  of  personnel  on  all  exposed  rotating  and  /  or 
moving machine parts.  All such guards with necessary spares and accessories shall be designed for easy 
installation and removal for maintenance purpose. 
 
B. The Contractor shall also conform to the general regulations governing personnel on the site and 
must keep to the working space allocated for their use.  
 

PMC: NSL E 24
Electrical: General Provisions Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

C. The  contractor  shall  be  responsible  for  any  kind  of  mishap,  etc.  happened  with  personnel.  The 
Owner shall not take the responsibility for any of such kind. 
 
2.5 TOOLS AND TACKLES: 
 
A. The Contractor shall supply with the equipment one complete set of all special tools and tackles 
for the erection, assembly, dismantling and maintenance of the equipments. 
 
END OF SECTION 

PMC: NSL E 25
Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
CONDUIT SYSTEM, CABLE TRAY, CABLE LADDER AND TRUNKING INSTALLATION 
 
 

PART 1 – GENERAL  
 
1.1 WORK DESCRIPTION 
 
A. This section describes the supply and installation of wiring facilities systems include conduits, 
cable trays, cable ladder and Trunking system, c/w associated fittings and accessories. 
 
B. All  cables  run  above  the  suspended  false  ceiling,  concealed  in  walls,  columns,  or  on  surface 
shall  be  supported  by  conduits,  cable  tray  and  Trunking  or  cable  ladder  system.    No  free 
slinging cable is allowed. 
 
C. The  cable  routes  as  shown  in  the  drawings  shall  be  used  as  a  guide  only.    Prior  to  the 
installation,  the  cable  routes  shall  be  coordinated  with  other  services.    Uncoordinated  and 
inaccessible routes after other services are installed, shall be relocated at the expense of the 
Contractor. 
 
D. All conduits, trunking, cable trays and cable ladders shall be earthed in accordance to IS: 4043. 
 
1.02 STANDARDS 
 
A. The complete wiring facilities system shall be manufactured, supplied, installed and tested in 
accordance  with  the  latest  revision  of  the  India‐Delhi  standards  and  the  appropriate  BS/IEC 
include: 
1. Steel Conduit and Fitting Accessories IS:9537 (Part‐II)/ BS4568 & BS731 
2. PVC Conduit and Fitting Accessories               IS‐9537/1983 (Part‐III)/BS6099 & BS4607 
3. Cable Tray                     BS729 
4. Cable Ladder                     BS729 
5. Cable Trunking                   BS4678 
 
B. The  complete  wiring  facilities  system  shall  also  conform  to  the  requirements  of  all  relevant 
local  codes,  as  applicable,  together  with  the  additional  requirements  referred  to  in  this 
Specification and Drawings, whichever is the more stringent and acceptable to the Engineer. 
 
C. In  the  adoption  of  standards  and  requirements,  the  Contractor  shall  take  the  following 
precedence: 
1. Engineer’s decision; 
2. Local codes of practice; 
3. Drawings; 
4. Specification; 
PMC: NSL E26
Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

5. International standards and requirements  
1.03 SUBMISSIONS 
 
A. All technical submissions shall be approved by the Engineer prior to the respective stages of 
construction. 
Routing of installation 
Sample with proprietary factory‐made accessories, elbows, risers, reducers, tees, crosses, etc.  
 

PMC: NSL E27


Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

PART 2 – PRODUCTS  
 
2.01 STEEL CONDUIT AND ACCESSORIES 
 
A. Steel Conduit 
1. All conduits shall be of heavy gauge  
2. solid drawn ERW welded manufactured out of 16 (1.6mm) gauge MS Sheet up to 32mm 
dia and of 14 (2 mm) gauge for sizes higher than this. 
3. Both inner and outer surfaces shall be smooth without burrs, dents and kinks. 
4. Conduits shall be black stove enameled inside and outside. The cross section of conduit 
shall be uniform throughout.  
5. The  welding  shall  be  uniform  such  that  welded  joints  do  not  yield  when  subjected  to 
flattening test. Welded joint shall not break when threaded or bent at an angle. 
6. Conduit shall conform to specifications of IS: 9537 (Part‐II) and the capacity of conduits 
shall be in accordance with the standards and shall never be exceeded. 
7. The minimum size of the conduit shall be 19/20mm dia. 
8. Care shall be taken to ensure that all conduits are adequately protected while stored at 
site prior to erection and no damaged conduit shall be used. 
 
Fittings 
1. Samples of conduit fittings shall be submitted for approval prior to installation. 
2. Fittings  shall  be  those  intended  for  use  with screwed conduits  and shall comply with IS 
9537.  However, bends, elbows and tees shall not be installed. 
3. Boxes  and  cover  plates  that  are  installed  outdoors  shall  have  fixing  lugs  exterior  to  the 
box so that fixing screws do not enter the box interior. 
4. Adaptors used with flexible conduits shall conform to IS: 9537. 
 
Circular Boxes 
1. Circular  boxes  shall  be  of  malleable  cast  iron,  galvanized  and  of  standard  pattern  with 
spout(s).  When used for connecting lengths of conduits, circular boxes shall be provided 
with cover plates of similar make that are complete with brass fixing screws. 
 
Rectangular Boxes 
1. Rectangular  boxes  (adaptable  boxes)  shall  be  of  mild  steel  not  less  than  2.4  mm  gauge 
and  galvanized.    When  used  as  junction  boxes,  lids  of  the  same  gauge  with brass fixing 
screws shall be used. 
 
Boxes for Accessories 
1. Boxes  for  accessories  shall  be  suitable  for  surface  mounting  or  recessed  mounting 
according  to  the  requirements.    Surface  mounted  boxes  and  accessories  shall  be  metal 
clad pattern.  Recessed boxes and accessories shall be complete with insulated moulded 
type cover plates conforming to IS: 5133 Part I‐1969. 
 
 

PMC: NSL E28


Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

Covers 
1.  All covers for boxes, etc shall be made of galvanized steel of 1.2 mm thickness. 
 
2.02PVC CONDUIT AND ACCESSORIES 
 
PVC Conduit 
1. All  conduits  shall  be  high  impact  rigid  2mm  thickness  PVC  heavy  duty  type  and  shall 
comply  with  I.E.E.  regulations  for  non‐metallic  conduit  2mm  thick  as  per  IS‐9537/1983 
(Part‐III). 
2. All sections of conduit and relevant boxes shall be properly cleaned and glued by using 
epoxy resin glue and the proper connecting pieces. 
3. Inspection  type  conduit  fittings  such  as  inspection  boxes,  drawn  boxes,  fan  boxes  and 
outlet boxes shall be M.S. or otherwise mentioned. 
4. Conduit shall be terminated with adopter/PVC glands as required. 
 
PVC Conduit Accessories 
1. Accessories used for conduit wiring shall be of an approved type complying to IS: 
3837‐1966. 
2. All accessories used shall be of standard white or black color, identical to conduit 
used. 
3. Plain  conduits  should  be  jointed  by  slip  type  of  couplers  with  manufacturer’s 
standard sealing cement. 
4. All conduit entries to outlet boxes, Trunking and switchgear are to be made with 
adaptors female thread and male bushes screwed. 
5. PVC‐switch and socket boxes with round knockouts are to be used.  The colors of 
these boxes and the conduits shall be the same. 
6. Standard PVC circular junction boxes are to be used with conduits for intersection, 
Tee‐junction, angle‐junction and terminal.  For the drawing‐in of cables, standard circular 
through boxes shall be used. 
7. Samples of accessories shall be submitted for approval prior to installation. 
8. All  jointing  of  PVC  conduits  shall  be  by  means  of  adhesive  jointing.    Adequate 
expansion joints shall be allowed to take up the expansion of PVC conduits. 
 
2.03CONDUIT INSTALLATION 
 
A. Layout 
1. The conduit layout and conduit routes shall be submitted for approval.  Allowance 
for adjustments due to site conditions shall be provided with no extra cost. 
2. Conduit  routes  shall  be  chosen  for  easy,  straight  runs  with  a  minimum  of  bends 
and  crossings.    Generally  they  shall  follow  the  structure  of  building,  running  at  right 
angles or in parallel to floors and ceilings.  Conduits shall be kept within 300 mm of floors 
and ceilings when running parallel to them. 
3. Outlet  boxes  for  housing  accessories  shall  be  used  as  draw  boxes.    The  total 
number of draw boxes shall be kept to a minimum and shall be provided so that conduit 
runs do not exceed 12 m or have more than two right angle bends. 

PMC: NSL E29


Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

4. All conduits shall be kept clear of gas and water pipes.  In particular, conduits shall 
be at least 150 mm away from gas pipes.  Where proximity to these pipes is unavoidable, 
they  shall  be  effectually  segregated  e.g.  using  rubber  or  other  insulating  material  to 
prevent appreciable voltage differences at possible points of contact.  Segregation from 
extra low voltage circuits and telecommunication circuits shall also apply unless these are 
wired to the same voltage requirements as lighting and power circuits. 
5. Conduits from different distribution boards shall not be connected to the same junction 
box.  Each run of conduit shall be assembled complete with draw‐in‐wires. 
 
Joints And Terminations 
1. Electrical and mechanical continuity shall be maintained throughout all conduit joints and 
terminations.    Conduit  threads  shall  be  thoroughly  cleaned  and  the  conduits  tightly 
screwed.  The conduit system shall be watertight after installation. 
2. Conduits shall be connected using couples or via boxes.  With a coupler, the ends of the 
conduit  shall  butted  close  together  and  the  running  coupler  is  screwed  tightly  on  and 
tightened by a locknut. 
3. Conduits terminating into boxes provided with spouts shall be threaded so that there are 
no  exposed  threads.    For  boxes  with  no  spouts,  the  termination  shall  be  made  using  a 
brass bush and a coupler.  The conduit is pushed through the knockout or drilled entry 
and the bush is screwed tightly onto its end.  The coupler is screwed to butt firmly against 
the exterior wall of the box. 
4. Where  conduits  are  not  jointed  or  terminated  in  boxes,  they  shall  be  terminated  in  a 
screwed brass bush. 
5. In all joints and terminations, conduit threads shall not be exposed.  Where this cannot 
be  avoided  as  in  a  running  coupler,  the  exposed  threads  shall  be  coated  with  red  lead 
paint to seal against the ingress of water. 
 
 
Bends 
1. Conduits  shall  only  be  bent  cold  with  an  approved  type  of  bending  block  or  bending 
machine, without altering the dimensions of their sections. 
2. All conduit bends shall be such as to permit compliance to the requirements for bends in 
cables to as stated in the BS 7671. 
3. Bends  shall  be  made  with  as  large  a  radius  as  the  position  of  the  conduit  within  the 
building  permits.    Where  the  bend  is  more  than  90  degree,  circular  or  rectangular 
junction boxes are to be used for connecting conduits. 
 
 
 
 
Cabling 
1. The  conduit  system  must  be  completely  installed  and  free  of  obstructions  and  sharp 
corners before any cables are drawn in.  Conduits shall be thoroughly swabbed to remove 
moisture and dirt immediately prior to the drawing in of cables. 

PMC: NSL E30


Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

2. Cables  shall  be  drawn  without  crossing  each  other  and  shall  not  be  pulled  against  the 
walls of the draw boxes.  Slack cables shall left in all draw boxes. 
3. Cables  shall  be  continuous  throughout  conduit  lengths  and  no  joints  are  permitted.  
There shall be no kink in cables, neither any cut, abrasion or chink in the cable insulation. 
4. The  same  conduit  shall  carry  the  lead  and  return  conductors  bunched  together.  
However, the same conduit shall not house cables from different distribution boards. 
5. Cables for power and lighting circuits and extra low voltage systems shall not be drawn 
into the same conduit.  Lighting and power final circuits shall be run in separate conduits 
except, where an adaptable box is employed as final distribution point, a number of final 
circuits may be grouped together in larger conduits between the distribution board and 
the adaptable box provided that all final circuits in one conduit are of the same phase.  In 
the case of three phase circuits, all three phases including neutral, if any, shall be drawn 
into the same conduit. 
6. Conduits  shall  not  constitute  the  earth  continuity  path  for  the  electrical  circuit.    A 
separate  circuit  protective  conductor  shall  be  installed  within  the  conduit.    The  whole 
conduit system shall be effectively earthed. 
7. Flexible conduits shall also have a separate earthing conductor installed within the tubing 
and connected at conduit ends.  Flexible conduits in general shall not be used for more 
than 3m length. 
8. Maximum  number  of  PVC  insulated  650/1100  V  grade/copper  conductor  cable 
conforming to IS:694‐1990 
 
Nominal  20mm  25mm  32mm  38mm  51mm  64mm 
Cross‐                         
Sectional 
area of 
Conductor 
in Sq.mm 
  S  B  S  B  S  B  S  B  S  B  S  B 
1  2  3  4  5  6  7  8  9  10  11  12  13 
1.50  5  4  10  8  18  12  ‐  ‐  ‐  ‐  ‐  ‐ 
2.50  5  3  8  6  12  10  ‐  ‐  ‐  ‐  ‐  ‐ 
4  3  2  6  5  10  8  ‐  ‐  ‐  ‐  ‐  ‐ 
6  2  ‐  5  4  8  7  ‐  ‐  ‐  ‐  ‐  ‐ 
10  2  ‐  4  3  6  5  8  6  ‐  ‐  ‐  ‐ 
16  ‐  ‐  2  2  3  3  5  5  10  7  12  8 
25  ‐  ‐  ‐  ‐  3  2  5  3  8  6  9  7 
35  ‐  ‐  ‐  ‐  ‐  ‐  3  2  6  5  8  6 
50  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  5  3  6  5 
70  ‐  ‐  ‐  ‐  ‐  ‐  ‐  ‐  4  3  5  4 
Note: 
 
i. The above table shows the maximum capacity of conduits for a simultaneous drawing 
in of cables. 

PMC: NSL E31


Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

ii. The  columns  heads  ‘S’  apply  to  runs  of  conduits  which  have  distance  not  exceeding 
4.25 m between draw in boxes and which do not deflect from the straight by an angle of 
more than 15 degrees.  The columns heads ‘B’ apply to runs of conduit which deflect from 
the straight by an angle of more than 15 degrees. 
iii. Conduit sizes are the nominal external diameters. 
 
Access And Drainage 
1. The  conduit  system  shall  be  rewirable,  that  is,  draw  boxes  must  be  accessible  for  the 
purpose.    Where  boxes  are  concealed,  their  covers  shall  be  flushed  with  the  finished 
surface. 
2. The need for accessibility notwithstanding, the conduit system shall be protected against 
the ingress of water and impurities.  When installed, conduits shall be kept dry and free 
of debris with approved pipe plugs or caps.  Such plugging is especially essential prior to 
pouring concrete for concealed installation.  As for boxes, they shall be covered by steel 
plates prior to concreting. 
3. When  installed  outdoor,  and  in  situations  liable  to  condensation  of  moisture,  conduits 
shall  be  arranged  to  be  self  draining,  so  that  water  may  drain  to  low  points  which  are 
fitted with a drain plug.  Conduits laid under concrete floors shall have watertight floor‐
traps of approved detail for access of these drainage points. 
4. Conduits  run  on  surfaces  other  than  structural  steel  members  shall  be  secured  using 
galvanized space bar saddles and brass fixing screws.  Spacing of saddles shall not exceed 
1.2 m for conduit sizes up to and including 25 mm and 1.8 m for sizes 32 mm and above. 
5. Conduits run on structural steel shall be secured using girder clips or an approved clamp.  
These  conduits  and  those  run  in  the  vicinity  of  structural  steel  shall  be  bonded  to  the 
steelwork using an efficient and permanent metallic connection.  The conduits shall not in 
any way be under mechanical stress. 
6. All conduit boxes except loop‐in patterns shall be fixed direct to the building structure in 
addition to the support provided by the conduits. 
7. Conduits terminating into surface boxes shall be secured by a minimum of 3 saddles at 
not less than 32 mm, 150 mm and 300 mm respectively from the box. 
8. Conduits  shall  be  painted  with  an  approved  paint  to  blend  with  visual  environment.    A 
zinc rich undercoat shall be provided before painting the final coat. 
 
2.04CABLE TRAY 
 
A. Cable  tray  shall  be  of  perforated  type  and  constructed  a  minimum  2.0  mm  hot  dipped 
galvanized mild steel for outdoor damp condition, and epoxy coated electro‐galvanized mild 
steel for indoor installation.  All cable trays shall be installed in a straight run parallel to walls 
where possible. 
 
B. Cable trays shall be supported by electro‐galvanized ‘U’ channel with galvanized threaded rod 
for indoor suspended tray and hot‐dipped galvanized for area subject to weather. 
 
C. All hangers shall be installed at 1 metre intervals and shall be primed and painted to match 
with the surrounding building finish approved by the Engineer. 

PMC: NSL E32


Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
D. For cable tray that are exposed to the weather, a hot‐dip galvanized covers of 1.5mm gauge 
steel, flush fixing type with gasket, shall be installed on top of the tray. 
 
E. Depending  on  the  size  of  cable  trays  spare  space  of  25%  shall  be  maintained  for  future 
expansion. 

F. Copper earth link bar shall be fixed at every joint of the cable tray run. 
 
 
 
 
2.05  CABLE LADDER 
 
A. All cable ladders and accessories installed indoors shall be heavy‐duty epoxy coated electro‐
galvanized mild steel type.  All cable ladders installed outdoors shall be heavy‐duty hot dipped 
galvanized hot rolled mild steel.  Thickness of the mild steel shall not be less than 2 mm.  
 
B. Cable ladder shall have a 150 mm high longitudinal side member for ladders width of 800 mm 
or above and 120 mm high longitudinal side member for ladder width less than 800 mm. 
 
C. The  rugs  shall  be  at  least  50  mm  wide,  with  slots  of  25  mm  x  10  mm  at  25  mm  intervals 
covering  the  length  of  the  rungs.    The  rungs  shall  be  space  at  300  mm  apart  along  straight 
lengths of the ladder. 
 
D. All nuts, bolts and washers for clips and brackets shall be zinc plated.  Each cable ladder shall 
be in standard manufacturer’s length and supplied complete with coupling sets consisting of 
fishplates, spined bolts, nuts and locking washers. 
 
E. The  complete  cable  ladder  installation  shall  be  provided  with  all  necessary  proprietary 
factory‐made  elbows,  risers,  reducers,  tees,  crosses,  drop‐outs,  etc.  and  any  site  fabricated 
items will not be permitted. 
 
F. Separate  flexible  earth  continuity  connectors  of  at  least  16mm2  copper  jumpers  shall  be 
installed between the ladder sections. 
 
G. All  cables  ladders  shall  be  supported  from  the  ceiling  concrete  slab,  steel  structures  or 
sidewalls  using  a  frame  system,  with  overhead  hangers,  support  channels,  hanger  rods  or 
angle brackets, beam clams and ceiling brackets. 
 
H. Fixings  and  supports  shall  be  installed  at  regular  intervals  not  exceeding  1000  mm  and  150 
mm from all bends, tees, inter‐sections and risers. 
 
I. When cable ladder is refined to install across structure expansion joints, the ladder shall be in 
two sections between supports installed on either side of the expansion joint. 

PMC: NSL E33


Electrical: Conduit system, cable tray Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
J. The  ladder  sections  shall  than  be  jointed  with  expansion  joint  fishplates,  bolts,  nuts  and 
washers installed in elongated holes permitting a lengthwise movement of 25 mm from the 
initial fastening position. 
 
K. For cable ladder that are exposed to the weather, a hot‐dip galvanized covers of 1.5mm gauge 
steel, flush fixing type with gasket, shall be installed on top of the ladder.  
 
L. Copper earth link bar shall be fixed at every joint of the cable ladder run. 
 
2.06CABLES TRUNKING 
 
A. Cable  trunking  shall  be  manufactured  from  1.6  mm  minimum  electro‐
galvanized  mild  sheet  steel  to  BS4678  finished  in  oven‐baked  electrostatically  coated  epoxy 
power coating with color to the Engineer’s choice. 
 
B. All trunking shall have removable lids extending over their entire lengths.  Lids 
shall  be  fixed  at  interval  not  exceeding  1  metre  by  means  of  brass  steel  screws  which  and 
protected against corrosion by a finish of zinc coating or equivalent to zinc coating. 
 
C. Factory‐made  bends,  joints,  elbow,  riser,  tee,  reducer  and  accessories  with 
same material shall be provided throughout the installation for trunking. 
 
D. Trunking space factor shall be in compliance with latest IS standards. 
 
E. Copper earth link bar shall be fixed at every joint of the cable trunking run. 
 
Note: All items mentioned in this section shall be manufactured to comply with the specifications 
of National Electrical Code (NEC) and National Electrical Manufacturer’s Association (NEMA) 
 
END OF SECTION 

PMC: NSL E34


Electrical: Earthing System Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

EARTHING SYSTEM 
 
PART 1 – GENERAL  
1.1 WORK DESCRIPTION 
 
A. This  section  specifies  the  engineering,  supply,  installation,  testing, 
commissioning  and  setting  to  work  of  the  complete  earthing  network  for  individual  earthing 
systems, circuit protective conductors and bonding conductors.  A complete earthing network 
comprising  cables,  copper  tapes,  electrodes  and  earth  bonding  of  all  relevant  necessary  non‐
current carrying metal parts of equipments/ apparatus shall have connected as required. 
 
B. The  system  shall  have  a  common  earthing  system  as  described  in  the 
Specification and as shown on the Drawings.  Individual earthing systems shall be provided as 
follows  as  per  drawing.    Earth  main  MV/LV/Generator  Electrical  Earthing  shall  have  2 
connection to the earthing system: 
1. MV Electrical Earthing 
2. LV Electrical Earthing 
3. Generator Earthing 
4. ELV Earthing 
5. Data Communication Earthing 
 
C. Sufficient  numbers  of  electrodes  interconnected  by  Cooper/  GI  (as  per  BOQ)  to  form 
earthing  mat  so  that  the  overall  earth  resistance  shall  be  less  than  1  ohm  for  each  individual 
earthing mat. 
 
D. The  number  of  earth  electrodes  of  the  earthing  mat  are  indicated  on  the  drawings  as 
minimum.    The  Contractor  shall  test  the  resistivity  of  soil  at  site.  Exact  number  of  earth 
electrodes shall be determined by the Contractor to achieve the earth resistance value subject 
to Engineer approval.  The complete earthing installation include earth plate, earth mat detail 
to achieve the earth resistance value shall be included in the Contract. 
 
E. The  Contractor  shall  inform  the  Engineer  or  his  representative  before  driving  Plate/  pipe 
earthing into the ground so that he may supervise the operation.  Driving shall be carried out 
only in the presence of the Engineer or the representative and all earthing plates/ pipes shall be 
submitted for the examination before use. 
 
1.2 STANDARDS 
 
A. Complete  earthing  system  shall  be  engineering  and  constructed  in 
accordance with the latest revision of the following standards and the appropriate BS/IEC: 
1. IS: 3043    :  Earthing 
2. BS6651    :  Lightning Protection System 
3. IEC 61024‐1‐2  :  Lightning Protection System 
 

PMC: NSL E35


Electrical: Earthing System Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

B. The detail of the Earthing System shall also conform to the requirements of 
all relevant local codes, as applicable, together with the additional requirements referred to in 
this  Specification  and  Drawings,  whichever  is  the  more  stringent  and  acceptable  to  the 
Engineer. 
 
1.3 SUBMISSION 
 
A. All  technical  submissions  shall  be  approved  by  the  Engineer  prior  to  the 
respective stages of construction. 
 
B. As minimum requirement, the submission shall include the following: 
1. Shop Drawings and Sample Submission; 
2. Builder’s work requirements; 
3. Testing  procedures  and  report  format  for  testing  of  the  earth  electrodes  and/or  earth 
strips; 
4. Soil resisting test report with calculation report for the details of the earthing system 
detail  including  quantity  and  layout  of  earth  electrodes  and/or  earth  strips  to  achieve  the 
required  earth  resistance.    The  report  shall  be  endorsed  by  the  Contractor’s  Installation 
Engineer who supervise and endorse the installation upon completion; 
5. Proposed  details  of  earthing  system  including  quantity  and  layout  of  the  earth 
electrodes and/or earth strips according to the calculation result. 
 
PART 2 – PRODUCT   
 
2.1 GENERAL 
 
A. The resistance between earthing system and the general mass of earth shall not be greater 
than 1 ohm. 
 
B. The earth loop resistance to any point in the electrical system shall not be in excess of 0.5 
ohms in order to ensure satisfactory operation of protective devices. 
 
C. The resistance to earth shall be measured at the following:‐ 
 
1. At each electrical system ground or system neutral ground. 
2. At  one  point  on  each  grounding  system  used  to  ground  electrical  equipment 
enclosures. 
3. At one point on each grounding system used to ground wiring system enclosures such 
as metal conduits and cable sheaths or armoured. 
 
D. All  earthing  conductors  shall  be  of  high  conductivity  copper/  G.I.  as  per  B.O.Q.  and  shall 
protected against mechanical damage. The cross‐sectional area of earth conductors shall not be 
smaller than half that of the largest current carrying conductor. However, the contractor shall 
use the sizes specified in the bill of quantities of the Tender.Common earth mats of resistivity of 
less than one (1) ohm, shall be constructed below the lowest floor structure prior to any ground 

PMC: NSL E36


Electrical: Earthing System Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

work  construction.    The  earth  mats  shall  comprise  the  complete  earth  electrodes,  earth 
strips/grids, earth inspection chambers, earth leads, main earth terminals, earth test link boxes 
at ground level, etc. Each individual earthing system shall have earth leads connecting its main 
earth terminal directly to an earth electrode underground as specified. 
 
E. All earthing products/accessories shall be according to IS standards. 
 
F. The mating surface of all tapes at joints etc shall be cleaned before clamping and all joints 
shall be riveted, joint with proper connector or exothermic welded.  All connections to electrical 
apparatus shall be made by a bolted connection in a visible and accessible position 
 
2.2 PIPE EARTH ELECTRODE 
 
A. G.I. pipe shall be of medium class 100mm dia and 3m in length. 
 
B. G.I.  Pipe  electrode  shall  be  cut  tapered  at  bottom  and  provided  with  holes  of  12mm  dia 
drilled not less than 7.5cm from each other upto 2m of length from bottom. 
 
C. The electrode shall be buried in the ground vertically with its top not less than 20cm below 
ground level. 
 
D. Clamping  of  the  earth  leads  to  the  earth  rod  shall  be  made  by  earth  clamp.    The  clamps 
shall be capable of providing a high pressure contact between the earth rod and the earth leads 
to achieve a low contact resistance. 
 
E. When two or more electrodes are driven to form a group, the heads of the electrodes in 
the group shall be bonded to each other by means of a 25 mm x 3mm GI/ Copper strip, laid at a 
depth of at least 600 mm in soil. 
 
F. All  earth  electrode  penetrations  through  basement  water  proofing  membranes  shall  be 
provided  with  manufacturer’s  recommended  water  seal  insert  sleeve  approved  by  Engineer.  
The installation of the water seal insert sleeve shall be under the supervision and endorsed by 
the  manufacturer’s  representative  to  ensure  the  installation  comply  with  the  manufacturer 
installation detail. 
 
2.3 PLATE EARTH ELECTRODE 
 
A. The  plate  earth  electrode  shall  consist  of  copper  plate  or  G.I.  plate  as  per  item  of  work.   
The plate electrode shall be buried in ground with its faces vertical and top not less than 4.5m 
below  Ground  level.  The  plate  shall  be  filled  with  charcoal  dust  and  common  salt  filling, 
extending 15cm around it’s on all sides.   
B. A watering pipe of 50mm dia of medium class G.I pipe shall be provided. 
 
C. The top of the pipe shall be provided with a funnel and a G.I. mesh screen for watering the 
earth.  In the case of pipe electrode a removable plug shall be provided.  

PMC: NSL E37


Electrical: Earthing System Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
D. The  earthing  lead  from  electrode  onwards  shall  be  suitably  protected  from  mechanical 
injury by a suitable dia medium class G.I. pipe in case of wire and size according to strip size. 
 
E. The overlapping of strips at joints shall done in approved manner 
a. GI strips shall be riveted with rivets/ bolted and welded. 
b. Copper strips shall be riveted with rivets/ bolted brass nuts, bolts and washers and 
brazed.    
 
F. The protection pipe within ground shall be buried at least 30 cm deep (to be increased to 
60cm in case of road crossing and pavements). 
 
G. The portion within the building shall be recessed in walls and floors to adequate depth. 
 
H. In the case of plate earth electrode the earthing lead shall be securely bolted to the plate 
with two bolts, nuts, check nuts and washers. 
 
I. In  case  of  pipe  electrode,  it  shall  be  connected  by  means  of  a  through  bolt,  nuts  and 
washers and cable socket. 
 
J. Main earthing conductor is taken from the earth electrode with which the connection is to 
be made. 
 
K. No earth pit shall be fixed within 1.5 M of a wall of foundation.  The location of the earth 
electrode will be such where the soil has reasonable chance of remaining moist.  Effort shall be 
made to locate them in grass lawns or near flower beds or water taps. 
 
2.4 EARTH INSPECTION CHAMBER 
 
A. Earth electrode shall be fitted with a heavy‐duty precast concrete inspection chamber/pit 
complete with heavy‐duty cover as specified on drawings. 
 
B. For  earth  electrodes  located  outside  or  on  the  apron  of  the  building,  earth  inspection 
chambers shall extend to a depth of not less than 300 mm below finished ground level and kept 
free of soil.  For earth electrodes located inside building, earth electrodes shall be buried not 
less than 100 mm below the floor slab structure. Each earth electrode shall be clearly marked 
‘SAFETY ELECTRICAL EARTH CONNECTION – DO NOT REMOVE. 
 
C. The  chamber  and  cover  shall  be  heavy  duty  detail  to  consider  the  traffic  load  at  the 
location  of  installation.    The  cover  shall  be  recessed  cover  to  receive  the  Architectural  floor 
finish at the location of installation. 
 
2.5 EARTH STRIP 
 
A. Earth strips/grids shall be of bare GI/ Copper strips of 25 mm x 3 mm as specified. 

PMC: NSL E38


Electrical: Earthing System Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
B. Earth strips shall be riveted or joint with proper connector to earth electrodes underground 
below the floor slab structure, and shall be buried not less than 300 mm below the floor slab 
structure. 
 
C. In order to minimise the mutual inductance between strips, earth strips shall be positioned 
at a distance not less than 6m apart unless otherwise specified. 
 
PART 3 – EARTH BONDING  
3.1 CIRCUIT PROTECTIVE CONDUCTOR 
 
A. Circuit  protective  conductor  (CPC)  is  a  system  of  conductors  joining  together  all  exposed 
conductive parts and connecting them to the main earth terminal. 
 
B. The  purpose  of  circuit  protective  conductor  is  to  provide  a  path  for  earth  fault  circuit  so 
that the protective device will operate to remove dangerous potential differences during a fault 
condition. 
 
C. The  circuit  protective  conductors  shall  take  the  form  of  separate  cable  with  a  sheath  in 
green/yellow color or copper tape of minimum size 25mm x 3mm. 
 
D. All  exposed  non‐current  carrying  metal  parts  of  light  fittings,  switchgears,  motors, 
enclosures, etc. shall be effectively earthed by circuit protective conductors for earth continuity 
protection. 
 
E. For  equipment  where  an  earth  terminal  is  provided,  the  earth  continuity  wire  shall  be 
firmly clamped.  Where no earth terminal is provided, the exposed metal part shall be cleaned 
of paint and surface rust before welding the earth continuity lead. 
 
F. The minimum size of the principal protective conductors shall be in accordance with to the 
current edition of IS: 3043/ BS7671 and BS7430. 
 
G. The  external  earth  terminal  on  the  outside  of  the  end  panel  of  any  switchboard  shall  be 
connected to the main earth bar provided in two independent points. 
 
H. Circuit  protective  conductors  shall  be  provided  in  electrical  and  mechanical  rooms  and 
along  the  routes  for  the  bonding  of  all  exposed  conductive  parts  and  extraneous  conductive 
parts.    A  suitably  sized  earth  terminal  shall  be  provided  at  each  zone  of  the  building  for  this 
purpose. 
I. All exposed conductive parts shall be effectively connected in an approved manner to the 
principal  protective conductors.  The circuit protective conductors shall be single core copper 

PMC: NSL E39


Electrical: Earthing System Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

cables  or  high  conductivity  annealed  copper  tapes  specified.    Unless  otherwise  specified,  the 
minimum  cross‐sectional  area  of  the  circuit  protective  conductors  shall  be  selected  in 
accordance with IS:3043/ BS7671: 
   
END OF SECTION 

PMC: NSL E40


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

PANELBOARDS 
 
 
PART 1 – GENERAL 
 
1.1 WORK DESCRIPTION 
 
A. This specification covers the ‘General Requirements’ for the design, manufacture, supply 
performance,  inspection,  testing  and  commissioning  including  supply  of  indoor  type  low 
voltage switch boards up to 1000 V including necessary termination, cabling and bus work 
required for satisfactory operation . 
 
B. The  Panel  boards  included,  distribution  boards  and  control  panels  shall  be  built  in 
accordance with IEC 439 “Factory Built Assemblies for Low Voltage” or BS 5486 “Factory‐
built Assemblies of Switchgear and Control Gear for Voltage up to and including 1000 AC 
and 1200V DC. 
 
C. All factory built assemblies subject to rain or wet conditions or located outside electrical 
switch  room  shall  be  weatherproof  constructed  to  IP  65,  able  to  withstand  high  impact 
strength  of  60  KN/m2  (min.),  temperature  resistant,  flame  retardant  and  corrosion 
resistant. 
 
D. Specific requirements shall be in accordance with single line diagram/specification & BOQ. 
 
E. The technical parameters of switchgear equipment’s, transformers etc. shall be referred.  
 
1.2 STANDARDS 
 
A. All equipment, material and components shall comply with the requirements of the latest 
editions  of  Indian  Standards  with  updated  amendments.  Standards  and  Regulations 
applicable in the area where equipment is to be installed shall also be followed. 
 
B. The equipment offered complying with other standards, these standards shall be equal to 
or  superior  to  those  specified  and  full  details  of  the  differences  shall  be  furnished  along 
with the tender. 
 
C. The  Panel  boards  shall  be  engineered  and  constructed  in  accordance  with  the  latest 
revision of the following Indian and British standards: 
 
1.  IS 13947     :  A.C. Circuit Breakers  
2.  IS 3427      :  Metal enclosed Switchgear & Control Gear 
3.  BS 162       :  Safety Clearances 
4.  IS 2705      :  Current Transformers  

PMC: NSL E41


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

5.  IS 3156      :  Voltage Transformers 


6.  IS 3202     :  Code of Practice for climate proofing of electrical equipment 
7.  IS 375    :  Marking & Arrangement for Switchgear Bus Bars, main 
connections         and auxiliary wiring. 
8.  ARE 722      :  A.C. Electric Meters 
9.  IS 1248      :  Direct acting Electrical Indicating Instruments 
10.  IS 3231      :  Electrical Relays for Power System Protection 
11.  IS 2544      :  Epoxy Cast Resin Insulators 
12.  IS 5082      :  Electrolytic Copper/ Aluminium 
13.  IS 5792      :  High Voltage HRC fuses 
14.  BS 88  :  Cartridge fuses for voltages up to and including 1000V AC and 
1500V DC. 
15.  BS 89  :  Direct acting electrical indicating analogue electrical measuring
instruments and their accessories. 
16.  BS 142  :  Electrical protective relays 
17.  BS 159  :  Busbar and Busbar connection 
18.  BS 1433  :  Copper for electrical purposes.  Rods and bars. 
19.  BS EN  :  Circuit‐breakers for over current protection for household and 
60898  similar installations. 
20.  BS 3938  :  Current transformers 
21.  BS EN  :  Low‐voltage  switchgear  and  control  gear,  Part  2  circuit‐
60947‐2  breakers. 
22.  BS 4794  :  Control switches (switching devices, Part 1 including contactor 
relays, for control and auxiliary circuits, for voltages up to and 
including 1000V AC and 1200V DC).  General requirements. 
23.  BS 5419  :  Air‐break  switches,  air‐break  disconnectors,  and  fuse 
combination  units  for  voltages  up  to  and  including  1000V  AC 
and 1200V DC. 
24.  BS 5420  :  Degrees of protection of enclosures of switch Part I great Part I 
and control gear for voltages up to and including 1000V AC and 
1200V DC. 
25.  BS 5424  :  Control  gear  for  voltages  up  to  and  including  1000V  AC  and 
1200V DC – Part 1 Contactors. 
26.  BS 5486  :  Low‐voltage  switchgear  and  control  gear  Part  1  assemblies. 
Part  I:  Requirement  for  type  tested  and  partially  type  tested 
assemblies. 
27.  BS 5685  :  Electricity  meters  –  Part  I:  Class  0.5,  1  and  2  single  phase  and 

PMC: NSL E42


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

poly phase, single‐rate and multi‐rate watt‐hour meters. 
28.  BS 5992  :  Electrical relays 
29.  BS 6004  :  PVC  insulated  cables,  (non‐armoured),  for  electric  power  and 
lighting. 
30.  BS 6231  :  PVC insulated cables for switchgear and control gear wiring. 
31.  IS 3043/  :  Earthing 
BS7430 
 
D. BS/IEC  or  IS  not  mentioned  above  but  are  applicable  to  this  installation  shall 
also apply. 
 
1.3 SUBMISSION 
 
A. Detailed  co‐ordination  with  other  services,  shop  drawings  for  various  electrical  layouts 
such as equipment layout and earthing layouts, including equipment installation and cable 
termination details etc. prior to start of work. 
 
B. Such drawings shall show the proposed method of construction of the cubicles, method of 
supporting  equipment  and  Busbar,  full  details  of  Busbar  layout,  method  of  support, 
electrical control wiring diagrams, equipment weight, colors, and surface treatment. 
 
C. The drawings shall also incorporate a full list of proposed materials.  The construction shall 
not commence until the drawings are approved for construction. 
 
D. Factory and site testing procedures and report formats shall also be included. 
 
E. Preparation of bill of materials for Different Items as mentioned in Schedule of Quantities. 
 
F. Lighting/power panel schedule. 
 
G. Interconnection drawing. 
 
H. Protection co‐ordination drawings/tables for complete power system. 
I. Shop inspection and testing procedures. 
 
J. Field testing and commissioning procedures. 
 
K. Preparation of as built drawings for the services the contractor is rendering. 
 
Any  other  work/activity  which  is  not  listed  above;  however  is  necessary  for  completeness  of 
electrical system.  
 
 

PMC: NSL E43


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

PART 2 – PRODUCTS 
 
2.1 PANEL BOARD 
 
A. The  switch  boards  shall  be  cubicle  type,  suitable  for  indoor  installation,  floor  mounting  and 
free standing. The design shall be totally enclosed, dust ‐ tight, damp‐proof and vermin proof 
offering degree of protection not less than IP‐42. 
 
B. Separate segregated compartments shall be provided for circuit breakers, bus bars, cable box, 
voltage  transformers,  wire  ways,  relays,  and  instrument  and  control  devices.  Switchgear 
cubicles/ modules shall be provided with hinged doors in front with facility for padlocking door 
handles. 
 
C. Vent  openings  shall  be  covered  with  grills  so  arranged  that  hot  gases  cannot  be  discharged 
through them in a manner that can injure the operating personnel. These vent openings shall 
be vermin proof. 
 
D. All panels shall be of same height, width and depth. Panels shall be bolted together to form a 
continuous flush front switch board, suitable for front of board operation.   
 
E. The switchgear cubicles shall be rigid and robust in design and construction, fabricated out of 
CRCA  sheet  steel.  Cubicles  shall  be  made  from  rigid  welded  structural  frames  made  of 
structural steel sections or of pressed/formed sheet steel of not less than 3mm thickness. The 
frames shall be enclosed by sheet steel of at least 2mm thickness, smoothly finished, leveled 
and free from flaws. Stiffeners shall be provided wherever necessary. 
 
F. All  doors,  panels,  removable  covers  shall  be  provided  with  non  deteriorating  (neoprene) 
gaskets all around the perimeter. 
 
G. All  doors  shall  be  removable  and  supported  by  concealed  type  hinges.  The  hinges  shall  be 
strong and braced to ensure freedom from sagging, bending and general distortion of panel or 
hinged part. 
 
H. Floor  mounted  cubicles  shall  be  provided  with  a  75mm  high  channel  base  frame.  The  total 
height  of  the  cubicle  shall  not  exceed  2400mm,  keeping  in  view  the  operating  height  of  top 
switch should not exceed 1750mm from FFL including base channel. 
 
2.2 BUSBARS & BUSBAR CHAMBER 
 
A. Three phase bus bars shall be of high conductivity electrolytic Aluminium as stated in B.O.Q. 
 
B. The bus bars shall be air insulated and housed in a separate compartment, segregated from all 
other compartments. 
 

PMC: NSL E44


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

C. Bus bars & bus bar connections shall be of uniform cross section shall be suitable for carrying 
rated  current  continuously  and  short  circuit  current  for  specified  duration  without 
overheating.  The  bus  bars  connections  shall  be  adequately  supported  on  insulators  to 
withstand  dynamic  stresses  due  to  short  circuit  current  specified.  Normal  operating 
temperature for bus bars shall be 85 Deg C.  Short circuit rating of the bus bars shall be 20 to 
50 KA for 1 sec as per BOQ. 
 
D. All bus bar joints and bus tap joints shall be silver or tin plated. Joints shall be bolted type and 
shall be insulated. Spring/Lock washers shall be provided to ensure good contact on the joints. 
 
E. Direct access to accidental contact with bus bars and primary connections shall be avoided by 
providing shrouds. All apertures and slots shall be protected by barriers to prevent accidental 
shorting  of  bus  bars.  To  provide  a  tight  seal  between  cubicles,  bushings  or  insulating  panels 
shall be provided for bus bars crossing from one cubicle into another. 
 
F. All  insulating  materials  used  shall  be  non‐hygroscopic  and  shall  be  treated  for  preventing 
fungus  growth.  Surface  of  insulators  shall  be  highly  glazed  and  treated  with  silicone 
compounds to minimize accumulation of dust, condensation and tracking. 
 
G. All bus bars shall be color coded as per IS:‐375. 
 
2.3 CURRENT TRANSFORMERS (CTs) 
 
A. Current transformers shall be of suitable ratio, burden & class/accuracy as specified in Single 
Line Diagram. 
 
B. Current  transformers  shall  conform  to  latest  edition  to  relevant  standards.  The  Current 
transformers shall be epoxy resin cast with bar Primary or ring type. 
 
C. The  design  and  construction  shall  be  sufficiently  robust  to  withstand  thermal  and  dynamic 
stresses due to the maximum short circuit current of the circuit. 
 
D. The  current  transformer  shall  preferably  be  capable  of  being  left  open  circuited  on  the 
secondary side with primary carrying rated full load current, without overheating or damage. 
Short time current rating and rated withstand time shall be same as corresponding C.B. 
 
E. CT core laminations shall be of high grade silicon steel. 
 
F. Secondary  terminals  of  CT  shall  be  brought  out  to  a  terminal  block  which  will  be  easily 
accessible  for  testing  and  external  connections.  Facility  shall  be  provided  for  short  circuiting 
and earthing of CT secondary leads through a removable and accessible link with provision for 
attaching test link. 
 
G. Rating plate details and terminal markings shall be according to the latest edition of relevant 
Indian Standard specification. 

PMC: NSL E45


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
H.  Current transformers (core) shall be used for metering and protection. 
 
2.4 POTENTIAL TRANSFORMERS (PTs) 
 
A. Potential Transformers shall conform to latest edition of relevant standards. 
 
B. Potential  transformers  shall  be  dry,  cast  epoxy  resin  type.  The  PTs  shall  be  of  single  phase 
construction.  
 
C. The PTs shall be capable of operating continuously at 110% of the rated voltage without any 
damage. When star ‐ star connection is required in non‐effectively or ungrounded system, the 
PTs shall be suitable for continuous operation with a persistent phase to ground fault. 
 
D. Maximum temperature rise of the transformer at rated burden and with rated primary voltage 
and frequency shall not exceed 40 Dig’s above an ambient of 45 Dig’s. 
 
E. HRC  Fuses  shall  be  provided  secondary  side.  It  shall  be  possible  to  replace  PT  fuses  easily 
without having to de‐energies the main bus bars. Prospective interrupting current rating of the 
fuses shall be same as the system fault level. 
 
F. Voltage transformer ratio, output and class shall be as specified in the drawing & BOQ. Name 
plate as per relevant standards shall be provided on the PT. 
 
2.5 PROTECTIVE RELAYS 
 
A. Relays type and numbers shall be in accordance with the protective scheme specified or as per 
drawings and B.O.Q. 
 
B. Relays  shall  be  enclosed  in  rectangular  shaped  cases,  suitable  for  flush  mounting  only,  dust 
tight covers projecting from the front cover panel. The case shall be dust tight, damp proof and 
tropicalised. 
 
C. Relays shall be accessible for setting from the front. Access to setting devices shall be possible 
only after removal of front cover. 
 
D. Protective relays shall be draw out type. Where it is not possible to provide protective relays of 
the draw out pattern, fixed type relays with facilities for plugging in a portable test plug shall 
be provided. Necessary test plugs shall be furnished along with the relays. 
 
E. Relays shall be provided with positive action self reset type with indicator. The indicator/s shall 
be visible from the front. 
 
F. Relays conform to relevant standards in all respects. 
 

PMC: NSL E46


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

G. Relays  shall  be  provided  with  minimum  two  pairs  of  self  or  hand  reset  type  contacts  as 
specified.  Auxiliary  relays  shall  have  the  number  of  NO  and  NC  contacts  as  specified  in  data 
sheet. 
 
2.6 SAFETY/ PROTECTION & INTERLOCKS/FEATURES 
 
Following  interlocks  and  features  shall  be  incorporated  for  equipment  protection  and 
personnel  safety  under  mal‐operation.  No  deviations  on  these  interlocks  and  safety  features 
are allowed. These interlocks and safety features shall be fail‐safe, positive and full‐proof. 
 
A. It shall not be possible to plug‐in or isolate a closed circuit breaker. An attempt to do so shall 
trip  the  breaker.  (In  case  of  breakers  with  vertical  isolation,  this  will  apply  to  raising  and 
lowering).  There  shall  be  a  positive  locking  facility  to  prevent  closing  of  circuit  unless  it  is  in 
Service or Test position. 
 
B. Closing and opening operations shall be possible only in discrete, well defined Test and Service 
positions and not in any position midway. An extension adapter cable with plugs and sockets 
shall be preferably be provided so that the closing and opening operation of the circuit breaker 
can be done in fully withdrawn position outside the cable. 
 
C. Slow  operation  of  circuit  breakers  shall  be  possible  only  in  the  circuit  breaker  in  Test  or 
Isolated position. 
 
D. Isolating  switches  if  provided  shall  be  interlocked  with  respective  circuit  breakers to prevent 
them making or breaking the current. 
 
E. 1 no. bus earthing truck shall be supplied with each panel to earth the out going cable of the 
VCB breaker. 
 
F. Automatic  safety  shutters  for  all  openings  which  will  lead  to  access  to  the  live  parts  of  the 
switchgear  upon  withdrawal  or  any  operation  the  switchgear  components/parts  shall  be 
provided, preferably with a padlocking facility. 
 
G. Spring  of  motor  operated  spring  charged  mechanism  shall  not  discharge  until  they  are  fully 
charged and charging means are fully disconnected. 
 
H. Where key interlocking is employed, tripping of a closed circuit breaker shall not occur if any 
attempt is made to remove the trapped key from the mechanism. 
 
I. Any other interlocks which manufacturer may deem to be required for safety and specifically 
specified separately required for the system shall be included. 
 
J. All  terminals,  connections  which  may  be  live  and  exposed  for  accidental  contact  shall  be 
adequately shrouded. 
 

PMC: NSL E47


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

K. Components within cubicles shall be properly labeled to facilitate testing. 
 
2.7 EARTHING 
 
A. The switch board shall be provided at the bottom throughout its entire length with an earth 
bus of copper of adequate size to carry the fault current for the duration same as short time 
rating of the circuit breaker. Earth bus shall have two earthing connection facility at its both 
ends of earthing conductor. 
 
B. All non‐current carrying metal parts, frames and equipment mounted in the switch board shall 
be bonded to earth bus. 
 
C. Earthing  of  moving  carriage  of  draw  out  equipment  shall  be  achieved  by  scraping  earthing 
device.  The  earthing  device  shall  maintain  positive  earth  continuity  in  all  Service  Test  and 
Isolated positions. 
 
D. It  shall  be  possible  to  connect  each  circuit  or  set  of  three  phase  bus  bars  to  earth  either 
through earthing trucks or through the circuit breakers. 
 
E. One  earthing  trolley  suitable  for  earthing  of  cables  &  bus  bars  for  all  circuit  breakers  of  the 
same type/rating shall be provided. 
 
2.8 INSTRUMENT & METERS 
 
A. Electrical indicating instruments shall be digital type with zero adjustment, probe from outside 
the cover. 
 
B. Multi function meter of CL 1.0 accuracy with RS 485 port shall be provided. 
 
C. Instruments/meters shall be suitable for flush mounting on the panel with flanges protecting 
outside the panel. 
 
D. All meters shall be industrial grade with accuracy of class 1.0 unless specifically indicated. 
 
2.9 CONTROL WIRING 
 
A. All wiring for control, protection, alarm and indicating circuits on all equipment shall be carried 
out with at least 650V grade, PVC insulated, stranded, copper, 1.5 Sq.mm conductors. 
 
B. All  wiring  shall  be  run  on  the  sides  of  the  panels  and  shall  be  neatly  bunched  and  cleared 
without affecting access to equipment mounted in the panel. Where wiring enters or passes 
through  compartments  containing  HT  apparatus  then  they  shall  be  in  earthed  metallic 
conduits or ducts. 
 
C. All wiring shall be taken to terminal blocks without joints or tees in their run. 

PMC: NSL E48


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
D. All wiring shall be color coded as follows: 
 
 Instrument Transformer AC circuit   ‐   Red, Yellow & Blue determined by 
                      the Phase with which the wire is associated. 
 AC Phase Wire                         ‐   White 
 AC Neutral                           ‐   Black 
 DC Circuits                           ‐   Grey 
 Earth connections                     ‐   Green 
 
E. Engraved core identification ferrules, marked to correspond with the wiring diagram shall be 
fitted  to  each  wire.  Ferrules  shall  fit  tightly  on  the  wires,  without  falling  off  when  wire  is 
removed. Ferrules shall be of white color with black lettering. Each wire shall be identified by 
letter to denote its function followed by a number to denote its identity at both ends. 
 
F. All  wiring  for  external  connections  shall  be  brought  out  to  individual  terminals  on  a  readily 
accessible terminal block. 
 
G. All  unused  auxiliary  contacts  of  the  circuit  breaker  and  relays  shall  be  wired  up  to  terminal 
block. 
 
2.10 FITTINGS AND ACCESSORIES 
 
A. Indicating Lamps 
 
1. LED  type  indicating  lamps  shall  be  provided  everywhere  except  where  low  voltage 
filament type with series resistor called for. 
 
2. Lamp  covers  shall  be  provided  with  interchangeable  colored  lenses  of  Perspex  or 
equivalent  unbreakable  material.  The  lenses  shall  not  discolor  in  course  of  time  due  to 
heat of the lamp. 
 
3. Bulbs and lenses shall be interchangeable and replaceable from the front. 
 
4. Following colors shall be used for the function indicated: 
 
Red          ‐    Circuit Breaker ‘ON’ 
Green        ‐    Circuit Breaker ‘OFF’ 
White        ‐    Continuous trip supply supervision 
Amber        ‐    Auto trip 
Blue         ‐    Spring charged 
R.Y.B        ‐    Potential indication 
 
B. Push Buttons 
 
PMC: NSL E49
Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

1. All push buttons shall be push to actuate the contact type. 
 
2. Start  &  Stop  push  buttons  shall  be  colored  green  and  red  respectively.  Reset  push 
buttons shall be yellow in color and test push buttons shall be blue in color. All other push 
buttons shall be black in color. 
 
3. Emergency  stop  push  buttons  shall  be  lockable  in  the  operated  position,  i.e.  push  to 
operate  and  key  to  release  type.  Push  buttons  for  emergency  stop  shall  be 
recessed/shrouded type to avoid accidental operation. 
 
C. Control & Selector Switches 
 
1. Control  and  Selector  switches  shall  be  of  rotary  type,  having  enclosed  contacts 
accessible only after removal of cover. 
 
2. All control and selector switches for circuit breakers and instruments shall be mounted 
on the front of the panel. Control switches for space heater/s and control supplies shall be 
mounted inside the panel. 
 
3. Circuit  Breaker  control  switches  shall  be  provided  with  pistol  grip  handles.  Selector 
switches shall be provided with round, knurled handles. All handles shall be black in color. 
Properly designated escutcheon plates clearly marked to show the operating positions shall 
be provided on all switches. 
 
4. Circuit breaker control switches shall normally have three position close ‐ Normal ‐ Trip 
with  spring  return  to  normal  position.  Switch  operating  mechanism  shall  prevent  the 
switch  from  being  operated  twice  successively  in  the  same  direction.  Circuit  breaker 
control switch shall have one NO‐NC contact along with other contacts as required. 
 
5. All other instruments and selector switches shall have stay put contacts. 
 
6. Contacts of all control and selector switches shall be rated for 10 Amps at 240V AC or 
20 Amps at 220V dc (inductive break). Switch for space heater supply and control voltage 
supply shall normally be two pole rated for 25A A.C. 
 
D. Control Terminal Blocks 
 
1. Box  ‐  clamp  type,  650V  grade  line  up  terminals  of  minimum  2.5  Sq.mm  size  shall  be 
provided. Connection to terminals shall be from front. 
 
2. Not  more  than  one  wire  on  each  side  shall  be  connected  on  any  terminal.  Where 
duplication  of  terminals  block/s  is  necessary,  suitable  solid  bonding  links  shall  be 
incorporated. 
 

PMC: NSL E50


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

3. Terminal  blocks  at  different  voltage  shall  be  segregated  into  groups  and  distinctly 
labeled. 
 
4. Current transformer secondary leads shall be brought to terminal blocks having facility 
for short circuiting and grounding the secondary. 
 
5. Terminals  shall  be  numbered  for  identification  and  grouped  according  to  function. 
Engraved back on white PVC labels shall be provided on the terminal blocks describing the 
function of the circuit. 
 
6. Separate terminal stems shall be provided for internal and external wiring. 
 
7. Control terminal blocks shall be so located that control cables are fully segregated from 
power cables. Suitable insulated or earthed metal race ways shall be provided for control 
wiring. Separate unrolled removable gland plate shall be provided for the control cables at 
the bottom of each panel. 
 
8. Minimum 10% of total number spare terminals shall be provided for future use. 
 
2.11 NAME PLATES AND LABELS 
 
A. One Name plate giving designation of the MV switchboard shall be affixed prominently 
on top of the switch board. Details of designation will be specified. 
 
B. Labels giving following details shall be affixed on each feeder panel: 
 
i. Feeder No. 
ii. Equipment reference no. & Description 
iii. Rating (HP/KW/KVA/Amp.) 
 
C. All  components  whether  mounted  inside  or  on  the  door  shall  be  permanently  and 
clearly labeled with reference number/letter or their function. Rating of fuse shall be part 
of fuse designation. Paper labels, stickers or labels fixed with adhesives are not acceptable. 
All  labels  shall  be  properly  fixed  by  screws  with  provision  to  prevent  distortion  due  to 
expansion. 
 
D. All labels shall be non‐corroding, preferably laminated plastic or rear engraved Perspex 
with white letters on black background. 
 
E. Labels  for  feeder  panel  designation  fixed  on  front  side  shall  be  fitted  with  chrome 
plated, self tapping, and counter sunk head screws. These labels shall be of identical size 
to permit interchange. 
 
2.12 SPACE HEATERS 
 

PMC: NSL E51


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

A. Adequately rated anti‐condensation space heaters shall be provided in each cubicle. 
 
B. Space heater/s shall be trip type, rated with operation voltage of 240V, 50 Hz. AC supply.   
 
C. Each space heater shall be complete with a 2P MCB, 10KA and a control thermostat. 
 
D. The space heater shall be rated for maintaining the panel inside temperature 10 Deg.C above 
outside ambient temperature. 
 
2.13 CUBICLE LIGHTING 
 
A.       Each  cubicle  shall  be  provided  with  interior  lighting  by  means  of  CFL  light  fixture.  An 
ON/OFF  switch/door  switch  shall  be  provided.  The  lighting  fixture  shall  be  suitable  for 
operation from a 240V single phase, 50 Hz. A.C. supplies. 
 
2.14 AUXILIARY SUPPLY 
 
A. Auxiliary  supply  for  control,  indication,  space  heater  etc.  shall  be  made  available  at  one 
point  on  the  switch  board.  Vendor  shall  provide  suitable  auxiliary  supply  in  the  switch 
board. 
 
2.15 FUSES 
 
A. Fuses shall be HRC cartridge link type (Diazed Fuses are not acceptable) and shall be provided 
with operation indicator which shall be visible without removal of fuses from service. 
 
B. Fuses  shall  be  pressure  fitted  type  and  shall  preferably  have  ribs  on  the  contact  blades  to 
ensure good line contact. 
 
C. It shall be possible to handle fuses during off load conditions with full voltage available on the 
terminals.  Wherever required fuse pullers shall be provide.  The fuse bases shall be so located 
in  the  modules  to  permit  insertion  of  fuse  pullers  and  removal  of  fuse  links  without  any 
problems. 
 
D. Mounting of fuse fitting shall ensure adequate dissipation of heat generated and shall facilitate 
inspection and easy replacement of fuse. 
 
2.16 CONTACTORS 
 
A. The contactors shall be air break type, equipped with three main contacts and minimum 2 
NO + 2 NC auxiliary contacts. The main contacts of a particular contactor shall have AC 3 
ratings for unidirectional motors & AC 4 for reversible motors.  
 
B. The  auxiliary  contacts  shall  be  rated  for  minimum  5  Amps  at  240V  AC  and  1.3  Amps  at 
110V DC (Inductive load). 

PMC: NSL E52


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
C. Unless  specified  otherwise,  the  coil  of  the  contactor  shall  be  suitable  for  operation  on 
240V, + 10% and – 15% 1 PH, AC supply. The contactor drop off voltage shall be between 
15% to 65% of the rated coil voltage. 
 
2.17 SINGLE PHASING PREVENTOR (SPP) 
 
A. Unless  specified  otherwise  SPPs  shall  be  provided  in  all  motor  starter  modules  with 
contactor rating of 200 Amps and above.  The SPP shall be of the current operated type and 
shall operate on the principle of sensing negative sequence component of current. 
 
B. In case of single phasing, the SPP shall operate after a time delay of 2 to 3 secs.  The 
relay  shall  be  of  the  hand  reset  type  and  visual  indication  of  the  relay  operation  shall  be 
available. 
 
C. The  SPP  shall  be  suitable  for  protection  of  the  non‐reversible  and  reversible  motors.  
The  relay  operation  shall  be  independent  of  the  loading and RPM of the motor prior to the 
occurrence of single phasing. 
 
2.18 CABLE TERMINATION 
 
A. The  switch  board  panel  shall  be  complete  with  suitable  cable  end  termination  for  XLPE 
insulated cables. Cable and sealing box shall preferably be mounted inside the panel. For XLPE 
cables  adequate  space  and  clearances  shall  be  made  for  heat  shrinkable  termination  e.g. 
Raychem or cold flowing stress grading joints. 
 
B. Two  earthing  terminals  shall  be  provided  in  each  panel  in  cable  box/cabling  chamber  for 
earthing armour/screen. 
 
C. Where more than one core is terminated on each phase, links suitably designed and properly 
supported shall be provided to avoid unnecessary bending of cable cores without decreasing 
the  length  of  insulated  cable  tail.    Electrical  clearances  which  would  normally  be  required 
when using one core per phase shall be maintained. 
 
D. Where  core  balance  type  current  transformers  are  provided  on  switchgear  feeder  circuit 
cable/s  for  earth  fault  protection  sufficient  space,  clearance  and  support,  mounting 
arrangement shall be provided for the CT. 
 
 
PART 3 – EXECUTION 
 
3.1 TESTING AND COMMISSIONING 
 

PMC: NSL E53


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

A. All  panel  boards  shall  be  inspected  &  tested  in  the  presence  of  Owner/  Consultant’s 
representative  and  certified  by  the  installation  Engineer  that  it  is  safe  before  supply  is 
energized, and that all the equipment comply with the requirements of the Specification. 
 
B. Generally such tests in the factory and repeated at site are as follows: 
 
1. All routine tests specified in relevant Indian/British Standards shall be carried out on all 
circuit breakers. 
2. Test for protective relay operation by secondary injection method. 
3. Operation of all meters. 
4. Secondary wiring continuity test 
5. Insulation test with 1000 Volts mugger, before and after voltage test. 
6. HV test on secondary wiring and components on which such test is permissible (2 KV 
for one minute) 
7. Simulating  external  circuits  for  remote  operation  of  breaker,  remote  indicating  lights 
and other remote operations, if any. 
8. Measurement of power required for closing/trip coil of the breaker. 
9. Pick up and drop out voltages for shunt trip and closing coils. 
10. CT Polarity test. 
11. Power frequency voltage withstand test. 
12. Earth continuity tests; 
13. Check of clearance and creep age distances; 
14. Tests  to  prove  correct  operation  of  controls,  interlocks,  tripping  and  closing  circuits, 
indications, etc.; 
15. Interfacing test with BMS control function 
16. All other tests required by the Engineer to verify compliance with the Specification. 
 
C. Triplicate  sets  of  all  principal  test  records  and  test  certificates  are  to  be  supplied  for  all  the 
tests  carried  out  in  accordance  with  the  Specification  to  the  Engineer  for  approval  before 
dispatch from the factory. 
 
D. All costs, materials, equipment, labour, etc. necessary for the execution of the testing shall be 
included in this portion of work. 
 
3.2 DRAWINGS AND INFORMATION 
 
A. The  Vendor  shall  furnish  following  drawings/documents  in  accordance  with  enclosed 
requirements: 
 
1. General  Arrangement  drawing  of  the  Switchboard,  showing  front  view,  plan, 
foundation  plan,  floor  cut‐outs/trenches  for  external  cables  and  elevations,  transport 
sections and weights. 
 

PMC: NSL E54


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

2. Sectional  drawings  of  the  circuit  breaker  panels,  showing  general  constructional 
features, mounting details of various devices, bus bars, current transformers, cable boxes, 
terminal boxes for control cables etc. 
 
3. Schematic  and  control  wiring  diagram  for  circuit  breaker  and  protection  including 
indicating devices, metering instruments, alarms, space heaters etc.   
 
4. Terminal plans showing terminal numbers, ferrules markings, device terminal numbers, 
function etc. 
 
5. Relay wiring diagrams. 
 
6. Equipment List. 
 
B. Vendor  shall  furnish  required  number  of  copies  of  above  drawings  for  Purchaser’s  review, 
fabrication  of  switch  boards  shall  start  only  after  Purchaser’s  clearance  for  the  same.  After 
final review, required number of copies and reproducible shall  be furnished as final certified 
drawings. 
 
C. The information furnished shall include the following: 
 
1. Technical literature giving complete information of the equipment. 
 
2. Erection, Operation and Maintenance Manual complete with all relevant information, 
drawings and literature for auxiliary equipment and accessories, characteristics curves for 
relays etc. 
 
3. A comprehensive spare parts catalogue. 
 
3.3 TOOLS 
 
A. One complete set of all special or non‐standard tools required for installation, operation 
and maintenance of the switch board shall be provided. The manufacturer shall provide a 
list of such tools individually priced with his quotation. 
 
3.4 SPARES 
 
A. The manufacturer/tendered shall also supply a complete list of commissioning spares and 
tools.  The same shall be included in the bid price.  No extra  payment shall be made on 
account of non‐availability of spares during commissioning. 
 
3.5 TRANSPORTATION 
 
A. Panel boards are not allowed to be delivered to site until the electrical room or switch room is 
in a clean and acceptable condition with lockable doors. 

PMC: NSL E55


Electrical: Panel Boards Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
B. Panel  boards,  transported  to  site  shall  be  fully  covered  with  weatherproof  covers  and 
transportation eye bolts shall be provided for handling at site. 
 
C. Panel boards, which are poorly packed and result in signs of corrosion, will be rejected. 
 
D. All necessary measures to cover and protect the panel boards at site shall be provided.  Such 
measures shall include a complete PVC blanket over the whole panel boards. 
 
3.6 REJECTION OF PANELBOARDS 
 
A. Deviation from specification must be stated in writing at the quotation stage. 
 
B. In absence of such statement, it will be assumed that the requirements of the specifications 
are met without expectation. 
 
C. If  any  of  the  above  tests  fail  to  comply  with  the  requirements  of  this  Specification  in  any 
respect whatsoever at any stage of manufacture, test, erection or on completion at site, the 
Engineer  may  reject  the  item  or  defective  component  thereof,  whichever  is  considered 
necessary,  and  after  adjustment  or  modification  as  directed  by  the  Engineer,  the  Contractor 
shall  submit  that  item  for  further  inspection  and/or  test.    In  the  event  of  the  defective  item 
being  of  such  nature  that  the  requirements  of  this  Specification  cannot  be  fulfilled  by 
adjustment or modification, such item is to be replaced by the Contractor at his own expense, 
to the entire satisfaction of the Engineer.  Delivery of panel boards on site without significant 
cable connection (Say 80%) shall not entitle progress payment certified for material delivery on 
site. 
 
 
 
 
END OF SECTION 
 
 
 
 
   

PMC: NSL E56


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

WIRES AND CABLES 
 
 
PART 1 – GENERAL 
 
1.1 WORK DESCRIPTION 
 
A. The design manufacture, testing and supply of single core PVC insulated 1.1 KV grade stranded 
twisted wires under this specifications shall comply with latest edition of following standards. 
 
 IS‐3961: Current rating for cables. 
 IS‐5831: PVC insulation and sheath of electric cables. 
 IS‐694: PVC insulated cables for working voltage up to and including 1100 volts. 
 IEC‐54 (I): PVC insulated cable. 
 
B. Copper/Aluminium stranded twisted conductor PVC insulated wires shall be used in conduit as 
per item of work.  Aluminium for power cables and copper for control cables shall be used. 
 
C. The wires shall be colour coded R Y B, for phases, Black for neutral and Green for earth. 
 
D. Progressive automatic in line indelible, legible and sequential marking of the length of cable in 
meters at every one‐meter shall be provided on the outer sheath of cable. 
 
E.  The design, manufacture, testing and supply of the cable under this specifications shall comply 
with latest edition of following standards: 
 
 IS: 8130: Conductors for insulated electric cables and flexible cords. 
 IS: 5831: HRPVC/HR PVC insulation and LSZH sheath of electric cables. 
 IS: 3975: Mild steel wires, strips and tapes for armouring cables. 
 IS: 3961: Current rating of cables. 
 
F. The routing and the minimum rated current carrying capacity of the LV power cables shall be 
as  indicated  on  the  Drawings.  The  Contractor  shall  consider  the  manufacturer  data  and 
engineering the cable sizing to ensure it suit the conditions, viz grouping, ambient temperature 
etc., and for making any necessary adjustment to the Engineer’s approval. 
 
G. All  LV  cables  for  normal  power/control  circuitries  within  buildings  shall  be  copper  conductor 
with XLPE insulated and PVC sheathed, denoted as XLPE/PVC cable or copper conductor with 
PVC insulated, denoted as PVC cable as specified. 

PMC: NSL E57


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
H. All  LV  cables  for  emergency  power  circuitries  serving  emergency  lightings,  Building 
Management  System  (BMS),  Fire  Protection  System,  Security  Systems,  emergency 
communication systems, and sump pump system and fire lifts etc. with back‐up from standby 
generator  sets  or  UPS  systems  or  incoming  and  outgoing  from  the  Emergency  Main 
Switchboard shall be fire resistant cables as required. 
 
I. Cablings in service ducts, open trenches, direct‐laid underground in soil shall be by means of 
armoured cables.  Non‐armoured cables shall be laid in conduits, trunkings or tray/ladder for 
mechanical protection.   
 
4.02 STANDARDS 
 
A. Complete cabling shall be manufactured and constructed in accordance with the latest revision 
of the following standards : 
 
1.  IS: 694  :  HRPVC/XLPE insulated (heavy duty) electric cables 
for working voltage up to and including 1100 volts. 
2.  IS: 424‐ :  Power cable‐flammability test. 
1475(F‐3) 
3.  IS: 7098(I)  :  Specification for cross‐linked polyethylene insulated 
LSZHPVC sheathed cable for working voltage up to 
1.1 KV. 
4.  IS: 1554  :  Specification for PVC insulated (heavy duty) electric 
cables for working voltages up to and including 
1100 volts. 
5.  ASTM‐D:  :  Standard method for measuring the minimum 
2863  oxygen concentration to support candle‐like 
combustion of plastics (Oxygen Index). 
6.  ASTM‐D:  :  Standard test method for measuring the density of 
2843  smoke from the burning or decomposition. 
7.  IEEE: 383  :  Standard for type of tests Class‐IE, Electric cables, 
field splices and connections for power generation 
station. 
8.  ASTME:  :  Standard test method for specific optical density of 
662/ IEC:  smoke generated by solid materials 
754(x) 
9.  IS: 10418  :  Cable drums. 
 

PMC: NSL E58


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

10  IS‐10810  :  Testing method of cable. 


11.  IS‐6121  :  Cable glands. 
12.  IS‐9537  :  Rigid steel conduit. 
 
 
B. The  manufacturing  of  the  cable  shall  also  conform  to  the  requirements  of  all  relevant  local 
codes, as applicable, together with the additional requirements referred to in this Specification 
and Drawings, whichever is the more stringent and acceptable to the Engineer. 
 
C. In  the  adoption  of  standards  and  requirements,  the  Contractor  shall  take  the  following 
precedence: 
1. Engineer’s decision; 
2. Local codes of practice; 
3. Drawings; 
4. Specification; 
5. International standards and requirements. 
 
4.03 SUBMISSION 
 
A. All technical submissions shall be approved by the Engineer prior to the respective stages of 
construction. 
 
B. As a minimum requirement, the submission shall include the following: 
1. Equipment submission with manufacturer’s data 
2. Sample submission 
3. Shop  Drawings  of  the  cable  routings  showing  the  co‐ordinated  routing  of  cables, 
arrangement on cable trays, methods of fixing of cable trays and  cables, etc.  All conduits 
including concealed conduit routing drawings shall also be included 
4. Cable test reports and IS Certification 
5. Builder’s works requirement 
6. Cable schedule indicate the following data include: 
a. Cable code and type and installation method 
b. Cable feed from and serve to 
c. Cable route length and voltage drop 
d. Cable capacity and 
e. Upstream protection breaker rating 
The cable schedule shall be prepare in according to the cable manufacturer’s data.. 
 
PART 2 – PRODUCT  
 

PMC: NSL E59


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

2.01LV  CABLES 
 
1. The  cables  shall  be  suitable  for  laying  in  racks,  ducts,  trenches  conduits  and  under‐
ground buried installation with uncontrolled back fill and chances of flooding by water. 
2. They  shall  be  designed  to  withstand  all  mechanical,  electrical  and  thermal  stresses 
under steady state and transient operating condition. 
3. The  aluminium/copper  wires  used  for  manufacturing  the  cables  shall  be  true 
circular/sector in shape before stranding and shall be of uniformly good quality, free from 
defects. The conductor used in manufacture of the cable shall be of H2 grade. 
4. The  cable  should  withstand  2.5  KA  for  1  Sec.  with  insulation armour insulated at one 
end.  Bidder  shall  furnish  calculation  in  support  of  capability  to  withstand  the  earth  fault 
currents.  The  current  carrying  capacity  of  armour  and  screen  (as  applicable)  shall  not  be 
less than the earth fault current values and duration.   
5. The  fillers  and  inner  sheath  shall  be  of  non‐hygroscopic  fire  retardant  materials  and 
shall be suitable for the operating temperature of the cable. Filler and inner sheath shall 
not stick to insulation and outer sheath. 
6. Progressive automatic in line indelible, legible and sequential marking of the length of 
the cable in metres at every one metres shall be provided on the outer sheath of all cables 
and at every 5 metre ‘LSZH marking in case of ‘LSZH cables. 
7. Strip/Wire  armouring  following  method  (b)  mentioned  in  IS:  3975  shall  only  be 
acceptable. For single core cable aluminium wire armouring shall be used. 
8. Allowable tolerance on the overall diameter of the cables shall be + 2mm. 
9. The normal current rating of all HRPVC/XLPE insulated cables shall be as per IS: 3961.  
10. A distinct inner sheath shall be provided by pressure extrusion process for all multicore 
armoured and unarmoured cables as per IS: 5831. 
11. Outer sheath shall be provided by extrusion process as per IS: 5031. 
12. The breaking load of armour joint shall not be less than 95% of that armour wire. Zinc 
rich paint shall be applied on armoured joint surface. 
13. In plant repairs to the cables shall not be accepted. 
14. All the cables shall be supplied in non‐returnable drums as per IS: 10418. 
15. In Case of LSZH Cables 
 The outer sheath of cables shall have an oxygen index of not less than 29 as per 
ASIMD : 2863. 
 The maximum acid gas generation by weight as per IEC:754 (i) shall not be more 
than 20% for outer sheath material of all cables. Bidder shall also guarantee the 
maximum theoretical acid gas generation with 20% by weight of outer sheath. 
 The cables outer sheath shall meet the requirement of light transmission of 40% 
(minimum and shall be tested as per ISTMD:2843). In case the test for light 
transmission is conducted as per ASTME:662. The bidder shall furnish smoke density 
values as per this standard and shall co‐relate the anticipated light transmission when 
tested as per ASTMD:2843. 
 The cable shall pass the fire resistance test as per SS:42, 41, 475 (I) and 
flammability test as per EEE:383. 
 

PMC: NSL E60


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

A. Inspection: 
All cables shall be inspected   on receipt of the same at site and checked for any damage 
during transit. 
 
B. Joints in Cables: 
The contractor shall take care that the cables received at site are distributed to various 
locations in such a manner as to ensure maximum utilization and avoidance of cable 
jointing. Cable shall be rechecked before cutting in lengths, where the joints are 
unavoidable, and the location of such joints shall be got approved from the 
Owner/Consultant. The joints shall be done by qualified jointer strictly in accordance with 
manufacturer’s instruction/drawings. 
 
C. Joint Boxes for Cables: 
The cable joint boxes shall be of appropriate size suitable for type of cable of particular 
voltage rating. 
 
D. Cable Joints: 
1. All cable joints shall be made in suitable, approved cable joints boxes, on the jointing of 
cables  in  the  joint  box  and  the  filling  in  of  compound  shall  be  done  in  accordance  with 
manufacturer’s instructions and in an approved manner. All straight through joints shall be 
done  in  epoxy  mould  boxes  with  epoxy  resins.  Straight  through  joints  shall  not  be 
permitted unless the length of run is in excess of cable drum. 
2. End  terminations  of  cables  more  than  1.1  KV  grade  shall  be  done  with  epoxy  mould 
boxed  and  epoxy  resin.  Cable  glands  shall  be  1.1KV  grade  double  compression  type  and 
made  to  tin  plated  heavy‐duty  brass  casting  and  machine  finished.  Glands  shall  be  of 
robust construction capable of clamping cable and cable armour, firmly without injury of 
cable. 
3. All washers and hardware shall be made of brass tinned. Rubber components used in 
the glands shall be made of neoprene of tested quality. 
4. Cable lugs shall be tinned copper/aluminium solder less crimping type conforming to IS: 
8309 suitable for aluminium or copper conductor. 
5. Crimping  of  terminals  shall  be  done  by  using  Corrosion  inhibitory  compound,  with 
crimping tool. 
6. Fire resistant paint has to be applied 1 Meter on either side of cable joint. 
7. The  contractor  shall  liaise  fully  with  all  other  contractors  to  achieve  an  efficient  and 
properly coordinated installation where equipment has to be re‐positioned due to lack of 
site liaison; no extra cost shall be incurred by the client. 
 
2.01H.T. CABLE (XLPE) (33 KV) 
 
A. The  cross  linked  polyethylene  (XLPE)  cable  shall  be  aluminium  conductor  PVC  outer  sheath 
steel  strip  armoured  over  inner  sheath  construction.  XLPE  cable  shall  conform  to  testing  in 
accordance  with  IS:7098  (Part‐I)  1977  and  (Part‐II)  1973.  The  screaning  shall  be  done  on 

PMC: NSL E61


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

individual  cover.  The  armouring  applied  over  the  common  covering  shall  be  flat  steel  wires. 
Each and every length of cable shall be subjected to routine test. 
 
B. The  termination  and  jointing  techniques  for  XLPE  cables  shall  be  by  using  heat  shrinkable  or 
push on cable jointing kits. 
 
C. While  laying  underground  cables  in  ducts  care  should  be  taken  so  that  any  underground 
structures such as water pipes, sewerage lines etc. are not damaged. Any telephone or other 
cable  coming  in  the  way  shall  be  properly  protected  as  per  instructions  of  the  Engineer‐in‐
charge.  The H.T. cable shall be laid at least 1200mm for cable upto 33 KV(E) below the ground 
level in a trench 450mm wide. 
 
D. After laying and jointing work is completed a high POT test shall be performed in presence of 
Engineer and test results submitted for approval in order to ensure that they have not been 
damaged during or after the laying operation. In case, the test results are unsatisfactory, the 
cost  of  all  repairs  and  replacement  and  all  extra  work  of  removal  and  relaying  will  be  made 
good by the contractor without any extra cost. 
 
Note:  All other procedure will be followed as per L.T. cables. 
 
PART 3 ‐ EXECUTION 
 
3.01 ERECTION OF CABLES 

A. Notwithstanding  the  cable  routes  indicated  on  the  Drawings  the  Contractor  shall  be  entirely 
responsible for the supply of correct lengths of the cables to be installed and for all allowances 
for connecting and terminating the cables to the switchgears and transformers respectively 
 
B. The Contractor shall submit proposed cable routes including details of supports for the cables 
for  approval  before  installation.    The  cable  shall  not  be  run  in  places  other  than  corridor, 
passageway, electrical riser or other designated areas subject to the Engineer’s approval.  The 
cost of support shall be deemed to have included in the Contract. 
 
3.02 CABLE PULLING 
 
A. Winching  of  cables  through  ducts/pipes  shall  only  be  carried  out  with  the  approval  of  the 
Engineer in which event a pulley eye shall be attached to the conductors.  Cable shall be run in 
neat  and  orderly  manner  to  allow  space  for  future  cabling  and  maintenance  and  under  no 
circumstances and cable shall be run diagonally across a room, cable basement, corridor, etc. 
 
B. A  cable  sheath  stocking  may  be  employed  or  cables  where  no  undue  stress  in  the  sheath  is 
likely to occur. 
 

PMC: NSL E62


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

C. Care shall be taken to ensure that the draw strain is applied to the armouring and protected 
during drawing against damage. 
 
3.03 CABLE LAYING 
 
A. The  cable  drum  shall  be  placed  on  jacks  before  unwinding  the  cable.  Great  care  shall  be 
exercised  in  laying  cables  to  avoid  forming  links.  At  all  changes  in  directions  in  horizontal  & 
vertical places, the cable shall be bent with a radius of bend not less than 8 times the diameter 
of cable. 
 
B. The  cable  of  1.1KV  grade  shall  be  laid  not  less  than  750mm  below  ground  level  in a 375mm 
wide  trench  (throughout),  where  more  than  one  cable  is  to  be  laid  in  the  same  trench,  the 
width  of  the  trench  shall  be  increased  such  that  the  interaxial  spacing  between  the  cables 
except  where  otherwise  specified  shall  at  least  be  150mm  minimum  or  as  per  site 
requirements or as approved by the Engineer‐in‐charge. Where single core cables are used in 
multiphase systems, the cables shall be installed in trefoil where possible. 
 
C. In case the cables are laid in vertical formation due to unavoidable circumstance the depth per 
tier  shall  be  increased  by  200mm  (minimum).  Cable  shall  be  laid  in  reasonably  straight  line, 
where a change in direction takes place a suitable curvature shall be i.e. either 20 times the dia 
meter of the cable or the radius  of the bend shall not be less than twice the diameter of the 
cable drum or whichever is less. Minimum 3 meter long loop shall be provided at both sides of 
every straight  through joint & 3 meters at each end of cable or as directed at site. 
 
D. Greater  care  shall  be  exercised  in  handling  the  cable  in  order  to  avoid  forming  ‘Kinks’.  The 
cable  drum  shall  in‐verbally  conveyed  on  wheels  and  the  cable  unrolled  in  right  direction  as 
indicated on the drum by the manufacturer. The cable shall be pulled over rollers in the trench 
steadily and uniformly without jerks and strains. 
 
E. Cables laid in trenches in single tier formation, 10 cms. allaround sand cushioning be provided 
below and above the cable before a protective cover is laid. For every additional vertical tier. 
The 30cm of sand cushion be provided over the initial tier. The cable shall be protected by 2nd 
class bricks of size not less than 230x115x75mm, stone tiles/RCC curved channel be placed on 
top of the sand breadth wise for the full length of the cable and where more than one cable is 
to be laid in the same trench the brick shall cover all cables and project at least 8 cms. over the 
outer sides of the end cables. 
 
F. Filling  of  trenches  shall  be  done  after  the  sand  cushioning  and  laying  of  tilesor  bricks  are 
carried out to the satisfaction of the Engineer‐in‐charge (Refer drawing). Back fill for trenches 
shall  be  filled  in  layer  not  exceeding  150  mm.  Each  layer    shall  be  properly  rammed  & 
consolidate before laying the next layer. 
 
G. PVC pipe shall be provided for all road crossing. The size of the pipe shall be according to the 
cable and a minimum 100mm dia. pipe shall be provided. The pipe shall be laid in ground with 
special arrangement and shall be cement jointed and concreting with 1:5:10   shall  be   made  

PMC: NSL E63


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

as  per    relevant  IS  with  latest  amendment.   Nothing  extra shall  be  paid  on  this  account.    
Location      of      cables      laid        directly  underground  shall  be  indicated  by  cable  marker  at  an 
interval of 30 meters &  with change of direction.  Aluminium strip cable tag of 20mm  wide 
with engraved tag no. shall be provided at both ends of cable. 
 
H. Where the cables are to be laid in ducts (pucca trenches) in side the building, they will have to 
be laid on MS rack/ on MS cable trays grouted in walls trenches. Cables sizing through floors 
shall be protected from mechanical damage by a steel channel to a height of one meter above 
the floor where cable pass through wall they shall be sleeved with PVC/steel conduit. 
 
I. Where the cables are laid in open (in building) along walls, ceiling or above false‐ceiling, cable 
rack  (ladder  type)  or  cable  tray  shall  be  provided.  The  size  of  the  cable  tray  or  rack  shall 
depend  on  the  number  of  cables  to  pass  over  that  rack.  Cable  tray/rack  shall  be  properly 
supported through wall/ceiling according to the site conditions. Cable laid on tray & riser shall 
be  neatly  dressed  &clamped  at  an  interval  of  1000  mm  &  750mm  for  horizontal  &  vertical 
cable  run  respectively  either  side  at    each  bend  of  cable.  All  power  cables  shall  be  clamped 
individually  &  control  cables  shall  be  clamped  in  groups  of  three  or  four  cables.  Clamps  for 
multicore cables shall be fabricated of 25x3 GI flats.  Single core power cable shall be laid in 
trefoil formation & clamped with trefoil clamps made of PVC/fibre glass. 
 
J. Cable  openings  in  wall/floor  shall  be  sealed  by  the  contractor  suitably  by  hession  tape  & 
bitumen compound or by any other proven to prevent ingress of water. 
 
K. After  the  cables  are  laid,  shall  be  tested  as  per  IS  and  the  results  submitted  to 
Architects/Engineer and in case the results found unsatisfactory, all the repairing/ replacing of 
cables will be done by the contractor free of charge. 
 
3.04 INTERNAL WIRING 
 
A. All the wiring installation shall be as per IS:732 with latest amendment. PVC insulated copper 
conductor  cables  as  specified  in  bills  of  quantity  shall  be  used  for  sub‐circuit  runs  from  the 
distribution boards to the points and shall be pulled into conduits. They shall be twisted copper 
conductors with thermoplastic insulations of 1100 volts grade. Colour Code for wiring shall be 
followed.  
 
B. Looping  system  of  wiring  shall  be  used,  wires  shall  not  be  jointed.  Where  joints  are 
unavoidable,  they  shall  be  made  through  approved  mechanical  connectors  with  prior 
permission of the consultant. No reduction of strands are permitted at terminations. No wire 
smaller than 1.5 sq.mm shall be used and shall be as per B.O.Q. Wherever wiring is run through 
trunkings  or  raceways,  the  wires  emerging  from  individual  distributions  shall  be  bunched 
together  with  cable  straps  at  required  regular  intervals.  Identification  ferrules  indicating  the 
circuit  and  DB  number  shall  be  used  for  submains,  sub‐circuit  wiring.  The  ferrules  shall  be 
provided at both end of each submain and sub‐circuit. 
 

PMC: NSL E64


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

C. Where single phase circuits are supplied from a three phase and a neutral distribution board, 
no  conduit  shall  contain  the  wiring  fed  from  more  than  one  phase.  In  any  one  room  in  the 
premises  where  all  or  part  of  the  electrical  load  consists  of  lights,  fans  and/or  other  single 
phase  current  consuming  devices,  all  shall  be  connected  to  the  same  phase  of  the  supply. 
Circuits  fed  from  distinct  sources  of  supply  or  from  different  distribution  boards  or  through 
switches  or  MCBs  shall  not  be  bunched  in  one  conduit.  In  large  areas  and  other  situations 
where  the  load  is  divided  between  two  or  three  phase,  no  two  single  phase  switches 
connected to different phase shall be mounted within two meters of each other. 
 
D. All splicing shall be done by means of terminal blocks or connectors and no twisting connection 
between conductors shall be allowed. 
 
E. Industrial sockets shall be of polycarbonate and deeply recessed contact tubes. Visible scraping 
type  earth  terminal  shall  be  provided.  Socket  shall  have  self  adjustable  spring  loaded 
protective cap. Socket shall have MCB/ELCB/RCCB as specified in the schedule of work. 
 
3.05 Fire Seal System 
 
A. All the floor/wall opening provided for cable crossing shall be sealed by fire seal system. 
 
B. The  fire  proof  sealing  system  shall  fully  comply  with  the  requirements  of  relevant  IS/BS:476 
Part‐B. The fire proof seal system shall have minimum one hour fire resistance rating. 
 
C. The  fire  proof  seal  system  shall  be  physically,  chemically,  thermally  stable  and  shall  be 
mechanically secured to the masonary concrete members. The system shall be completely gas 
and smoke tight, antirodent and anti‐termite. 
 
D. The  material  used  in  fire  proof  seal  system  shall  be  non‐toxic  and  harmless  to  the  working 
personnel. 
 
E. Type  of  fire  proof  seal  system  shall  be  foaming  type  or  flamemastic  type  compound  or 
approved equivalent. 
F. After laying and jointing work is completed, high voltage test should be applied to all cables to 
ensure that they have not been damaged during or after the laying operation and that there is 
not fault in the jointing. 
 
G. Cables for use on low and medium voltage system (1.1KV grade cables) should withstand for 
15  minutes  a  pressure  of  3000V  DC  applied  between  conductors  and  also  between  each 
conductor  and  sheaths.  In  the  absence  of  pressure  testing  facilities  it  is  sufficient  to  test  for 
one minute with a 1000V insulation tester In case the test results are unsatisfactory the cost of 
repairs  and  replacements  and  extra  work  of  removal  &  laying  will  be  made  good  by  the 
contractor. 
 
H. Cable  shall  be  installed  so  that  separations  shown  in  the  table  below  are 
observed. 

PMC: NSL E65


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

1. HV Cable (33 KV)       ‐   HV Cable (33 KV)      50 mm 


2. ELV & LV 230 V/433 V    ‐  ELV & LV cable 230 V/433 V  50 mm 
3. HV cables (33 KV)  ‐   ELV & LV cables 230 V/433 V   300 mm 
4. LV cables 433 V            ‐   Telephone/Instrument cable      350 mm 
5. All cables            ‐    All hot  pipe work               200 mm 
 
3.05 FACTORY TESTS 
 
A. Each type of cable specified shall be fully type tested according to IEC 502 and the appropriate 
British Standards.  The types and sizes of cables required are shown on the Drawings. 
 
B. Should  the  Engineer  require  it,  the  Contractor  shall  submit  reports  issued  by  a  national  or 
international testing authority on type test that have been successfully performed on the cable 
for his approval. 
 
C. The type test shall include the following test: 
1. Partial discharge test; 
2. Bending test, plus partial discharge test; 
3. Tan   measurement as a function of the voltage and capacitance measurement; 
4. Tan   measurement as a function of the temperature; 
5. Heating cycle test plus partial discharge test ; 
6. Impulse withstand test, followed by a power frequency voltage test; 
7. Medium‐voltage alternating current test; 
8. Type test (non‐electrical) as stipulated in IEC 502, Table VI. 
 
D. Cable routine test shall be conducted at factory in accordance with IEC 502 for the following 
tests: 
Measurement of the electrical resistance of conductors. 
Partial discharge test, 
4‐hour MV test. 
 
3.06 SITE ACCEPTANCE TEST 
 
A. The Contractor shall supply all necessary testing equipment for site testing.  When required, 
these testing equipment shall be calibrated at the expense of the Contractor at a recognized 
national laboratory. 
B. The  Contractor  shall  engage  an  Authorised  Medium  Voltage  Testing  Engineer  who  is 
recongnised by SEB to perform all site tests. 
C. In addition to SEB’s requirements and those recommended by the manufacturer, the following 
tests shall be carried out: 
1. Continuity test, 
2. Earth test, 
3. Polarity test, 
4. Insulation resistance test, 

PMC: NSL E66


Electrical: Wires & Cables Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

5. DC high voltage test.  The test voltage shall be in accordance with SEB’s requirements 
and Engineer’s approval. 
 
END OF SECTION 
 

PMC: NSL E67


Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

WIRING DEVICES 
 
 
PART 1 – GENERAL  
 
1.01 WORK DESCRIPTION 
 
A. The drawings for the lighting and power points indicate approximate positions of all 
lighting fittings, switches, power outlet points, isolating switch points and the like.  
The actual positions of all fittings, switches, the wiring details and cable routes shall 
be  co‐ordinated  with  other  trades  on  site  and  submitted  for  the  approval  of  the 
Engineer.    All  time  and  cost  required  adjusting  the  layout  or  adjusting  the 
completed  installation  to  Engineer  satisfaction  and  to  suit  site  co‐ordination  is 
included in the Contract. 
 
B. During  the  exact  positioning  of  lighting  and  power  points,  due  consideration  shall 
be  given  to  the  operational  requirements  of  the  installation,  the  selection  of  the 
most accessible routes for wiring and the convenience of switching. 
 
C. No additional cost will be entertained should the final positions be relocated within 
the same room  or not more than five  (5)  metres away from the original locations 
due to any requirement. 
 
D. For the purpose of this Specification and related Drawings, each lighting and small 
power  point  circuits  shall  in  general  be  coded  with  a  prefix  to  indicate  the 
corresponding distribution board number; details on the circuit way and phase shall 
be submitted for the approval of Engineer. 
 
E. Certain types of electrical equipment or systems involving sudden changes, or low 
frequency  or  of  direct  electric  current  such  as  fluorescent  lamps,  contactors,  etc. 
shall  be  fitted  with  radio  and  television  interference  suppression  components 
suitable to meet the levels specified in BS 800 “Limits of Radio Interference”. 
 
F. This section included the specification of the following : 
1. Distribution boards 
2. Miniature circuit breakers 
3. Earth leakage circuit breakers 
4. 6A Switch Socket Outlet 
5. 16A Switch Socket Outlets 
6. Shaver Outlets 
7. Isolating Switches 
8. Conduit Boxes 
9. Contactors 
10. Dimmers Switch 
11. Time Switch  
12. Cooler Control Units  
13. Water Heater Switches 
14. Bell Push Switches  

PMC: NSL  E 68   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
1.02 STANDARDS 
 
A. The  complete  wiring  installation  shall  be  engineered  according  to  manufacturer 
data  and  constructed  in  accordance  with  the  latest  revision  of  the  IS  and  the 
appropriate BS/IEC 
 
B. In  the  adoption  of  standards  and  requirements,  the  Contractor  shall  take  the 
following precedence: 
1. Engineer’s decision; 
2. Local codes of practice; 
3. Drawings; 
4. Specification; 
5. International standards and requirements. 
 
1.03 SUBMISSION 
 
A. All technical submissions shall be approved by the Engineer prior to the respective 
stages of construction. 
 
B. As a minimum requirement, the submission shall include the following: 
1. Equipment catalogues submission with manufacturer’s data; 
2. Sample submission include all wiring accessories; 
3. Shop  Drawings  of  the  lighting  and  power  positions,  circuit  numbers,  cable  routings, 
switching arrangement, mounting height, etc. The positions and mounting heights 
shall be coordinated with other services.  Fixing details of all wiring accessories shall 
also be included. 
4. Drawings showing the installation details. 
5. Labeling system 
6. Builder’s works requirement. 
 
PART 2 – PRODUCT  
 
2.01 LIGHTING POINT  INSTALLATION 
 
A. The various types of light fittings to be supplied and installed are described in the 
drawings and the Schedule of Lighting Fittings on Drawing 
 
B. Surface  mounted  light  fitting  shall  terminate  at  a  junction  box  having  entries 
appropriate  to  the  run  of  conduit  and  shall  be  complete  with  porcelain/  PVC 
connector suitable for the size and number of connections to be made at the point 
and the wiring required to connect the specified fitting.  Wiring to the light fittings 
within the false ceiling spaces shall be by means of heat resistant (butyl or silicon 
rubber  insulated  to  BS  6500)  cables  i.e.  between  the  junction  box  and  the  lamp 
holder/terminal blocks, in flexible conduits. 
 
C. At  every  light  fitting  an  approved  type  earthing  terminal  shall  be  provided  for 
connection of the circuit protective conductor of the final circuit. 

PMC: NSL  E 69   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
D. Ferrous  metalwork  shall  be  of  minimum  thickness  of  1mm.  treated  against 
corrosion by galvanising after welding or be lead primer or other approved process.  
Metalwork  shall  be  painted  with  one  priming  coat,  one  under‐coat  and  two  top 
coats finished stove‐enamelled matt white, unless otherwise specified. 
 
E. Cables  used  for  internal  wiring  of  the  lighting  fittings  shall  be  of  appropriate  type 
and  size  and  number.    Conductor  shall  be  of  size  not  less  than  1.5  sq.mm.  single 
core  or  the  equivalent.    The  insulation  of  the  cables  shall  be  able  to  withstand 
throughout  the  life  of  the  fitting  the  maximum  temperature  to  which  it  will  be 
subject  in  normal  use  without  deterioration  which  could  affect  the  safety  of  the 
fitting. 
 
F. Cables within the lighting fittings shall be neatly bundled by nylon self locking cable 
ties;  wiring  shall  be  properly  routed  and  secured  away  from  control  gear  etc. 
wherever possible. 
 
G. All  cable  terminations  within  the  light  fittings  shall  be  suitably  shrouded  to  the 
approval of the Engineer. 
 
H. All  lighting  fittings  shall  be  self‐supporting  complete  with  the  appropriate  fixing 
accessories  such  as  clips,  supporting  brackets,  suspension  sets,  nuts,  washers, 
screws  etc.  for  the  proper  installation  of  the  fittings  on  different  types  of  ceiling 
panels.  Suspension sets shall be of adjustable type suitable to carry the weight of 
the  lighting  fittings  and  unless  otherwise  stated  or  indicated  on  Drawings,  the 
suspension  sets  shall  be  generally  900  mm  in  length;  exact  lengths  required  shall 
suit site situations. 
 
I. All  lamps  complete  with  control  gear  necessary  in  operational  condition  shall  be 
provided together with the lighting fittings as specified. 
 
2.02 SWITCHES 
 
A. Lighting switches, unless otherwise specified, shall be single pole, quick make and 
slow‐break,  silent  switch  action  type  with  solid  silver  alloy  contacts  and  totally 
enclosed switch action for flush or surface mounting as required.  
 
B. Lighting  switches  shall  be  suitable  for  indoor  or  outdoor  service  according  to 
location,  housed  in  standardized  purpose  manufactured  galvanized  steel  boxes 
completed  with  conduit  knockouts  made  up  into  single  or  multi‐gang  units 
employing  a  grid  switch  system  of  fully  interchangeable  components  at 
standardized fixing centres of matching switches of different types and ratings but 
of  identical dimensions,  push  buttons,  neon  indicator  lamps,  blanking  units, grids, 
steel  boxes  and  plates  all  capable  of  integration  into  standard  composite 
assemblies in any combination as required. 
 
C. Grids shall be adjustable for variation in depth of plaster and for squaring errors 
and of the same type for surface or flush mounting. 

PMC: NSL  E 70   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
D. Switches in mechanical plant rooms and electrical sub‐stations and switch rooms 
shall  be  of  the  metal  clad  type  approved  by  the  Engineer,  mounted  in  flush  or 
surface conduit boxes as specified elsewhere. 
 
E. Switches  located  on  brick  or  concrete  walls  shall  be  mounted  in  horizontal 
arrangement  in  plaster  depth  steel  boxes  or  in  galvanized  steel  boxes  using  box 
suspension straps and cover plates.  Countersunk screws shall be provided for fixing 
to the conduit boxes. 
 
F. Switches for external use shall be of weatherproof construction with IP65 rating, 
unless otherwise specified. 
 
G. Samples of all switches, conduit boxes and plaster depth boxes shall be submitted 
to the Engineer for approval prior to installation. 
 
H. Samples shall be rated for 6 Amps (minimum light switch rating 6A), 16 Amps or 
20 Amps as determined by circuit load which  for inductive lighting circuit shall be 
assessed at twice the steady state connected load current, one way or two ways as 
indicated  on  the  drawings  and  fixed  generally  at  a  height  of  1200  mm  from  floor 
level and where located in rooms the switch shall, where possible be located on the 
inside  of  the  room  on  the  handle  side  of  the  door  as  close  to  the  door  as  is 
practicable. 
 
I. An  earthing  terminal,  connected  to  the  earth  continuity  terminal  shall  be 
provided and connected to the circuit protective conductor at every lighting switch 
positions. 
 
J. Single pole switches shall be connected to break the phase wire of the supply; the 
neutral wire shall not be routed through switch boxes. 
 
K. Switches which are mounted in the same location shall be of multi‐gang type, of 
the maximum number of gangs available. 
 
L. All  switches  used  shall  be  of  approved  or  prescribed  items  as  required  by  local 
Authorities. 
 
M. Circuit  from  different  phase  and  circuit  from  emergency  power  should  have 
separate switch plate. 
 
2.03 ISOLATION SWITCH 
 
A. Isolating  switches  shall  be  of  the  current  ratings  and  number  of  poles  (generally 
double pole for single phase and 4‐pole three phases) as indicated on the Drawings. 
 
B. Isolating  switches  shall  be  of  the  totally  enclosed  pattern,  metal‐clad  or 
polycarbonate with positive quick‐make and quick‐break action. 
 

PMC: NSL  E 71   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

C. Switches  shall  be  capable  of  passing  and  also  interrupting  their  full  rated  current 
safety and without damage.   
 
D. Ferrous materials shall be galvanised, switch handles shall be interlocked to prevent 
opening the cover with the switch "ON". 
 
2.04 6 AMP SWITCH SOCKET OUTLETS 
 
A. Switch  socket  outlets  shall  be  as  per  BS1363  single  pole  6  Amp  3  round  pin 
shuttered  outlets,  one  or  two  gang  for  indoor  service  except  otherwise  specified 
and either surface or flush mounting according to location. 
 
B. Switches shall be of the quick‐make slow break type with silent, totally enclosed 
switch action and solid silver alloy contacts.  Switched socket outlets for indoor use 
shall  be  housed  in  suitable  galvanized  steel  boxes  to  BS  4662  with  conduit 
knockouts.    Types  and  finishes  of  socket  plates  shall  match  those  for  the  lighting 
switches. 
 
C. Generally  switch  socket  outlets  shall  be  positioned  300  mm  above  floor  level 
except in plant rooms, kitchen, etc. where they shall be positioned 1400 mm above 
floor level or 150 mm above counters or benches whichever is suitable. 
 
D. Switch  socket  outlet  in all  mechanical  plant  rooms,  electrical  switch  rooms  shall 
be of the metal clad type, with recessed or protected switch dolly, mounted in flush 
or surface conduit boxes as specified elsewhere. 
 
E. All switch socket outlets used shall be of an approved quality. 
 
2.05 16 AMP SWITCH SOCKET OUTLETS 
 
A.  16  Amp  switch  socket  outlets  shall  be  3  pin  round  type  to  BS  546  shuttered,  of  a 
finished  similar  to  6  Amp  switch  socket  outlets  and  flush  mounted  in  galvanised 
steel conduit boxes to BS 4662 requirements. 
 
2.06 WEATHERPROOF ISOLATOR 
 
A.  Weatherproof  enclosure  shall  be  of  the  high  impact,  water  resistant  to  IP65.  The 
isolator  provided  shall  complete  with  lockable  device.    Isolators  shall  be  double‐
pole, 4‐pole as specified. 
 
2.07 LIGHTING DIMMERS SWITCH 
 
A. Lighting  dimmer  switch shall  be  the  solid state,  variable  load,  Thyristor  controlled 
type  suitable  for  controlling  fluorescent  and  or  incandescent  lighting  circuits 
operating at 230V ± 6% 50Hz single phase AC supply. 
 
B. Dimmer  switch  shall  be  manufactured  to  eliminate  TV  and  radio  frequency 
interference in compliance with IS. 

PMC: NSL  E 72   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
C. The  ratings  of  the  dimmer  units  shall  be  suitable  for  lighting  circuit  specified  on 
Drawing. 
2.08 TIME SWITCHES 
 
A. Time switches shall be self‐contained units suitable for mains operation.  All units 
shall  have  a  self‐starting  synchronous  motor  with  a  single‐pole  fuse  in  the  motor 
circuit,  a  3‐way  terminal  block  and  a  thirty‐six  (36)  hours spring  reserve  complete 
with an automatic solar dial. 
 
B. When fitted, the solar dial shall be capable of switching ON at sunset and OFF at 
sunrise throughout the year by control of a secondary calendar dial with month and 
day settings, and the automatic switching time shall be adjustable. 
 
C. Time  switches  shall  be  encased  in  a  dust‐tight  metal  casing  have  a  hinged  front 
cover with a clear Perspex window.  The casing shall be effectively earthed. 
 
D. A  manual  bypass  switch  shall  be  incorporated  with  the  time  switch  to  facilitate 
maintenance of the latter. 
 
2.09 MINIATURE CIRCUIT BREAKER 
 
A. The  MCB  shall  be suitable  for  manual closing  and  opening and  automatic  tripping 
under overload and short circuit. The MCB shall also be trip free type. 
 
B. Single pole/three pole versions shall be furnished as required. 
 
C. The MCB shall be rated for 10 KA fault level. 
 
D. The MCB shall be suitable for its housing in the lighting boards and shall be suitable 
for  connection  at  the  outgoing  side  by  tinned  cable  lugs  and  for  bus‐bars 
connection on the incoming side. 
 
E. The  terminal  of  the  MCBs  and  the  open  and  close  conditions  shall  be  clearly  and 
indelibly marked. 
 
F. The MCB shall generally conform to IS: 8828. 
 
2.10 EARTH LEAKAGE CIRCUIT BREAKER 
 
A. ELCB  shall  be  4  pole  415  volts  50Hz,  30‐300mA  sensitivity.  These  shall  be  of 
approved make.  The rating of the ELCB shall be as required.  These shall be suitable 
for manual closing and opening and automatic tripping under earth fault circuit of 
30‐300mA as specified in item of work. 
 
B. The enclosure of  the ELCB shall  be moulded from high quality  insulating material. 
The material shall be fire retardant, anti tracking, non‐hygroscopic, impact resistant 
and shall with stand high temperature. 

PMC: NSL  E 73   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
C. All parts of switching mechanism shall be non‐greasing, self lubricating material so 
as to provide consistent and trouble free operation. 
 
D. Operation of ELCB shall be independent of mounting position and shall be trip free 
type. 
 
2.11 LIGHTING/SMALL POWER DISTRIBUTION BOARDS 
 
A. Distribution  boards  shall  be  of  standard  make  with  MCBs  as  per  approved  make 
given. Distribution boards shall be constructed out of steel sheet all weld enclosure 
with double door IP42 protection and shall be powder coated. 
 
B. Ample  clearance  between  the  conductors  of  opposite  pole,  between  conductors 
and  sheet  steel  body  shall  be  maintained  in  order  to  obviate  any  chance  of  short 
circuit.  Removable  conduits  entry  plates  shall  be  provided  at  top  and  bottom  to 
facilitate drilling holes at site to suit individual requirements. 
 
C. Also  on  additional/separate  adopter  box  of  suitable  length  and  size  shall  be 
provided to accommodate wires and cables.  No. of conduits etc. and nothing shall 
be payable on this account. 
 
D. The MCBs shall be mounted on high grade rigid insulating support and connected 
by electrolytic copper bus bars. 
 
E. Each  incoming  MCB  isolator  shall  be  provided  with  solder‐less  cable  sockets  for 
crimping. 
 
F. Phase  separation  barriers  made  out  of  arc  resistant  materials  shall  be  provided 
between the phases. Bus bars shall be colour coded for phase identification. 
 
G. Distribution  boards  shall  be  recessed  in  wall  niche  or  if  required  mounted  on  the 
surface of the wall with necessary clamp bolts etc. 
 
H. The  mounting  height  shall  not  exceed  1200mm  from  finished  floor  level. 
Distribution  board  shall  be  provided  with  proper  circuit  identification  name  plate 
and danger sticker/plate as per requirements. 
 
I. All  the  distribution  boards  shall  be  provided  with  engraved  name  plates  with 
‘lighting’, ‘power’ or ‘UPS’  with DB Nos., as the case may be. 
 
J. Each  DB  shall  be  provided  with  a  circuit  list  giving  details  of  each  circuit.  All  the 
outgoing  circuit  wiring  shall  be  provided  with  identification  ferrules  giving  the 
circuit number & phase. 
 
K. Each distribution board shall have a separate neutral connection bar and a separate 
earth  connection  bar  mounted  within  the  DB  each  having  the  same  number  of 
terminals  as  the total  number  of  outgoing  individual  circuits  from  the distribution 

PMC: NSL  E 74   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

board.  Conduit  &  cable  armouring  shall  be  bonded  together  &  connected  to  the 
distribution board earth bar. 
 
L. Where  oversized  cables  are  specified  due  to  voltage  drop  problems,  it  shall  be 
contractors  responsibility  to  ensure  that  satisfactory  terminal  arrangements  are 
provided without an extra cost.  
 
2.12 TELEPHONE OUTLETS 
 
A. Telephone outlets  where called  for  shall  be  single  or  twin  of  the  flush  mounted 
type  suitable  to  receive  the  plug‐in  telephone  cable  lead  to  the  approval  of  the 
Telecom.    The  finishes  of  the  telephone  outlet  plates  at  various  areas  shall  be  as 
specified for lighting switches. 
 
 
2.13 WATER COOLER DRINKING FOUNTAIN SWITCHES 
 
A. Water cooler switches shall be flush‐mounted having double pole AC switch rated 
at 20 amps and marked “water cooler”. 
 
B. Associated connector units shall be provided next to the water cooler. 
 
C. The switches and the connector shall be IP65 waterproof rating. 
 
2.14 BELL PUSH SWITCHES 
 
A. Bell push switches shall be flush‐mounted having a single‐pole AC switch rated at 
6 amps and marked with bell symbol. 
2.15 SHAVER OUTLETS 
 
A.  Shaver  outlets  shall  comprise  a  20VA  continuously  rated  double  wound  isolating 
transformer to provide an earth‐free AC supply at mains frequency, complete with 
self  resetting  thermal  overload  device  filled  in  the  primary  circuit  an  insulated 
voltage selector switch to provide either 115 or 230 volt output, one ON‐OFF switch 
and  one  universal  socket  outlet  suitable  for  British,  American,  Continental  and 
Australian  razor  plugs,  all  contained  in  a  recessed  sheet  steel  box  with  insulated 
moulded  front  plate  suitable  for  flush,  mounting  and  suitably  inscribed  to  give  a 
clear indication of the voltages available at the outlet and the service of the outlet. 
 
2.16 COOLER CONTROL UNITS 
 
A. Cooler Control Units shall be flush mounted having a double pole AC switch rated 
at  30  amps  complete  with  pilot  indicating  lamps  and  a  self  adhesive  plastic 
identification  label  mounted  on  a  removable  chassis  contained  within  steel  box 
finished  aluminium  stoved  enamel  provided  with  conduit  knockouts  and  earthing 
terminals.    The  cover  plates  shall  be  of  the  same  finish  as  those  specified  for  the 
lighting switches. 
 

PMC: NSL  E 75   
Electrical: Wiring Devices Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

B. Associated connector units shall be provided adjacent to the cooler units. 
 
C. Wirings between the cooler control units and associated connector units shall be 
provided in concealed conduits. 
 
2.17 WATER HEATER SWITCHES 
 
A.  Water heater switches shall be flush mounted having double pole AC switch rated 
at  20  amps  fitted  with  pilot  lamp  and  marked  “water  heater”.    The  cover  plates 
shall  be  of  the  same  finish  as  those  specified  for  the  other  switches.  Associated 
connector units shall be provided next to the water heater units.  
 
2.18 POWER SUPPLY FOR LIGHTING AT WET CONDITION  
 
A.  Residual  Current  Circuit  Breakers  shall  be  provided  individually  for  each  circuits 
serving lighting subject to wet condition. 
 
 
 
 
END OF SECTION 
 

PMC: NSL  E 76   
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

CIRCUIT BREAKER

PART 1 – GENERAL

1.1 SCOPE

A. Circuit breaker including Air-circuit breaker (ACB), Moulded Case Circuit Breakers (MCCB), Miniature
Circuit Breakers (MCB) and Residual Current Circuit Breakers (RCCB / RCD) shall be provided according to the
specification.

B. All breakers shall be capable of withstanding the electrical, mechanical and thermal stress of the
prospective fault level experience. The prospective fault levels of the various breakers shall be verified according to
result in short circuit/co-ordination study.

C. The drawings, specification and BOQ compliment each other and which is shown or called for one shall be
interpreted as being called for on both. Material, if any, which may not have been specified but fairly required to
make a complete assembly of switch gear as shown on the drawing, specifications shall be construed as being
required and no extra charges shall be payable on this account.

1.2 STANDARDS

A. All equipment, material and components shall comply with the requirements of the latest
editions of Indian Standards with updated amendments. Standards and Regulations applicable in the
area where equipment is to be installed shall also be followed.

B. The equipment offered complying with other standards, these standards shall be equal
to or superior to those specified and full details of the differences shall be furnished along with the
tender.

C. The Panel boards shall be engineered and constructed in accordance with the latest
revision of the following Indian and British standards:

1. IS:13947 : Air circuit breaker/molded case circuit breaker.


1993/
IEC 947-
1989
2. IS: 3156 : Voltage transformers.
3. IS: 2705 : Current transformers for metering and protection with classification
Part-I, II & III burden and insulation.
1964
4. IS: 9224 : Low voltage fuse and protection.
5. IS: 3231 : Specification for electrical relays for power system protection.
6. IS:8623 : Specification for factory built assemblies of switchgear and control gear
for voltage unto and including 1000-V AC/1200 V-DC.
7. IS: 4237 : General requirements for switch gear and control gear for voltage not
exceeding gear.
8. IS: 2147 : Degree of protection provided by enclosures for low voltage switch gear
and control gear.
9. IS: 1018 : Switchgear and control gear selection/installation and maintenance.
10. IS: 1248 : Direct acting electrical indicating instruments.
11. IS: 375 : Arrangement for switchgear, bus bars, main connections, auxiliary
wiring and marking.
12. IS: 2959 : AC contactors for voltage not exceeding 1000V.
13. IS: 5578 : Guide for marking of insulated conductors.

PMC: NSL E 77
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

14. IS: 11050 : Guide for forming system of marking and identification of conductors &
apparatus terminal.
15. IS: 1248 : Direct acting indicating analogue electrical measuring instruments and
testing accessories.
16. IS: 6005 : Code of practice for phosphating of iron & steel.
1. BS EN 60898 : Circuit breakers for over current protection for household and similar
IEC 898 installations.
2. BS EN : Low-voltage switchgear and control gear, Part 2 circuit breakers.
60947-2 IEC
947-2
3. BS 5419 : Air-break switches, air-break disconnectors, and fuse combination units
for voltage up to and including 1000V AC and 1200 VDC.
4. BS 5486 : Low-voltage switchgear and control gear Part 1 assemblies. Part 1
requirement for type tested and partially type tested assemblies.
5. BS 4293 : Residual Current Circuit Breaker

D. BS/IEC or other National standards not mentioned above but are applicable to this
installation shall also apply.

1.3 SUBMISSION

A. A component list and catalogues.

B. Preparation of bill of materials for Different Items as mentioned in Schedule of


Quantities.

C. Factory and site testing procedures and report formats shall also be included.

D. Protection co-ordination drawings/tables for complete power system.

E. Shop inspection and testing procedures.

F. Field testing and commissioning procedures.

G. General Arrangement drawing of the Switchboard, showing front view, plan, foundation
plan, floor cutouts/trenches for external cables and elevations, transport sections and weights.

H. Sectional drawings of the circuit breaker panels, showing general constructional


features, mounting details of various devices, bus bars, current transformers, cable boxes, terminal
boxes for control cables etc.

I. Schematic and control wiring diagram for circuit breaker and protection including
indicating devices, metering instruments, alarms, space heaters etc.

J. Terminal plans showing terminal numbers, ferrules markings, device terminal numbers,
function etc.

K. Relay wiring diagrams.

L. Equipment List.

M. Vendor shall furnish required number of copies of above drawings for Purchaser’s
review, fabrication of switch boards shall start only after Purchaser’s clearance for the same. After final
review, required number of copies and reproducible shall be furnished as final certified drawings.

N. The information furnished shall include the following:

PMC: NSL E 78
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

a. Technical literature giving complete information of the equipment.

b. Erection, Operation and Maintenance Manual complete with all relevant information, drawings
and literature for auxiliary equipment and accessories, characteristics curves for relays etc.

c. A comprehensive spare parts catalogue.

Any other work/activity which is not listed above; however is necessary for completeness of electrical
system.

PART 2 – PRODUCTS

2.1 AIR CIRCUIT BREAKERS

A. Air circuit breakers shall be metal clad, flush mounted, horizontal draw out isolation, air break type
complying to IEC 60947-2: 1995/ IS:13947-1993. Air circuit breakers shall have a rupturing capacity of not less
than short circuit current experienced at location of installation for 3 seconds certified by ASTA or other recognized
testing authorities.

B. The breaker shall be provided with variable microprocessor based releases for over load, short circuit and
earth fault protection (and shall be compatible with PC) and shall be in conformance with this specifications.

C. All air circuit breakers (ACBs) shall be of draw-out type encased in metal clad housings. The manufacturing
of the breaker shall be such that there is no compulsory safety clearance imposed around the breakers, in order to
optimise the switchboard space requirement.

D. The ACBs shall be so manufactured that they comprise of main and arcing contacts of adequate ratings
and housed in reinforced polyester casings, offering double insulation from the front face and ensuring no possibility
of “Flashover” between phases. The main contacts shall have double-actions in each pole and all contacts shall be
silver-plated and replaceable.

E. Arc chutes with stainless steel filters shall be provided on each pole of the breaker as an efficient means of
arc control. The filters must be effective to minimize the diffusion of ionized gas outside the breaker when the
contacts open on short circuits. This manufacturing detail must be effective at all levels of current for which the
breaker is manufacture to operate. Any arc created as a result of the opening of the breaker’s contacts during fault
conditions shall be completely contained in the chute without any possibility of a “Flashover” between poles or to
adjacent earthed metallic parts.

F. The draw out version of ACBs shall have three indicated positions as follows:
1. Connected : The breaker is fully racked-in with all the main & auxiliaries engaged.
2. Tested : The breaker is racked out and with the main disconnected, but all auxiliaries are still
connected.
3. Disconnected : The breaker is fully withdrawn and all circuits disconnected.

G. A clear means of Positive Contact Indication (PCI) shall be provided by a mechanical flag marked “ON” or
“OFF” to indicate the circuit breaker’s contact positions. The stored energy mechanism shall also have clear
indications marked “CHARGE” or “DISCHARGE” to reflect its status.

H. Safety shutters shall be provided to all drawout breakers in order to inhibit inadvertent access (degree of
protection IP20) to the “live” clusters when the breakers are in the “Test” or “Disconnected” positions. It must be
possible to padlock the safety shutters in the SHUT position.

PMC: NSL E 79
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

I. Auxiliary switches shall be equipped for each breaker for indication, alarm and control purposes. Auxiliary
switches shall be robust, with double break-action, easily accessible for maintenance and having adequate current
ratings to carry the connected load. Each breaker shall have provision for extending the number of auxiliary
switches to cover future alarm or signalling circuit requirements. All auxiliary circuitry wiring shall be connected on
the front face of the breaker on a set of disconnecting terminals to facilitate the automatic disconnection of auxiliary
circuits when the breaker is in the “Disconnected” position.

J. Circuit breakers shall be manufactured for optimum performance with minimum maintenance. The
mechanical endurance (C-O cycles) without maintenance shall be at least 12500 cycles for breakers up to 1600A,
10000 cycles for breakers from 2000A to 4000A and 5000 cycles for 5000A and 6300A breakers. The electrical
endurance (C-O cycles) at 440V without maintenance shall be 10000 cycles for breakers up to 1600A, 8000 cycles
for breakers of 2000A, 5000 cycles for breakers of 2500A to 4000A and 1500 cycles for 5000A and 6300A
breakers.

K. The circuit breakers shall be equipped with electrical motor operating mechanisms for automatic charging
of the stored energy spring mechanism. However, this shall not prohibit the breakers to be operated manually, if
required. Closing operations can be initiated either from the local push button on the front face of the circuit breaker
or by remote control. The closing coils shall be rated at 23OVac. After closing, the stored energy spring mechanism
shall immediately be recharged automatically by the motor, so as to be ready for next closing operation when the
breaker trips.

L. Normal manual opening of the circuit breaker shall be accomplished either from the local push button on
the front face of the circuit breaker or by means of a trip coil. The trip coil must be capable of carrying continuous
rated current, i.e. being permanently energized, for electrical interlocking purposes. The tripping mechanism shall
be robustly built and stable without possibility of being inadvertently operated by shock or jerk. The trip coil shall be
manufactured such that the plunger operates immediately when activated, without having undue delay for the
building up of the coil’s magnetic field. Regardless of all circumstances, the speed of closing and opening shall be
independent of the operator.

M. The operating mechanism, carriage and hinged panel shall be so interlocked that it is not possible to
withdraw the circuit breaker while it is in the closed position. Closing of circuit breaker in between service and
disconnected position is also not possible and vice versa.

N. Provision shall be made so that it is possible to operate the circuit breaker mechanism when it is in the
disconnected position.

O. The main circuit breakers for the incoming supply and the bus-tie (couple) breaker shall be mechanically
and electrically interlocked such that only two of the three circuit breakers can be closed at any one time. The
mechanical interlock shall be achieved be means of Ronis keys and electrical interlock by means of a permanently
energized coil. The system shall be so arranged that the withdrawal of any one circuit breaker shall in no way effect
the operation of the others.

P. Pad locking facilities shall be provided for each breaker so that breaker operation can be locked in a
particular position if so indicated.

Q. The tests to verify the characteristics of circuit breaker shall include type tests, routine tests and special
tests.
1. Type test shall include:
a. Verification of temperature rise unit
b. Verification of dielectric properties
c. Verification of rated short-circuit making and breaker current
d. Verification of mechanical operation and endurance
2. Routine test shall include:
a. Mechanical operation tests
b. Calibration of releases

PMC: NSL E 80
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

c. Dielectric tests

R. Other tests, which are to be carried out on request of the relevant authorities, shall be done on the Vendor’s
account. Vendors must submit type test certificates issued by ASEFA, ASTA or other recognized testing authorities
together with the Technical documents or upon request.

2.02 MOULDED CASE CIRCUIT BREAKERS (MCCB)

A. The MCCB shall comply with IS13947-1993/ IEC 947-2:1995. The MCCB shall be provided with over
current protection by means of thermal and magnetic tripping element.

B. All MCCB tripping mechanism shall be ambient temperature compensated. MCCB of frame sizes greater
than 150 amps shall be equipped with continuously adjustable magnetic pick up setting. MCCBs used for incoming
main feeders shall in addition be provided with continuously adjustable rated current settings in the range of 60 to
100% rated current.

C. The MCCBs shall have quick make and quick break mechanism independent of the operating speed. The
tripping mechanism shall be mechanically “trip free” from the handle so that the handle cannot be closed against
fault conditions.

D. The MCCB shall be provided with door interlock handles. All handles shall be large and robust to carry out
the switching operation with ease. The handle shall clearly indicate the “ON”, “OFF” and “TRIP” positions. The
handle shall be able to be locked in the “ON” or “OFF” positions. When locked in the “ON” position it shall still be
possible for the handle to indicate “TRIP” when the MCCB has tripped. An interlock release mechanism shall be
provided to enable the door to be opened when the MCCB is locked in the “ON” position.

E. Multi-pole MCCB shall have a common-trip bar so that a fault condition on any one pole of the MCCB will
cause all poles to trip simultaneously.

F. The MCCB interrupting capacity shall be not less than that indicated on the drawings unless alternative
scheme using cascading protection or other schemes are utilised.

G. MCCBs of ratings 200A and above shall be of Busbar termination type, adaptable for use with bolts and
cable lugs.

H. Automatic change over MCCBs shall be of the motorised type, fully withdrawable, with both mechanical and
electrical interlock. The transfer operation shall be controllable by an adjustable time delay of between 0.1 to 30
sec. The actual transfer time of the MCCBs shall not exceed 2 sec. The motor mechanism shall utilise universal
motor with electro magnetic clutch and shall be equipped with full handles to allow manual operation of the MCCB.
All automatic change over MCCBs shall have a minimum mechanical life of 10,000 operations.

I. MCCB when used for motor protection shall have characteristics suitable for the motor starting. Standard
range MCCB shall not be substituted for motor protection circuits.

J. All fully withdrawable MCCB shall have interlocks to prevent withdrawal when the MCCB is “ON”.

K. All main moulded case circuit breaker shall be provided with at least 2 pairs N/O and N/C auxiliary contact.

L. Indicating lamps shall be of the panel mounting, LED type and shall have execution plates marked with its
function wherever necessary. The colour of the lamp cover shall be red for ‘ON’ and green for ‘OFF’ indicating
lamps shall be provided with series resistor.

2.03 MINIATURE CIRCUIT BREAKERS (MCB)

PMC: NSL E 81
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

A. MCBs shall comply with IEC 898:1995. They shall be of the current limiting type having a sealed ambient
temperature independent thermal magnetic tripping mechanism providing overload and short circuit
protection. All MCBs shall be of 35mm D/N symmetrical rail mounted type.

B. The breaking capacity of MCBs shall be at least equal to the prospective fault level at the point installation,
unless back-up by a current limiting upstream breaker of the same make.

C. The MCB operating mechanism shall be mechanically trip free from the operating handle so as to prevent
the contacts from being held closed against short circuit and overload conditions. It shall be of the
automatic resetting type.

D. The individual operating mechanism of each pole of a multi-pole MCB shall be directly linked within the
MCB casing and not with the operating handles.

E. The operating handle shall be of the toggle type with possibility for mounting of padlocking facility.

F. Each pole shall be provided with bi-metallic thermal element for overload protection and magnetic element
for short circuit protection.

G. It shall be possible to fit on site auxiliaries like shunt-trip coil, under-voltage release, ON/OFF switch or
alarm switch.

2.04 RESIDUAL CURRENT CIRCUIT BREAKERS (RCCB)

A. RCCB shall comply with BS 4293 and shall be of the current operated type.

B. The RCCBs shall be manufactured to trip within 0.1 second for 30 mA.

C. The RCCBs shall be of 2-pole construction for single phase and 4-pole construction for 3 phases.

D. All RCCBs shall be complete with test buttons.

E. All RCCBs shall be batch tested and bear the appropriate test label of approval to SEB requirement.

F. All RCCBs shall be of high sensibility type as appropriate and as specified in the drawing. They shall be of
surge proof manufacture to prevent nuisance tripping due to transient over voltage.

PART 3 – EXECUTION

3.1 TESTING AND COMMISSIONING

A. All Switch gears shall be inspected & tested in the presence of Owner/ Consultant’s
representative and certified by the installation Engineer that it is safe before supply is energized, and
that all the equipment comply with the requirements of the Specification.

B. All routine tests specified in relevant Indian/British Standards shall be carried out on all
circuit breakers.

1. Test for protective relay operation by primary or secondary injection method.

2. Operation of all meters.

3. Secondary wiring continuity test

4. Insulation test with 1000 Volts megger, before and after voltage test.

PMC: NSL E 82
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

5. HV test on secondary wiring and components on which such test is permissible (2 KV for one
minute)

6. Simulating external circuits for remote operation of breaker, remote indicating lights and other
remote operations, if any.

7. Measurement of power required for closing/trip coil of the breaker.

8. Pick up and drop out voltages for shunt trip and closing coils.

9. CT Polarity test.

10. Tests to prove correct operation of controls, interlocks, tripping and closing circuits, indications, etc.;

11. Interfacing test with BMS control function.

12. All other tests required by the Engineer to verify compliance with the Specification.

C. Vendor shall provide all facilities such as power supply, testing instruments and
apparatus required for carrying out the tests.

D. Required copies of test certificates for all the tests carried out along with copies of type
test certificates and certificates from Sub-Vendor for the components procured from them are to be
submitted before dispatch of switch boards.

3.2 TOOLS

A. One complete set of all special or non-standard tools required for installation, operation
and maintenance of the switch board shall be provided. The manufacturer shall provide a list of such
tools with his quotation.

3.3 SPARES

A. The manufacturer/tenderer shall also supply a complete list of commissioning spares


and tools. The same shall be included in the bid price. No extra payment shall be made on account of
non-availability of spares during commissioning.

3.4 QUALITY ASSURANCE

A. Quality Assurance shall follow the requirements of Owner/ Consultant as applicable.

B. Quality Assurance involvement will commence at enquiry and follow through to


completion and acceptance thus ensuring total conformity to Purchaser’s requirements.

3.5 DEVIATIONS

A. Deviation from specification must be stated in writing at the quotation stage.

B. In absence of such a statement, it will be assumed that the requirements of the


specifications are met without exception.

C. If any of the above tests fail to comply with the requirements of this Specification in any
respect whatsoever at any stage of manufacture, test, erection or on completion at site, the Engineer
may reject the item or defective component thereof, whichever is considered necessary, and after

PMC: NSL E 83
Electrical Circuit Breakers Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

adjustment or modification as directed by the Engineer, the Contractor shall submit that item for further
inspection and/or test. In the event of the defective item being of such nature that the requirements of
this Specification cannot be fulfilled by adjustment or modification, such item is to be replaced by the
Contractor at his own expense, to the entire satisfaction of the Engineer.

END OF SECTION

PMC: NSL E 84
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
 
FIRE DETECTION SYSTEM 
 
PART 1 – GENERAL 
 
7      FIRE DETECTION AND ALARM SYSTEM :‐ 
 
7.1        SCOPE 
 
The  scope  of  this  section  covers  design,  manufacturers,  supply,  installation,  connecting,  testing  and 
commissioning of conventional type fire detection and alarm system. 
 
The work include supply, installation, testing and commissioning of: 
 
a. M S conduit work with all accessories. 
b. Complete wiring in existing concealed/surface conduits 
c. Photoelectric type smoke detectors. 
d. Rate of rise cum fixed temperature heat detectors. 
e. Manual alarm stations. 
f. Response indicators. 
g. Main control and indicating panel/zonal panel. 
 
A  high  degree  of  operational  safety,  high  quality  and  well  designed  detectors,  signal  panels  and 
auxiliary equipment shall be accepted.  Supplier shall confirm that the electronic components used in 
alarm and indicating panels are of standard manufacturers and are approved type, also the name of 
the manufacturer shall be indicated. 
 
The  Contractor  shall  obtain  clearance  and    approval  form  the  Local  Fire  Authorities,  the  insurance 
company insuring the building or any other agencies whom approval is required. 
 
7.2  STANDARDS 
   
  For Spacing of detectors    BS  :  Code of Practice 
                CP 1019, Section 2.7 
  For sensitivity of smoke detector    BS  :  5446 ‐ 1977 
  For control and indicating panel   IS  :  2189 – 1988 
 
  For smoke Detector      IS  :  11360 ‐ 1985 
 
  For Heat Detector      IS  :  2175 – 1988 
 
7.3  OPERATING VOLTAGE 
 
  220 volts AC + 10% 50 cycles (single phase) and 24 volts DC +‐ 10% 
 
 

PMC: NSL E 85
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
 
 
7.4  DETECTORS IN GENERAL   
 
7.4.1    COMPATIBILITY 
 
All automatic fire detectors shall be inter changeable without requiring different mounting bases nor 
alternations in the signal panel. 
 
7.4.2     RESPONSE SPECTRUM 
 
Combustion  gas  detectors  shall  respond  to  both  visible  and  invisible  aerosols,  size  and  colour  of  the 
aerosols shall not have a decisive influence on the response of the detector. 
 
7.4.3    SENSITIVITY 
 
On average, 30 mgr of burned material per cu.m (as measured in a 1 cu.m chamber) shall release an 
alarm. 
 
 
            POWER CONSUMPTION 
 
Each  detector  shall  use  the  minimum  of  power,  for  economic  circuits,  so  that  it  shall  be  possible  to 
connect atleast 20 detectors per zone.  Distance upto 1000 meters from detector to signal panel shall 
not influence the number of detectors per zone. 
 
            BUILT‐IN‐RESPONSE INDICATOR 
 
Each  detector  shall  incorporate  indicator  “LED”  at  the  base  of  the  detector  which  shall  light  up  on 
actuation of the detector to located the detector which is operated.  The detector shall not be affected 
by failure of the response indicator lamp. 
     
            RESPONSE INDICATORS 
 
It shall be possible to provide a secondary response indicator for the detector outside the closed room. 
 
             MAINTEANCE 
 
All  detectors  shall  be  fitted  either  with  plug‐in  system  or  bayonet  type  connections  only,  from  the 
maintenance and compatibility point of view. 
 
            CONSTRUCTION 
 
The  detector  shall  be  vibration  and  shock  proof.    When  disassembling  for    cleaning  purpose,  its 
components must not be damaged by static over voltage. 
 
 

PMC: NSL E 86
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

             ATMOSPHERIC AND THERMAL DISTURBANCES 
 
The detector shall also be designed as to be practically immune to environmental criteria such as air 
currents, humidity, temperature fluctuations, pressure and shall not release false alarm. 
 
            CONTINUOUS OPERATION 
 
An alarm release shall not effect a detector’s good functioning.  After resetting the alarm the detector 
shall resume operation without re‐adjustment of any kind. 
 
            DAPTABILITY TO AMBIENT CONDITIONS 
 
Detectors shall be designed for adaptability to humid and explosion endangered locations. 
 
18      PHOTOELECTRIC SMOKE DETECTORS 
 
Smoke  detectors  shall  connect  with  two  wires  to  one  of  the  Fire  Alarm  Panel  Loops.    The  detectors 
shall  use  the  photoelectric  (light‐scattering)  principal  to  measure  smoke  density  and  shall,  on 
command  from  the  control  panel,  send  data  to  the  panel  representing  the  analog  value  for  smoke 
density.  The detectors shall be ceiling mounted type and shall include a twist‐lock base. 
 
The detectors shall provide dual alarm and power LEDs.  Both LEDs shall flash under normal conditions, 
indicating that the detector is operational and in regular communication with the control panel.  Both 
LEDs  may  be placed into steady illumination by the control panel; indicating that an alarm condition 
has  been  detected.    An  output  connection  shall  also  be  provided  in  the  base  to  connect  an  external 
remote alarm LED. 
  
  The area covered by each smoke detector shall be as per IS‐2189. 
 
  Detectors shall be suitable for an operating temperature 0 degree C to 55 degree C and    
  Relative humidity of 0% to 95%. 
 
Detectors shall be suitable for a supply voltage of 17 to 28 V DC without affecting the sensitivity. 
 
The detector shall have the approval of UL/FM/VDS/LPC only. 
 
19.   THERMAL DETECTORS 
 
Thermal detectors shall connect with two wires to one of the Fire Alarm Panel loops.  The detectors 
shall use an electronic detector to measure thermal conditions caused by a fire and shall, on command 
from the control panel, send data to the panel representing the level of such thermal measurements.  
The detectors shall be ceiling‐mounted type and shall include a twist‐lock base. 
 
The detectors shall provide dual alarm and power LEDs.  Both LEDs shall flash under normal conditions.  
Both  LEDs  may  be  placed  into  steady  illumination  by  the  control  panel,  indicating  that  an  alarm 
condition has been detected. 
 

PMC: NSL E 87
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

Detectors  shall  be  suitable  for  an  operating  temperature  0  degree  C  to  22  degree  C  and  relative 
humidity of 0% to 95%. 
 
Detectors shall be suitable for a supply voltage of 17 to 28 V DC without affecting the sensitivity. 
 
The detector shall have the approval of UL/FM/VDS/LPC only. 
 
7.6  MANUAL CALL STATIONS 
  Manual Call stations shall be provided to connect to the Fire Alarm Panel loops. 
 
Manual  stations  shall  be  constructed  of  high  impact  LEXAN  sheet  with  clearly  visible  operating 
instructions provided on the cover.  The word FIRE shall appear on the front of the stations in raised 
letters.  Press/back stations with reset table capacity shall be acceptable. 
 
Stations  shall  be  suitable  for  surface  mounting  as  shown  on  the  plans,  or  semi‐flush  mounting,  and 
shall  be  installed  not  less  than  42  inches,  nor  more  than  48  inches  above  the  finished  floor  unless 
otherwise specified by applicable building codes. 
 
7.7  RESPONSE INDICATOR 
 
Response indicator shall be LED (light emetting diode) type, and shall indicate when a detector senses 
the fire. 
 
 7.8      REPEATER PANEL 
Repeater panels are to be provided at remote location for monitoring the health of FAS.  It should have 
2 line 40 inches character display along with CEO status indicator.  Battery backup shall be provided as 
an in‐built feature and all information will be presented in clear English language.  It shall be suitable 
for operation from 0 degree C to 49 degree C and shall be flush mounted. 
 
 
 
 7.9  ELECTRONIC HOOTERS 
 
All Hooters should be able to provide at least a minimum of 3 different tones, which should be user 
configurable.  The minimum decibel level of each hooter should be 90db at 1 mtr.  All hooters should 
be UL/FM listed. 
 
The Electronic Hooters shall be housed in MS enclosure of 1.5 mm sheet metal. 
 
The Hooters shall be with built on oscillator & amplifier. 
 
The Hooters shall give wailing sound whenever it received 24 V supply from panel on receipt of Fire 
signal. 
 
The MS box shall be painted with Fire Red ( Power Coated) 
 
7.10     MAIN FIRE ALARM CONTROL PANEL 
 

PMC: NSL E 88
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

Control Panel 
 
The  control  cabinet  shall  be  dust  proof  and  shall be provided with a glass door with lock and key to 
prevent tempering by unauthorized persons. 
 
The  control  circuit  shall  consists  of  glass  epoxy  (PCB)  printed  circuit  board,  silver  plated  and  treated  
with protective layer of special lacquer for protection against corrosion. 
The alarm circuitry shall be 100% solid state without the use of any relays anywhere in zone card. 
 
The zone cards shall be modular and interchangeable. 
 
Every zone shall have individual control for test acknowledge and any zone shall be isolated without 
effecting the working of the other zones in the panel. 
 
Sounder  silencing  control  shall  be  provided  which  shall  remain  in  visual  indication  at  the  same  time 
making the panel from to receive alarm from any other zone without the need for resetting the entire 
panel. 
 
Silencing switches/push buttons – the system shall be so designed that once an alarm has been given it 
shall continue till the alarm sounder is switched off.  The silencing switches/push buttons in their ‘OFF’ 
position shall give and indication of this fact on the main control panel or transfer the alarm signal to 
supervisory sounders under the supervision of the responsible person so that they may put use of the 
smallest number of call points. Operation of silencing switch shall not prevent sounding of alarm from 
any other zone simultaneously. 
  

Central control and indicating panel shll be suitable for conventional Fire Detection and Alarm System and shall 
comply with IS:2189‐1988. 
  Control panel shall support the following Fire‐Detection components. 
 
  Smoke Detectors 
  Detectors (Both fixed & rate of temperature rise type) 
  Manual Call Stations 
 
System shall be completely backed up against Mains failure for atleast 8 hours and shall be suitable for 
the following types of batteries. 
 
  Lead acid Maintenance free. 
  Lead acid non‐maintenance free 
  Lead acid semi‐maintenance free 
  Nickel Cadmium. 
 
  System shall be self diagnostic and shall cover the following: 
  Components/Modules of the fire panel. 
  Faulty detectors 
  Missing detectors 
  Open circuit short circuit conditions of the detector cable. 
  Suitable indication shall be given on the panel. 

PMC: NSL E 89
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
  Zone wise annunciation of alarm by using: 
  Buzzer Sounders 
 
 
 
 
7.11.  BATTERY 
 
Suitable rating ampere Hours 24 Volts DC sealed maintenance free batteries shall be provided for Fire 
Detection and Alarm System.  The battery rating is indicative only.  It shall be sized by bidder to cater to 
all momentary and short time loads in addition to supplying the continuously rated loads for a duration 
of 8 hours.  However minimum size shall be 65 AH. 
 
 

    Battery Charger 
 
Bidder  shall  furnish  the  battery  charging  system  complete  with  all  necessary  accessories  such  as 
transformer, rectifier, switches, fuses, starters, contactors, ammeter, voltmeter, protections and other, 
devices for trouble free operation. 
 

Construction features 
 
Housing  of  battery  charger  shall  be  2  mm  thick  CRCA  steel  sheet  cabinet  for  indoor  installation  and 
shall  be  floor  mounted  type.    The  cabinet  shall  be  folded  and  braced as necessary to provide a rigid 
support for all components.  Louvers shall be provided in the cabinet for ventilation.  PVC sheets of 3 
mm thick shall be provided on the selves on which the batteries are to be placed. 
 

Input 
 
240 volts AC 50 cycles, single phase with tappings of 0‐200‐220‐240‐260 volts on the primary side of 
the transformer. 

               Output 
 
DC output shall be 24 volts.  DC bridge rectifier shall be of silicon type, having full wave rectification.  
Suitable contactor, relay, reset shall be provided as required. 
 
7.12  CABLES 
 
All PVC insulated FRLS copper conductor stranded cables shall be 650 volts grade and shall generally 
conform to IS‐1554‐1988 and meet the signal cabling requirement of the system manufacturer. 
 
Strands of cables shall not be cut to accommodate & connect to the terminals.  Terminals shall have 
sufficient cross‐sectional area to take all the strands. 

PMC: NSL E 90
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
Cables shall be laid by skilled and experienced workmen using adequate rollers to minimize stretching 
of the cable.  The cable drums shall be placed on jacks before unwinding the cable.  Great care shall be 
exercised in laying cables to avoid forming kinks.  At all changes in direction in horizontal and vertical 
planes,  the  cable  shall    be  bent  smooth  with  a  radius  as  recommended  by  the  manufacturer’s.    All 
cables shall be laid with minimum one diameter gap and shall be clamped at every metre and shall be 
tagged  for  identification  with  aluminium  tag  and  clamped  properly.    Tags  shall  be  provided  at  both 
ends and all changes in directions both sides of wall and floor crossings.  All cable shall be identified by 
embossing on the tag the size of the cable, place of origin and termination. 
 
These  shall be measured on linear basis including the fittings  required like, end termination junction 
box. 
 
8.3         PUBLIC ADDRESS DEVICES 
 
8.3.1  Speakers: 
 
    All speakers shall operate on 25 VRMS or with field selectable output taps from 0.5 to 2.0 
Watts. 
 
    Speaker in corridors and public spaces shall produce a nominal sound output of 84 dBA at 3 
meter. 
Frequency response shall be a minimum of 400 HZ to 4000 HZ. 
 
The back of each speaker shall be sealed to protect the speaker cone from damage and dust. 
 
8.3.2 Fixed Emergency Telephone Handset   
 
    The telephone cabinet shall be painted red and clearly labeled as “Emergency Telephone”.  The 
cabinets shall be located where  shown on drawings. 
 
The handset cradle shall have a switch connection so that lifting the handset off of the cradle shall send 
a  signal  to  the  fire  command  center  which  shall  audibly  and  visually  indicate  its  on‐line  (off‐hook) 
condition. 
 
On  activating  the  remote  phone,  the  phone  earpiece  shall  sound  a  telephone  ring  signal  until  the 
master handset is lifted. 
 
The  two‐way  emergency  telephone  system  shall  support  a  minimum  of  seven  (7)  handsets  on  line 
without degradation of the signal. 
   
 
 
 
 
 
END OF SECTION 

PMC: NSL E 91
Electrical: Fire Alarm Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
 

PMC: NSL E 92
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

LAN CABLING SYSTEM 
 
Cabling Installation Guidelines 
Guidelines for establishing the LAN 
 The  vendor  will  carry  out  the  site  survey  for  LAN  creation.  The  survey  shall 
include  the  routes,  distance  between  the  offices,  hindrances  and  all  other 
activities  that  are  required  to  be  carried  out  for  the  site  survey  before  LAN 
creation. 
 After the field survey, the vendor shall calculate the number of different type 
of interface components required for establishing FOC links. 
LAN cable laying specifications 
 
ISO 11801 cabling standards and local construction and tele‐communication regulations    
Provide a user friendly environment with adequate technical support for maintenance 
Enable easy performance upgrade 
 
The following standards are to be compiled with unless otherwise specified: 
 
 ISO/IEC  11801:2002  –International  standard  for  generic  cabling  for  customer 
premises 
 EIA/TIA  568B  –  Commercial  Building  Telecommunications  Cabling  Standard 
(2002) 
 EIA/TIA  568B.2‐1‐  Commercial  Building  Telecommunications  Cabling  Standard 
(2002) 
 
Cabling to be done in a structured way using RJ 45 connectors, RJ I/O boxes in concealed 
conduits 
All  passive  components  and  cable  should  be  from  same  OEM  and  should  accomplish 
complete end to end channel warranty (20 years), Certification from OEM 
 
UTP Cabling Installation Specifications 
 
1. Cables  shall  be  coiled  in  the  surface‐mount  boxes  if  adequate  space  is  present  to 
house  the  cable  coil  without  exceeding  the  manufacturer’s  bend  radius.  No  more 
than 12” of slack shall be stored. 
2. In addition, each cable type shall be terminated as indicated below: 
a. Cables  shall  be  dressed  and  terminated  in  accordance  with  the 
recommendations made in the ANSI/TIA/EIA‐568‐B.2.1 document. 
b. Pair untwist at the termination shall not exceed one‐half an inch for Category 
6 connecting hardware. Bend radius of the cable in the termination area shall 
not be less than 4 times the outside diameter of the cable. 
c. The  cable  jacket  shall  be  maintained  as  close  as  possible  to  the  termination 
point. 

PMC: NSL E 93
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

d. Cables  shall  be  neatly  bundled  and  dressed  to  their  respective  panels  or 
blocks. Each panel or block shall be fed by an individual bundle separated and 
dressed back to the point of cable entrance into the rack or frame. 
e. Each cable shall be clearly labeled on the cable jacket behind the patch panel 
at  a  location  that  can  be  viewed  without  removing  the  bundle  support  ties. 
Cables labeled within the bundle, where the label is obscured from view shall 
not be acceptable. 
 
1. Cable  shall  be  installed  in  accordance  with  manufacturer’s  recommendations  and 
best industry practices. 
2. Cables  shall  be  installed  in  continuous  lengths  from  origin  to  destination  (no 
splices).  The  cable’s minimum  bend radius  and maximum  pulling  tension  shall  not 
be exceeded. 
3. Horizontal  distribution  cables  shall  be  bundled  into  groups  of  not  greater  than  40 
cables. Cable bundle quantities in excess of 40 cables may cause deformation of the 
bottom cables within the bundle. 
4. Cables  shall  not  be  attached  to  ceiling  grid  or  lighting  support  wires.  Any  cable 
damaged  or  exceeding  recommended  installation  parameters  during  installation 
should be replaced by the contractor prior to final acceptance at no cost. 
5. A self‐adhesive label or PVC marker ferules shall identify the Cables. A cable label 
shall be applied to the cable behind the faceplate on a section of cable that can be 
accessed by removing the cover plate. Similar label or marker ferrules shall also be 
placed on a section of the cable near to the patch panel termination. 
6. Unshielded twisted pair cable shall be installed so that there are no bends less than 
four times the cables outside diameter (4 X cable outside diameter) at any point in 
the run. 
7. Pulling tension on 4‐pair UTP cables shall not exceed 25‐pounds for a single cable or 
cable bundle. The pathway shall be adequately sized so as not to exceed the 80% 
cross‐section fill of cables. The pathway shall be securely installed in the facility. 
 
 Proper tagging for identification of cables to be done 
 The vendor shall do the cabling from the cross connect at the floor distributor 
(FD) administration sub system using CAT 6 and RJ 45 Jacks 
 Each  run  of  the  cable  from  the  cross  connect  at  the  FD  to  the  information 
outlets should be continuous without any joints / splices 
 The  vendor  should  ensure  that  the  cabling  is  done  in  such  a  way  that  error 
free transmission is done 
 The cross connect module should be fire retardant 
 Necessary  electrical  connections  to  be  provided  for  all  the  equipments  / 
devices to be installed by the vendor 
 Cabling provision to include connection with UPS and earthing 
 Where ever required patch chords to be used with the given specifications 
 

PMC: NSL E 94
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

Horizontal distribution cable & installation 
 
 Cable shall be installed in accordance with manufacturer’s recommendations 
and best industry practices. 
 Cable  raceways  shall  not  be  filled  greater  than  the  manufacturer 
recommended guidelines. Cables shall be installed in continuous lengths from 
origin  to  destination  (no  splices).  The  cable’s  minimum  bend  radius  and 
maximum pulling tension shall not be exceeded. 
 Cables shall not be attached to ceiling grid or lighting support wires. Any cable 
damaged  or  exceeding  recommended  installation  parameters  during 
installation should be replaced by the vendor prior to final acceptance at no 
cost to CVENT. 
 A self‐adhesive label or PVC marker ferules shall identify the Cables. A cable 
label shall be applied to the cable behind the faceplate on a section of cable 
that  can  be  accessed  by  removing  the  cover  plate.  Similar  label  or  marker 
ferrules shall also be placed on a section of the cable near to the patch panel 
termination. 
 Unshielded twisted pair cable shall be installed so that there are no bends less 
than  four  times  the  cables  outside  diameter  (4  X  cable  outside  diameter)  at 
any point in the run. 
 Pulling  tension  on  4‐pair  UTP  cables  shall  not  exceed  25‐pounds  for  a  single 
cable  or  cable  bundle.  The  pathway  shall  be  adequately  sized  so  as  not  to 
exceed  the  80%  cross‐section  fill  of  cables.  The  pathway  shall  be  securely 
installed in the facility. 
 
 
UTP Cabling System Specifications 
Description  CAT 6 UTP Cabling System 
Type  Unshielded twisted pair cabling system, 
ANSI/TIA/EIA 568‐B.2.1 Category 6 cabling system 
Networks  10 / 100 Ethernet, 155 Mbps ATM, 1000 Mbps IEEE 
Supported  802.3ab Ethernet 
ANSI/TIA/EIA 568‐  UL Listed/ETL Verified 
B.2.1 
IEEE 802.3ab  Zero‐bit Error 
Warranty  20‐year systems warranty; Warranty to cover 
Bandwidth of the specified and installed cabling 
System, and the installation costs 
Performance  Attenuation, Pair‐to‐pair and PS NEXT, ELFEXT 
characteristics to  and PSELFEXT, Return Loss, ACR and PS ACR for 
be provided along  4‐connector channel 
with bid 
 

PMC: NSL E 95
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

Material 
Material   
Conductors  24 AWG solid bare copper 
Insulation  Polyethylene/Polyolefin 
Jacket  LSZH  (Low smoke zero halogen) 
Approvals  UL Listed 
ETL verified to ANSI/TIA/EIA 568‐B.2.1 Cat 6 
Operating  ‐20 Deg. C up to +60 Deg. C 
temperature 
Frequency tested  250 MHz 
Up to   
Delay Skew  25ns‐45ns / 100m MAX. 
Impedance  100 Ohms + / ‐ 6 ohms 
Performance  Attenuation, Pair‐to‐pair and PS NEXT, ELFEXT 
characteristics to  and PSELFEXT, Return Loss, ACR and PS 
be provided along 
with bid 
 
1. PVC Channel 
Flexible white /ivory, Double Locking, Suitable size, ISI mark 
 
2. UTP Patch Panel 
UTP Patch Panels 
Type  24‐port, Modular, PCB based, Unshielded Twisted 
Pair, Category 6, ANSI/TIA/EIA 568‐B.2.1 
Category  Category 6 
Circuit  Port Labeling for port identification on each of 24‐ 
Identification  Ports 
Scheme 
Port Identification  Labels on each of 24/48‐ports (to be included in 
Supply) 
Height  1 U (1.75 inches) 
Modular Jack  750 mating cycles 
Wire terminal (110  200 termination cycles 
block) 
Accessories  Strain relief and bend‐limiting boot for cable or rear 
cable manager for cable support/ Cable Support 
accessories 
Jack contacts  Phosphorous bronze, plated with gold 
Panel  Black, powder coated steel 
Approvals  UL listed/ETL Verified 
Termination  ANSI/TIA/EIA 568 A and B 
Pattern 

PMC: NSL E 96
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

Performance  Attenuation, NEXT, PS NEXT, FEXT and Return Loss 
 
 
3. UTP Jacks 
 
UTP Jacks 
Type  PCB based, Unshielded Twisted Pair, Category 6, 
ANSI/TIA/EIA 568‐B.2.1 
Modular Jack  750 mating cycles 
Wire terminal  200 termination cycles 
Accessories  Strain relief and bend‐limiting boot for cable or 
conductor management piece to maintain pair 
untwist 
  Integrated hinged/spring dust cover 
Jack contacts  Phosphorous bronze, plated with gold 
Approvals  UL listed/ETL Verified 
Performance  Attenuation, NEXT, PS NEXT, FEXT and Return 
Characteristics to  Loss 
be provided with 
bid 
     
 
 
 
 
 
 
4. SMB 
Surface Mount Box / Faceplates 
Type  1‐port, Shuttered, White, with surface box for 
surface mount applications 
Material  ABS/Polycarbonate 
No. of ports  One 
Protection  Shutters 
Identification  To be supplied with label for port identification 
   
5. Patch chords  
Workstation / Equipment mounting Cords 
Type  Unshielded Twisted Pair, Category 6, 
ANSI/TIA/EIA 568‐B.2.1 
Conductor  24 AWG 7 / 32, stranded copper 
Length  3 / 7 feet 
Plug Protection  Matching colored boot to maintain bend radius 

PMC: NSL E 97
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

Warranty  20‐year component warranty 
Category   Category 6 
Terminals  Phosphor Bronze with gold plating 
Jacket  LSZH (Low Smoke Zero Halogen) 
Insulation  Flame Retardant 
 
 
 
 
 
 
 
6.         24 Port switch 
 
General   24‐port 10/100Mbps + 2 Nos. 1000 mbps base T 
requirements:   All  ports  can  auto‐negotiate  between 
  10Mbps/100Mbps,  half‐duplex  or  full  duplex 
and flow control for half‐duplex ports. 
 Support 8K MAC address 
 6.0  Gbps  Switching  fabric  capacity  for  24port 
switch. 
 Packet Forwarding Rate should be 6.5 Mpps  
 Redundant power supply support (if required) 
 Support IGMP V3 Snooping. 
 Automatic  medium‐dependent  interface 
crossover  (Auto‐MDIX)  to  automatically  adjust 
transmit  and  receive  pairs  if  an  incorrect  cable 
type  (crossover  or  straight‐through)  is  installed 
on a copper port. 
 Should support IPv6 
 Should  support  a    protocol  that  enables  devices 
connected  through  fiber‐optic  or  twisted‐pair 
Ethernet  cables  to  monitor  the  physical 
configuration  of  the  cables  and  detect  when  a 
unidirectional link exists 
 Should support enforcement of access privileges 
when  an  endpoint  attempts  to  connect  to  a 
network example anti virus version. 
 Should  be  able  to  discover  devices  that  are 
neighbors of already known devices. 
 
Performance   Multi‐layer ACL and QoS control 
   At least 8MB packet buffer per device.  

PMC: NSL E 98
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 Should support Per‐port broad cast, multi cast & 
uni cast storm control. 
 The  switch  must  support  Port  Mirroring,  Port 
Trunking  and  802.3ad  LACP  Link  Aggregation 
port trunks 
 Support  IEEE  802.3x  flow  control  for  full‐duplex 
mode ports. 
 Support  802.1D  Spanning  Tree  and  IEEE802.1W 
RSTP, multiple Spanning Tree (V2) 
 Unidirectional  Link  Detection  Protocol  for  loop 
avoidance in case of Unidirectional fiber. 
 The  Switch  should  be  capable  of  detecting  and 
disabling the port to avoid the STP loop caused 
due to single connectivity on the physical layer 
on fiber ports.  
 It  should  be  possible  to  configure  STP  on  a  per 
VLAN basis. 
 Support 802.1Q VLAN, IGMP snooping,  
 802.1p Priority Queues, port mirroring 
 Support  based  on  802.1p  priority  bits  with  at 
least  4 priority queues 
 
Access control    Support port security 
   Support  Advanced  Access  Control  Lists  (ACL), 
enhanced TACACS+ and RADIUS authentication 
 Support  802.1x  port‐based  and  MAC‐based 
access control and authentication 
 SSHv2 and SNMPv3 support 
 DHCP snooping 
 500 Access Control entries Supported. 
 IGMPv3 snooping 
 Unicast MAC filtering 
 Unknown unicast and multicast port blocking 
 IGMP filtering 
 BPDU guard 
VLAN   Support 802.1Q Tagged VLAN and port based  
   The  switch  must  support  dynamic  VLAN 
Registration . 
 Dynamic Trunking Protocol or equivalent. 
 VLAN Trunking Protocol or equivalent 
 802.1s,  802.1w,  Per  VLAN  Rapid  Spanning  Tree 
protocol 

PMC: NSL E 99
Electrical: LAN Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
Protocol and Traffic    Simple Network Time Protocol support 
   Multicast filtering per port should be supported 
 Switch should support traffic segmentation 
 Traffic  classification  should  be  based  on  user‐
definable  application  types:  TOS,  DSCP,  Port 
based,  Mac  address,  IP  address,  TCP/UDP  port 
number 
 
Management   Switch  needs  to  have  RS‐232  console  port  for 
  management via a console terminal or PC 
 Must have support SNMP upto ver.3 
 Support  Web‐based  management,  Web  GUI 
traffic monitoring 
 Web  management  should  enable  management 
for a minimum of 15 geographically distributed 
switches through a common browser window. 
 CLI management support. and IP filtering on the 
management interface 
 Must have have TFTP support 
 Layer 2 trace route 
 Switch  should  CPU  utilization  monitoring  and 
Port description 
 

PMC: NSL E 100


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
 
Three‐Phase Uninterruptible Power System 
 
Configuration Details:  
 
UPS System, connected in parallel redundant configuration in load sharing mode, shall be provided to supply 
uninterrupted  power  for  the  Server/  Network  loads.  Battery  banks  to  give  total  15  minutes  back  up  on  the 
above mentioned UPS system shall be provided for the units feeding to Server/Network loads.  
 
1.0 General 
1.1 Summary 
The  units  will  have  state‐of‐the‐art  technology  with  high  degree  of  reliability  in  operation  for  continuous 
operation, i.e. 24 hrs, 365 days an year. This specification defines the electrical and mechanical characteristics 
and requirements for a continuous duty, highly reliable stand alone type true on‐line double conversion UPS 
system using PWM IGBT technology i.e. the Rectifier of the UPS system converts the input AC power to DC and 
then the inverter converts the DC into clean AC power. The UPS must use the most advanced Microprocessor 
technology.  The  UPS  shall  provide  high  quality  AC  power  for  sensitive  electronic  equipment  loads.  It  should 
also supply clean power automatically without any break in the supply in the absence of raw power. Under no 
conditions will the protected system get direct supply from the raw mains unless there is fault in the protected 
system. The Block diagram of the UPS system should be as shown in Block Schematic Fig. 1. 

Mains ~ - output
- ~

 
Fig‐1 
The major items constituting of the blocks of the above schematic Fig.‐1 are shown as below in Fig‐1(A). 
 
 
 
 
Incoming
 
mains 415 V,
3 Phase  
 
 
Fig.‐1(A) 
 
 
 
 

PMC: NSL E101


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
The main circuit and the bypass can use the same or different sources as per the discretion of customer. The 
details of the above schematic are as given below:     
Q1:       Connects rectifier to Utility source 
Q2:       Connects bypass to Utility source 
 
Q5:       Connects UPS output to the Load 
 
Q3BP:  Connects bypass input source to the load switch  
 
KM:      Battery Circuit Breaker 
 
TR2:      Galvanic Output Isolation Transformer (Delta‐ Zigzag) 
 
REC:     Rectifier Module 
 
INV:     Inverter Module 
 
System Configuration and operation in normal conditions:   
 
The  utility  source  should  be  input  at  Q1  and  should  pass  through  the  fuse,  and  inductor  and  into  the  high 
frequency rectifier, which will convert the AC power into DC power. The rectifier should have PFC and charger 
function and should make use of soft start and microprocessor based control to improve the system immunity 
against surge, improve the stability of the DC bus voltage, reduce the charging current ripple and prolongs the 
battery life. 
 
The output should be isolated from the load by Delta‐Zigzag transformer, static switch, fuse and isolators.  
The bypass source should be input at Q2 and output through the bypass static switch as mentioned in above 
Fig‐1(A).  
 
The main elements of the configurations are:  
- Fully Microprocessor Controlled SCR Based, 6 pulse Rectifier  
- Fully Microprocessor Controlled PWM IGBT Based Inverter 
- Delta / Zig Zag Isolation Transformer at the O/P of the Inverter to provide Galvanic isolation and 
separating the I/P and O/P Neutral. 
- Full Capacity Static Switch at the O/P of the Inverter  
- Full Capacity Static Switch in the Bypass path 
- Full Capacity Manual Bypass Switch 
 
Please note that all the above mentioned elements should form a part of the UPS system and are to be in 
the same sequence as mentioned in the Fig.‐1 (A) along with all the Isolators etc. within a Single Cabinet. 
2.0 Modes of Operation 
 
The UPS shall be able to operate as an on‐line reverse transfer system in the following modes: 
 

PMC: NSL E102


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

2.1. Normal mode 
When the utility is normal, the UPS powers the load through the rectifier and inverter and charges the batteries 
at the same time, as shown in Bold Lines in Fig‐2 (A).     
Bypass

Mains ~ - output
- ~
           
Fig‐2 (A) 
2.2. Emergency/ Battery Mode ‐ When the utility fails, the UPS system shall switch to battery mode without 
interruption and the battery will power the load through the inverter.  
The UPS shall return to normal mode automatically when the utility returns to normal, shown in Bold Lines in 
Fig‐2(B).    
Bypass

Mains ~ - output
- ~
 
                      Fig.‐2(B) 
 
 
2.3.  Recharge  ‐  Upon  restoration  of  AC  input  power,  during  the  ‘Emergency’  mode  of  operation,  the 
rectifier/charger  shall  automatically  restart,  walk‐in,  and  gradually  assume  the  inverter  and  battery  recharge 
loads. 
 
2.4. Bypass ‐ In the event of an inverter overload which last longer than the typical time, an output short circuit 
or a fault on the inverter, the UPS will transfer the load to bypass. There should be two kinds of bypass modes.   
In the first kind, the UPS can be set to return to normal mode automatically when the fault is cleared.  In the 
second kind, the UPS is set to return to normal mode only with a manual transfer. 
When  the  main  UPS  circuit  fails,  the  battery  is  depleted  or  a  severe  fault  occurs,  the  inverter  shall  be  shut 
down  and  the  system  will  remain  in  the  bypass  mode.    The  system  can  return  to  normal  mode  only  with  a 
manual reset after the fault is cleared, shown in Bold Lines in Fig‐2(C).    
Bypass

Mains ~ - output
- ~
 
                                    Fig.‐2(C) 
 
 
 

PMC: NSL E103


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
 
2.5. Maintenance Mode 
 
When the UPS has to undergo routine maintenance, the UPS shall be set to maintenance mode by switching on 
the  maintenance  bypass  circuit  breaker.  The  load  will  be  powered  from  the  maintenance  bypass  supply 
without interruption.  
During maintenance, the circuit breakers Q1, Q2, QF1 and Q5 should be switched off to ensure the safety of 
maintenance personnel.  As shown in Bold Lines in Fig‐2 (D).    
Q3BP

Bypass Q2

Mains Q1 ~ - Q5 Output
- ~
QF1

 
Fig. –2(D) 
 
 
2.6 Basic Functions 
 
Battery Management Function ‐ The UPS has advanced battery management functions including battery fault 
detection and backup time forecast.  
 
Soft Start Function ‐ Complete delay soft start function can reduce the surge to the UPS unit and utility source. 
 
Alarm  and  Protection  Function  ‐  The  UPS  can  generate  audible  and  visual  alarm  through  LCD,  input/output 
contacts and network transmission.  It can help maintenance personnel to locate and clear the faults that are 
sent out in time, accurately and in detail.  
 
Automatic Re‐start when Utility returns – On failure of the input mains supply the UPS goes to battery mode. 
After the batteries are completely discharged the UPS system shuts down. It must automatically restart on the 
resumption of the input supply.  
 
 
1.2 SYSTEM DESCRIPTION 
 
1.2.1 Design Requirements ‐ UPS Module 
 
A. Voltage. 
 
Input/Out voltage specifications of the UPS shall be: 
 

PMC: NSL E104


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

Rectifier Input: (380) (400) (415) volts, three‐phase 4‐wire‐plus‐ground. 
Bypass Input (if used): (380) (400) (415) volts, three‐phase, 4‐wire‐plus‐ground. 
Output: (380) (400) (415) volts, three phase, 4‐wire‐plus‐ground. 
 
B. OUTPUT LOAD CAPACITY 
 
Specified output load capacity of the UPS shall be rated kVA at 0.8 lagging power factor. 
 
 
 
 
 
1.2.3 PERFORMANCE REQUIREMENTS 
 
1. AC Input to UPS 
 
A. Voltage Configuration: three‐phase, 4‐wire plus ground. 
B. Voltage: (380) (400) (415) V 
C. Voltage Range: +/‐15% of nominal. 
D. Frequency: Field selectable 50Hz or 60 Hz 
E. Frequency: Nominal frequency + 5% 
F. Voltage distortion The harmonic content introduced into the mains supply shall comply with IEC 61000‐3‐4 / 
AS2279 Part 2 for harmonic voltage distortion at the Point of Common Coupling (PCC) with other loads. Where 
higher  impedance  Mains  or  Generator  supplies  are  present,  the  manufacturer  shall  offer  reduced  current 
distortion options to ensure IEC 61000‐3‐4 / AS2279 Part 2 requirements are complied to when interfaced with 
the proposed UPS system.  
 
2. AC Output, UPS Inverter 
 
A. To isolate the input disturbances from the output side a Galvanic Isolation Transformer is mandatory 
to be included in the design at the output of the Inverter. 
 
B. Voltage: (380) (400) (415) V 
 
C. Voltage Configuration: three‐phase, 4‐wire plus ground. 
 
C. Voltage Regulation: ± 1% steady state. 
 
D. Frequency: Field selectable 50 Hz or 60Hz, (+ 0.5 or 2Hz adjustable). 
 
E. Frequency Slew Rate: 0.1 to 1Hz /sec adjustable 
 
 
F. Phase Displacement: ± 1 degree for balanced load. 
 
                  ± 1 degree for 100% unbalanced load. 
 

PMC: NSL E105


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

G. Voltage Distortion: 1% Typical 2% maximum for liner loads 
 
                  <5% total harmonic distortion (THD) for 100% non‐linear loads with 3:1 crest factor. 
 
H. Output Power Rating: Rated kVA at 0.8 lagging power factor. 
 
I. Overload Capability: 110% for 60 minutes 
                     125% for 10 minutes 
                     150% for 1 minute 
                     200% single phase for 30 secs 
 
J. VOLTAGE TRANSIENT RESPONSE: ±5% 
 
K. Transient Recovery Time: to within ±1% of output voltage within 20 milli secs 
 
L. Voltage Unbalance: Balanced load 1% 
 
                     100% unbalanced load 2% 
 
M. Inverter Short Circuit Current Limit: 
                      150% full load current for 5 seconds 
                      220% single phase for 5 seconds 
 
 
1.3 ENVIRONMENTAL CONDITION 
 
1.3.1  The  UPS  shall  be  able  to  withstand  the  following  environmental  conditions  without  damage  or 
degradation of operating characteristics: 
 
A. Operating Ambient temperature 
UPS Module:   0ºC to 40ºC 
Battery: 25 ± 5ºC 
 
B. Storage/Transport Ambient Temperature 
‐25ºC to 70ºC 
 
C. Relative Humidity: <90% at 20ºC 
 
D. Altitude Operating: to 1000 meters above mean Sea Level de‐rated for higher altitude applications. 1% per 
100m between 1000 & 2000 
 
E. Audible Noise 
Noise generated by the UPS under any condition or normal operation shall not exceed 60 dbA measured 1.5 
meters from surface of the UPS. 
 
1.3.2 Design Requirements ‐ Matching Battery 
 

PMC: NSL E106


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

A. Battery Cells: Sealed, lead‐acid, valve‐regulated. 
 
B. Reserve Time: 15 minutes at full load, 0.8 power factor, with ambient temperature between 20 and 30ºC. 
 
1.4 UPS Delivery Submittals 
 
Submittal upon UPS delivery shall include: 
 
One instruction manual:  Manual shall include a functional description of the equipment with block diagrams, 
safety  precautions,  instructions,  step‐by‐step  operating  procedures  and  routine  maintenance  guidelines, 
including illustrations. 
 
1.5 Quality Assurance 
 
1.5.1 Manufacturer Qualifications 
A  minimum  of  five  year’s  experience  in  the  design,  manufacture,  and  testing  of  solid‐state  UPS  systems  is 
required. Standards ISO90001, CE certified to level A of EN55022. 
 
1.5.2 Factory Acceptance Test 
Before  shipment,  the  Contractor  shall  fully  and  completely  test  the  system  to  assure  compliance  with  the 
specification.  He  will  give  a  factory  inspection  call  for  acceptance  of  the  ordered  material  by  NBCC  at  his 
manufacturer’s works. The manufacturer shall fully coordinate with NBCC as required by the inspecting team. 
All  expenditure  towards  conducting  any  test,  to  and  fro  airfare,  lodging,  boarding  shall  be  borne  by  the 
contractor within at his quoted rates.  
 
2.0 PRODUCT 
 
2.1 Fabrication 
 
2.1.1 Materials 
All materials of the UPS shall be new, of current manufacture, high grade and free from all defects and shall not 
have been in prior service except as required during factory testing. 
 
2.1.2 Construction and Mounting 
The  UPS  unit,  comprised  of  input  isolator,  rectifier/charger,  inverter,  static  transfer  switch,  maintenance 
bypass  switch,  and  static  bypass  input  switch  should  be  housed  in  a  freestanding  steel  enclosure  with  key‐
lockable doors. Front access only shall be required for expedient servicing, adjustments, and installation. The 
enclosure will be built to comply with IP20 when the doors are open. The UPS cabinet shall be cleaned, primed, 
and  painted  with  the  manufacturer’s  standard  color.  The  UPS  shall  be  constructed  of  replaceable 
subassemblies.  Printed  circuit  assemblies  shall  be  plug‐in.  Like  assemblies  and  like  components  shall  be 
interchangeable. 
 
2.1.3 Cooling 
Cooling of the UPS shall be forced‐air. Low velocity fans shall be used to minimize audible noise output. Fan 
power shall be provided by the UPS output. Temperature will be monitored by thermal sensors. 
 
2.2 Components 

PMC: NSL E107


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
2.2.1 Rectifier/Charger 
 
A. General 
The term rectifier/charger shall denote the solid‐state equipment and controls necessary to convert incoming 
AC power to regulated DC power for input to the inverter and for battery charging. The rectifier/charger shall 
be  12  Pulse  three  phase‐controlled  thyristor  bridge  type  with  constant  voltage/current  limiting  control 
circuitry.  Input Current harmonic has to be < 10 %  
 
B. Input Current Walk‐In 
The rectifier/charger shall contain a timed walk‐in circuit that causes the unit to gradually assume the load over 
a 10‐second time interval after input voltage is applied. 
 
C. Fuse Failure Protection 
Power  semiconductors  in  the  rectifier/charger  shall  be  fused  with  fast‐acting  fuses,  so  that  loss  of  any  one‐
power semiconductor shall not cause cascading failures. 
 
D. DC Filter 
The  rectifier/charger  shall  have  an  output  filter  to  minimize  ripple  voltage  into  the  battery.  Under  no 
conditions shall ripple voltage into the battery exceed 1% RMS. The filter shall be adequate to insure that the 
DC output of the rectifier/charger will meet the input requirements of the inverter. The inverter shall be able 
to operate from the rectifier/charger with the battery disconnected. 
 
E. Battery Recharge 
In addition to supplying power for the inverter load, the rectifier/charger shall be capable of producing battery‐
charging current to recharge the battery. After the battery is recharged the rectifier/charger shall maintain the 
battery  at  full  charge  until  the  next  emergency  operation.  The  charging  shall  be  an  automatic  cycle  per  DIN 
41772 characteristic I ‐U (boost to floating charge switching, with current measuring criteria and control during 
recharge).  Both  float  and  recharge  voltages  shall  be  adjustable.  The  charge  voltage  can  also  be  manually 
controlled. The use of the inverter is inhibited during manual charging. 
 
2.2.2 Inverter 
 
A. General 
The  term  inverter  shall  denote  the  solid‐state  equipment  and  controls  to  convert  DC  power  from  the 
rectifier/charger  or  battery  to  regulated  AC  power  for  supporting  the  critical  load.  The  inverter  shall  be  an 
Insulated Gate Bipolar Transistor, phase‐controlled, pulse width modulated (PWM) design capable of proving 
the specified AC output. 
 
B. Overload Capability 
The inverter shall be capable of supplying current and voltage for overloads exceeding 100% and up to 150% of 
full load current. A status indicator and audible alarm shall indicate overload operation. The UPS shall transfer 
the load to bypass when overload capacity is exceeded. 
 
C. Fault Clearing and Current Limit 
Without bypass supply available to the inverter shall be capable of supplying an overload current of 200% of its 
full‐load  rating  in  excess  of  Thirty  Seconds.  For  greater  currents  or  longer  time  duration,  the  inverter  shall 

PMC: NSL E108


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

have  electronic  greater  currents  or  longer  time  duration,  the  inverter  shall  have  electronic  current‐limiting 
protection to prevent damage to components. The inverter shall be self‐protecting against any magnitude of 
connected output overload (Vce Trip). Inverter control logic shall sense and disconnect the inverter from the 
critical AC load without the requirement to clear protective fuses. 
 
D. Output Frequency 
The output frequency of the inverter shall be controlled by an oscillator. The oscillator shall hold the inverter 
output frequency to + .01% for steady state and transient conditions. 
 
E. Isolation Transformer: To isolate the input disturbances from the output side a double wound delta‐zigzag 
transformer  to  galvanically  isolate  the  input  from  output  is  mandatory  to  be  included  in  the  design  at  the 
output of the inverter as shown the Figure 3 below. The isolation transformer will be connected as shown in 
the Fig 1(a). The combination of the inverter and Output isolation transformer shall form a separately derived 
source wherein the Input neutral and the three Phases are completely isolated from the output neutral and the 
three phases.  
 
    Dc Bus +500 V dc 
 
                       
                      R 
Inverter Section
             
                      Y 
 
                      B 
 
                      N 
    DC Bus –500V dc 
 
               Isolation Transformer 
               (Delta Zigzag Type)       
       
            Fig. ‐ 3 
 
 
 
2.2.3 Display and Controls 
 
A. Monitoring and Control 
The UPS shall be provided with a microprocessor based unit status display and controls section designed for 
convenient  and  reliable  user  operation.  A  system  controls  section  designed  for  convenient  and  reliable  user 
operation.  A  system  power  flow  diagram,  a  percentage  load  and  battery  time  remaining  display  shall  be 
provided  as  part  of  the  monitoring  and  controls  sections,  which  depicts  a  single‐line  diagram  of  the  UPS. 
Illuminated visual indicators shall be of the long‐life light‐emitting diode (LED) type. All of the operator controls 
and monitors shall be located on the front of the UPS cabinet. The monitoring functions such as metering, and 
alarms shall be displayed on an alphanumeric LCD display. Additional features of the monitoring system shall 
include: 
Menu‐driven display with test format selectable in five (5) languages (English, 

PMC: NSL E109


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

German, French, Spanish, or Italian). 
 
B. Metering 
 
The following parameters shall be displayed: 
Battery voltage 
Battery charge/discharge current 
Input voltage and frequency 
Output AC voltage line‐to‐line and line to neutral and % load used of nominal capacity for each phase. 
Output AC current for each phase and neutral 
Output frequency 
Active Power (kW) Apparent Power (kVA) 
Temperature ‐ Ambient, battery, inverter assembly module 
 
C. Warning and Alarm Messages 
Normal Operation Input breaker open 
Output breaker open Rect. breaker open 
Battery breaker open On Manual bypass 
Bypass absent Bypass over limits 
Bypass under limits Bypass freq. over limit 
Bypass Phase Rotation Bypass SCR fail 
Bypass inhibit Local Bypass inhibit remote 
Load on bypass on bypass due to over temperature 
Rectifier off Local Rect. off remotely 
Rectifier Block Rectifier overload 
Rectifier over temp Rectifier Fuse fail 
Inverter off local.  Inverter off remotely 
Inverter block Inverter overload 
Inverter over temperature. Inverter out of sync 
Inverter over voltage Inverter under voltage 
Inverter fuse fail D.C Volts High 
D.C Volts low Inverter no voltage 
Inverter Peak Volts low Battery under test 
Battery test fail Discharge battery 
Battery E.O.D. Boost Charge 
DC Bus over volt Battery Low 
Battery Fuse Fail Bat. Fast over volt 
Bypass overuse Cut‐off overload 
Cut‐off overtemp Cut‐off emergency stop 
Overload Cut‐off max overload 
Software Warnings 
Bad EPROM program Err. LRC param. Pag 1 
Err. LRC Param Pag 2 Err. LRC Param Pag 3 
Err. LRC Alarm Hist Err. LRC Even Hist 
Back‐up battery low Error LRC table 
Error LRC Panel Modem Wrong Config 
Modem no response Modem false command 

PMC: NSL E110


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

Modem time‐out trasm Can bus no response 
Autonomy XXXX min 
 
 
 
 
 
 
D. Controls 
Four pushbuttons shall be located on the operator control panel. 
Enter 
Escape 
Up 
Down 
The push buttons shall permit the operator either to select options from a menu for display on the LCD winder 
or to change the value of some parameters. One push‐button and alarm silence switch. 
 
E. Power Status Diagram 
A mimic panel shall be provided to depict a single line diagram of the UPS. 
Indicating lights shall be integrated within the single line diagram to illustrate the status of the UPS. The three 
LEDs shall indicate the following status. 
Bypass voltage OK 
Load on bypass 
Load on inverter 
Included  in  the  power  status  diagram  shall  be  an  LED  bar  graph  indicating  %  load  with  amber  overload 
indication. Also an LED bar graph indicating % battery time remaining shall be included. 
Ethernet Connectivity Interface Port 
An Ethernet Connectivity based interface port shall be provided for remote display of UPS status information 
on a computer terminal (by others). 
 
2.2.4 Static Transfer Switch 
 
A. General 
Static transfers switch and bypass circuit shall be provided as an integral part of the UPS. The static switch shall 
be  naturally  commutated  high‐speed  static  (SCR‐type) device rated to conduct full load current continuously 
and shall have a contactor in the output of the inverter circuit to enable the critical load to be connected to the 
inverter  output  or  bypass  power  source.  the  static  transfer  switch  control  logic  shall  contain  and  automatic 
transfer control circuit that senses the status of the inverter logic signals, and operating and alarm conditions. 
This control circuit shall provide an uninterrupted transfer of the load to an alternate bypass source, without 
exceeding the transient limits specified herein, when an overload or malfunction occurs within the UPS, or for 
bypassing the UPS for maintenance. 
 
B. Uninterrupted Transfer 
 
The transfer control logic shall automatically turn on the static transfer switch, transferring the critical AC load 
to the bypass source, after the transfer logic senses any of the following conditions: 
Inverter overload capacity exceeded 

PMC: NSL E111


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

Critical AC load over voltage or under‐voltage 
UPS fault condition. 
The transfer control logic shall inhibit and automatic transfer of the critical load to the bypass source if any of 
the following conditions are present: 
Inverter/bypass voltage difference exceeding pre‐set limits 
Bypass frequency out of limits  
Bypass out‐of‐synchronization range with inverter output. 
 
C. Uninterrupted Retransfer 
Retransfer of the critical AC load from the bypass source to the invert output shall be automatically initiated 
unless inhibited by manual control. The transfer control logic shall inhibit an automatic retransfer of the critical 
load to the inverter if one of the following conditions exists: 
Bypass out of synchronization range with inverter output 
Inverter/bypass voltage difference exceeding pre‐set limits 
Overload condition exists in excess of inverter full load rating 
UPS fault condition present. 
 
 
2.2.5 Maintenance Bypass Isolator 
 
A. General 
A  manually  operated  maintenance  bypass  isolator  shall  be  incorporated  into  the  UPS  cabinet  to  directly 
connect  the  critical  load  to  the  input  AC  power  source,  bypassing  the  rectifier/charger,  inverter,  and  static 
transfer switch. 
 
B. Maintenance Capability 
With  the  critical  load  powered  from  the  maintenance  bypass  circuit,  it  shall  be  possible  to  check  out  the 
operation of the rectifier/charger, invert, battery, and static transfer switch. 
 
C. Wall Mounted Battery Circuit Breaker (BCB) 
A  battery  circuit  breaker  shall  be  provided  to  isolate  the  battery  from  the  UPS.  This  breaker  together  with 
battery  circuit  breaker  controller  board  shall  be  in  a  separate  wall  mounted  enclosure.  The  battery  breaker 
provides a manual disconnecting means, short circuit protection, and over‐current protection for the battery 
system. When opened, there shall be no battery voltage in the UPS enclosure. 
 
D. Split Bypass standard feature 
UPS  shall  have  both  a  rectifier  input  and  bypass  input.  Two  separate  input  sources  must  be  provided.  An 
internal bypass circuit breaker shall be provided for connection to the bypass source. 
 
3.0 FIELD ENGINEERING SUPPORT 
The  UPS  manufacturer  shall  directly  employ  a  national  field  service  network  staffed  by  factory  trained  field 
service engineers to provide start up, maintenance and repair of the UPS equipment. 
 
 

PMC: NSL E112


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

   UPS TOPOLOGY  True on‐line double conversion PWM IGBT 
based. 
A  INPUT   
1  Input voltage   415V, 3 phase, 4 wires 
2  Input voltage tolerance  +10 % , ‐15% 
3  Input frequency  50 Hz 
4  Input frequency tolerance  +/‐ 5 % 
5  Input current limit  115% (Adjustable between 100 ‐ 125%) 
6  Power walk ‐ in period  30 seconds 
7  Input circuit  IGBT rectifier. Input current harmonics 
<10%. 
8  Inbuilt Input & Bypass Isolator with SFU  Required, Isolator with fuse unit.  
 

PMC: NSL E113


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

B  OUTPUT   
1   Module full load rating KVA/ KW   40 kVA/ 32 kW 
2   Rated voltage   415 V 3 PH, N 
3   Rated current   Vendor to specify 
4   Phase Voltage  asymmetry (For Three Phase   
output UPS only )   
a] Balance load   1% 
b] 100% unbalanced load   2% 
5   Voltage Phase shift ( In case of three phase   
Output UPS )   
                    ‐ with balanced load  120  +/‐ 1 deg 
                    ‐ With Unbalanced laod  120  +/‐ 1 deg 
6   Output voltage adjustment range  +/‐ 5% 
7   Phase displacement ( In case of three phase   
Output UPS )   
   
a] Balance load  120 deg. +/‐ 1 deg 
b] 100% unbalanced load  120 deg. +/‐ 1 deg 
8   Output power factor range  0.7 to unity 
9   Internal oscillator stability  +/‐ 0.2 %  
10   Mains synchronization tracking  +/‐ 1 Hz (settable to +/‐2) 
11   Max. rate of change of frequency  1 Hz. Per second 
12   Output voltage harmonics   
a]  Linear load  < 1% 
b]  Non‐linear load ( Crest factor of 3:1)  < 5 % 
13   Crest Factor  3 : 1 
14   Overload rating  110% for 60 minutes 
125% for 10 minutes 
150% for 60 seconds 
15   Overload trip  10 min at 125% reducing to 60 seconds at 
150%  
16   Inverter Efficiency  > 92 % 
17   Current limit short  Set at 150% of the output power 
18   Transient Response   
a] 100% load change  < +/‐ 5% 
b) Manual transfer of load from UPS to   0 msecs. when in sync 
     bypass and vice‐versa   
C] Automatic transfer of load form UPS   0 msecs. in sync 
     to bypass 
19   Transient recovery time  Recovery to +/‐ 3 % in  < 4  msec.  
20   Manual Bypass Isolator  One with each UPS Module  

PMC: NSL E114


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

TECHNICAL SPECIFICATIONS OF 2X 40 KVA UPS SYSTEM 
 
 
 
 
C  DC CHARACTERISTICS   
1  Nominal DC bus voltage  408 V 
2  Battery isolation  Manually closed circuit breaker with under 
voltage release and over current trip 
3  Battery fully discharge voltage  326V 
4  Allowable voltage drop in battery cables  3 volts at end of discharge voltage. 
5  Battery float voltage   459 V 
6  Battery end voltage  340 V 
7  DC Bus voltage ripple  < 1 RMS 
8  Battery recharge current limit  Amps,  Vendor to specify 
9  No. of cells  Vendor to specify 
 
 
 
 
D  CONTROLS 
1   Charger input Isolator 
2   Battery circuit breaker (mounted separately in its own enclosure) 
3   Inverter output Isolator 
4   Bypass line Isolator 
5   Maintenance Bypass Isolator 
6   Alarm acknowledge / Reset  button 
7   Inverter On‐Off Pushbutton for Manually switching of the Inverter 
8   Emergency off push button 
E  MEASURING INSTRUMENTS 
1  LCD panel for Measuring Input Voltage, Output voltages, Output currents and Frequency, 
Battery Voltage and Charging / Discharging current.  
2  LCD panel should display status of the Battery capacity and  backup Time in minutes.  
   
E  PROTECTIONS 
1   RC surge suppressor. 
2   Sustained under voltage on input side 
3   Phase loss on input side. 
4   Negative sequence on input side 
5   Semiconductor fuses in the lines for thyristor 
6   Snubber circuit for device dv/ dt protection 
7   Charger input current limit 
8   HRC fuses for filter capacitors 
9   Battery current limit 
10   DC over voltage 

PMC: NSL E115


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

11   Low battery 
12   Semiconductor fuses at inverter output 
13   Overload 
14   Over temperature for the inverter 
15   HRC fuses in the control circuit 
   
   
 
F  INDICATIONS (ALARMS) 
1   Inverter Failure 
2   Overload (if load exceeds 100%) 
3   Overload shutdown 
4   Emergency shutdown  
5   Equipment over temperature 
6   Maintenance Bypass ON  
7   DC over voltage 
8   Low battery 
9   Battery circuit breaker open 
10   Battery on load 
11   Mains failure 
12   Rectifier Failed or Off 
13   Inverter Unsynchronized 
14   Load on bypass 
15   Output voltage error 
 
 
 
 
G. DC link characteristic for total 15 Min.      
battery run on 2 x 40 KVA KVA UPS System 
No. of  SMF lead acid batteries  Vendor to Specify rating and no. 
AH rating of one 15 Mins. Bank   Vendor to Specify rating and no.  
Model / Make  G & Y/ Panasonic/ Rocket 
Float voltage  459 V 
Final discharge voltage  340 V 
Voltage tolerance  +/‐ 1 % 
DC ripple  < 1 % 
Charging current limit  10 % 
Battery Isolation  With U/V release type Battery Circuit Breaker 
 
 
 
 
 
 

PMC: NSL E116


Electrical: UPS Pharmacy Council of India, 3rd Floor, NBCC
Center, Okhla, New Delhi

 
Mechanical Dimensions: 
 
Weight of UPS – Kg  Vendor to specify 
Dimension of UPS ( L x D x H ) in mm  Vendor to specify 
Ventilation   Forced air cooled with internal fans  
Protection Level :    
 *  with enclosure  closed    IP 20 
 *  with front doors open      IP 20  
 
Environmental: 
 
Operating   temperature   0 – 40 deg.C. 
Relative  humidity    < 90 % (20 deg. C.) 
Altitude    1000 m 
Storage temp.   from ‐25   to + 70 deg. C. 
 

PMC: NSL E117


Electrical: CCTV,& Access Control Pharmacy Council of India, 3rd Floor,   NBCC                  
                                   Center, Okhla, New Delhi 

TECHNICAL SPECIFICATIONS FOR CCTV & ACCESS CONTROL SYSTEM 
 
GENERAL SITE CONDITIONS: 
Max. Ambient Temperature : 45 degree C and 50 degree C ( designed)  
Min. Ambient Temperature : 4 degree C  
Max. R H : 97%  
Min. R H : 30%  
Altitude : 1000 meters  
 
INSPECTION OF SITE:  
The bidder should inspect and examine the site and its surrounding and shall satisfy as to the nature of the 
ground and sub soil, the quantities and nature of work, materials necessary for completion of the work 
and their availability, means of access to site and in general to obtain all necessary information as to risks, 
contingencies and other circumstances which may influence or affect his offer. No extra claim consequent 
on any misunderstanding or otherwise shall be allowed.  
 
DESIGN CONCEPT & SCOPE OF WORK : 
 
1) IP CCTV SURVEILLANCE SYSTEM  
 
(i) DESIGN CONCEPT:  
• The entire IP surveillance system is designed to control and monitor the facility. 
• There are two types of cameras shall be installed to monitor the movement of the people as follows:  
‐ IP fixed dome camera indoor type 
 ‐ IP fixed dome camera indoor type with Day & Night Capability. 
• IP fixed dome camera shall be installed at the entrances and connecting corridors of the main entrance, 
hub room, server room, lobbies service areas, and fire exits 
• All cameras shall be true IP camera.  
•All outdoor cameras shall be in vandalproof housing.  
•All the Cameras should be UL, CE and FCC Certified. 
•All outdoor items for cameras like JBs, power supply, media convertor etc. shall be in water poof  
and dust proof housing.  
• Purchaser’s LAN network being laid by third party would be utilized to extend the IP CCTV connectivity to 
central server  
•All CCTV cameras shall have connectivity to PoE port of purchaser’s networking switches on LAN.  
• UPS Power supply for each camera.  
• Tentative locations of cameras are indicated in the IP CCTV layout drawing enclosed with this tender  
•All the cameras and Software should be of the same make. Combination of different make for software 
and cameras will not be considered. 
 
(ii) SCOPE OF WORK:  
 
•Supply, installation, testing and commissioning high quality fast‐acting IP CCTV surveillance system long 
with power supply, power distribution and required accessories in the facility as indicated in BOQ. 
• The entire system shall be as per BOQ, drawings and technical specifications enclosed with tender 
documents. 
• The price coated by the vendor should include all the expenses incurred in commissioning of all  
cameras with power supply, accessories and other devices complete with software. 

PMC: NSL E 118  


Electrical: CCTV,& Access Control Pharmacy Council of India, 3rd Floor,   NBCC                  
                                   Center, Okhla, New Delhi 

• The CCTV surveillance system should consist of IP Fixed dome cameras (indoor type), IP fixed box type 
cameras, software, server, power supply and cables. 
• Video management software shall offer both video stream management and video stream  
Storage management. Recording frame rate and resolution in respect of individual channel shall  
be programmable.  
• The system is presently designed for 35 cameras whereas not limited to the same and scalable  
upto unlimited cameras if required in the future. 
• Provide supervisory specialists and technicians at the job to assist in all phases of system installation, 
start up and commissioning. 
• Cat 6cable/fiber cable connectivity with all required hardware upto purchaser’s networking switches of 
LAN, locations of networking switches in  
• 230 volts AC Power supply distribution from UPS to each location of cameras along with DBs ,JBs, cabling 
work etc. with required accessories. 
• Power supply unit as required for cameras. 
• Integrated testing and commissioning of CCTV system on LAN being provided by the third party  
in faility. 
• Training & handing over of all materials, equipment and appliances. 
• Any other items/accessories required for installation, testing and commissioning of CCTV system.  
• No extra cost shall be paid for miscellaneous items if required to complete the work as per the  
design concept.  
• The contractor shall submit the technical specifications and GA drawing for approval before commencing 
the work at site. 

Detailed Technical Specifications: 

1). Fixed Dome Type IP Colour Cameras: 
 
   Description 

1  IP Fixed Dome Day/Night Very High Resolution HD1080P (2.1MP) WDR Indoor Camera 

   1/2.8" or bigger Progressive CMOS Sensor 
   Wide dynamic range support 
   Minimum Illumination : Day 0.5 lux / Night 0.05 lux 
   3mm‐9mm varifocal, Auto Iris lens 
   Adjustable Horizontal coverage between 40° to 110° 
   Manual pan/tilt adjustment up to 350°/+‐90° 
   Automatic Gain Control, BLC, White balance: On/Off 
   3D Noise reduction: ON/Off 
   Tamper Detection: On/Off 
   Compression : Dual H.264 streams 
   Resolution & FPS Maximum Performance: Stream 1: 1920 x 1080 @ 25FPS and Stream 2: 
720 x 576 @ 25FPS on two streams respectively at the same time 
   Bandwidth : 64Kbps to 8Mbps 
   Built‐in Multi‐zone motion detection 
   Unicast, Multicast, RTP, TCP, UDP, HTTP, IGMP, ICMP, DHCP, DNS, ONVIF 
   10/100 Base‐T Auto sensing, Half/Full Duplex (RJ45) 

PMC: NSL E 119  


Electrical: CCTV,& Access Control Pharmacy Council of India, 3rd Floor,   NBCC                  
                                   Center, Okhla, New Delhi 

   S/N Ratio: >50db 
   Built in  SD card slot to support up to 32GB storage for local recording with configurable 
support for Continuous, Motion triggered, Network failure triggered, Input triggered. 
   Power : 802.3af class 3 PoE and 12VDC/24VAC auto sensing 
   Vandal resistant clear bubble surface mount enclosure. 
   Operating Temp: 0° C to 50° C 
   Humidity : 90% (Non‐condensing) 
   UL,CE and FCC certified 
   Warranty: Minimum 4 year Manufacturer warranty 
 
 
2). Fixed Box Type IP Color Cameras: 
 
   Description 

  IP Fixed Box Day/Night Very High Resolution HD1080P 1920x1080, WDR Indoor Camera 

   1/2.8" or bigger Progressive CMOS Sensor 
   Wide dynamic range support 
   Minimum Illumination : Day 0.5 lux / Night 0.05 lux 
   3.1‐8mm  varifocal, Auto Iris, Full HD, D/N lens 
   IR sensitivity between 680 to 1100nm IR cut filter 
   Manual pan/tilt adjustment up to 350°/+‐90° 
   Automatic Gain Control, BLC, White balance: On/Off 
   3D Noise reduction: ON/Off 
   Tamper Detection: On/Off 
   Compression : Dual H.264 streams 
   Resolution & FPS Maximum Performance: Stream 1: 1920 x 1080 @ 25FPS and Stream 2: 
720 x 576 @ 25FPS on two streams respectively at the same time 
   Bandwidth : 64Kbps to 8Mbps 
   Built‐in Multi‐zone motion detection 
   Unicast, Multicast, RTP, TCP, UDP, HTTP, IGMP, ICMP, DHCP, DNS, ONVIF 
   10/100 Base‐T Auto sensing, Half/Full Duplex (RJ45) 
   S/N Ratio: >50db 
   Built in  SD card slot to support up to 32GB storage for local recording with configurable 
support for Continuous, Motion triggered, Network failure triggered, Input triggered. 
   Audio IN and Audio out for two way audio communication using suitable microphones 
and speakers 
   At least one potential free Alarm IN and one Alarm out
   Power : 802.3af class 3 PoE and 12VDC/24VAC auto sensing 
   Vandal resistant enclosure with IP66 rated, built in Heater and Blower, Sun shield. 
   Operating Temp: 0° C to 50° C 
   Humidity : 90% (Non‐condensing)
   UL,CE and FCC certified 
   Warranty: Minimum 4 year Manufacturer warranty 

PMC: NSL E 120  


Electrical: CCTV,& Access Control Pharmacy Council of India, 3rd Floor,   NBCC                  
                                   Center, Okhla, New Delhi 

3). Network Video Management Software  

A NVMS SERVER SOFTWARE  
1 The  NVMS  software  shall  consist  of  an  MS‐SQL  2005  or  better  based  Main  Directory 
Database, Failover directory, Recording Server licenses, Failover recording, Digital Virtual 
Matrix, Incident Reports and  Alarm Management. All the related software licenses should 
be the part of the offered system. 
2 Vendor should consider additional server for maintaining system administration database 
if  required  by  their  offered  system  configuration  apart  from  two  (minimum)  recording 
servers. 
3 The NVMS system should be accessible from at least 25 computers from the network for 
system administration and video monitoring with minimum 5 simultaneous users. System 
administration  and  monitoring  can  be  distributed  depending  on  the  sub  division  of  the 
surveillance areas/zones. Even though system should allow to create unlimited user ID’s in 
the system. 
4 The NVMS shall support up to 70 camera connections in single directory.  
5 The NVMS Archive Server, for video, shall be capable to support and manage 65 cameras 
@ 1920x1080 @ 25FPS or 150 camera @ 1280x720 @ 25FPS or 230 cameras @ 704x576 
@  25FPS.  But  considering  the  future  intention  to  zonalise  the  recording  not  more  than 
120 cameras be loaded on any server during initial design of the system. 
6 The  NVMS  shall  support  web  based  clients  connecting  to  the  NVMS  system  via  the 
Internet. 
7 The NVMS shall be based on a true open architecture that allow for use of non‐proprietary 
PC  and  storage  hardware  that  shall  not  limit  the  storage  capacity  and  shall  allow  for 
gradual upgrades of recording capacity 
8 The  NVMS  should  allow  to  configure  automatic  scheduled  backup  of  videos  from  user 
selected  cameras  to  specified  network  drive.  It  should  also  allow  to  configure  specific 
timings of the day whose video need to be backed up. 
9 The NVMS shall provide module to allow access of system through iPAD, iPHONE, Android 
phones. At least one license for the same shall be supplied. 
10 The  NVMS  shall  provide  the  facility  so  as  any  Android  OS  smart  phone  can  capture  the 
video using its in‐built camera and stream it to the NVMS server through 3G, 4G, LTE or 
wi‐fi  network.  NVMS  shll  have  the  capability  to  automatically  popup  this  video  and  also 
indicate the GPS location of the smart phone. At least one license for this facility shall be 
supplied. 
11 The  NVMS  shall  provide  alarm  management  module  without  the  need  of  any  additional 
license. 
a) The alarm management shall be able to set any monitor or groups of monitors to 
automatically display cameras in response to alarm inputs.  
b) The  alarm  management  shall  be  able  to  reset  automatically  or  manually  alarmed 
video. 
c) The alarm management shall allow for multiple modes of alarm handling capability, 
these modes to be programmed within the same system. 
 
 
B NVMS CLIENT  
1 The  NVMS  client  shall  perform  the  following  applications  simultaneously  without 
interfering with any of the Archive Server operations (Recording, Alarms, etc.): 
a) Live display of cameras 
b) Play Live audio 
c) Broadcast audio to remote locations 

PMC: NSL E 121  


Electrical: CCTV,& Access Control Pharmacy Council of India, 3rd Floor,   NBCC                  
                                   Center, Okhla, New Delhi 

d) Live display of camera sequences 
e) Live display of panoramic camera views 
f) Control of PTZ cameras 
g) Playback of archived video and audio 
h) Playback of panoramic camera clips 
i) Retrieval of archived video and audio 
j) Instant Replay of live video and audio 
k) Instant Replay of panoramic camera clips 
l) Use of graphical controls (maps) 
m) Configuration of system settings 
2 The NVMS client applications shall support any form of IP network connectivity, including: 
LAN, WAN, VPN, Internet, and Wireless  
3 The  NVMS  client  applications  shall  support  IP  Multicast  (UDP)  and  Unicast  (UDP)  video 
streaming. 
4 NVMS Client MONITOR Application 
a) The Client Monitor application shall allow for live monitoring of video and audio.   
i The  Monitor  shall  enable  view  of  up  to  25  video  tiles  simultaneously  on  a 
single monitor. 
ii The IP Based NVMS Shall provide more than 15 tile layouts on each of the VGA 
monitors independently including below formats 
1) Full  screen,  Quad,  3x3,  4x4,  5x5,  1  +  9  (One  large  and  9  small  view), 
1+11 (One large and 11 small view), 1+12 (One large center tile and  12 
small view), 1+15 (One large and 15 small view), And more 
b) The  NVMS  Monitor  application  shall  allow  operators  to  view  an  instant  replay  of 
any camera or audio input (microphone).  
i The operator shall be able to define the amount of time he wishes to go back 
from a predefine list or through a custom setup period.  
ii The operator shall be able to control the playback with play, pause, forward, 
and speed buttons. 
c) The NVMS Monitor application shall allow operators to add bookmarks to recorded 
clips of video or audio 
d) The  NVMS  Monitor  application  shall  display  all  camera  sequences  created  in  the 
system. 
e) The NVMS Monitor application shall allow for unlimited cameras sequences, which 
can  be  run  independently  of  each  other  on  either  digital  monitor  tiles  or  analog 
CCTV monitors. 
f) The  NVMS  Monitor  application  shall  allow  operators  to  control  (Pause/Play,  skip 
forwards,  skip  backwards)  Camera  Sequences,  without  affecting  other  operators’ 
ability to view and control the same sequence. 
5 The  NVMS  should  provide  the  application  which  should  be  integrated  to  the  offered 
NVMS  and  provide  the  below  mentioned  Incident  Reporting  and  backup  mechanism. 
Offered prices should include the price of this application. 
a) This application should provide the facility to create the incident reports for specific 
incidents. 
b) It should be possible to access recorded video within the NVMS system for playback 
and export from this application. 
c) It should also allow the operator to write the text, attach the snapshots, video clip, 
audio  clip  or  any  other  type  of  attachment  which  can  be  used  in  connection  with 
this incident and form the entire incident report. 
d) Entire report should be archived on specific portion on the storage and should be 
accessible from the web browser. 
e) It  should  create  the  library  of  all  the  reports  and  options  should  be  available  to 
search the required report by time frame, subject, report number etc. 

PMC: NSL E 122  


Electrical: CCTV,& Access Control Pharmacy Council of India, 3rd Floor,   NBCC                  
                                   Center, Okhla, New Delhi 

f) It should be possible to send these reports by email or archived on offline media. 
6 Software shall have the facility to monitor the desktop of any networked computer in 
camera tiles. We intend to use this facility to create the central monitoring display of all 
the systems (BMS, FAS, ACS, PIDS etc.) on same monitor simultaneously. 
 
C ALARM MANAGEMENT  
1 The IP based NVMS shall provide alarm management module 
2 The IP based NVMS shall notify a user on any alarm set in the system 
3 The NVMS user shall be able to support multiple alarms 
4 The NVMS system administrator shall be able to set for each user the maximum alarms to 
be viewed at one time 
5 It should be possible to populate the alarm on the maps indicating there actual location 
and current status. 
6 It should be possible to drag the alarm related video on tile directly from the map. 
7 It should also be configurable to popup the procedural URL/standard operating procedure 
for alarm handling specific to the active alarm. 
8 Alarms  should  be  prioritized  and  displayed  in  different  color  for  easy  understanding  of 
operators. 
9 The NVMS user shall be able to forward alarms to other users 
10 The NVMS alarm database shall provide multi time schedule support and shall be able to 
save the alarm database for different period of time as the recorded video schedule. 
 
 

PMC: NSL E 123  


Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

AUDIO VIDEO SYTEM 

 
1. Professional  display  monitor  75”    Class  (75"  diagonal)  with  d‐LED  technology,  with  a  contrast 
ratio of up to 4,000:1 with local dimming set to high, Full 1920 x 1080 (1080p) Resolution, High 
Brightness (320 cd/m²). Extensive Interface Capability includes as standard interfaces HDMI input 
x1, D‐Sub 15‐pin RGB input, RS‐232C input/output, DVI‐D input,  Component/Composite, stereo 
audio (1/8”) input x 1, stereo audio (1/8”) output. 
 
a. Scheduling of LFD. Max. Resolution 1,920 x 1,080 pixels, Max. Display Colors’ (approx.) 1,064 
million colors, Pixel Pitch (H x V) 0.2865 x 0.8595 mm, Max. Brightness 320 cd/m2, Contrast 
Ratio 4000: 1. 
b. Viewing  Angle  (H/V)  178°/178°  ,  Response  Time  4  ms  (gray  to  gray,  avg.),  Computer  Input 
Video Analogue RGB (0.7 Up‐p) [75], Digital (conforms to DVI 1.0 standards) Synchronization 
Horizontal/vertical separation (TTL positive/negative), Sync on green. 
c. RS‐232C  D‐sub  9‐pin  (input  x  1,  output  x  1),  Mounting  VESA    400  mm  x  400  mm,  Power 
Supply  AC  100  ‐  240  V~  (+/‐  10  %),  50/60  Hz,  Power  Consumption  247W.  Operating 
Temperature 0°C to 40°C. 
d. Built in Speaker (10W + 10W), PIP/PBP, Narrow Bezel, Light Weight, RS232 In/Out, 1 D‐Sub & 
1 HDMI. 
e. Standby Power Consumption 1.0W (standby mode in Standard), 0.5W (standby mode in Low 
Power). Operating Humidity 10% to 80% RH. 
 
 

2. Professional  display  monitor  55”    Class  (55"  diagonal)  with  d‐LED  technology,  with  a  contrast 
ratio of up to 5,000:1 with local dimming set to high, Full 1920 x 1080 (1080p) Resolution, High 
Brightness (350 cd/m²). Extensive Interface Capability includes as standard interfaces HDMI input 
x1, D‐Sub 15‐pin RGB input, RS‐232C input/output, DVI‐D input,  Component/Composite, stereo 
audio (1/8”) input x 1, stereo audio (1/8”) output. 
a. Scheduling of LFD. Max. Resolution 1,920 x 1,080 pixels, Max. Display Colors’ (approx.) 1,064 
million colors, Pixel Pitch (H x V) 0.2865 x 0.8595 mm, Max. Brightness 350 cd/m2, Contrast 
Ratio 5000: 1. 
b. Viewing  Angle  (H/V)  178°/178°  ,  Response  Time  8  ms  (gray  to  gray,  avg.),  Computer  Input 
Video Analogue RGB (0.7 Up‐p) [75], Digital (conforms to DVI 1.0 standards) Synchronization 
Horizontal/vertical separation (TTL positive/negative), Sync on green. 
c. RS‐232C  D‐sub  9‐pin  (input  x  1,  output  x  1),  Mounting  VESA    400  mm  x  400  mm,  Power 
Supply  AC  100  ‐  240  V~  (+/‐  10  %),  50/60  Hz,  Power  Consumption  180W.  Operating 
Temperature 0°C to 40°C. 
d. Built in Speaker (10W + 10W), PIP/PBP, Narrow Bezel, Light Weight, RS232 In/Out, 1 D‐Sub & 
1 HDMI. 
e. Standby Power Consumption 1.0W (standby mode in Standard), 0.5W (standby mode in Low 
Power). Operating Humidity 10% to 80% RH. 
 
   

PMC:NSL E 124  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

3. Professional  display  monitor  65”    Class  (65"  diagonal)  with  d‐LED  technology,  with  a  contrast 
ratio of up to 5,000:1 with local dimming set to high, Full 1920 x 1080 (1080p) Resolution, High 
Brightness (400 cd/m²). Extensive Interface Capability includes as standard interfaces HDMI input 
x1, D‐Sub 15‐pin RGB input, RS‐232C input/output, DVI‐D input,  Component/Composite, stereo 
audio (1/8”) input x 1, stereo audio (1/8”) output. 
 
a. Scheduling of LFD. Max. Resolution 1,920 x 1,080 pixels, Max. Display Colors’ (approx.) 1,064 
million colors, Pixel Pitch (H x V) 0.2865 x 0.8595 mm, Max. Brightness 350 cd/m2, Contrast 
Ratio 5000: 1. 
b. Viewing  Angle  (H/V)  178°/178°  ,  Response  Time  8  ms  (gray  to  gray,  avg.),  Computer  Input 
Video Analogue RGB (0.7 Up‐p) [75], Digital (conforms to DVI 1.0 standards) Synchronization 
Horizontal/vertical separation (TTL positive/negative), Sync on green. 
c. RS‐232C  D‐sub  9‐pin  (input  x  1,  output  x  1),  Mounting  VESA    400  mm  x  400  mm,  Power 
Supply  AC  100  ‐  240  V~  (+/‐  10  %),  50/60  Hz,  Power  Consumption  180W.  Operating 
Temperature 0°C to 40°C. 
d. Built in Speaker (10W + 10W), PIP/PBP, Narrow Bezel, Light Weight, RS232 In/Out, 1 D‐Sub & 
1 HDMI. 
e. Standby Power Consumption 1.0W (standby mode in Standard), 0.5W (standby mode in Low 
Power). Operating Humidity 10% to 80% RH. 
 
 
4. Professional display monitor 55”  Class (55" diagonal) with d‐LED BLU  technology, with a contrast 
ratio of up to 5,000:1 with local dimming set to high, for 24/7 Commercial Use, Full 1920 x 1080 
(1080p)  Resolution,  High  Brightness  (450  cd/m²).  Extensive  Interface  Capability  includes  as 
standard interfaces D‐Sub, Component, Composite, HDMI, DVI, USB, SD, RS232C In/Out, IR In/Out 
and more. Easy media sharing and screen control with built‐in Wi‐Fi.  
 
a.  Max.  Resolution  1,920  x  1,080  pixels,  Max.  Display  Colors’  (approx.),  Max.  Brightness  450 
cd/m2, Contrast Ratio 5000: 1 Wi‐Fi and All Share Cast. 
b. Viewing  Angle  (H/V)  178°/178°  ,  Response  Time  8  ms  (gray  to  gray,  avg.),  Computer  Input 
Video Analogue RGB (0.7 Up‐p) [75], Digital (conforms to DVI 1.0 standards) Synchronization 
Horizontal/vertical separation (TTL positive/negative), Sync on green. 
c. RS‐232C  D‐sub  9‐pin  (input  x  1,  output  x  1),  Mounting  VESA    400  mm  x  400  mm,  Power 
Supply  AC  100  ‐  240  V~  (+/‐  10  %),  50/60  Hz,  Power  Consumption  176W.  Operating 
Temperature 0°C to 40°C. 
d. Video:  VGA  (D‐Sub  15  Pin),  DVI‐D,  Display  Port  1.2  Component/Composite,  HDMI,  Audio: 
Stereo Mini Jack. Output Video: Display Port 1.2 (Loop‐Out), Audio: Stereo Mini Jack, external 
control RS232C (In/Out) thru Stereo Jack, RJ45 
e. Standby Power Consumption 1.0W (standby mode in Standard), 0.5W (standby mode in Low 
Power). Operating Humidity 10% to 80% RH. 
 
5. Projection & Video Display System: 4000 or above  ANSI Lumens Brightness, 3 D ready , DLP Chip 
x  1  with  Brilliant  Color  Technology  with  6  segment  color  wheel,    support  1080p,  1080i,  720p, 
576i, 540p, 480p, 480i; NTSC, PAL, SECAM Multi Media Projector, True XGA, Auto Keystone, LAN 
(RJ‐45)  Port  etc  with  Standard  Lens,  Lamps  with  Wireless  e‐Projector  gateway,  Uniformity  min. 

PMC:NSL E 125  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

85%, Contrast Ratio > 2200:1, Zoom, Auto focus with minimum 10 watt speaker minimum 20,000 
hrs lamp life . 
 
a. Brightness 4000 ANSI Lumens, Contrast Ratio 1400:1. 
 
b. Light source LED Hybrid 
 
c. Keystone correction manual 
 
d. Color Reproduction Full color (16.77 Million colors) 
 
e.  Power  consumption  Operating  power:  350W  (with  Eco  Mode  “Eco  1”  selected),  430W  (with 
Eco Mode Off “Bright” selected) stand by 0.4 w (LAN OFF), 4.8 w (LAN ON). 
 
f. Operating Temperature 41~95°F, Operating humidity 20~80% (non condensation). 
 
g. Mini D‐Sub 15 pin x 2 Also use as Ycbcr/YPbPr input— commercially available adapter required, 
Native Resolution 786,432 pixels , HDMI Type A x 1, Mini D sub 15 pin x 1 RCA (R/L) x1, Stereo 
mini x 2. 
 
 
6. Projection & Video Display System   100" Optical Motorized Projection Screen Glass Beaded Dust‐ 
Resident,  Flame  retardant,  Mildew  resistant,    Projection  Surface,  built  in  tubular  synchronous 
motor system with IR receiver, high gain (> 2)  & viewing  angle,  Noise less Up/Down operation, 
Image Size   2420x1830. 
 
a. Glass  Beaded  Screen  surface  can  be  cleaned,  flame  retardant,  and  Mildew 
resistant, viewing angle is 35°and Gain is 2.8. 
 
 
b. Matte  White Screen  surface can be  cleaned,  flame  retardant,  Mildew resistant, 
viewing angle is 55°and Gain is 1.2. 
 
c. Product  Specification  peaceful  and  smooth  tubular  motor,  heat  protection 
system,  which  prolongs  motor's  life.  It's  our  most  economical  and  popular 
motorized screen. 
 
d. High quality screen, offers clear and vivid image. 
 
e. IR and RF are available, changing the traditional control ways, which make it easy 
to operate. 
 
f. Furnished  with  junction  box  and  3‐position  wall  switch  for  recessed  wall 
mounting .Available with 110V and 220V motors. 
 
 
g. Be  suit  for  using  in  different  places,  such  as      schools,  business  affairs,  home 
cinemas,  casino  places  and  other  entertainment  sites,  120"    2430*1820    2620  
2640  2640*95*140  2965*140*140. 

PMC:NSL E 126  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

 
 
7. Projection & Video Display System ‐ Retractable Motorized Micro Ceiling Lift Voltage: 220V 50Hx 
or  110V  60H.  Dimension:  350×280×130mm  (L×W×H),  Bottom  Panel  Dimension:  50cmx50cm, 
Loading Capacity: 20KG, Travel Length: 100cm, Open cut in ceiling: 480x480mm. 
 
8. Multimedia wooden podium with Dimension (mm) 590(w) x 600(h) x 1200(d) 
And one key and all the equipments are locked and safe inside. It consists of an Interactive Tablet 
Monitor, Built‐in goose neck microphone for ease of use. Sliding Shelf for placement of extra lap 
top & For Documents. Inputs Built‐in RGB, USB, LAN Port. Audio in, Audio Out, AC Power etc. 
 
9. Full  swing  wall  mount  kit  tilt  mechanism  adjusts  to  provide  fingertip  tilt  with  most  flat  panels. 
Cable  Trac  System  provides  built‐in  cable  management  channels  inside  the  arms  for  a  clean 
installation. 
 
10. Table  connectivity  box  with  Power  socket,  VGA  receptacle,  Video  3.5MM  stereo  socket,  HDMI, 
VGA,  C‐Video,  Audio,  Network,  Telephone,  Power  etc.  with  Control  Switch  built‐in  ,   Neat  & 
elegant  topside,  Input  voltage:  110V‐220V/50‐60Hz,  Surface  Mountable  Enclosure  for  Cables 
AAPs.  Dual‐Net  socketLocking  Device,  Smooth  Pneumatic  Support  Structure,   Desktop  Hidden 
Connection Box, Mechanical . 
 
11. Desktop  Motorised  Hidden  Connection  Box,  l  Locking  Device,  Smooth  Motorised    Support 
Structure,  VGA  with  Audio  through  cable  and  wirelessly  both,  HDMI,  C‐Video,  Audio,  Network, 
Telephone,  Power  etc.  with  Control  Port  built‐in,  Neat  &  elegant  topside,  Input  voltage:  110V‐
220V  /  50‐60Hx,  RCA,  3.5  mm  Audio  Jack,  USB,  Surface  Mountable  Enclosure  for  Cables  with 
cables & connectors as required  
 
12. Professional display systems requiring a true 4x8 computer graphics and audio matrix operation. 
Multimedia and presentation source, and acceptor selection. 
 
a. 4 UXGA with loop on 15−pin HD connectors, 4 unbalanced stereo audio 3.5mm mini 
jacks.  8  UXGA  on  15−pin  HD  connectors,  8  balanced  stereo  audio  terminal  block 
connectors. 
b. Bandwidth (3dB) Video: 360MHz, Audio: 22kHz. Difference gain 0.05%. 
c. Flexible Control  Options front  panel, RS−232  (K−Router  Windows−based so ware  is 
included), RS−485, Ethernet and IR remote (included), embedded Web page. 
d. Delayed Switching Mode Glitch−free switching of non−gen locked sources by se ng 
the transition time of a switch from 0 to 3.5sec. 
e. S/N ratio Video: 66dB @5MHz, Audio: 82dB, crosstalk Video: −52dB @5MHz, Audio: 
Bal: <−70dB @20kHz. Input/output selector buttons, all, off, video, audio, AFV, store, 
recall,  take  audio  level,  and  lock  buttons;  RS  −232,  RS−485,  and  Ethernet  control; 
input and output level control, infrared. 
f. Power consumption 100−240V AC, 19VA. Coupling Video: DC, Audio: AC. 
 
13. Professional display systems requiring a true 8x4 computer graphics and audio matrix operation. 
Multimedia and presentation source, and acceptor selection. 

PMC:NSL E 127  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

 
a.  8 UXGA with loop on 15−pin HD connectors, 8 unbalanced stereo audio 3.5mm mini 
jacks.  4  UXGA  on  15−pin  HD  connectors,  4  balanced  stereo  audio  terminal  block 
connectors. 
b. Bandwidth (3dB) Video: 360MHz, Audio: 22kHz. Difference gain 0.05%. 
c. Flexible Control  Options front  panel, RS−232  (K−Router  Windows−based so ware  is 
included), RS−485, Ethernet and IR remote (included), embedded Web page. 
d. Delayed Switching Mode Glitch−free switching of non−gen locked sources by se ng 
the transition time of a switch from 0 to 3.5sec. 
e. S/N ratio Video: 66dB @5MHz, Audio: 82dB, crosstalk Video: −52dB @5MHz, Audio: 
Bal: <−70dB @20kHz. Input/output selector buttons, all, off, video, audio, AFV, store, 
recall,  take  audio  level,  and  lock  buttons;  RS  −232,  RS−485,  and  Ethernet  control; 
input and output level control, infrared. 
f. Power consumption 100−240V AC, 19VA. Coupling Video: DC, Audio: AC. 
 
 
14. Automatic computer and presentation UXGA routing, Presentation systems with wall plates. 
 
a. 2 computer graphics video with loop on 15−pin HD connectors, 2 unbalanced stereo 
audio on 3.5mm mini jacks. 1 computer graphics video on a 15−pin HD connector, 1 
unbalanced stereo audio on a 3.5mm mini jack. 
b. BANDWIDTH (‐3dB) Video: 300MHz; Audio: >100 kHz, Difference gain 0.03%. 
c. Automatic Standby Switching Switches from secondary input to primary input when a 
signal is detected. 
d. CROSSTALK  Video:  –59dB  @5MHz;  Audio:  <–66dB  @1kHz,  S/N  ratio  video:  71dB; 
Audio: 71dB weighted. 
e. Maximum output level Video: 1.6Vpp; Audio: >10.5Vpp. 
 
15. High−performance matrix switcher for HDMI signals It must relocks and equalizes the signal and 
can route any input to any or all outputs simultaneously. 
 
a.  4 HDMI input connectors and 8 HDMI output connectors. 
b. Bandwidth 6.75Gbps (2.25Gbps per graphic channel), must support HDMI, EDID and 
HDCP, resolution Up to UXGA; 1080p 
c. Control Options Front panel, IR remote, RS−232, Ethernet, Support: 3D, Deep Color, 
x.v.Color. 
 
16. High−performance matrix switcher for HDMI signals It must relocks and equalizes the signal and 
can route any input to any or all outputs simultaneously. 
 
a. 8 HDMI input connectors and 4 HDMI output connectors. 
b. Bandwidth 6.75Gbps (2.25Gbps per graphic channel), must support HDMI, EDID and 
HDCP, resolution Up to UXGA; 1080p 
c. Control  Options Front  panel,  IR  remote,  RS−232,  Ethernet,  and  Support: 3D,  Deep 
Color, x.v.Color. 
 
17. High−performance  matrix  switcher  for  HDMI  signals,  unit  automatically  switches  to  the 
secondary input whenever the primary video signal is interrupted. 
 

PMC:NSL E 128  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

a. 2HDMI input connectors and 1 HDMI output connectors. 
b. Bandwidth 6.75Gbps (2.25Gbps per graphic channel), must support HDMI, EDID and 
HDCP, resolution Up to UXGA; 1080p 
c. HDMI  Support Deep  Color,  x.v.Color,  Lip  Sync,  up  to  7.1  Uncompressed  Audio 
Channels, CEC. 
 
18. High performance HDMI audio de−embedded unit can de−embed audio from the HDMI input or 
from  the  HDMI  output  Audio  Return  channel  to  S/PDIF,  TOSLINK  and  analog  audio  outputs 
simultaneously. 
 
a. Bandwidth 6.75Gbps (2.25Gbps per graphic channel), must support HDMI, EDID and 
HDCP, resolution Up to UXGA; 1080p. 
b. HDMI Support ARC and HDMI Uncompressed Audio Channels. 
 
 
19. Touch  Panel  Control  System      Control  Pack  with  Dual  Bus  Architecture  3‐Series  Centralized 
Control  processor  ‐  Built  in  4x2  AV  Switcher,  2  RS‐232  port,  Eight  IR,  4  Relays,  4  I/O  Port  and 
Ethernet port, Power Supply, E‐Control and Isis 8.4" or more Active Matrix Touch Control panel 
with accessibility, 4 Sets of IR Emitting Probes. 
 
20. Control Pack with Dual Bus Architecture 3‐Series Centralized Control processor ‐ Built in 2 RS‐232 
port,  5  IR,  2,  1USB  ,1  Relays,  1  Input  Port  and  Ethernet  port,  Power  Supply,  E‐Control    or  with 
accessibility. 
 
21. Touch Panel Control System: Wireless Access Point between Touch Panel & Control System. 

a. Touch  Panel  Control  System  Wireless  Access  Point  between  Touch  Panel  &  Control 
System. 
 
b. Processor CPU 32‐bit free scale Cold Fire Microprocessor. 
 
c. Memory   SDRAM   64 MB, NVRAM   256 kobo, Flash   4 MB, Compact Flash   expandable 
up  to  2  GB  (not  included),  Operating  System,  Real‐time,  preemptive  multi‐
threaded/multitasking  kernel;  FAT32  file  system  with  long  names;  supports  SIMPL 
Windows and SIMPL+. 
 
d. Ethernet    With  C2ENET‐1    10/100BaseT,  auto‐negotiating,  full/half  duplex,  static  IP  or 
DHCP/DNS, SSL, TCP/IP, UDP/IP, CIP, SMTP, SNMP, built‐in Web server and e‐mail client; 
supports  e‐Control 2 Panel and Room View applications, With   All above features plus  
built‐in firewall, router, and network address translator (NAT). 
 
e. Y‐Bus  Connectors  &  Expansion  Slots    40  Mb/s  parallel  communications;  Internal 
backplane  for  integrated  control  ports  and  Y‐Bus  expansion  slots,  (6)  DB9  male, 
bidirectional  RS‐232/422/485  ports,  Up  to  115.2k  baud;  Hardware  and  software 
handshaking support; Ports C‐F support C2N‐NPA8 Network Poll Accelerator. 
 
f. INFRARED‐SERIAL  OUTPUT  A  ‐  H,  (8)  2‐pin  3.5mm  detachable  terminal  blocks,  IR/Serial 
output ports; IR output up to 1.2 MHz, 1‐way serial TTL/RS‐232 (0‐5 Volts) up to 115.2k 

PMC:NSL E 129  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

baud;  Individual  signal  generator  per  port,  allowing  simultaneous  firing  of  all  ports/O 
Versiports  1  ‐  8,  (1)  9‐pin  3.5mm  detachable  terminal  block  comprising  (8)  digital 
input/output  or  analog  input  ports  (referenced  to  GND);Digital  Input      Rated  for  0‐24 
Volts  DC,  input  impedance  20k  ohms,  logic  threshold  1.24  Volts  DC;Digital  Output   
250mA  sink  from  maximum  24  Volts  DC,  catch  diodes  for  use  with  “real  world”  loads; 
Analog  Input      Rated  for  0‐10  Volts  DC,  protected  to  24  Volts  DC  maximum,  input 
impedance 20k ohms; Programmable 5 Volts, 2k ohms pull‐up resistor per pin. 
 
g. RELAY OUTPUT 1 ‐ 8, (2) 8‐pin 3.5mm detachable terminal blocks comprising (8) normally 
open, isolated relays; Rated 1 Amp, 30 Volts AC/DC;MOV arc suppression across contacts, 
Expansion  Slots,(3)  Y‐Bus  expansion  slots  (Requires  CAGE2  accessory,  sold 
separately);Accept all Y‐Bus control cards. 
 
h. Z‐Bus Expansion Slots  300 Mb/s parallel communications; Backplane for Z‐Bus expansion 
slots, Expansion Slot, (1) Z‐Bus expansion slot; Accepts all Z‐Bus control cards, Additional 
Connectors, COMPUTER  (2) DB9 female; Front and rear panel RS‐232 computer console 
ports,  (1)  4‐pin  5mm  detachable  terminal  block;    port,  Master/Slave  selectable; 
Expandable via C2N‐NPA8 Network Poll Accelerator. 
 
i. 50/60  Hamates  with  removable  power  cord,  included,  Ground  (1)  6‐32  screw,  chassis 
ground  lug,  Reset  Buttons,  HW‐R  Hardware  reset  (reboots  the  control  system),  SW‐R 
Software reset (restarts the SIMPL program), LED Indicators, PWR (1 green) Indicated AC 
power  supplied  to  unit,  NET  (1  yellow)  Indicates    bus  activity,  MSG  (1  red)  Indicates 
control  system  has  generated  an  error  message,  LNK  A  (1  red)  Indicates  a  valid 
connection on LAN port A, LNK B (1 red) Indicates a valid connection on LAN port B, ACT 
B (1 red) Indicates activity on LAN port B. 
 
j. Power  Requirements      Main  Power  2.3  Amps,  100‐250  Volts  AC,  50/60  Hz,  Available  
Power 50 Watts (shared with control card expansion slots), Environmental   Temperature 
41° to 113°F (5° to 45°C), Humidity 10% to 90% RH (non‐condensing), Enclosure, Chassis 
Steel, black matte powder coat finish, Faceplate Extruded aluminum, black matte powder 
coat finish with polycarbonate label overlay, Mounting Freestanding or 2U 19‐inch rack‐
mountable (adhesive feet and rack ears included), Dimensions. 
 
k. Height    3.56 in (9.04 cm);3.47 (8.81 cm) without feet, Width 17.03  in (43.26 cm); 19.0 in 
(48.26 cm) with ears, Depth 10.31 in (26.19 cm),Weight 7.1 lb (3.22 kg) – with line cord. 
 
22. Touch  Panel  Control  System      Programmable  8  Port  Relay  Module  &  4  digital  /  analogue  input 
module 0‐24 Volts DC, low‐voltage relay, 6 Watts Power @ 12Volts / 240 V, 44k Input Impedance. 

a. Connectors  RELAY OUTPUT 1 ‐ 8, (1) 16‐pin 5mm detachable terminal block comprising 
(8)  normally  open,  isolated  (form  ‘C’)  relays;,  Rated  1  Amp,  30  Volts  AC/DC;MOV  arc 
suppression across contacts. 
 
b. Power Requirements Power Usage 3 Watts (0.125 Amps @ 24 Volts DC). 
 
c. Environmental Temperature   41° to 113°F (5° to 45°C), Humidity   10% to 90% RH (non‐
condensing). 

PMC:NSL E 130  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

 
d. Construction  Y‐bus  expansion  card,  occupies  (1)  Y‐bus  card  slot  in  a  2‐Series  control 
system. 
 
e. Dimensions Height  0.98 in (2.49 cm), Width  5.00 in (12.70 cm), and Depth  6.78 in (17.21 
cm). 
 
 
 
 
23. Programmable Lighting Control System   4 Preset Scene Zones,  2300 Watts Load capacity (800 
Watts  per  Zone),  Dimming  of  Incandescent/CFL  /  Halogen/Tungsten/T5  (with  optional 
ballast/interface), Fade time setting between 0‐59 Sec. or 1‐60 min. Channels, Control Port built‐
in Infrared Port serial with Front Panel, Lockout options to avoid accidental changes. 
 

a. Multi‐Scene  Preset  Lighting  Control  System,  Set  up  and  Recall,  Create  lighting 
scenes  for  common  activities  all  at  the  touch  of  a  button.  Smooth  Transitions, 
Fade between lighting scenes – from instantly to one hour. Expand the System. 
 
b. Accessory  controls  allow  one‐touch  control  from  any  location,  Integration, 
Integrates  easily  with  touch  screens  and  other  AV  equipment.  RTISSTM 
Technology  Included,  Compensates  for  incoming  line  voltage  variations, 
frequency shifts, harmonics, and line noise. One Control, Just one model provides 
control of all modern light sources. Reliability, Control is able to withstand short 
between  load  hot  and  either  load  neutral  or  earth  without  damage.  Provides 
pushbutton recall of four preset lighting scenes, plus off. Allows setup of lighting 
scenes  using  buttons  on  the  Control  Unit.,  Controls  many  light  source  types 
directly, and others using power interfaces. Provides lockout options to prevent 
accidental  changes.  Includes  built‐in  infrared  receiver  for  operation  with  an 
optional remote control, Specifications. 
 
c. Input Power 120 V, 220‐240 V (non‐CE), 230 V (CE) or 100 V, 50/60Hz., Lightning 
Strike  Protection  Meets  ANSI/IEEE  standard  62.41‐1980.  Can  withstand  voltage 
surges of up to 6000 V and current surges of up to 3000 A. 
 

d. Lighting  Sources/Load  Types  Controls  the  following  lighting  sources  with  a 


smooth, continuous Square Law dimming curve or on a full conduction non‐dim 
basis  Incandescent,  Tungsten,  Magnetic  Low  Voltage  Transformer,  To‐Wire 
Electronic  Fluorescent  Dimming  Ballast,  Neon  and  Cold  Cathode,  Controls  the 
following lighting sources with a smooth continuous Square Law dimming curve 
through  separate  power  interfaces,  Electronic  Low  Voltage  Transformer, 
Electronic Fluorescent Dimming Ballast. 
 

PMC:NSL E 131  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

e. Preset  Control  4  preset  lighting  scenes  and  off  are  accessible  from  the  Control 
Unit front panel.12 additional scenes are stored in the Control Unit. These scenes 
are  accessible  via  Wall  stations  and/or  Control  Interfaces.,  Light  levels  fade 
smoothly  between  scenes.  Fade  time  can  be  set  differently  for  each  scene, 
between 0‐59 sec. and 1‐60 min. Fade time from Off is capped at 5 sec. 
 
f. Design  Features  Meets  IEC  801‐2.  Tested  to  withstand  15kV  electrostatic 
discharge  without  damage  or  memory  loss.  Compensates  in  real  time  for 
incoming  line  voltage  variations      No  visible  flicker  with  +/‐2%  change  in  RMS 
voltage/cycle  and  +/‐2%  Hz  change  in  frequency/second.10‐year  power  failure 
memory  automatically  restores  lighting  to  levels  prior  to  power  interruption. 
Faceplate snaps on with no visible means of attachment. 
 
g. System Communications  and Capacities   Low‐voltage type  Class 2  (PELV)  wiring 
connects  Control  Units,  Wall  stations,  and  Control  Interfaces,  Up  to  8  Control 
Units may be linked to control up to 48 zones., Up to 16 total Wall stations and 
Control Interfaces may be added for a total of 24 control points .Environment 32‐
104 °F (0‐40 °C). Relative humidity less than 90% non‐condensing. 
 
24. Touch Panel Control System interfacing device to controlling all the equipment. Wi‐Fi , 9.7‐inch 
(diagonal)  LED‐backlit  Multi‐Touch  display with  IPS  technology,  2048x1536  resolution  at  264 
pixels per inch, Built‐in 32.4‐watt‐hour rechargeable lithium‐polymer battery. 
 
25. Video  collaboration  The  End  Point  should  be  a  codec  based  hardware.  No  software  based 
solution is accepted here. It should be from the same OEM. 
 
a.  Package  Should  Include  Full  HD  1080p  camera,  codec,  Microphone  Array,  cables,  and 
remote  control,  Following  Video  Standards  and  Protocols  should  be  supported:  H.261, 
H.263, and H.264. H.239   H.263   & H.264 Video error concealment. 
 
b. Video Input It should have 2 x HD camera Interface It should have another 3 x HDMI port. 
c. It should have 1 x VGA port. Video out It should have at least 3 x HDMI port to connect 
displays. 
 
d. Following People Video Resolution should be supported:  
1080p, 60 fps from 1740 Kbps 
1080p, 30 fps from 1024 Kbps 
720p, 60 fps from 832 Kbps 
720p, 30 fps from 768 Kbps 

PMC:NSL E 132  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

4SIF/4CIF, 60 fps from 512 Kbps 
4SIF/4CIF, 30 fps from 128 Kbps 
SIF (352 x 240), CIF (352 x 288) from 64 kbps 
QSIF (176 x 120), QCIF (176 x 144) from 64 kbps 
W 288p from 128 kbps 
W 448 from 384 kbps 
W 576p from 512 Kbps 
The  same  codec  should  also  support  1080p,  60  fps  from  1740  Kbps  via  a  software 
upgrade in future 
e. Following Input and Output Content Video Resolution should be supported:  
 Input: WUXGA (1920 x  1200), HD (1920 x 1080i), HD (1920 x 1080p), WSXGA+  (1680 x 
1050),  UXGA (1600 x 1200), SXGA  (1280 x  1024), WXGA (1280 x 768), HD (1280x720p), 
XGA (1024 x 768), SVGA (800 x 600). 
Output: WUXGA (1920 x 1200), HD (1920 x 1080), WSXGA+ (1680 x 1050), SXGA+ (1400 x 
1050), SXGA (1280 x 1024), HD (1280 x 720), XGA (1024 x 768), VGA (640 x 480). 
The  Content  Frame  Rate  of  5  ‐  30  fps  (up  to  1080p  resolution  at  30  fps)  should  be 
supported; The Content Frame Rate of 60 fps (up to 1080p resolution at 60 fps) should 
also be supported on the same codec via a software upgrade. it should be possible to do 
Content Sharing during a VC call. 
f. Following  Camera  specifications  should  be  met:  Full  HD,  1280  x  1080p  CCD  imager, 
Optical Zoom ‐ 12X or more, Field of View 72 Degree. 
g. Following  Audio  Input    ports  should  be  available  on  the  codec:  It  should  support  1  x 
Microphone  Array  (supporting  a  total  of  2  microphones),  It  should  have  1  x  HDCI  (  for 
camera),  It  should  have  another  1  x  HDMI  port,  It  should  also  have  1  x  3.5mm  Stereo 
Line‐in port. It should have at least 2 x USB 2.0, It should have at least 1 x RS‐232 Mini‐
DIN 8‐Pin port. 
h. Following  Audio  Standards  and  Protocols  should  be  met:  Siren  22,AAC‐LD,  20  kHz 
bandwidth  with  G.719,  14  kHz  bandwidth  with  Siren  14,  G.722.1  Annex  C,  7  kHz 
bandwidth  with  G.722,  G.722.1,  3.4  kHz  bandwidth  with  G.711,G.728,  G.729A  OR 
Equivalent  OR  Better,  It  should  support  Automatic  gain  control,  It  should  support 
Automatic  noise  suppression,  It  should  support  Keyboard  noise  reduction,  It  should 
support  Live  music  mode,  It  should  support  Instant  adaptation  echo  cancellation,  It 

PMC:NSL E 133  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

should  have  Audio  error  concealment,  It  should  support    Lost  Packet  Recovery  or 
equivalent technology, It should support Stereo Surround technology. 
i. Following Security specifications should be supported: Algorithms: SHA‐1, SHA‐256, AES 
(256‐ bit, CBC/OFB/counter), PRNG, Authenticated access to admin menus, web interface 
and  telnet  API,  FIPS  140‐2  Validated  Cryptography  (Validation  Certificate  #918),  PKI  & 
certificate management (TLS 1.0 and SSL 3.0). 
j. It should also support Internal Multipoint license for up to 8 sites via software upgrade. 
User  will  decide  on  how  many  units  is  this  feature  required.  It  should  be  possible  to 
integrate a conference phone (Optional). 
 
26. Video collaboration digital microphone array is the only audio pickup device for video  
Conferencing system which must have s consistent, reliable, 360‐degree  
Voice pickup and Stereo Surround audio. 360‐degree directional pickup, three cardioids elements 
per  microphone  Elements  spaced  120  degrees  apart,  Each  Ceiling  Microphone  Array  should  at 
least  covers  a  24’  diameter.  Dynamic  microphone  steering,  Full‐duplex  digital  audio  &  Instant 
Adaptation Echo Cancellation. 
 
27. Video collaboration installed audio solution deliver clear, immersive sound for more productive 
voice and video conferences. 
 
a. Connectors RS‐232: DB9F, OBAM In/Out: IEEE 1394B, CLINK2 : RJ45, LAN: RJ45, Control 
/Status:  DB25F,  Audio:  Mini  (3.5mm)  quick  connect  terminal  blocks,  IR  Receive:  Mini 
(3.5mm) quick connect terminal block. 
b. Power  should  be  Input  voltage  of  90‐250  VAC;  50‐60  Hz;  line  power  requirements 
(including 0.6 PF): 95VA, 0 to 40°C operating temperature. 
c.  Input  Phantom  power:  48  V  DC  through  6.8kOhm  series  resistor  per  leg,  7.5mA  per 
channel, software selectable, Analog input Gain: ‐20 to 64 dB on all inputs in 0.5 dB steps, 
software adjustable, Maximum input amplitude: +20.4 dBu, 1% THD + N, Nominal level: 0 
dBu (0.775V rms), Equivalent input noise: <‐122 dBu, 20 ‐ 20,000 Hz, Rs=150 Ohms (1%). 
d. Output Output Gain: ‐100 to 20 dBu in 1 dB steps, software Maximum output amplitude: 
+23 dBu, 1% THD + N, Nominal output level: 0 dBu (0.775 V rms), Output impedance: 50 
Ohm, each leg to ground, designed to drive loads > 600 Ohms. 

PMC:NSL E 134  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

e. System at least has Frequency response: 20‐22,000 Hz, + 0.1 /‐ 0.3 dB, Idle channel noise: 
<‐109  dB  FS  no  weighting,  20‐  20,000  Hz,  ‐60dB  FS,  0.997  kHz  input  signal,  0  dB  gain. 
Dynamic  range:  >109  dB  FS  no  weighting,  20  ‐  20,000  Hz,  ‐60  dB  FS,  0.997  kHz  input 
signal, 0 dB gain, Linearity: 0 dB FS to ‐122 dB FS +/‐ 1 dB. 
28. Video  collaboration  1080p60  video  and  content  collaboration  heightens  realism  and  speeds 
adoption. 
a. Package  includes  camera,  codec,  cables,  remote  control,  Microphone  Array.  Video 
standards  and  protocols  H.261,  H.263,  H.264  AVC,  H.264  High  Profile,  H.264  SVC,  RTV 
H.239/   P+c H.263 & H.264 video error concealment  
b. Video input 1 x HD camera (HDCI) , 1 x HDMI 1.3 & 1 x VGA. Video Output 2 x HDMI 
 
c. Following People Video Resolution should be supported:  
1080p, 60 fps from 1740 Kbps 
1080p, 30 fps from 1024 Kbps 
720p, 60 fps from 832 Kbps 
720p, 30 fps from 768 Kbps 
4SIF/4CIF, 60 fps from 512 Kbps 
4SIF/4CIF, 30 fps from 128 Kbps 
SIF (352 x 240), CIF (352 x 288) from 64 kbps 
QSIF (176 x 120), QCIF (176 x 144) from 64 kbps 
W 288p from 128 kbps 
W 448 from 384 kbps 
W 576p from 512 Kbps 
 
d. Following Input and Output Content Video Resolution should be supported:  
 Input: WUXGA (1920 x  1200), HD (1920 x 1080i), HD (1920 x 1080p), WSXGA+  (1680 x 
1050),  UXGA (1600 x 1200), SXGA  (1280 x  1024), WXGA (1280 x 768), HD (1280x720p), 
XGA (1024 x 768), SVGA (800 x 600). 
Output: WUXGA (1920 x 1200), HD (1920 x 1080), WSXGA+ (1680 x 1050), SXGA+ (1400 x 
1050), SXGA (1280 x 1024), HD (1280 x 720), XGA (1024 x 768), VGA (640 x 480). 
The  Content  Frame  Rate  of  5  ‐  30  fps  (up  to  1080p  resolution  at  30  fps)  should  be 
supported; The Content Frame Rate of 60 fps (up to 1080p resolution at 60 fps) should 

PMC:NSL E 135  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

also be supported on the same codec via a software upgrade. it should be possible to do 
Content Sharing during a VC call. 
e. Following  Camera  specifications  should  be  met:  Full  HD,  1280  x  1080p  CCD  imager, 
Optical Zoom ‐ 12X or more, Field of View 72 Degree. 
f. Following  Audio  Input    ports  should  be  available  on  the  codec:  It  should  support  1  x 
Microphone  Array  (supporting  a  total  of  2  microphones),  It  should  have  1  x  HDCI  (  for 
camera),  It  should  have  another  1  x  HDMI  port,  It  should  also  have  1  x  3.5mm  Stereo 
Line‐in port. It should have at least 2 x USB 2.0, It should have at least 1 x RS‐232 Mini‐
DIN 8‐Pin port. 
g. Following  Audio  Standards  and  Protocols  should  be  met:  Siren  22,AAC‐LD,  20  kHz 
bandwidth  with  G.719,  14  kHz  bandwidth  with  Siren  14,  G.722.1  Annex  C,  7  kHz 
bandwidth  with  G.722,  G.722.1,  3.4  kHz  bandwidth  with  G.711,G.728,  G.729A  OR 
Equivalent  OR  Better,  It  should  support  Automatic  gain  control,  It  should  support 
Automatic  noise  suppression,  It  should  support  Keyboard  noise  reduction,  It  should 
support  Live  music  mode,  It  should  support  Instant  adaptation  echo  cancellation,  It 
should  have  Audio  error  concealment,  It  should  support    Lost  Packet  Recovery  or 
equivalent technology, It should support Stereo Surround technology. 
h. Following Security specifications should be supported: Algorithms: SHA‐1, SHA‐256, AES 
(256‐ bit, CBC/OFB/counter), PRNG, Authenticated access to admin menus, web interface 
and  telnet  API,  FIPS  140‐2  Validated  Cryptography  (Validation  Certificate  #918),  PKI  & 
certificate management (TLS 1.0 and SSL 3.0). 
i. It should also support Internal Multipoint license for up to 6 sites via software upgrade. 
User  will  decide  on  how  many  units  is  this  feature  required.  It  should  be  possible  to 
integrate a conference phone (Optional). 
29. Video  collaboration  1080p60  video  and  content  collaboration  heightens  realism  and  speeds 
adoption. 
 
a. Package  includes  camera,  codec,  cables,  remote  control,  Microphone  Array.  Video 
standards  and  protocols  H.261,  H.263,  H.264  AVC,  H.264  High  Profile,  H.264  SVC,  RTV 
H.239/ P+C H.263 & H.264 video error concealment  
b. Video input 1 x HD camera (HDCI) , 1 x HDMI 1.3 & 1 x VGA. Video Output 2 x HDMI 
c. Following People Video Resolution should be supported:  
1080p, 60 fps from 1740 Kbps 

PMC:NSL E 136  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

1080p, 30 fps from 1024 Kbps 
720p, 60 fps from 832 Kbps 
720p, 30 fps from 768 Kbps 
4SIF/4CIF, 60 fps from 512 Kbps 
4SIF/4CIF, 30 fps from 128 Kbps 
SIF (352 x 240), CIF (352 x 288) from 64 kbps 
QSIF (176 x 120), QCIF (176 x 144) from 64 kbps 
W 288p from 128 kbps 
W 448 from 384 kbps 
W 576p from 512 Kbps 
 
 
d. Following Input and Output Content Video Resolution should be supported:  
 Input: WUXGA (1920 x  1200), HD (1920 x 1080i), HD (1920 x 1080p), WSXGA+  (1680 x 
1050),  UXGA (1600 x 1200), SXGA  (1280 x  1024), WXGA (1280 x 768), HD (1280x720p), 
XGA (1024 x 768), SVGA (800 x 600). 
Output: WUXGA (1920 x 1200), HD (1920 x 1080), WSXGA+ (1680 x 1050), SXGA+ (1400 x 
1050), SXGA (1280 x 1024), HD (1280 x 720), XGA (1024 x 768), VGA (640 x 480). 
The  Content  Frame  Rate  of  5  ‐  30  fps  (up  to  1080p  resolution  at  30  fps)  should  be 
supported; The Content Frame Rate of 60 fps (up to 1080p resolution at 60 fps) should 
also be supported on the same codec via a software upgrade. it should be possible to do 
Content Sharing during a VC call. 
e. Following  Camera  specifications  should  be  met:  Full  HD,  1280  x  1080p  CCD  imager, 
Optical Zoom ‐ 12X or more, Field of View 72 Degree. 
f. Following  Audio  Input  ports  should  be  available  on  the  codec:  It  should  support  1  x 
Microphone  Array  (supporting  a  total  of  2  microphones),  It  should  have  1  x  HDCI  (  for 
camera),  It  should  have  another  1  x  HDMI  port,  It  should  also  have  1  x  3.5mm  Stereo 
Line‐in port. It should have at least 2 x USB 2.0, It should have at least 1 x RS‐232 Mini‐
DIN 8‐Pin port. 
g. Following  Audio  Standards  and  Protocols  should  be  met:  Siren  22,AAC‐LD,  20  kHz 
bandwidth  with  G.719,  14  kHz  bandwidth  with  Siren  14,  G.722.1  Annex  C,  7  kHz 
bandwidth  with  G.722,  G.722.1,  3.4  kHz  bandwidth  with  G.711,G.728,  G.729A  OR 
Equivalent  OR  Better,  It  should  support  Automatic  gain  control,  It  should  support 

PMC:NSL E 137  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

Automatic  noise  suppression,  It  should  support  Keyboard  noise  reduction,  It  should 
support  Live  music  mode,  It  should  support  Instant  adaptation  echo  cancellation,  It 
should  have  Audio  error  concealment,  It  should  support    Lost  Packet  Recovery  or 
equivalent technology, It should support Stereo Surround technology. 
h. Following Security specifications should be supported: Algorithms: SHA‐1, SHA‐256, AES 
(256‐ bit, CBC/OFB/counter), PRNG, Authenticated access to admin menus, web interface 
and  telnet  API,  FIPS  140‐2  Validated  Cryptography  (Validation  Certificate  #918),  PKI  & 
certificate management (TLS 1.0 and SSL 3.0). 

30. Audio System speaker system with rated output 30 w (high impedance) two‐way speaker systems 
designed for high efficiency, wide range, and high power input handling capability. 
 
a. Power handling capacity Continuous pink noise: 60 W (8 Ω), 30 W (16 Ω) & Continuous 
program: 120 W (8 Ω), 60 W (16 Ω) 
b. Rated  Impedance  100  V  line:  330  Ω  (30  W),  1  kΩ  (10  W),  3.3  kΩ  (3  W),  10  kΩ  (1  W) 
70  V  line:  170  Ω  (30  W),  330  Ω  (15  W),  1  kΩ  (5  W),  3.3  kΩ  (1.5  W),  10  kΩ  (0.5  W) 
25  V  line:  170  Ω (3.7  W),  330  Ω  (1.9  W),  1  kΩ (0.6  W),  3.3 kΩ (0.2  W),  10  kΩ  (0.06 W) 
16 Ω, 8 Ω 
c. Sensitivity 90 dB (1 W, 1 m), Frequency Response 70 Hz ‐ 20 kHz (‐10 dB), 50 Hz ‐ 20 kHz 
(‐20 dB). 

31. Audio  System  power  amplification  with  rated  output  240  W  power  amplifier  featuring  high 
performance amplification. 
 
a. Power consumption 238 W (EN60065), 520 W (AC operation at rated output), 15 A (DC 
operation at rated output). 
b. Frequency response 50 Hz ‐ 20 kHz (±3 dB), Distortion 1 % or less at 1 kHz, 1/3 rated  
Power.Input  Line  in:  0  dB,  10  kΩ,  balanced,  screw  terminal,  distance  between  barriers: 
8.3  mm  (0.33")  Speaker  line  in:  40  dB,  330  kΩ,  Unbalance,  screw  terminal,  distance 
between  barriers:  8.3  mm  (0.33").    Output    Loop  out:  0  dB,  10  kΩ,  balanced,  screw 

PMC:NSL E 138  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

terminal,  distance  between  barriers:  8.3  mm  (0.33")  Speaker  out:  Balanced  (floating) 
High impedance: 42 Ω (100 V), 21 Ω (70 V) Low impedance: 4 Ω (31 V). 
c. S/N Ratio 60 dB or more Tone Control Bass: ±10 dB at 100 Hz Treble: ±10 dB at 10 kHz. 
 
32. CENTRAL UNIT: ‐ Power Source 230 V AC, 50/60 Hz Power Consumption Max. 60 W Rated Output 
35 V DC, 650 mA × 2 Input MIC: ‐60 dB*, 600 Ω, unbalanced, phone jack AUX: ‐20  dB*, 10 kΩ, 
unbalanced, phone jack Output Recording: ‐20 dB*, 10 kΩ, unbalanced, phone jack, pin jack × 2 
Equalizer  Insertion  Input Control  Priority  speech  chime:  Operation,  priority  button  activates  a 
single‐tone chime. 
 
a. Rated Output should be 35 V DC, 650 mA × 2. 
b. Power Source should be 230 V AC, 50/60 Hz. 
c. Device should have input of MIC: ‐60 dB, 600 Ω, unbalanced, phone jack and AUX: ‐20 dB, 10 kΩ, 
unbalanced, phone jack. 
d. Device should have output of Recording: ‐20 dB*, 10 kΩ, unbalanced, phone jack, pin jack × 2. 
e. Equalizer Insertion Input Terminal ‐ Input: ‐20 dB*, 10 kΩ, pin jack, Output: ‐20 dB*, 10 kΩ, pin 
jack. 
f. Expansion Input and Output Terminal ‐ Input: ‐20 dB*, 10 kΩ, pin jack × 2, Output: ‐20 dB*, 10 
kΩ, pin jack × 2, Control: 10 kΩ or more, voltage output, pin jack × 2. 
g. 70 (Max. 35 units per line), Max 210 (when 3 expansion amplifiers). 
 
33. CHAIRMAN UNIT:‐ compact and lightweight design Power Source 35 V DC, under 30 mA (supplied 
from Central Unit) Output Headphone/Recording: 32 Ω (headphone)/10 kΩ, ‐20 dB* (recording), 
unbalanced, mini jack (with VR) Internal speaker: 130 Ω, 200 mW Contact output: 24 V DC, max. 
50  mA  Control  Speech  button:  Microphone,  speaker  on‐off  control  by  speech  switch  Priority 
button: Microphone, speaker on‐off, other microphone cutoff, and single‐tone chime activation. 
a. Output  should  be  a  Headphone/Recording  of32  Ω  (headphone)/10  kΩ,  ‐20  dB*  (recording) 
unbalanced, mini jack (with VR). 
b. Internal speaker: 130 Ω, 200 mW 
c. Contact output: 24 V DC, max. 50 mA 
d. Control ‐ Speech button: Microphone, speaker on‐off control by  speech switch, Priority button: 
Microphone, speaker on‐off, other microphone cut‐off, and single‐tone chime activation. 
 
34. DELEGATE  UNIT:‐  Power  Source  35  V  DC,  under  30  mA  (supplied  from  Central  Unit)  Output 
Headphone/Recording: 32 Ω headphone)/10 kΩ, ‐20 dB* (recording),unbalanced, mini jack (with 
VR) Internal speaker: 130 Ω, 200 mW Contact output: 24 V DC, max. 50 mA Control Microphone, 
speaker on‐off control by speech switch Operating Temperature 0Ԩ to +40Ԩ (32゜F to 104゜F) 
Operating Humidity Under 90% RH (no condensation) 

PMC:NSL E 139  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

a. Power Source should be 35 V DC, under 30 mA. 
b. It  should  have  output  of  Headphone/Recording:  32  Ω  (headphone)/10  kΩ,  ‐20  dB* 
(recording),and unbalanced, mini jack (with VR). 
c. Internal speaker: 130 Ω, 200 mW. 
d. Device should have control Microphone, speaker on‐off control by speech switch. 
e. Case: ABS resin, black Panel: ABS resin, gray metallic, semi‐gloss, paint. 
 

35. LONG  MICROPHONE  UNIT:‐  Directivity  Unidirectional 


Rated  Impedance  1.8  kΩ  Rated  Sensitivity  ‐37  dB  (1  kHz  0  dB  =  1  V/Pa)  LED  Indicator  Speech 
indicator  (ring  type)  Frequency  Response  100  ‐  13,000  Hz  Output  Connector  Combined  type  of 
XLR‐4‐32 Finish Gooseneck: Stainless steel, black Other: ABS resin, black. 

a. Electret condenser microphone type. 
b. Unidirectional 
c. Rated Impedance should be 1.8 kΩ. 
d. Rated Sensitivity should be ‐37 dB (1 kHz 0 dB = 1 V/Pa). 
e. LED Indicator ‐ Speech indicator (ring type). 
f. Frequency Response should be 100 ‐ 13,000 Hz. 
g. Device should have combined type of XLR‐4‐32 output connector. 
 
 
36. EXTENSION  CORD:  ‐  Cable  Length  10  m  (32.81  ft)  Connector  8  pins  DIN  socket  pins  DIN  plug 
(going to the cord). 

a. Connector ‐ 8 pins DIN socket (going to the unit's base), 8 pins DIN plug (going to the cord). 
b. Cable Length ‐ 10 m (32.81 ft) or more. 
 
37. EXTENSION CORD:‐ Cable Length 2 m (6.56 ft) Connector 8 pins DIN socket pins DIN plug (going to 
the cord). 

a. Cable Length ‐ 2 m (6.56 ft). 
b. Connector ‐ 8 pins DIN socket (going to the unit's base), 8 pins DIN plug (going to the cord). 
 

38. REMOTE DELEGATE INTERFACE UNIT. Power Source 35 V DC, 30 mA or less Input ‐60 dB*, 200 Ω, 
balanced, mini phone jack with VR control Output ‐60 dB*, 22 Ω, balanced, mini phone jack with 
VR  control  Speech  Mode  AUTO:  Voice‐activated  Automatic  switching  MANUAL:  Talk  key  on‐off 
switching. 

a. Device should have input of ‐60 dB*, 200 Ω, balanced, mini phone jack with VR control. 
b. Device should have input of ‐60 dB*, 22 Ω, balanced, mini phone jack with VR control. 
c. Device should have auto and manual Speech Mode. 
d. VR control Speech Mode AUTO: Voice‐activated Automatic switching MANUAL. 
 

39. Sound  Reinforcement  (Audio)  System  ‐  Acoustical  Boundary  Microphone,  Embedded  Half 
Cardioids  Polar  Pattern,  Imp  220  ohms,  Condenser  Back  electrets  Transducer,  Omni  directional 

PMC:NSL E 140  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

Pickup pattern ,Extended Frequency response High sensitivity with low frequency roll off, can be 
fixed on the Conf. Table in the Circular Opening provided on the Central Table. 

a. Features  shall  be  amiable  half‐cardioids  polar  pattern,  High  gain‐before‐feedback,  Flat, 
wide range frequency response, High‐quality reproduction of speech. 
b. Unobtrusive  design  shall  be  Ceiling  or  tabletop  mounting,  fast  and  easy  installation 
Transducer type Condenser (back electrets), Operating principle Pressure gradient. Polar 
pattern Semi‐cardioids. 
c. Open circuit voltage at 1 kHz (0dB = 1V/Pa) 15 mV/Pa= ‐36.5 dab 
Nominal impedance 220 ohms, Load impedance = 1000 ohms, Connector 3‐pin XLRM 
d. Length  76/67  mm  Shaft  diameter  M  20  x  1.5  threads,  Head  diameter  30  mm,  Weight 
without cable approx. 70 g. 
e. Frequency response 40 ‐ 20,000 Hz, Max. SPL at 1 kHz 124 dB, S/N ratio rel. to 1 Pa 60 dB, 
A‐weighted equivalent SPL 26 dB. 
f. Power supplies 8 ‐ 52 V phantom power. 
g. Current consumption 3.4 MA. 
h. Sensitivity (at 1000 Hz) ‐60±3dB* (1mV)* 0dB=1V/μbar 
i. Attenuation switch shall be ‐10db 
j. Signal to Noise Ratio shall be 68db. 

40. WIRELESS SET (Hand Held) :‐ :Diversity wireless tuner Frequency Range 576 ‐ 865 MHz (*1), UHF 
Tone  Frequency  32.768  kHz  Operating  Temperature  ‐10  Ԩ  to  +50  Ԩ  (14  ゜F  to  122  ゜F) 
Accessory  AC  adapter  (*2)  …1,  Screw  driver  …1 
Microphone  holder  W3/8  (with  stand  adapter)  Wireless  microphone  Microphone  Element 
Electret  condenser  microphone  unit:  Unidirectional  Modulation  Frequency  modulation  Channel 
Selectable 64 channels RF Carrier Power Less than 50 mW Oscillator PLL synthesized Maximum 
Input Level 126 dB SPL Maximum Deviation ±40 kHz Audio Frequency Response 100 Hz ‐ 15 kHz 
Battery rechargeable battery (option) or AA alkaline dry cell battery. 

a. Frequency Range should be 576 ‐ 865 MHz (*1), UHF. 
b. Tone Frequency should be 32.768 kHz. 
c. Electret condenser microphone unit: Unidirectional. 
d. Frequency modulation 
e. Device should have 64 channels . 
f. RF Carrier Power should be Less than 50 mW (Factory preset 10 mW ERP). 
g. Oscillator should be  PLL synthesized. 
h. Maximum Input Level should be 126 dB SPL. 
i. Maximum Deviation should be ±40 kHz. 
j. Audio Frequency Response ‐ 100 Hz ‐ 15 kHz. 
k. Built‐in Antenna. 
 

41. WIRELESS SET (color Mic) :‐ :Diversity wireless tuner Frequency Range 576 ‐ 865 MHz (*1), UHF 
Tone  Frequency  32.768  kHz  Operating  Temperature  ‐10  Ԩ  to  +50  Ԩ  (14  ゜F  to  122  ゜F) 

PMC:NSL E 141  

 
Electrical: AV System Pharmacy Council of India, 3rd Floor, NBCC  Center,                   
                     Okhla, New Delhi 

Accessory  AC  adapter  (*2)  …1,  Screw  driver  …1 


Microphone holder W3/8 (with stand adapter) Wireless microphone Element Electret condenser 
microphone  unit:  Unidirectional  Modulation  Frequency  modulation  Channel  Selectable  64 
channels RF Carrier Power Less than 50 mW Oscillator PLL synthesized Maximum Input Level 126 
dB  SPL  Maximum  Deviation  ±40  kHz  Audio  Frequency  Response  100  Hz  ‐  15  kHz  Battery 
rechargeable battery (option) or AA alkaline dry cell battery. 

42. Rack  Structure  42  U  Air  Cooled  AV  Equipment  Rack  with  Two  Nos.  of  Vertical  Power  Strips, 
Cantilever Selves, Cable routing perforations, 4 No. of Spin Wheels. 
43. Rack  Structure  20  U  Air  Cooled  AV  Equipment  Rack  with  Two  Nos.  of  Vertical  Power  Strips, 
Cantilever Selves, Cable routing perforations, 4 No. of Spin Wheels. 
44. Rack  Structure  12  U  Air  Cooled  AV  Equipment  Rack  with  Two  Nos.  of  Vertical  Power  Strips, 
Cantilever Selves, Cable routing perforations, 4 No. of Spin Wheels. 
45. Cables  &  Connectors  with  Patch  Panel  Terminal  ‐  tin  Audio  /  Video  Cables  &  Connectors  with 
Accessories. 
a. The following specifications shall be adhered to for all AV Patch Panels installations. 
b. Laptop  VGA + 3.5mm inputs, 
c. Laptop w/Interactive Whiteboard  VGA + 3.5mm+USB inputs, 
d. Analogue A/V  Phono x 3 (R, W, Y) inputs, 
e. Digital A/V  HDMI input, 
f. Network/Data shall be 1 outlet per laptop connection, 
g. Power 240v  1 outlet per laptop or A/V connection. 
h. Foil  (Shielding)  shall  be  characterised  as  an  aluminium  foil  coating  around  a  cables 
conductor. 
 
 

PMC:NSL E 142  

 
Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

 
Technical Specification of ISDN & IP Ready EPABX System: 
 
1.  General Requirement:‐ 
 
a. The exchange shall be Integrated Services Digital Network & IP ready EPABX System of SPC type  
           PCM/TDM  based non‐blocking supporting ISDN and IP features for subscriber lines and trunks / tie‐ 
           lines/junctions and shall house all operating software in Flash‐ Memory or in HDD. 
 
b. The system shall have hot swappable peripheral cards. To replace any peripheral card, system shutdown  
           Should not be required. 
 
c. The system should support up to 672 ports. 
 
d. The system should have at least one port for External Music on Hold and background music. 
 
e. System should have built‐in fast modem (V.92 ITU‐T) up to 56Kbps for remote maintenance. 
 
f. System should have  a capacity of  50,000 BHCA (Busy Hour Call Attempts, a measure of a telephone  
          System’s ability to handle high traffic demands. 
g. System should be 19” Rack  mountable 
h. System should be RFI protected 
i. Should have simple Input/output (I/O) cable routing from the rear panel. 
 
2.  Architecture:‐ 
 
a. The  system  should  be  the  state‐of‐art  based,  software  controlled  and  should  switch  simultaneously 
Voice, 
           Data & Images without any degradation of service quality. 
 
b. The system shall be IP enable telecom server. The switch should support MGCP protocol  and Session  
           Initiation Protocol (SIP) for transmission of voice over IP network. It should also support G.711, G.723 &  
           G.729A encoding standards. The system should support IP Video Telephony. 
 
c. The system should support Q‐sig over IP. 
 
d. The IP Phone should support MGCP/SIP protocol. The same IP Phone should be configurable for MGCP  
           as well as SIP. 
 
e. The system should support IP extension as well as IP trunks also. 
 
o The system should support in skin DECT facility based on IP. 
 
o The system should have in skin Universal Gateway card. The Universal Gateway (UGW) card should 
function  as  internal  gateway  for  IP  station  sets  and  QSIG  inter‐PBX  networking.  Each  card  should 
provide the capacity to drive up to 240 IP endpoints regardless of their physical location and provides 

PMC: NSL E143


Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

full features to these ports. Voice calls maintained on the UGW should be carried out entirely on the 
network  when  both  ports  involved  are  IP  ports,  allowing  for  heavy  traffic  configurations.  These 
activities occur seamlessly within the stable environment of the PBX. The PBX system should support 
a  multitude  of  PUGW  cards  with  load  sharing  and  redundancy  capabilities  for  both  media  and 
signaling data streams. This card should support the following 
 
 Up to 240 IP phones 
 Should support  trunks (FXO): QSIG Net‐IP, analog trunks (loop start), SIP IP trunks 
 Should support  redundancy 
 Media channels ‐ load sharing 
 Complies with voice compression support in either G.711, G.723.1 or G.729 standards 
 Voice over IP standard: MGCP 
 Session Initiation Protocol Support — SIP 
 Full QSIG protocol transparency 
 Should support 3rd party IP phone and Video phoned (SIP) 
 
o System should be based on Universal port architecture and except for Common Control and Power  
           supply card. System should not impose any restriction in terms of slots usage for a particular functional  
           benefit 
 
o System shall work on 230 V AC or (‐) 48 Volts DC Power Supply with voltage varying between 42 to 58 V 
          and shall not need any proprietary charger or battery bank for the purpose. 
 
o The exchanges shall support Caller Line Identification for all ISDN & IP network subscribers including  
          analog subscribers and analog trunks. 
 
o     Analog line card should have loop resistance of  min. 1800 ohms 
 
o     It should be possible  to extend the digital phone to extend up to 6 K.M. on .5 mm copper cable 
 
o     Exchange should provide the caller id on analog extension as well as on analog trunks (CO lines) 
o  
 
o Exchange shall support following signaling Protocols: 
 
 ISDN PRI, R2MFC, CEPT 
 ISDN BRI 
 E&M (2/4 Wire) 
 Ring Down 
 DTMF 
 Loop Tie on DTMF 
 All the Common Signaling Standards adopted for ISDN / Non ISDN connections to PSTN 
 
o Exchange should have build in ACD functionality. Exchange should be upgradeable to CTI with direct  
          Ethernet Connectivity to LAN. 
 

PMC: NSL E144


Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

3.  System Facilities : 
 
o Abbreviated Dialing – The system shall be able to store at least 1000 lists of abbreviated dialing 
(AD).    The  AD  list  entry  size  &  maximum  AD  entries  per  system  shall  be  indicated  by  the 
manufacturer / supplier. 
o Integrated Directory 
o Call Coverage – The system shall automatically redirect calls to be covered by different coverage 
paths  and  at  different  times  of  the  day  and  days  of  the  week  to  the  other  voice  terminals  & 
messaging services where the calls can be answered.  The minimum number of coverage paths 
for automatic redirection of calls may be indicated by the supplier. 
o Conference – Three parties & Fourteen party conferences.  The system should have at least one 
14 party conference. It should also support up to 80 party single conference or 6 simultaneous 
conferences of 14 parties each. It should also possible to configure the conference in advance so 
that it can be used at any time. 
o Consultation hold 
o Ring Control – The system should be capable to have ringing preferences such as No Ring, Ring 
and Delayed Ring etc. 
o Flexible  Station  Move  –  The  system  should  give  complete  flexibility  to  dial  a  person  his 
identification number from any location & thus utilize all the facilities from that point. 
o Authorisation Codes – Codes shall be of 4 to 7 digits length. 
o Malicious Call Tracing – It shall be possible to identify malicious calls in case it is from CO, Tie or  
      Other outstation & provided the exchange. 
 
4.      DECT: 
The PBX must have inskin IP based DECT. Base stations should be connected to the PBX thru IP interface so that 
base  station  can  be  placed  at  several  locations.  It  should  also  possible  to  customize  multi‐site  solution  with  a 
number of single‐cell and multi‐cell solutions depending on the size of each individual location. The base station 
should support codec G.711 and G.729. The PBX should support up to 1500 wireless users. 
 
 
 TECHNICAL SPECIFICATION OF OPERATOR CONSOLE: ‐ 
The Operator Console should work only on two wires. 
a) Minimum 3 x 40 character LCD Display with adjustable Display 
b) 5 soft keys with Navigation buttons. 
c) Minimum 62 Programmable Keys for extension busy status, junction programming, feature  
          programming 
d) Message Waiting Indicator 
e) Incoming Speech Gain Control 
f) Hot Dial keypad 
g) Ringer Volume Control 
h) Should provide multiple ringing cadences for differentiating between ringing of 2 Key Telephones  
          placed nearby. 
i) Full speakerphone. 
j) Hot dial from keypad. 
k) Adjustable Handset and Monitor speaker volume with auto save. 
l) Monitor Speaker/On‐hook Dialling/ Background Music Selection/ Voice page. 
m) Message waiting indicator. 

PMC: NSL E145


Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

n) VIP Ringing Facility 
 
 
 
A) TECHNICAL SPECIFICATION of  Digital telephone  
 
Digital telephones shall have the following features: 
 LCD display of minimum 3 line and each line should have  20 characters 
 Dialed number and caller is identified by name, telephone number 
 Hands free operations through single key press 
 Volume control function 
 3 Soft keys for feature activation 
 Call log for missed and answered calls  (minimum 60 calls ) 
 Automatic call back display 
 Ringing tone control 
 Display of trunk name for external call 
 Ten numbers memory 
 Voice mail indicator 
 Single button abbreviated dialing for six numbers 
 Boss secretary feature 
 Programmable keys for feature operation 
 
Technical Specification for Passive LAN Copper & Fibre cable 
 
Category 6 UTP Cable, 4 Pair CM rated, with LSZH  
 
Characteristic  Min. Required Specification 
  Category 6 Unshielded Twisted Pair  
100ohm  cable  shall  be  compliant  with  EIA/TIA  568‐C.2 
transmission performance specifications. 
Category 6 UTP cables shall extend between the work area 
location and its associated telecommunications closet and 
consist of 4 pair, 23 AWG, UTP  
The 4 pair Unshielded Twisted Pair cable shall be UL Listed  
 
Conductor: Solid Copper  
Conductor Diameter: 0.57±0.005mm (23 AWG only)  
Insulator Polyolefin  
Jacket: LSZH (Low Smoke zero Halogen) 
Outer Diameter: 6.0±0.4mm  
Filler: PE  
Weight (kg/km): 42  
Fire performance ‐ 332.1  
NVP (%): 68  
Insulation Dia. (±0.05mm): 1.04  

PMC: NSL E146


Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

Insulator Polyolefin  
Third party certificate for IEC 60332‐3‐22:2009   needs to 
submitted along with technical  bid is mandatory 
 
 
6 Core Outdoor Unitube Single Sheathed Armoured 50/125μm OM3 Type 
 
Min. Required  Specification 
Features: 
 
Cable containing   6 optical fibres in water blocked one  
loose tube, taped, corrugated steel tape armoured (STA) 
polyethylene (HDPE) outer sheathed embedded with two 
steel wires on the periphery 
 
 
 
Number of elements :             5 
Tube Idenification :                 Single tube 
Fibre Protection(Tube) :          Polybutylene Terephthalate (PBT) 
Water Blocking :                      Thixotropic Gel (Tube) 
                                                Petroleum Jelly (Interstices) 
Core Wrapping :                       Polyethylene Terephthalate 
Armouring :                               Corrugated Steel Tape Armour 
                                                   (ECCS Tape) 
Peripheral Strength Member:      Two GI Steel wires only 
Sheath :                                        UV Stabilised Polyethylene (HDPE) 
 
 
 
Technical Specifications 
Attenuation; 
At 850 nm:   3.0 dB/km 
At 1300 nm:   1.0 dB/km 
 
Min. Bandwidth; 
At 850 nm:   2000 MHz 
At 1300 nm:   500 MHz 
 
 
Dimensions and Mass 
Overall Cable (Nominal) :   9.8 mm 
Mass (Nominal) :     95 kg/km 
 

PMC: NSL E147


Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

 
Mechanical and Environmental Performance 
 
Max. Bending Radius (during installation) :   20 X Overall diameter 
Max. Bending Radius (during full load) :  10 X Overall diameter 
Max. Tensile Strength‐Short Term :     1500N 
Max. Crush Resistance‐Short Term :   2000N/10 cm 
Operating/Storage Temperature range :  ‐40°C ‐+70 
Mode Field Diameter @ 850nm :     50 + 3.0 μm 
Cladding Diameter                      :    125 + 2.0 μm 
 
Physical Characteristics 
Mode Field Diameter @ 850nm : 50 + 3.0 μm 
Cladding Diameter   :         : 125 + 2.0 μm 
 
Certifications 
ISO.IEC 11801 ‐ 2nd Edition, type OM3; AS/ACIF S008; 
AS/NZS 3080 
 
 
(ii)  FIBER PATCH PANELS – RACK MOUNT 
Characteristic  Min. Required Specification 
  Have  sufficient  slots  accommodate  duplex  SC  adapters 
individually. 
Should have fiber management provision inside 
Have earthing plugs and other accessories. 
Panel cover should be slide out for easy maintenance 
Provide  self‐adhesive,  clear  label  holders  (transparent  plastic 
window type) and white  designation labels with the panel, for 
front panel labeling. 
Should be upgradeable as Intelligent Patch Panel without 
changing the existing Patch Panel hardware by simple retro 
fitting of intelligent sensors as and when required. 
 
(iii)  SC DUPLEX ADAPTORS 
Characteristic  Min. Required Specification 
Features  All SC adaptors should be duplex type with shutter for 
protection.  Adapters should be snap mount for easy insertion 
and removal.  

PMC: NSL E148


Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

 
(iv)  Optical Fiber Pigtails (SC) 
Characteristic  Min. Required  Specification 
Features  _ Standard or custom assemblies 
_ Precision ferrule endface geometry 
_ Controlled fibre protrusion 
_ Factory polished, tested and serialized. 
Connector End : 1xSC connectors, singlemode, 
zirconia ceramic ferrule, 
composite body 
Insertion Loss : 0.35dB max. 
Retention Strength : 100N 
Operating Temperature : ‐10°C to 60°C 
Cable Sheath 
Material : PVC/LSZH 
Colour : Random 
Characteristics 
Cable : 900μm Buffered 
Outside Diameter : 900μm 
Buffer Diameter : 900μm tight buffer 
Min. Bend Radius : 30mm 
Attenuation : 
@ 850nm <2.5dB/km 
@ 1300nm <0.7dB/km 
 
(v)  Optical Fiber Patch Cords (3 Mtr.) 
Characteristic  Min. Required  Specification 
Features  All optical fiber patch leads shall comprise of Multimode mode 
50/125µm fiber with SC, fiber connectors terminated at each 
end. The optical fiber patch leads shall comply with the 
following specifications:  
Connector: Zirconia ceramic ferrule 
Pre‐radiuses and pre‐polished ferrule 
Sheath ‐  LSZH Jacket 
Epoxy type fiber encapsulation 
Color‐coded connector boots fitted to connectors on duplex 
patch leads.   

PMC: NSL E149


Electrical: EPABX Pharmacy Council of India, 3rd Floor,NBCC
Center, Okhla, New Delhi

Dust caps shall be fitted on each connector at the assembly 
Cable:  50/125, OM3 
Strength member:  aramid yarn 
Bandwidth : 
@ 850nm 2000MHz/km 
@ 1300nm 500MHz/km 
Attenuation : 
@ 850nm <2.5dB/km 
@ 1300nm <0.7dB/km 
 

PMC: NSL E150


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
 
 
 
 
 
 
 
 
 

 
 
 
SPECIFICATIONS FOR HVAC 
SECTION B3 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                     

PMC: NSL
CONTENTS
1. SECTION- 01
Special Conditions for submission of Tender

2. SECTION -02
Appendix to the Conditions of the Contract

3. SECTION -03
Design Parameters

4. SECTION -04
Standard Specifications

5. SECTION -05
Noise & Vibration Controls

6. SECTION -06
Standard Specification of VAV Boxes

7. SECTION -07
Standard Specification of Thermal/Acoustic Insulation

8. SECTION -08
Standard Specification of Air Circulation System

9. SECTION -09
Standard Specification of Electrical Motors & Starters

10. SECTION -10


Standard Specification of Motor Control Center,
Sub-Panels, Power & Control Cabling

11. SECTION -11


Modes of Measurement

12. SECTION -12


Painting Work

13. SECTION -13


List of Approved make of Equipment / Materials

14. SECTION -14


Basis of Design and Scheme

15. SECTION -15


Associated Civil / Electrical & other Works
(To be provided free of cost to AC Contractor)
SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
Schedule of Equipment

16. SECTION -16


Standard Specifications of Variable
Refrigerant Volume System

17. SECTION -17


Standard Specifications of Indoor Unit

18. SECTION -18


Standard Specification of Refrigerant Piping Work

19. SECTION -19


Standard Specification of Schedule of Equipment’s

20. SECTION -20


Technical Data
(To be furnished by AC Contractor)

21. SECTION -21


Bill of Quantities

PMC: NSL HVAC 2


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION - 01
SPECIAL CONDITIONS FOR SUBMISSION OF TENDER

CENTRALISED LOW SIDE AIR CONDITIONING WORK FOR PHARMACY


COUNCIL OF INDIA, NEW DELHI-110002

1. INTRODUCTION :-

DEVELOPER SCOPE:-

i) Existing 2X13000CFM Air Handling Units with Chilled water piping & Valves.

PHARMACY COUNCIL OF INDIA SCOPE:-


LOW SIDE AIR CONDITIONING SYSTEM SHALL BE COMPRISED OF
FOLLOWING ITEMS:-

i) Non VRF 4# 2TR DX type Hi-Wall Unit for UPS & Server Room (1w+1s)

ii) VRV Type 7# 3.18TR Cassette Units for President Cabin, Secretary Room,
meeting room and cabin

iii) 1X20HP Outdoor Units VRF Type (cooling & Heating both)

iv) VRV Type 2#2.0 TR Cassette Units for V.P Room and cabin

v) Main intelligent controller for VRF & Timer for Non VRF to work the system
24 x7 automatically.

vi) Insulated Refrigerant piping for above units

vii) VAV box with sound attenuator to control air volume.

viii) GSS rectangular ducting for air conditioning system

ix) Duct insulation & lining.

The detailed quantity for air-conditioning work & its connected accessories shall be as
per detail mention in the SECTION- 21 Bill of Quantities

2. LIST OF DRAWING:-

Ac layout Plan HVAC -01

PMC: NSL HVAC 3


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
3. OWNER AND ARCHITECT/CONSULTANT

The addresses of the Owner and of the Consultant responsible for the preparation of the
Contract Agreement/Documents are as follows:-

THE CLIENT M/S PHARMACY COUNCIL OF INDIA

THE PMC M/S NBCC, NEW DELHI

THE ARCHITECT M/S ENABLE CORPORATION ARCHITECTS & ENGG

THE AC M/S GSP DESIGN CONSULTANT


CONSULTANT

4. SITE

The site is located at PHARMACY COUNCIL OF INDIA, COMBINED


COUNCIL’s BUILDIND, KOTLA ROAD, AIWAN-E-GHALIB MARG, NEW
DELHI-110002

5. SCOPE OF WORK
The scope of work to be carried out under this contract comprises of the Air-conditioning
system for PHARMACY COUNCIL OF INDIA as NEW DELHI called for in the
Tender Documents. The contractor shall carry out and complete the work under this
contract in every respect, in conformity with the stipulations of the Bureau of Indian
Standards and with the directions of and to the satisfaction of the Architect / Consultant /
Owner. The contractor shall furnish all lab our, materials, appliances, equipment,
installation, testing and commissioning of the whole air-conditioning system as specified
herein and shown on drawings. This also includes any materials, appliances, equipment and
incidental work not specifically mentioned herein or noted on the Drawings/Documents,
but essential for ensuring a properly connected installation in good working order. The
work shall include all incidental jobs connected with air-conditioning installation such as
laying cables, drilling holes through walls and floor and making good and grouting of
equipment etc

The scope of work to be carried out as described above and briefly listed below shall
include supply, installation, testing and commissioning of :

a) Air distribution ducting, grilles & Diffusers.


b) Rectangular Ducting as per AC Layout Plan
c) Aluminum Extruded Grills
d) Any Other miscellaneous Work

6. SHOP DRAWINGS

PMC: NSL HVAC 4


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
On the award of the work, the Contractor shall immediately proceed with the preparation
of Detailed working drawings showing the detail of the equipment that are to be installed
and the ancillary works that are to be carried out.
Within Two weeks after award of work Contract, the Contractor shall submit the shop
drawing for the approval of the Consultant, two sets of detailed shop drawings of all
equipment and materials including piping layout, and wiring layouts required to complete
the project as per Specifications and as required by the Consultant. These Drawings
shall contain details of construction, size, arrangement, operating clearances,
performance characteristics, and capacity of all items of equipment, as also the details of
all related items of work by other contractors.

If the Consultant makes any amendments in the above drawings, the Contractor
shall supply two fresh sets of drawings with the amendments duly incorporated,
along with the drawings on which corrections were made. After final approval, the
Contractor shall submit a further 4 sets of shop drawings for the exclusive use of
and retention by the Consultant.

b. The shop drawings shall be submitted for approval sufficiently in advance of planned
delivery and installation of any material, to allow Consultants ample time for scrutiny.
No claims for extension of time shall be entertained because of any delay in the work due
to his failure to produce shop drawings at the right time.

c. Samples, drawings, specifications, catalogues, pamphlets, and other documents submitted


for approval shall be in quadruplicate, each item in each set shall be properly labelled,
indicating the specific service for which material or equipment is to be used, giving
reference to the governing section and clause number of Specifications.

d. Approval rendered on shop drawings shall not be considered as a guarantee of


measurements or of building conditions. Where drawings are approved, said approval
does not mean that drawings have been checked in detail nor does it in any way relieve
the contractor from his responsibility or necessity of furnishing material or
performing work as required thereof, shall be prepared by the Contractor at his own
cost and approved by the Consultant.

e. Where the work of the Contractor has to be installed in close proximity to, or will
interfere with work of other trades, he shall assist in working out space conditions to
make satisfactory adjustments. If the contractor installs his work before co-coordinating
with other trades, or so as to cause any interference with work of other trades, he shall
make all the necessary changes without extra cost to the Owner.

The following shop drawings shall be prepared by the AC contractor for approval

a) AC Ducting Layout Plan

b) Chilled Water Layout Plan

PMC: NSL HVAC 5


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
c) Schematic layout Plan

d) MVAC Electrical panel, power & control wiring drawings.

e) Any other shop drawings necessary for the project.


7. AS BUILT DRAWINGS
At the completion of work and before issuance of certificate of virtual completion the
contractor shall submit Four (04) sets to the Engineer-in-charge, layout drawing drawn at
appropriate scale indicating the complete MVAC system “as installed”.

The tender is to be submitted in DUPLICATE in the separate sealed cover in the


following format:

a) The tenderer shall submit the offer in Duplicate sealed two separate sealed covers duly
complete in all respects viz. Technical cum Commercial Bid & Price Bid for the above
work. The Technical cum Commercial Bid & Price Bid shall be submitted
simultaneously..

b) The Technical Bid shall be complete with the following :


 Deviation, if any from N.I.T. specifications.
 Complete technical data duly filled as per Performa enclosed.
 A set of leaflets of all the equipments offered.
 Makes considered for equipments& accessories.
c) The price bid in a separate sealed cover shall be in the same format as in the tender
papers supplied by the consultant/client

8. INSTRUCTION / MAINTENANCE / OPERATION MANUAL

The Contractor shall prepare and produce instruction, operation and maintenance
manuals in English for use, operation and the maintenance of the supplied equipment and
installations, and submit to the Owner (03) three copies at the time of handing over. The
manual shall generally consist of the following:
a) Description of the Project.

b) Operating instructions.

c) Maintenance instructions including procedures for preventive maintenance.

d) Manufacturers catalog.

e) Spare parts list.

f) Trouble shooting charts.

g) Drawings.

PMC: NSL HVAC 6


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

h) Type and routine test certificates of major items.


One (1) set of reproducible ‘as built’ drawings.

9. PRICES, UNIT RATES & DUTIES ETC

9.1 The prices and unit rates quoted by the bidder in the bid shall be firm and deem to be
adequate to cover the entire responsibility involved in the execution and completion of
work. The rates shall be complete in all respects including cost of materials, erection,
fabrication, labour, supervision, tools and plant, transport, contingencies, breakage,
wastage, sundries, scaffoldings, insurance etc. on the basis of works contract.
9.2 The contract value shall be inclusive of custom duty, CVD etc on Imported
Equipment’s (fans Motorized valves etc.) & inclusive of excise duty, local sales tax
on indigenous Equipment’s/Materials and inclusive of octroi, VAT duty or any
other duties or fees levied by government or any public or local bodies as applicable
in state of New Delhi
Please indicate separately the assessable value & quantum / rate of excise duty included
on each excisable refrigeration equipment separately in your price bid.

The AC contractor shall include the cost of supply, installation, testing, commissioning
of imported & indigenous equipment’s from port to site, insurance up to commissioning
at site etc. as required in Indian Rupees.

ASSUMPTION 1 US $ Exchange Rate = Rs.64.81

9.3 The contract value shall remain firm during the currency of the contract and shall be
subject to statutory variation in sales tax on works contract or on rate of custom duty /
excise duty applicable on refrigeration equipment’s only. In case assessable values are
increased by the manufacturer of refrigeration equipment during the currency of contract,
the client shall not pay any increase in quantum of excise duty on account of change in
assessable value. No increase in prices due to change of rate of excise duty on bought out
items such as G.SS, M.S. angles / flats, motor, cables, controls etc., shall be paid. No
increase due to change in daily wages of labour be paid, due to any reasons whatsoever.

9.4 The total contract price quoted by the bidders shall be inclusive of all taxes & duties as
applicable in this state & TDS shall be deducted by the Client at source & certificate shall
be issued for the same. The works contract price quoted shall remain firm till completion
of job and handing over the same in working condition to the client.

9.5 The price should not be subject to exchange rate variations. No foreign exchange and
license shall be arranged by the Client and it shall be contractor’s responsibility to do so,
if required.

9.6 The rates quoted shall be deemed to allow for all minor extras and constructional details,
which are not specifically shown on drawings or given in the specifications but are

PMC: NSL HVAC 7


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
essential in the opinion of the Owner / Consultant / Architect for the execution of works
to con-form to good workmanship and sound engineering practice.

9.7 The Owner / Consultant / Architect decision to clarify any item under minor changes,
minor extras and constructional details shall be final, conclusive and binding on the
Contractor.

9.8 The rates quoted by the Contractor shall be net so as to include all the requirements
described in the contract agreement and no claim whatsoever due to fluctuations in the
price of materials and labour will be entertained.

9.9 In case the rates of identical items under different sub-heads / parts are different, the
lowest of these will be taken for the purpose of making the payments.

9.10 The contractor shall provide all equipments, instruments, labour and such other assistance
required by the Owner / Consultant / Architect for measurement of the works, materials
etc.

10. VARIATION IN QUANTITIES & TENDER DRAWINGS:

The quantities for ancillary works given in the schedule and / or in drawings are for the
guidance of the tenderer. The contractor shall be paid on the basis of actual quantities of
works carried out. However the contractor shall check these quantities before quoting and
will bring to the notice of Owner / Consultant / Architect for any major variation. MVAC
drawings issued with the tender are diagrammatic only and indicate the general
arrangement only. The data given in the drawings and specifications is as exact as could
be secured, but its accuracy is not guaranteed. Contractor shall carry out his own
computations and provide all such equipment, as required to achieve the specified
conditions. The contract shall be on works contract basis and the Client reserves the right
to add / delete any items of work during the currency of contract.
The price variation shall be permitted only if the actual quantities differ from the
quantities given in the document to and not exceeding 5% of the value of that item
limited extent for the following items:-
a) Ducting / duct lining / duct insulation etc.

b) Insulated Chilled Water & drain piping for AC system

c) Powder coated Aluminum Extruded Grills / diffusers.

c) Power & control cabling.

11. PERFORMANCE BOUND CONTRACT

The contract will be a performance bound contract and therefore the Bidder shall make
their independent check for Heat Load, selection of equipment’s etc. The drawings
enclosed with the tender documents shall be only tentative layout plans and for guidance

PMC: NSL HVAC 8


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
purpose only. The detailed shop drawings shall be prepared and submitted for approval to
the Owner / Consultant / Architect.
The contractor shall guarantee the specified inside condition at specified outside
condition considering the fresh air as detailed in the basis of design of the tender
documents. The contractor shall guarantee that the capacity of various components as
well as the whole system shall be within ± 3% of the specified capacity.

12. GUARANTEE

The contractor shall guarantee the complete AC system for a period of 12 months of the
date of handing over the plant after successful initial testing & one major seasonal test i.e.
either summer or monsoon whichever is earlier during guarantee period. Or 18 months
from date of delivery of major equipment’s The Tenderer shall guarantee the AC system
to maintain space conditions as specified in SECTION -14, Basis of Design / Scheme.
They shall also guarantee that the performance of the various equipment’s individually
and jointly shall be within ± 3% of the specified ratings when working under operating
conditions for the complete installation.

During guarantee period loss of refrigerant and oil, if any shall be borne by the air-
conditioning contractor. De-scaling, if required during the guarantee period, shall be done
by air-conditioning contractor free of cost if certified by OWNER.

13. REPAIRS / REPLACEMENT OF PARTS DURING GUARANTEE

Any defects or other faults which may appear within defect liability / guarantee period of
twelve months from the date of handing over the plant in a satisfactory working
conditions to the Client (except for normal wear and tear) arising in the plant from
material or workmanship not in accordance with the contract specification will be
rectified by the contractors free of cost & nothing shall be paid extra on any account.

14. TESTING
All testing instruments, velocity meter, digital thermometer, pyschrometer, measuring
steel tapes, tools, scaffolding and ladders etc. that may be required for taking
measurements shall be arranged by air-conditioning contractor at his own cost.
All types of routine and other tests shall be carried out at the works of the Contractor or
the manufacturers of the components and the before dispatch The Client shall be free to
witness any or all tests, if they so desired. The Contractor has to inform to the Client
before dispatch of any material / equipment.
On the completion of the installation the Contractor shall arrange to carry out various
initial tests as detailed below, in the presence of Owner / Consultant / Architect and to the
entire satisfaction of the Owner / Consultant / Architect. Any defect or short-coming
found during the tests shall be speedily rectified or made good by the Contractor at his
own expenses.

15. The initial tests shall include, but, not be limited to the following:

PMC: NSL HVAC 9


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

a) To operate and check proper functioning of all electrically operated components viz.,
pumps, fan of indoor units etc. as well as other electrical motors.

b) To test and check the proper functioning of electrical gears, safety and other
controls to ensure their proper functioning.
c) To check & balance the air distribution system and to provide designed air flow in all
areas by adjusting the grills, diffusers and dampers for air-conditioning.

d) To check & balance / adjust the refrigerant flow in the circuit for smooth and
noiseless flow.

f) To check the systems against leaks in different circuits, alignment of motor, ‘V’ belt
adjustments, control setting and all such other tests which are essential for smooth
functioning of the plant.

g) Contractor shall have to submit the capacity test of all equipment at site.

g) On the satisfactory completion of all ‘Initial’ tests & one major seasonal test i.e.
either summer or monsoon the plant shall be considered ‘virtually Complete’ for the
purpose of taking over by the Client.
h) In addition to the ‘Initial’ test the Contractor shall also give summer, monsoon &
winter tests of the plant, each of (3) three days duration, and each one during the full
specified outside conditions (when the ambient conditions are close to the specified
ambient conditions). The first running test may be taken on the completion of the
initial test, provided the ambient temperature and humidity are near their peak. Inside
condition as per the contract, performance of each equipment, Airflow etc. shall be as
per the requirement of the contract during these tests.
It is clarified that guarantee period shall start after successful completion of one major
test i.e. either summer or monsoon for all equipments & inside temperature in the
working area if any.

16. LIQUIDATED DAMAGES CLAUSE

Liquidated damage shall be 0.5% of the contract sum per week of delay subject to a
maximum of 5% of total contract value, in case the work is not completed to our
satisfaction, within the stipulated period. The sum indicated above is by way of liquidated
damage and not as penalty during which the work remain un-commenced or unfinished
after the expiry of completion date.
17. OPERATION OF PLANT

The tenderer shall arrange to operate the plant for a period of ONE MONTH from the
date of commissioning of plant and successful completion of initial test free of cost.

PMC: NSL HVAC 10


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
18. TRAINING OF PERSONNEL
The contractor shall impart training to the minimum three technical staffs appointed by
the Client free of cost during erection and commissioning of the plant also trained
operator should be available for 15 days.

19. WEEKLY PROGRESS REPORT

A weekly progress report of site shall be submitted in writing to the Owner / Consultant /
Architect.

20. INSPECTION & TESTING

All major imported & indigenous equipments such as AHU units, electrical panels,
remote controls etc. may be got inspected & tested before dispatch if desired by the client
at the manufacturers work.
The manufacturer of these equipments must have a facility of testing the equipments at
especially the on test bed on full load and partial load at their works. All the test readings
mutually taken shall be recorded & evaluated with the technical data furnished by the AC
Contractor.
21. STORAGE OF MATERIALS / EQUIPMENTS

Plant room, if ready can be used for storage of materials / equipment brought to site by
the contractors. Watch and ward of the same shall be the contractor’s responsibility. In
case the plant room space is not readily available, it shall be contractor’s responsibility to
make his own temporary structure at site with approved location from the client at his
own cost.

22. POWER SUPPLY & CIVIL WORK

Electricity for erection purposes shall be provided to the AC Contractor at one point only.
On payable basis. All Type of civil work such as wall opening & making goods etc done
by the AC Contractor. However power required for testing & commissioning shall be
provided by the client.
23. INSURANCE
The contractor shall be responsible for the storage and safe custody of all equipment /
materials brought to site from time to time till the plant is taken over by the department.
The contractor may provide adequate and comprehensive insurance coverage for storage
and execution.
The contractor shall be responsible for all the injury or damage to persons, buildings,
structures, property etc., which may arise form any act of omission on part of the
contractor or his servants or sub contractors or his employee etc. The contractor shall
indemnify and keep indemnified the owner and hold him harmless in all respects of and
any expenditure liability, loss, claims or proceeding arising from any such injury or
damage to persons or property as aforesaid.

PMC: NSL HVAC 11


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
The contractor may undertake all risk policy including earthquake risk with an insurance
company approved by the owner in the joint names of owner and contractor at his own
expense.
24. QUIET OPERATION AND VIBRATION

All work shall operate under all conditions of load without any sound or vibration which
is objectionable in the opinion of the Consultant. In case of moving machinery sound
or vibration noticeable outside the room in which it is installed, or annoyingly
noticeable inside its own room, shall be considered objectionable. Such conditions
shall be corrected by the Contractor at his own expense.

25. ACCESIBILITY

The Contractor shall verify the sufficiency of the size of shafts and openings of clearance
in cavity walls and suspended ceilings for the proper installation of his equipment and
piping. His failure to communicate insufficiency of any of the above shall constitute his
acceptance of sufficiency of the same. The contractor shall locate all equipment which
must be serviced, operated or maintained in fully accessible positions. The exact
location and size of all access panels required for each concealed control, damper,
valve or other devices requiring service shall be finalised and communicated in
sufficient time, to be installed in the normal course of work; failing which, the
Contractor shall make all the necessary repair and changes at his own expense.
26. BALANCING, TESTING AND COMMISSIONING
Balancing of all systems and all tests as called for in the Specifications shall be carried
out by the Contractor in accordance with the Specifications, the relevant Indian Standard
Specifications and recommendations of the American Society of Heating Refrigeration
and Air-conditioning Engineers (USA). Test results for summer and monsoon cooling
shall be tabulated in approved manner and four copies shall be submitted to the
Consultant for his scrutiny. Four copies of the certified manufacturer’s performance
curves for each piece of equipment shall be submitted along with the test results.
The contractor shall also provide to the Consultant four copies of record of all safety and
automatic control settings for the entire installation. The contractor shall pay for and
arrange, without any extra cost to the Owner, all necessary balancing and testing
equipment, instruments, materials, accessories, power, water and the requisite labour. The
installation shall be tested again after removal of defects and shall be commissioned only
after approval by the Consultant.
All tests shall be carried out in the presence of the representatives of Consultant.

27. COMPLETION CERTIFICATE


On completion of the installation, a certificate shall be furnished by the Contractor,
countersigned by the licensed supervisor, under whose direct supervision the installation
was carried out.

28. COMPLETION DRAWINGS


On completion of the work in all respects, the contractor shall supply to the Consultant
four (4) complete sets of drawings, on approved scale, indicating the work as installed.

PMC: NSL HVAC 12


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
These drawings shall clearly indicate the complete plant room layouts, piping layouts,
location of wiring, exact location of all concealed piping, valves, controls, wiring
and other services. The Contractor shall also submit four (4) sets of consolidated
control diagrams, technical literature on all automatic controls and complete technical
literature on all equipment and materials.

29. SITE ENGINEER


AC Contractor shall appoint one experienced Site Engineer dedicated at site for
Supervision. The Site Engineer will be approved by client and experience and
qualification of the site Engineer to intent the client / Consultant.

All technical data to be filled by the bidders in SECTION -20 shall be accepted in
metric system only unless specifically asked for any bidder submitting the technical
data in any other unit would render his bid liable for rejection. The
Technical data should be typed in capitals only.

END OF SECTION – 01

PMC: NSL HVAC 13


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION -02
APPENDIX-I
GUARANTEE PROFORMA

GUARANTEE FOR YEAR - ROUND HVAC SERVICES


We hereby guarantee that the entire MVAC system which we have installed in the building as
described below:

Site: PHARMACY COUNCIL OF INDIA 5TH FLOOR

Location: NEW DELHI

Client: M/S PHARMACY COUNCIL OF INDIA

for a period of one year from this date, the date of acceptance of the installation. WE AGREE
to repair or replace to the satisfaction of the owner, any or all such work that may prove
defective in workmanship, equipment, or materials within that period, ordinary wear and tear and
unusual abuse or neglect excepted, together with any other work which may be damaged or
displaced in so doing. In the event of our failure to comply with the above mentioned conditions
within a reasonable time, after being notified in writing, we collectively and separately, do
hereby authorize the Owner to proceed to have the defects repaired and made good at our
expense, and shall pay the cost and charges thereof immediately upon demand.

We also hereby UNDERTAKE to test the installation, following the completion of the
installation, to check and do everything necessary to ensure that all systems (as applicable in
contract) are properly balanced, that all controls are calibrated accurately, and that all units and
peripheral controls are functioning satisfactorily, balance the air flow and to test the capacity of
the equipment, check the power consumption and noise level and ensure that all the controls and
instruments contained in System are functioning satisfactorily.

Signature of the Contractor for


Year-round MVAC Services

SEAL:

DATE: ____________________

PMC: NSL HVAC 14


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

APPENDIX-II
CONDITIONS OF CONTRACT

1. SUBMISSION OF TENDER
Complete tender duly filled in duplicate as mentioned above shall reach to following
Address on ------------ before 13Hr.
------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------

2. TERMS OF PAYMENT:-

 10% Mobilization Advance of the contract value.

 10 % against prorata submission of shop drawings as required.

 65% prorata on delivery of material / equipment at site..

 05% prorata on completion of installation.

 Balance 10% of total contract price including high and low side on testing &
commissioning against bank guarantee valid for a period till the end of defect
liability period.

3. COMPLETION PERIOD : Three month from the date of work


order

4. VALIDITY OF TENDER : 30 days from the date of submission

5. LIQUIDATED DAMAGE CLAUSE : 0.5 % per week of delay subject to a


Maximum of 5% of the total contract
value
As per point 15 Liquidated damages,
Of SECTION -01

END OF SECTION - 02

PMC: NSL HVAC 15


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION -03
DESIGN PARAMETERS

1.00 Given below are some design parameters which should be followed in addition to those
given in various sections of technical specifications enclosed.

1.01 AIR - HANDLERS


a) Maximum Face velocity across cooling coil MPM : 152.0
b) Maximum face velocity across pre-filters MPM : 152.0
c) Maximum water pressure drop across the coil in Mt. : 4.6
d) Maximum water velocity through coil in MPS : 2.5
e) Fan outlet velocity (maxm.) MPS : 10.0

1.02 DUCTING WORK


a) Method of Duct Design : Equal friction
Method
b) Maximum air velocity in supply duct MPM : 365.0
c) Maximum air velocity in return duct MPM : 305.0
d) Friction loss in duct ( maxm.) MM Wg in 100 Mt run. : 8.33
e) Maximum Velocity at supply air grill outlet MPM : 150.00

1.03 INSULATION
Maximum temperature rise in the supply air duct from Air-handlers outlet to farthest
outlet in 1.1 ºC.

END OF SECTION -03

PMC: NSL HVAC 16


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION -04
STANDARD SPECIFICATION

1.1.1 SCOPE OF WORK

The complete scope of work shall cover supply, erection, testing and commissioning of
the entire MVAC system as detailed under specification.

1.1.2 BASIS OF DESIGN


The entire system has been based and designed on climatologically data available as
given under Basis of Design and Scheme.

1.1.3 TERMS AND DEFINATIONS


The followings terms have been used in the tender specifications, drawings etc.

ISI Bureau of Indian Standards.

ASHRAE American Society of Heating Refrigeration & Air-conditioning


Engineers, USA.

ASME American Society of Mechanical Engineers.

ASA American Standard Association.

B.S. British Standards.

CMH Cubic Meter per Hour.

US GPM US Gallons per minute.

IGPM Imperial Gallons per Minute.

RPM Revolutions per Minute.

BTU/Hr. British thermal unit per Hour.

Kcal/Hr. Kilo Calories per Hour.

HZ Hertz.

H.P. Horse Power

Kg/Cm2 Kilo Gram per Square Centimeter.


SAG Supply Air Grills.

SAD Supply Air Diffuser.

PMC: NSL HVAC 17


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SAF Supply Air Filters.

FD Fire Damper.

VCD Volume Control Damper.

RAD Return Air Damper.

FAD Fresh Air Damper.

RH Relative Humidity.

DB Dry Bulb Temperature.

WB Wet Bulb Temperature.

MV Mechanical Ventilation.

DP Drain Point.

1.1.4 The codes, regulation as detailed below shall be followed in this contract:-

1. Safety code for air-conditioning


(Revised) amendment 1 IS 659: 1964 (reaffirmed 1991)

2. Safety code foe mechanical


Refrigeration IS 660: 1963 (reaffirmed 1991)

3. Testing of refrigeration
Compressors IS 5111: 1993

4. Air-cooled heat exchangers IS 10470 : 1983


(Amendment 1) (Reaffirmed 1991)

5. Packaged Air-conditioner IS 8148: 1976


(Amendment 1991) (Reaffirmed 1991)

6. Hermetic compressors IS 10617: Part I, II & III 1983


(Reaffirmed 1991)

7. Suppliers data sheet for clean IS 12357: 1998


Air equipment (laminar flow)

8. Thermostats for use in IS 11338: 1965


Refrigeration etc. (Reaffirmed 1991)

PMC: NSL HVAC 18


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

9. Code of practice for design and IS 11338: 1965


Construction of flue chimneys. (Reaffirmed 1991)

10. Metal Duct Work IS 655: 1963 (reaffirmed 1991)

11. Steel for general structural IS 2062: 1992


Purpose

12. Piping Work IS 1239 Part I & II 1990 / 1992


IS & BS: 3601

13. Welding IS: 3589

14. Refrigeration as per ASHRAE / ISI


Air-conditioning & Refrigeration
Air-conditioning institute Standards.

15. Hot Dip Zinc Coated Steel Tubes IS 4736: 1968

16. Gate Valves for Water lines IS 778: 1980

17. Copper Alloy Gate Globe Check IS 778: 1980


Valve for water lines

18. Butterfly Valve IS 13095: 1991

19. Steel Pipe flanges IS: 6392

20. Gaskets IS 638: 1979 (reaffirmed 1993)

21 Mild steel tubes & fittings IS 1239 Part I & II

22. Dual plate Check Valve for AP: 194


Water Lines

23. Color code for the identification IS 2379: 1963


Of pipe lines

24. Specific requirements for the IS 4064 (Part II) 1978


Direct switching of the individual
Motors.

25. PVC insulated (HD) Electric IS: 1554 (Part I)


Cables for working voltage up
Including 1100 Volts

PMC: NSL HVAC 19


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

26. HRC Cartridge fuse links IS 2208: 1976


Up to 650 Volts.

27. Starter IS 8554 (Part I) 1979

28. Inspection and testing of IS 732 (Part III) 1979


Installation

29. Galvanized steel wire for fencing IS 277: 1977

30. Three phase induction motors IS : 325

31. PVC insulated (heavy duty ) IS 1554 : 1981 Part I & II


Cables for working voltage
up to 1.1. KV and up to 11 KV
Grade respectively.

32. Code for practice for electrical IS 732 : 1989


wiring installations.

33. Code for practice for earthing IS 3043 : 1966

34. Horizontal centrifugal pumps IS : 1620

35. Centrifugal fans ( 1st. Division) IS 894 : 1987 (reaffirmed 1991)

36. Wrought aluminium & aluminium IS : 737


alloy sheet and strip for general
Engineering purposes.

37. Mild steel tubes, tublar and other IS : 1239


wrought steel fittings.

38. Bourdon tube pressure and vacuum IS : 3624


gauges.

39. Glossary of terms used in refrige- IS : 3615


ration and air-conditioning.

40. Code for practice for standard for IS : 7403


selection of standard worm and
helical gears.
41. Three phase induction motors. IS : 325
42. Specification for single phase small IS : 996
A/C & universal motors

PMC: NSL HVAC 20


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

43. Specifications for flame proof motors IS : 2148


44. Circuit breaker A.C IS 2516 : 1980 Part I & II
45. Contactors for A.C for voltage IS 2959 : 1975
upto 1100 V.

46. Low voltage switch gear and control IS 8623 : 1993 Part I & II
gear assemblies.

47. Code of practice for selection IS 3914


of starters for AC induction motors

48. Specification for cables glands IS 4821


49. Code for selection, installation & IS 10118 : 1982 Part I to IV
maintenance of switch gear and
control gear.
50. Conduits for electrical installations IS 9537 : 1981 Part I to IV
51. Permissible limits of noise level IS 12065 : 1987
for rotating electrical machines.
52. Code of practice for installation IS 3106 : 1966
and maintenance of motors
53. Bourden tube pressure and vacuum IS : 3624
gauges
54. Code of practice for selection of IS : 7403
standard worm and helical gear boxes.

55. Mild tubes, tubulars and other IS : 1239


wrought steel fittings.

56. Electrically welded steel pipes IS : 3589


for water, gas and sewage.
57. Gum metal gate, globe and check IS : 778
Valves for general purposes
58. Wrought aluminum and aluminum IS : 737
Alloy steel and strips for general
Engineering purposes
59. HRC cartridge fuse links upto 650 volts IS : 2208
60. PVC insulated (heavy duty) electric IS : 1554 ( Part I)
Cables for working voltage upto &
Including 1100 watts
61. Method for testing Panel type air IS 7613 : 1975 (reaffirmed 1991)
Filters for AC purposes

PMC: NSL HVAC 21


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
62. Unbounded glass wool for thermal IS 3690 : 1974
insulation ( 1st. Revision)
63. Expanded polystyrene for thermal IS 4671 : 1984 (reaffirmed)
insulation purposes. ( 1st. revision)
64. Propeller type AC Ventilation fans 1IS 2312 : 1967 (reaffirmed 1991)
65. Electrical axial flow fans IS 3588 : 1987 (reaffirmed 1991)

1.1.5 SAFTEY CODES


The following IS codes shall be followed:
Safety code for mechanical refrigeration IS 660
Safety code for air conditioning IS 659
Safety code for scaffolds & ladders IS 3696
Code of practice for fire precaution in IS 3016
Welding & cutting operations
Code for safety procedures and practices IS 5216
In electrical works
Code of practice for safety and health IS 3696
Requirements in electrical & gas welding
And cutting operations.

1.1.6 SPACE
All shop drawings shall be prepared by the A.C Contractor after examining the
Architectural & AC drawings & as per site.

1.1.7 TENTATIVE LAYOUT PLANS


The tentative layout plans enclosed with the tender documents are only for guidance
purposes only.

END OF SECTION-04

PMC: NSL HVAC 22


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-05
NOISE AND VIBRATION CONTROLS

1.00 The air conditioning contractor must take all necessary precautions to have minimum
noise generation and its transmission. Minimum vibration as permitted by IS relevant
code shall be ensured. A few points for guidance only are given below:
1.01 a) Double fire retardant flexible connections shall be provided from air discharge to
outlet of air-handler to the duct.
b) Vibration isolation pads of suitable thickness commensurate to loading for
isolation of vibration shall be provided under all air handlers fans etc. in
consultation with manufacturer for proper selection of vibration isolators
c) Flexible conduit connections of minimum diameter of 50mm to motors shall be
provided. All loops should be large enough to allow connections to remain
flexible.
d) All conduit connection where conduits are 60mm or larger shall be made of 1.2
meters minimum length conduit installed in the shape of U and grossly slack to
provide maximum vibration isolation.
e) Operating clearance of 40mm shall be kept between the base and the inertia base.

f) The floor supported piping shall be mounted on pipe supports with 7.5mm ribbed
neoprene pads between the base plate of the pipes and the floors.
g) All items suspended from false ceiling shall be isolated on separate hangers.
h) In case of ducts, conduits, pipes & tubes the annular space between construction
and penetrating element shall be sealed with sand cement plaster.
i) The supply duct 5 Mt starting from air handling unit & suppy air duct collar of the
AHU shall be provided with acoustic lining of 25 mm thick fibre glass rigid board
and remaining will be insulated as indicated in the tender drawings. The duct
lining shall be done with fibre glass rigid board of density of 48 kg/cubic meter.

j) All axial flow fans shall be hanged with Vibration isolator spring .

k) The air-conditioning contractor shall take all other precautions or shall make his
own arrangements even if not specified in the tender documents for eliminating
high noise levels & shall minimize vibrations in all mechanical equipments
without any additional cost.

END OF SECTION-05

PMC: NSL HVAC 23


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-06
STANDARD SPECIFICATION OF VAV TERMINAL UNIT
The scope of this section comprises supply installation, testing and commissioning of Single
Duct VAV Terminal Unit confirming to these specifications and in accordance with
requirements of drawings and schedule of quantities.

VAV is a single duct pressure dependent variable volume unit designed for use with standard air
handling systems at medium and low pressures. Room temperature is controlled by supplying
only enough conditioned air to the space to achieve room thermostat set point. Excess air is
diverted (bypassed) directly to the return air ceiling plenum for free or ducted return. Airflow to
each occupied zone will vary on thermostat demand, from full flow to shut-off or to a
mechanically set minimum air volume. A bypass box, also referred as a "dump box" handles
supply of primary air through its inlet and uses a bypass damper to divert partial supply air into
the plenum return. Room thermostat directly controls the damper to provide the volume of air
required to meet the thermal demand. The air volume and pressure requirements are set by an
Inlet volume control damper. Another manual damper for balancing the bypass air is provided
and has to be field adjusted to maintain minimum airflow to the space.
Construction:
Casing - 22 ga. galvanized steel with round inlets. Outlets are rectangular with flanged/slip
connections.
Damper - 20 Ga. (1.0mm) Galv. Steel Damper blade with seals.
Complete with internal sound absorbent/insulating open/closed cell Nitrile polymer lining
Easily adjustable bypass port balancing dampers.
Sizes range:
o Circular Inlet: 6" (150mm) to 20" (500mm) with capacities from 100 to 4100 CFM
o Elliptical inlet: upto 12” (300mm) x (700mm) with capacities upto 4200 CFM.
Minimum air volume stopper provided on electric actuator. It cannot be factory set and must be
field adjusted as required for the
application.
Controls:
Pressure dependent electronic control. Factory supplied and mounted.
Variety of control options available, based on applications. • Electronic thermostat and actuator
provide accurate
modulating control.

END OF SECTION - 06

PMC: NSL HVAC 24


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-07
STANDARD SPECIFICATION OF THERMAL / ACOUSTIC
INSULATION

1) This section deals with supply and fixing of thermal / acoustic insulation of
Ducts, pipes etc. as per the specification given in this section

2) THERMAL DUCT INSULATION


For Duct thermal insulation - Nitrile Rubber – as follows:

3) INSULATION ON SHEET METAL DUCTING

OUTSIDE/INSIDE INSULATION FOR RECTANGULAR/OVAL DUCTING

Thickness of material:
For Coastal Ares:
Supply Duct running in Non AC areas : Thickness 25mm Closed Cell Elastomeric
Nitrile Rubber with Al PE Foil

Return Duct running in Non AC areas : Thickness 19 mm Closed Cell Elastomeric


Nitrile Rubber with Al PE Foil

Supply Duct Running in AC areas : Thickness 19mm Closed Cell Elastomeric


Nitrile Rubber with Al PE Foil
Return Duct Running in AC areas : Thickness 13mm Closed Cell Elastomeric
Nitrile Rubber with Al PE Foil

For Non- Coastal Ares:


Supply Duct running in Non AC areas : Thickness 19mm Closed Cell Elastomeric
Nitrile Rubber with Al PE Foil

Return Duct running in Non AC areas : Thickness 13 mm Closed Cell Elastomeric


Nitrile Rubber with Al PE Foil

Supply Duct Running in AC areas : Thickness 13mm Closed Cell Elastomeric


Nitrile Rubber with Al PE Foil
Return Duct Running in AC areas : Thickness 09mm Closed Cell Elastomeric
Nitrile Rubber with Al PE Foil
Note: No Al foil required for internal duct insulation.

4) MATERIAL SPECIFICATIONS
 Insulation material shall be Closed Cell Elastomeric Nitrile Rubber with anti-microbial
properties and with factory laminated Aluminum Foil with reinforced glass scrim of 12

PMC: NSL HVAC 25


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
microns thickness.
 Thermal conductivity of insulation material shall not exceed 0.033 W/(m.K) at mean
temperature of 0C as per EN 12667.
 Moisture Diffusion Resistance Factor or ‘µ’ value of insulation material shall be
minimum 10,000 without any external barrier as per EN 12086.
 The insulation material shall have fire performance such that it passes Class 1 as per
BS476 Part 7 for surface spread of flame and also passes Fire Propagation requirement as
per BS476 Part 6 to meet the Class ‘O’ Fire category as per 1991 Building Regulations
(England & Wales) and the Building Standards (Scotland) Regulations 1990.

 The insulation material shall have fire performance of V0, HB as per UL 94, 1996.

 The insulation material shall be FM (Factory Mutual), USA Approved.

 Density of insulation material shall be between 40 to 55 Kg/m3.

 The insulation material shall be dust and fibre free.

 The insulation material shall withstand maximum surface temperature of +85 Deg.C and
minimum surface temperature of +7 Deg.C as per EN 14706.

 The insulation material shall have an anti-microbial product, which is EPA


(Environmental Protection Agency), as an integral part of insulation that cannot be
washed off or worn off.

 The insulation material shall give enhanced level of protection against harmful Microbes
such as bacteria, mold, mildew and fungi and should confirm to following standards: DIN
EN ISO 846 Method A - Fungi / Mould Resistance and DIN EN ISO 846 Method C -
Bacterial Resistance.

 The material shall have ODP (Ozone Depletion Potential) and GWP (Global Warming
Potential) of Zero.
 The Aluminum foil shall be of 12 micron thickness with reinforced glass scrim and
weight shall be 70 gsm as per EN 22286, tensile strength shall be 250N/50mm as per ISO
527-3 with elongation of 4% as per DIN 53354.

 Thickness of the insulation shall be as specified for the individual application.


 The insulation material shall be installed as per manufacturer’s recommendation.

5) ADHESIVE FOR DUCT THERMAL INSULATION:-:


 Special adhesive for installing all flexible insulation materials. Adhesive shall be used for
bonding the seams securely together. All butt & longitudinal joints, fittings and coverings
must be closed with adhesive.
 The adhesive shall be specially formulated for the Duct insulation application and
supplied by insulation manufacturer. The adhesive shall be free from benzene.

PMC: NSL HVAC 26


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
 The adhesive shall have excellent bonding to porous and non-porous surfaces.

Technical Details
Solvent Based Rubber contact adhesive
Colour: Pale Yellow
Temperature Range: +5°C to +85°C
Form: Liquid
Material: Rubber based contact adhesive in blend of solvents
Minimum Drying Time (airing time): 4-5 minutes
Setting Time: 36 hours
Viscosity @ 30°C: 700 - 1200 cps
Specific Gravity: 0.80 - 0.85 g/cc
Density: 0.083 kg/m3 + 0.01
Flash Point: > 10 °C
Coverage: 6-8 square meters of bonded area per Litre (Bonded area – Area of insulation
material and duct together)
Tack Retention Time: 25 minutes

Or CRRX Compound of Shalimar Product for Adhesive.

6) ROUND DUCT THERMAL INSULATION :

Insulation for Round or capsule duct should be carried out from inside of the duct
applied with good quality adhesive. Contents of thickness & adhesive are
described as above.

7) DUCT THERMAL INSULATION : (Within the building)

Thickness & Nitrile specifications shall be above point no 3.

8) EXPOSED TO SUN , THERMAL INSULATION :-

For Rectangular ducts (Exposed to Sun): Thickness & Nitrile specifications


shall be as per point no 3

Further, the material should be with a protective layer of mechanical cloth which is
factory laminated over the Nitrile rubber.

9) SPECIFICATION FOR CLOTH

- Manufacturer bonded / Factory Laminated Treated Woven Glass Fibre


Technical Details: Temperature Range: 0°C to + 105°C Overall (irrespective of the

base product) Color: Black / Grey / Red / Blue

Treatment: Shall be treated Water Based Acrylic binder to give crisp and non-piling

PMC: NSL HVAC 27


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
property to the fabric, to help in easy installation, minimize fiber erosion, good aesthetics
and resistance to abrasion. Fibre spillage / Thread raveling should be minimum.
Density: 200 +/- 20 GSM

Weight: 205 +/- 10 grams per square meter

Tensile Strength: 275 +/- 25 Kg / 50 mm

(minimum) Thickness: 0.18 mm / 7 mill

Pressure sensitive self-adhesive tape (PSA) Tape: 50 mm width (with glass cloth
only).

Type: Solvent based Acrylic Adhesive

Peel Strength: 1000 gm / 25 mm (minimum) - (Adhesive to steel)


UV Resistance: Glass Cloth shall be UV resistant for artificial weathering as per EN ISO
4892-2 Method - A.

Specification for Tapes:

Glass Cloth foil based tape with self-adhesive ability to ensure 100% leak-proof joints.
The tape shall be with a pre coated layer of solvent based adhesive which is non-
hazardous in nature.

Width: 50 mm +/- 2 mm
GC Thickness: 180 micron
Length: 8.4 meter +/- 100 mm

10) DUCT ACOUSTIC INSUALTION:-

Thickness for Duct Acoustic: 15 mm

Specifications: Ducts are included in Schedule of Quantities shall be provided with


acoustic lining of thermal insulation for a distance of minimum 5 meters (or 30% of the
duct length whichever is more).

Scope: The scope of this section comprises the supply and application of insulation
conforming to these specifications.

Acoustic Insulation
 Acoustic insulation material shall be Open Cell Engineered Nitrile Rubber foam.

 The Random Incidence Sound Absorption Coefficient (RISAC) of the material - Tested
as per ISO 354:2003, ISO 11654:1997 & ASTM C 423 and shall be minimum as per

PMC: NSL HVAC 28


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
enclosed chart.
Freq 125 250 500 1000 2000 4000 NRC
(Hz)
6 mm 0.00 0.05 0.10 0.25 0.55 1.00 0.20
10 mm 0.00 0.05 0.15 0.40 0.85 1.00 0.35
15 mm 0.00 0.10 0.30 0.75 1.00 0.90 0.55
20 mm 0.05 0.15 0.40 0.90 1.00 0.95 0.60
25 mm 0.05 0.25 0.85 1.00 0.90 0.95 0.80
30 mm 0.10 0.35 0.95 1.00 0.95 1.00 0.85
40 mm 0.15 0.50 1.00 0.90 0.95 0.95 0.85
50 mm 0.25 0.75 1.00 1.00 1.00 1.00 1.05

 The acoustic insulation material shall be dust and fibre free.


 The acoustic insulation material shall have good sound absorption, damping and barrier
properties.
 The density of acoustic insulation material shall be within 140-180 Kg/m3.
 The acoustic insulation material shall have Microban®* antimicrobial product protection,
and shall pass Fungi / Mould Resistance as per DIN EN ISO 846 method A and Bacterial
Resistance as per DIN EN ISO 846 method C, from an independent testing agency.
 The acoustic insulation material shall have a thermal conductivity not exceeding 0.047
W/(m.K) @ 20 Deg. C as per EN 12667.
 The acoustic insulation material shall withstand maximum surface temperature of +85
Deg.C and minimum surface temperature of -20 Deg.C as per EN 14706.
 The material shall conform to Class 1 rating for surface spread of Flame in accordance to
BS 476 Part 7 & UL 94 (HB, V-0) in accordance to UL 94, 1996.
 The acoustic insulation material shall pass Air Erosion Resistance Test in accordance to
ASTM Standard C 1071-05 without any laminate or covering (section 12.7), from an
independent accredited testing agency.
 Thickness of the insulation shall be as specified for the individual application.
 The insulation material shall be installed as per manufacturer’s recommendation.

Adhesive for Duct Acoustic Insulation:

Specifications: The adhesive shall be formulated for the Duct insulation application and
supplied by insulation (Nitrile) manufacturer. The adhesive shall be rubber based, solvent
based contact adhesive, free from benzene. The adhesive shall have minimum tear
strength resistance of > 20 N / 25 mm when tested as per AFERA – 4001. The adhesive
shall be quick drying characteristics for tropical conditions and shall have service
temperature of 0 deg to +85 °C.
Installation Procedure
The inside surface for the ducts shall be covered with adhesive recommended by the
manufacturer. Cut Foamed sheets into required sizes apply adhesive on the foam and
stick it to the duct surface

11) TREATED WOVEN GLASS FIBRE CLOTH SPECIFICATION :-

PMC: NSL HVAC 29


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
Technical Details: Temperature Range: 0°C to + 105°C Overall (irrespective of the base
product) Colour: Black / Grey / Red / Blue
Treatment: Shall be treated Water Based Acrylic binder to give crisp and non-piling
property to the fabric, to help in easy installation, minimize fiber erosion, good aesthetics
and resistance to abrasion. Fibre spillage / Thread raveling should be minimum.
Density: 200 +/- 20 GSM
Weight: 205 +/- 10 grams per square meter
Tensile Strength: 275 +/- 25 Kg / 50 mm
(Minimum) Thickness: 0.18 mm / 7 mill

Pressure sensitive self-adhesive tape (PSA) Tape: 50 mm width (with glass cloth
only).
Type: Solvent based Acrylic Adhesive
Peel Strength: 1000 gm / 25 mm (minimum) - (Adhesive to steel)
UV Resistance: Glass Cloth shall be UV resistant for artificial weathering as per EN ISO
4892-2 Method - A.

12) SPECIFICATION FOR TAPES :-

Glass Cloth foil based tape with self-adhesive ability. The tape comes with a pre coated
layer of solvent based adhesive which is non-hazardous in nature. Tape ensures 100%
leak-proof joints whether used along with sheets with GC laminate or tubes with
laminate.
Width: 50 mm +/- 2 mm
Thickness: 180 micron
Length: 8.4 meter +/- 100 mm

13) DRAIN PIPE INSULATION

 Drain pipes carrying condensate water shall be insulated with 9 mm thick Nitrile
rubber as specified in the Boq.
 (Class ‘0’ Nitrile - sleeve without bonded cloth & neither self-sleeve Nitrile shall be used
for drain piping) i.e. only plain Nitrile rubber sleeve to be applied with the help of
specified adhesive. In case the pipes are exposed, then mechanical cloth (protection
against mechanical impact and UV protection, insulation manufacturer bonded Treated
Woven Glass Fibre Covering) should be applied separately over the insulation.

14) THERMAL DUCT INSULATION- XLPE


For Duct thermal insulation - XLPE – as follows:

Fixing of external thermal insulation on ducts with Closed Cell Cross Linked
Polyethylene (XLPE) Foam of density 30 Kg/m³ with 12 mm /9mm thick & thermal
Conductive. is 0.032 W/m²K at an average Temperature of 23°C. The Material Shall be
rated as Class 1, As per BS 476 Part 6 & 7(1987) ISO 5659 - 2, The Smoke Density as
per As - 1530.3 Shall not exceed 1. The Material shall have Fire Approval from CBRI-

PMC: NSL HVAC 30


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
Roorkie. Adhesive used for setting the insulation shall be non - flammable, vapour
Proof.

To be applied by manufacturer approved adhesive and installation team. All Joints should
be sealed with 50 mm same PE tape and Flange to be overlapped by 6" width of the same
material thickness. Finally Duct insulated should be strapped by 12 mm Plastic Packing
strip at every meter of duct length centre to centre.

INSULATION ON SHEET METAL DUCTING

a) Supply Air Duct 12 mm thick Closed Cell Cross Linked Polyethylene


(XLPE) Insulated with factory Laminated Al PE Foil.

a) Return Air Duct 09 mm thick Closed Cell Cross Linked Polyethylene


(XLPE) Insulated with factory Laminated Al PE Foil.

b) Fresh Air Duct 12 mm thick Closed Cell Cross Linked Polyethylene


(XLPE) Insulated with factory Laminated Al PE Foil.

c) Duct Collars 12 mm thick Closed Cell Cross Linked Polyethylene


(XLPE) Insulated with factory Laminated Al PE Foil.

15) ACOUSTIC LINING OF DUCT

a) RESIN BONDED FIBRE GLASS WOOL


The Thermal conductivity values in W/m.K of fibre glass shall confirm to following:

Mean Temperature °C Density in Kg / Cmt. Thermal Conductivity


W/m.k
For Duct Lining

25 C 48 0.030

50 C 48 0.033

The material to be used for duct lining shall be 25 mm thick resin bonded fibre glass rigid
board having a density of 48 Kg/m³ & covered with 0.5 mm thick perforated aluminum
sheet. The lining of initial length of the duct shall be done as shown in the tender layout
drawings & shall be carried out as follows.

a) Clean the duct piece thoroughly,

b) Fix the board of suitable thickness inside the duct & cover with fiber glass tissue
paper.

PMC: NSL HVAC 31


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
c) Cover the insulation board with 0.5mm thick perforated aluminum sheet with
at least 20% perforation.

d) Secure the insulation board & aluminum sheet with cadmium coated bolts nuts & cup
washers / steel screws.

f) Finally seal the ends completely, so that no lining material is exposed.


.

END OF SECTION -07

PMC: NSL HVAC 32


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-08
STANDARD SPECIFICATION FOR AIR CIRCULATION SYSTEM

1.0 This section deals with supply, erection, testing & balancing of GI sheet metal duct work
either site fabricated or Factory fabricated as specified in the SECTION-23 Detailed
Bill of Quantities and air registers conforming to specifications as given below:

2.0 MATERIAL FOR RECTANGULAR DUCTING: - SITE FABRICATED

The duct shall be fabricated out of galvanized sheet, class VIII (Zinc coating 120
gm/m² as per the parameters given below which are conforming to IS 655-1963.

MAXIMUM THICKNESS TYPE OF TRANSVERSE BRACING


SIDE OF GI SHEET JOINT CONNECTIONS

(1) (2) (3) (4)


mm mm
Up to 300 0.63 S-drive, pocket or bar None
Slips, on 2.5m centers

301 to 600 0.63 S-drive, pocket or bar None


601 to 750 slips, on 2.5m centers 25 x 25 x 3 mm
S-drive, 25mm pocket angles, 1.2m
or 25 mm bar slips on from joint
2.5m centers.

751 to 1000 0.80 Drive, 25-mm pocket or 25 x 25 x 3 mm


25mm bar slips, on 2.5 m angles, 1.2 m
centers 40 x 40 mm angle from joint
Connections,
1001 to 1500 or 40-mm bar slips, with 40 x 40 x 3 mm
35 x 3 mm bar reinforcing angles, 1.2 m from
on 2.5 m centres. joints

1501 to 2250 1.00 40 x 40 mm angle conn- 40 x 40 x 3 mm


ections, or 40-mm bar diagonal angles, or
slips, 1 m maximum 40 x 40 x 3 mm
centers with 35 x 3 mm angle 60 cm from
bar reinforcing . joint.

2250 to above* 1.25 50 x 50 mm angle connec- 40 x 40 x 4 mm


tions, or 40 mm pocket or diagonal angles, or
40 mm bar slips, 1 m max. 40 x 40 x 3 mm
centers with 35 x 3 mm bar angles, 60 cm
Reinforcing. From joint.

PMC: NSL HVAC 33


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
* Ducts 2250 mm and larger require special field study for hanging and supporting
Methods.
In addition to above the following points should be also taken into account while
fabrication of ducts.

a) All ducts of size larger than 450mm shall be cross broken.

b) All ducts shall be supported from the ceiling / slab by means of MS rods of dia
9mm with MS angle of size 40 x 40 x 5 mm at the bottom with neoprene pad in
between the duct & MS angle. The ducts shall be suspended from the ceiling with
the help of dash fasteners. Provision for necessary ancillary materials required for
hanging the ducts shall be arranged by the contractor.

c) The vanes shall be provided wherever required and shall be securely fastened to
prevent noise & vibration.

d) The rubber gasket shall be installed between duct flanges in all connections and
joints.

e) All flanges and supports should be primer coated.

f) The flexible joints shall be fitted to the delivery side of AHU fans with Fire
Retardant Double canvass. The length of flexible joints should not be less than
150 mm and not more than 300 mm between faces.

g) The ducting work can be modified if deemed necessary in consultation with the
Engineer in Charge to suit actual site conditions in the building.

h) Box Type Dampers & Splitters

These dampers shall be provided in the ducting work for proper control and
balancing of air distribution. All dampers shall be louver type robust construction.
These dampers shall be fitted with easily accessible operating mechanism,
complete with links, levers, quadrant for proper control and setting in a desired
position. The position of the handle of the damper operating mechanism shall be
clearly visible and shall indicate the position of the damper in the duct. All
dampers, splitters shall be fabricated out of G.S. sheet of two gauges higher than
the duct piece having these fittings. Dampers shall be installed in duct at all
required locations. No extra payment shall be made separately since these
form part of Air Circulation System.

NOTE: In case angle iron supports are not feasible to be installed for supporting the
ducts due to height constraint then the contractor shall support the ducts with M.S flats
of at least double the thickness of the angle iron supports.

PMC: NSL HVAC 34


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
3.0 MATERIAL FOR RECTANGULAR DUCTING: - FACTORY FABRICATED

DUCT MATERIAL
All ducts shall be fabricated from galvanized steel sheets of the following thickness:

Gauge Thickness
(mm)
Rectangular ducts upto 750mm 24 0.63

Rectangular ducts greater than 750 mm


and upto 1500mm 22 0.80

Rectangular ducts greater than 1500mm


and upto 2250mm 20 1.00

Rectangular ducts greater than 2250mm 18 1.25

FACTORY FABRICATED DUCTS SHALL HAVE THE THICKNESS OF THE SHEET


AS ABOVE AND SHOULD HAVE BEADING AT EVERY 300mm.
Recommended SMACNA Standard at 4 Feet Transverse Joint Reinforcement

Duct static pressure


Sin Inches 2''
Duct Size (mm)
150-300 B-26
301-550 C-26
551-700 D-26
701-900 E-24
901-1000 F-22
1001-1200 G-22
1201-1300 H-20
1301-1500 H-20 R
1501-1800 I-18
1801-2100 J-18 R
2101-2400 J-18 R

Ducts shall be straight and smooth on the inside. Longitudinal seams shall be airtight and
at corners, which shall be either Pittsburgh or snap Button Punch as per SMACNA
practice, to ensure air tightness.
Note:
 SMACNA – Sheet Metal & Air Conditioning Contractor National Association
Inc. “ MVAC Duct construction standard Metal & Flexible” – 1995 USA.
 In 1” static pressure i.e. comfort cooling application optional “ C&S and C&SS
cleats joints can be used

PMC: NSL HVAC 35


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
Upto 450mm duct size use C&S Cleats
451 mm to 750mm duct size use “ C&SS cleats.
Over 750mm duct size use TDC Flanges with respective gauges as mentioned above.
 Alphabets B, C, D, E, F, G, H, I and J per SMACNA 1995, transverse joint
reinforcement table 1-12m (T-25b flanged) and TDC addendum.
 R means reinforcement with Zeebar Stiffener.

DUCT FABRICATION
All Galvanized ducts shall be factory fabricated from lock form grade galvanized sheet
steel zinc coated conforming with IS: 277, coating grade 120 or aluminium sheets
conforming to ISS:737-1955 (wherever aluminium ducts are specified).and installed in a
workman like manner. To suite pieces shall be fabricated at site as per ISS: 655 latest
editions.

Ducts shall be straight and smooth on the inside with neatly finished joints. All joints
shall be made airtight by applying sealant during the assembly of the ductwork; Sealing
of the seams shall be accomplished by using approved sealant. Transverse joints shall be
made using sponge rubber sulphur-free foam rubber gasketing (3mm thick and 20mm
wide) All exposed ducts within conditioned spaces shall have only slip joints and no
flanged joints. The internal ends of slip joints shall be made in the direction of Air flow.

Changes in dimensions and shape of ducts shall be gradual. Curved elbows, unless
otherwise approved, shall have a center line radius equal to one and half times the width
of the duct. Air turns shall be installed in all abrupt elbows and shall consist of curved
metal blades or vanes, arranged to permit the air to make the turns without appreciable
turbulence.

All ducts shall be rigid and shall be adequately supported and braced where required with
standing seams to keep the ducts true to shape and to prevent buckling, vibration or
breathing.

All sheet metal connections, partitions and plenums required to confine the flow of air to
and through the filters and fans, shall be constructed out of 18 gauge galvanized steel
sheet, thoroughly stiffened with 25mm x 25mm x 3mm angle iron braces and fitted with
all necessary doors, to give access to all parts of the apparatus. Doors shall not be less
than 45cm x 45cm in size.
Volume control dampers wherever indicated on the drawings shall be installed as a
minimum. The final duct design may call for additional volume control dampers based
on final duct configuration.

4.0 MATERIAL FOR OVAL / ROUND DUCTING: - FACTORY FABRICATED

SCOPE
The Specification covers the general design material , construction features ,
manufactures ,shop inspection & testing at manufacture‘s work ,delivery at site ,
installation testing commissioning & carrying out performance test at site of air

PMC: NSL HVAC 36


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
distribution system. All ducts shall be factory fabricated. The accepted factories are listed
in the approved list of makes.
CODES & STANDARDS
The design material ,construction features ,manufactures ,inspection ,testing &
performance of air distribution system shall comply with all currently applicable statues
regulation , codes & standards in the locality where the system is to be installed nothing
in the specification shall be constructed to relieve the contractor of this responsibility . In
particular, the air distribution system shall conform to the latest edition of following
standards:
IS 277 Galvanized Steel Sheets (Plain & Corrugated)
SMACNA MVAC system –Testing adjusting & balancing
UL181 Factory made air ducts & connectors
UL555 Fire dampers
ASHRAE 70 method of testing for rating the performance of air outlets & inlets

MATERIAL REQUIREMENT:
Ducting shall be fabricated of galvanized steel sheet & stainless steel as specified in BOQ
a) GSS duct shall be lock forming grade , zinc coated conforming to IS 277 coated grade
120 GSM
b) SS duct shall be of SS304 as per ASTMA167

CONSTRUCTION FEATURES:
Fabricated detail shall be generally in accordance with the detail given here under:
ROUND DUCT:
a) Dead End caps / Blank off shall be dish type.
b) Round duct thickness in mm/G for GSS/SS shall be given below:
c) Slip type coupling shall be used for transverse joints & shall be joined with each other
with Al 3mm to 5mm POP RIVERTS.

Up to 600mm 3mm POP RIVERTS


Above 600mm 5mm POP RIVERTS
d) Duct shall be forming using lock forming machine.

ROUNDDUCT Up to65mm WC static


S.NO Gauge DIAMETER(mm) pressure positive
Spiral Seam (mm
thick/Gauge)
1 24G Up to 200mm dia 0.63 /24
2 24G 201 to 350mm dia 0.63 /24

3 24G 350 to 600mm dia 0.63 /24


4 22G 601 to 900mm 0.80/22

5 20G 901 to 1250mm 1.00/20


6 18G 1251 to 1600 1.25/18
Round duct shall have longitudinal or spiral seam as specifies above

PMC: NSL HVAC 37


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

DUCT SUPPORTS & HANGERS:

Round duct shall be supported using one/two hanger straps & rods. Straps or Rods shall be of
GSS. Supporting of round duct shall be as given below:

G.IThreaded
S.No Duct Dia.mm G.I Strap 2.5mm Thick Rod
Nos. Width(mm) Thickness(G) Nos. Dia. MM
1 Up to 600mm dia 1 30 22 1 10
601 to 900mm
2 dia 1 30 20 1 10
901 to 1250mm
3 dia 2 30 20 2 10
1251to1600mm
4 dia 2 40 18 2 10

Zinc coated anchor fasteners or embedded plates shall be provided for upper attachment in the
buildings. Anchor fasteners, embedded plates & necessary supports to hang the duct shall be
provided by the contractors. Anchor fasteners shall be loaded to maximum 30% of the maximum
rated capacity specify by the mafuctures. Site engineers shall approve all anchors fasteners for
supporting ducts. In case of insulated duct anchor fasteners shall be selected based on the actual
load.
The spacing between supports should not be greater than 2.5meter

5.0 STEEL WIRE ROPE HANGER & SUPPORTS:-

Wire Hangers shall be used to suspend all static HVAC Air Distribution services.

Wire Hangers should consist of a pre-formed wire rope sling with a range of end fixings
to fit various substrates and service fixings, these include a ferruled loop, permanently
fixed threaded M6 (or M8, M10) stud, permanently fixed nipple end with toggle, at one
end or hook or eyelet, cladding hook, barrel, wedge anchor, eyebolt anchor or any other
end fixture type or size as per manufacturers recommendation and design. The end
fixings and the wire must be of the same manufacturer with several options available.
The system should be secured and tensioned with a Hanger self-locking grip at the other
end. Once the grip is locked for safety purpose unlocking should only be done by using a
separate setting key and should not be an integral part of the self-locking grip. Only wire
and/or supports supplied and/or approved, shall be used with the system.

a. Wire Hangers should have been independently tested by Lloyds Register. APAVE, TUV,
UL NEBS, CSA, Chiltern International fire, ADCAS, Intertek, ECA, and SMACNA,
approved by ULC and CSA and comply with the requirements of DW/144 and BSRIA –
wire Rope Suspension systems. Wire rope should be manufactured to BSEN 12385: 2002

PMC: NSL HVAC 38


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
The contractor shall select the correct specification of wire hanger to use for supporting
each particular service from table 1 below. Each size is designated with a maximum safe
working load limit (which incorporates a 5:1 safety factor).

The correct specification of wire hanger required is determined using the following
formula.

Weight per meter of object suspended (kg) X distance between suspension points (m)
= weight loading per Hanger suspension point (kg).

Where the installed wire rope is not vertical then the working load limit shall be reduced in
accordance with the recommendations give in the manufacturer’s handbook.

The contractor shall select the correct length of wire rope required to support the service.
Lengths from 1-10m lengths. Specials can be made, check with manufacturer. No in–line
joints should be made in the rope.

Table. 1

Wire (Gripple) Hanger Safe Working Loads


minimum breaking load working load limit
size of Wire Rope (kg/lbs)
No. 1 80kg/176 lbs 0-10 kg / 0-22 lbs
No. 2 260kg/572 lbs 10-45 kg / 23-100 lbs
No. 3 580kg/1276 lbs 45-90 kg / 101-200 lbs
No. 4 1500kg/3300 lbs 90-225 kg / 210-495 lbs
No. 5 2160kg/4752 lbs 225-325 kg / 496-715 lbs
No. 6 2500kg/5500 lbs 325-500 kg / 715-1100 lbs

The standard range of Hanger Kits should contain galvanized high tensile steel wire rope or
stainless steel wire rope as per the application, the minimum specification is as above and should
be manufactured to BS 302 (1987), BSEN12385. Comply with manufacturer's load ratings
and recommended installation procedures.Note the testing is done to the minimum breaking
load of the wire thus giving a minimum safety factor of 5: 1.

HVAC Supports – Gripple Hanger Supports are suitable for: Rectangular duct, Spiral
Duct, Oval Duct, Fabric Duct, Desertification fans, Air Conditioning Units, Plenum Boxes,
Fan Coil Units, Diffusers

Ducting Supports:

a) All ductwork shall be independently supported from building construction. All


horizontal ducts shall be rigidly and securely supported, in an approved manner, with

PMC: NSL HVAC 39


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
hangers formed of galvanized steel wire ropes and galvanized steel angle/channel or a
pair of brackets, connected by galvanized steel wire hangers under ducts, rigid supports
may be provided at certain interval if need be. The spacing between supports should be
not greater than 2.4 meter. All vertical ductwork shall be supported by structural
members on each floor slab. Duct supports may be through galvanized steel insert plates
or Toggle end wire fixing left in slab at the time of slab casting. Galvanized steel cleat
with a hole for passing the wire rope hanger shall be welded to the plates. Trapeze hanger
formed of galvanized steel wire rope using Gripple shall be hung through these cleats.
Wherever use of metal insert plates is not feasible, duct support shall be through
dash/anchor fastener driven into the concrete slab by electrically operated gun. Wire rope
supports shall hang through the cleats or wire rope threaded studs can be screwed into the
anchor fasteners. In case of PEB structure Loop and Catenary system can be used based
on the site conditions as per approved suspension system drawings.

b) All horizontal ducts shall be adequately secured and supported. In an approved manner,
with trapeze Hangers formed of galvanized steel wire rope in a cradle support method
(refer to typical drawings) under ducts at no greater than 3000mm centre, for 3001mm-
above appropriate size angle along with neoprene pad in between the duct & MS angle
should be used with prior approval. All vertical duct work shall be supported by
structural members on each floor slab. Duct support shall be through dash / anchor
fastener driven into the concrete slab by electrically operated gun. Hanger wires shall
then hang around the ducting. Rigid supports shall be used in conjunction with wire rope
hangers to assist with alignment of services where recommended for by the manufacturer.
Rigid support must also be used in conjunction with wire rope hangers with duct work at
each change of direction or connection or as per approved drawings. Support ducting in
accordance with Schedule I at the end of this Section. Any other Gripple solution can be
used based on manufacturer’s recommendation on site conditions after prior approval. In
cases of Spiral ducting the wire can be wrapped directly around the ducting without the
need for a spiral ducting clamp for sizes above 1100 a cradle support should be provided,
refer to manufacturer’s recommendations.

c) Ducting over furred ceiling shall be supported from the slab above or from beams after
obtaining approval of Construction manager/consultant. In no case shall any duct be
supported from false ceiling Hangers or be permitted to rest on false ceiling. All metal
work in dead or furred down spaces shall be erected in time to occasion no delay to other
Contractor’s work in the building. All supports of pipe shall be taken from structural
slab/wall by means of fastener.
Catenary Supports: Refer to manufacturer’s recommendations on Catenary supports
with C-clip, special care should be taken with tensioning of the wire and angles at which
the installation of services are made.
Stainless Steel Supports should be available for food, chemical and High Corrosion areas
near coastlines.
Refer to manufacturers catalogue and installation guide for further technical
information.Comply with manufacturer's load ratings and recommended installation
procedures.
Schedule I: Duct Hanger Schedule

PMC: NSL HVAC 40


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

For ducts with external SP upto 250 Pa For ducts with external SP upto 500 Pa
Maximum Duct Size Gauge Gripple Maximum Duct Size Gauge Gripple
(mm) Hanger No. (mm) Hanger No.

1 - 750 26 1 or 2 1–600 mm 26 1 or 2
751-1000 26 2 601-750 mm 26 2
1001-1200 24 2 or 3 751-1000 mm 24 2 or 3
1201 - 1500 24 3 1001-1200 mm 22 3 or 4
1501 - 1800 22 3 or 4 1201-1300 mm 20 3 or 4
1801-2100 20 3 or 4 1301-1500 mm 18 4
2101‐2700 18 4 1501-1800 mm 18 4
1801-2100 mm 18 4
2101-2250 mm 18 4 or 5
2251-2400 mm 18 4 or 5
2401-2700 mm 18 4 or 5

Notes: All supports are considered at 2400 mm interval in above table and may vary
as per the design but should not be greater than 2400mm.

Desertification fans, Air Conditioning Units, Plenum Boxes, Radiant Panels,


Heaters, Fan Coil Units, Diffusers, Cassette units and Chilled Beams.

All units shall be adequately secured and supported in an approved manner using wire
hanger suspension Y fit solution as per manufacturers’ recommendation with prior
approval.

Rigid Supports: `

Rigid supports if required in conjunction with wire hangers shall be of steel, adjustable
for height and Zinc chromate primer coated and finish coated black. Where supports and
clamps are of dissimilar materials, a gasket shall be provided in between. If the MS angle
at the bottom if required as per design should be as per following table:

Longer size
of Duct Type of Joints
Up to 750 25x25x3 mm L angle with M8 nuts & bolts
751-1000 25x25x3 mm L angle with M8 nuts & bolts
1001-1500 40x40x5 mm L angle with M8 nuts & bolts
1501-2250 50x50x5 mm L angle with M10 nuts & bolts
2251 &
above 50x50x6 mm L angle with M10 nuts & bolts

All the supporting system should be supplied from same manufacturer.

PMC: NSL HVAC 41


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
6.0 THE SUPPLY AND RETURN AIR GRILLS AND CEILING DIFFUSERS
The supply and return air grills and ceiling diffusers shall be made of 50 micron powder
coated extruded aluminum sections. The supply air grills / diffusers shall be provided
with screw operated opposed blade volume control device made of extruded aluminum in
black anodized finish.
All grills / diffusers shall have soft continuous rubber / foam gasket between the
periphery of the grills / diffusers and surface on which it has to be mounted. The colour
of grills / diffuser shall be as per the approval of the Engineer in Charge.

7.0 LINEAR SUPPLY AND RETURN GRILLS


The linear continuous supply / return air grills shall be made of 50 micron powder coated
extruded aluminum construction with fixed horizontal bars. The thickness of fixed bar
louvers shall be 5mm in front and the flange shall be 20mm wide with round edges. The
register shall be suitable for concealed fixing and horizontal bars of the grills shall
mechanically crimped from the back to hold them.
The colour of grills shall be as per the approval of the Engineer in Charge. The volume
control device made of extruded aluminum construction in black anodised finish shall be
provided in supply air duct collars only.

8.0 FRONT FIXED BAR REAR ADJUSTABLE LOUVERED GRILLS.


The grills shall be made of 50 micron powder coated extruded aluminum construction
with front fixed horizontal bar at 0 degree inclination with one way or two way deflection
with rear vertical individually adjustable louvers in black shade mounted on Nylon
bushes to hold deflection setting under all conditions of velocity and pressure.
The colour of grills shall be as per the approval of the Engineer in Charge. The volume
control device of extruded aluminum construction in black anodised finish shall be
provided in supply air duct collars.

9.0 SQUARE / RECTANGULAR CEILING DIFFUSERS.


The square / rectangular ceiling diffusers shall be made of 50 micron powder coated
extruded aluminum construction with flush fixed pattern. The diffusers shall have Anti-
Smudge ring and spring loaded removable central core in various pattern for air flow
direction. The diffusers shall be mounted by concealed screw fixing arrangement. The
volume control device of extruded aluminum construction in black anodised finish shall
be provided in supply air diffusers. The colour of diffuser shall be as per the approval of
the Engineer in Charge.

10.0 VOLUME CONTROL DEVICE


The opposed blade volume control device shall be made of Powder Coated extruded
aluminum construction in black anodised finish. Opposed blades shall be pivoted to
extruded aluminum frame with Nylon bushes. Specially designed blade shall have an
overlapping lip which shall ensure a tight closure.

11.0 FRESH AIR INTAKE LOUVERS WITH BIRD SCREEN


The fresh air intake louvers at least 50mm deep will be made of 50 micron powder coated
extruded aluminum construction. Bird / insect screen will be provided with the intake

PMC: NSL HVAC 42


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
louvers. The blades shall be inclined at 45 degree on a 40mm blade pitch to minimize
water ingress. The lowest blade of the assembly shall be extended out slightly to facilitate
disposal of rain water without falling on door / wall on which it is mounted.
The intake louvers shall be provided with factory fitted aluminum construction volume
control dampers in black anodised finish.

12.0 JET NOZZLE /CIRCULAR DIFFUSER


The jet diffusers shall be made of 50 micron powder coated extruded aluminum
construction frame & inner rings. Jet nozzle section is mounted in aluminum square plate
covered by flange border. Nozzle cane adjusted 30° /40° up and down to maintain
required level/through as per site .It also be rotated 360° by adjusted the mounting frame .
The noise level for jet nozzles shall not exceed to 35 db for air quantity.
The color of jet diffuser shall be as per the approval of the Engineer in Charge

5.0 PAINTING
All ducts collar / shoot behind the grills / diffuser shall be given at least two coats oil
black enamel paints.

6.0 TESTING
The complete duct system shall be tested for air leakage & complete air distribution
system shall be balanced in accordance with air quantities indicated on the approved
drawing.

END OF SECTION-08

PMC: NSL HVAC 43


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-09
STANDARD SPECIFICATION ON ELECTRICAL MOTORS AND
STARTERS

1.00 This section deals with supply, installation, testing and commissioning of all types of
motors used for , air-handlers, etc. The motor installation, wiring & its control shall be
carried out in accordance with the specifications as detailed below.

1.10 MOTORS

MAKE OF MOTORS

The make of motors shall be as specified in List of Approved Make.

a) The motor shall be of the following design and should run at all loads without any
appreciable noise or hum.

i) Totally enclosed fan cooled Sq. Cage.

ii) Screen protected drip proof wound Sq. Cage motor.

Enclosure and type of motor shall depend upon duty and usage unless otherwise
specified.

b) The winding of motors shall be class ‘F’ insulation and suitable for local conditions.
The insulation of motors shall confirm to IS:325/1978.

c) All motors shall comply with IS:325, IEC-34.1 or BS – 2313, IEC-72.1 for foot
mounted motors.

d) The rating of the motor shall be as indicated in the Schedule of Equipment & Bill of
Quantities. The motors shall be selected on the basis of ambient temperatures and
allowable maximum temperature rise.

e) Motor above 1HP shall be three phase unless otherwise specified.

f) All motors shall be rated for continuous duty as per IS:325. Motor shall be suitable
for operation on 415 volts ± 10% volts, 50 ± 5% Hz AC supply (or 230 ± 10% volts,
50 ± 5% Hz for single phase AC supply).

g) Motors shall be provided with cable box to receive Aluminum conductors, PVC
insulated, PVC sheathed and armoured cables.

h) All motors shall be provided with combination of ‘Ball and Roller Bearing’. Suitable
grease nipples for regreasing the bearing shall be provided.

PMC: NSL HVAC 44


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
i) Motors above 0.25 HP shall be provided with overload protection. Motors above 100
HP shall be provided with thermal protection and thermostat detector in the starter
winding.

j) The starter current and the type of starter to be used shall be as follows (unless
otherwise specified)

Type of motor Starting Current Starting method

a) Sq. Cage motor 600% of full load D.O.L


up to 7.5 hp current

b) Above 7.5 hp 250% of full load Star / Delta


up to 60 hp current

c) 75 HP & above 200% of full load Closed transition Star / Delta


current

1.20 MOTOR STARTERS

a) All starters shall confirm to IS: 13947. The starter shall be enclosed in sheet metal
enclosure, which would be dust vermin proof.

b) All starters should have suitable range of voltage and frequency.

c) All starter shall have integral stop/start push button of international colour code.

d) Contactor shall have number of poles as required for appropriate duty. Contacts
should be made of solid silver faced & shall be suitable for at least 40 contacts per
hours.

e) In event of power failure, the starter should automatically disconnect.

f) All starters shall be provided with thermal over load relay.

g) All star delta starters shall have adjustable timers.

h) Terminal blocks with integral insulating barrier shall be provided for each starter.

i) All starters shall be provided as specified in Bill of Quantities. All starters shall
be compatible to the drive and driven equipment.

j) Extra contact for interlocking purpose shall be provided in the starter.

1.30 INSTALLATION OF MOTORS

PMC: NSL HVAC 45


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
a) The motor and drive machine shall be fixed on slide rails to facilitate belt and
other adjustments.

b) Vibration isolation arrangement shall be provided.

c) The installation of motor shall be carried out as per IS: 900.

d) All motor shall be wired as per specifications. Earthing of motor frame shall be
done with GI strips as specified in ‘Bill of Quantities’.

e) All motors shall be tested at manufacturer’s works as per I.S. standard and test
certificates shall be furnished.

f) All motors after installation shall be tested at site for vibrations, heating and
electrical insulation resistance by AC contractor.

END OF SECTION-09

PMC: NSL HVAC 46


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-10
STANDARD SPECIFICATION OF MOTOR CONTROL CENTER (MV
PANEL), AHU SUB-PANEL, POWER & CONTROL CABLING
1.00 This section deals with supply, installation, testing & commissioning of Motor Control
Centre (MV panel), AHU Sub-Panels etc. & shall be manufactured by CPRI approved
venders. The power / control cabling & earthing work shall be carried out as per the
specification given below:

1.10 SCOPE
All work shall confirm to Indian Electricity Act (amended up to date), I.S. code of
practices local rules and regulations etc. Power cabling shall be carried out with approved
make of cables as indicated in the List of approved make of equipment / materials
and shall be of grade 1100 volts, PVC insulated & sheathed, armoured aluminum
conductors cables. Control cabling shall be of approved make and shall be of grade 1100
volts, PVC insulated & sheathed, copper conductor armoured multicore cables as
specified in B.O.Q.

1.20 MOTOR CONTROL CENTRE (MV PANEL) / AHU SUB-PANEL

Motor control centre (MV Panel) floor mounted extendable type & wall mounted AHU
sub-panel shall be fabricated out of 14G C.R.C.A. Sheet. These panels shall be cubical
sectionalized type, totally enclosed dust & vermin proof. Gaskets shall be provided in all
joints to prevent dust to reach the internals of the panels to make it completely dust proof.
The degree of protections for panels shall be IP 52 for indoor applications and IP 55 for
outdoor applications as per IS: 2147.

These panels (MV) shall be suitable for voltages up to 500 volts, three phase 50 Hz, 4
wire supply capable of functioning satisfactorily in temperature ranging up to 45 to 50
degree centigrade and rupturing capacity suitable for connected load & design should be
type tested for 42 KA fault level. All joints of panels shall be welded and braced as
necessary to provide a rigid support for all components. The base channel provided in the
floor mounted MV panel shall be 75mm high & a clear space of 200mm between the
floor and the bottom most part of the unit shall be provided. The panel shall be correctly
positioned. Self- threading screws shall not be used in the construction of control panels.
Appropriate knock-out holes of proper sizes shall be provided for incoming and outgoing
cables. The facility for bottom or top entry of cables in the panels shall be provided.
Necessary cables clamps shall provided for holding the cables in position.

All power/control wiring inside the panel shall be colour coded and control wiring
ferruled for identification purpose. All labeling shall be provided in engraved anodized
aluminum strips on the front face of the panel.

Each circuit breaker shall be housed in separate compartments. It shall have steel sheets
on top and bottom of compartment. The steel sheet hinged door shall be interlocked with
the circuit breaker on the “ON” position. When the breaker is on the “ON” position,

PMC: NSL HVAC 47


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
suitable preventive measures shall be provided, such as interlocks, to prevent the breaker
from being drawn out. When the breaker is in “ON” position steel sheet shall be provided
between the tiers in the vertical section. The door of this compartment shall not form part
of the draw out arrangements.

1.30 BUS-BARS

The bus-bar and its connections shall be aluminum Electrolytic grade E-91 as per IS:
5082 and shall be of rectangular section. The minimum amperage capacity of aluminum
bus bar shall 1A / Sq. mm. These should be suitable for full load current for phase bus-
bar and neutral bus-bar shall be of half rated current capacity. The bus-bar should have
provision on either side for extension for main panel. The bus-bar should be sleeved with
colour coded heat shrinkable PVC sleeve. Bus-bar supports shall be of fibre glass
reinforced thermosetting polyester having in built and tracking barriers to break the path
of conducting dust through moulded ribs.

In panels bus-bar connections shall be done by drilling holes with cadmium coated bolts
and nuts. Extra cross section shall be provided to compensate drilling of the holes.
Insulated aluminum strips of suitable size of full rated current capacity shall be used for
interconnecting bus-bar and breaker.

A horizontal / vertical wire way shall be provided for interconnecting control wiring
between different vertical sections.

The terminal blocks shall be used for outgoing terminals and neutral link at a suitable
located place in the control panel. Separate compartments for outgoing and incoming
cable shall be provided. The current transformers of all instruments shall be mounted
with terminal blocks.

All live parts including incoming and outgoing link / terminals should be totally shrouded
by means of non hygroscopic and fire retardant material.

1.40 ROTARY SWITCH / SELECTOR SWITCH / SWITCHES / HRC FUSES /


STARTERS / SINGLE PHASE PREVENTERS / TOGGLE SWITCH.

These shall be of approved make and conforming to relevant ISI standard. The rupturing
capacity of HRC fuses should not less than 80 KA and in case of switches it should be 60
Amps maximum.

1.50 CURRENT TRANSFORMER

The current transformers shall have accuracy of class 1, 5 and 5P10 / 10P10 and suitable
VA burden for operation of the connected meters and relays.

1.51 OVERLOAD RELAYS

PMC: NSL HVAC 48


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
All the motors shall have overload relay protections conforming to relevant IS.

1.52 TIME DELAY RELAYS

These shall be adjustable type with time delay adjustments of 0-180 or as per
manufacturers standards.
1.53 INDICATING LAMPS AND METERING

These shall confirm to BS37 & BS39. All meters shall be flush mounted and draw-out
type. The indicating lamp shall be LED type.

1.54 VOLTMETER AND AMMETERS

Motor Control Centre (MV Panel) shall have flush type voltmeter & ammeter of size 96 x
96 mm analog or digital type as detailed in B.O.Q.

1.55 PUSH BUTTON STATIONS

These shall be suitable for panel mounting and accessible from front without opening.
These shall be provided for manual starting and stopping of motors/equipments as per
normal practices. The contacts shall be suitable for 2amps current capacity.

1.56 CONDUITS

These shall be preferable made of mild steel, stove enameled from inside and outside
with minimum wall thickness of 1.6 mm for conduits up to dia of 25mm and 2 mm for
conduits above 25 mm diameter.

1.57 CABLES

These shall be PVC insulated, pre-sheathed, aluminum conductor armoured cables as per
IS:694 and as per list of approved make of equipment / materials. Control Cables
shall be multi-core PVC-insulated PVC sheathed copper conductor and armoured cables
of approved make only.

1.58 LAYING OF CABLES

These shall be laid as Indian Standard code of practice. All cables shall be laid on 16G
Cadmium Plated U shaped Channel 40mm x 20mm cable trays. In case more than one
cable is running, then proper space in between the two cables shall be provided to avoid
loss of current carrying capacity. While cables are running on walls, proper saddles must
be provided.

1.59 WIRE SIZES

PMC: NSL HVAC 49


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
Multi-strands PVC-copper conductor wires shall be used inside the control panel for
interconnecting different components. All wires shall be neatly dressed and coloured
beads shall be provided for easy identification in control wiring. The minimum size of
control wiring shall be 1.5sq.mm. Testing of panels as per code of practice shall be done
at works by AC contractor before inspection & dispatch to site.

1.60 DRAWINGS
Necessary drawings of all control panels and wiring of equipment etc., shall be submitted
by the A.C contractor for approval of the Engineer in Charge. On final completion of job
and before handing over of AC System As Built Drawings shall be submitted to the
Department.

1.61 TESTING

The complete electrical installation shall be tested in accordance with relevant ISI codes
in presence of Electrical Supervisor of the Department before commissioning of plant.

1.62 PAINTING OF PANELS

All sheet metal enclosures shall be powder coated only after de-rusting & hot-dip
phosphating degreasing through seven tank process at works only.

NOTE: Rubber mats of 1100 volts shall be laid in front of all switch boards

1.63 POTENTIAL FREE CONTACTS


The AC contractor shall provide fire shunt relay (24V.DC) in his panel wherever
necessary either it is specified in the Schedule of Quantities or not free of cost for all the
starter feeder meant for AHU Fan, etc. to take fire input signal and trip the starter in the
event of fire.

END OF SECTION-10

PMC: NSL HVAC 50


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-11
MODE OF MEASUREMENT

The following measurement code shall apply to the Contract:

1.0 SHEET METAL WORK

1. DUCTING

a) The final finished sheet area in sqmt shall be measured only.

b) Vanes, splitters, flanges, access doors etc. shall not be separately measured. These
shall be treated as part of duct work.

c) Bends, Elbows, Transformation, pieces etc. shall be measured along the centre
line and measured as per duct work.

d) Canvas connections, Duct Supports, Stiffening members, frames etc. shall not be
measured separately and shall form part of duct work.

e) For each drawing, all supply of duct work must be accompanied by computer-
generated detailed bill material indicating all relevant duct sizes, dimensions and
quantities. In addition, summary sheet are also to be provided showing duct areas
by gauge and duct size range as applicable.
f) Measurement sheet covering each fabricated duct piece showing dimensions and
external surface area along with summary of external surface area of duct guage-
wise.
g) All duct pieces shall a part number, corresponding to the serial number assigned
to it in the measurement sheet. The above system shall ensure speedy and proper
site measurement, verification and approvals

2. GRILLS / DIFFUSERS / FIRE DAMPERS

All Grills / Diffusers / Fire Damper areas will be measured in terms of effective
area (Neck Area). Any Extruded aluminum grill / diffusers having an area less
than 0.1 sq.mt shall be accounted as 0.1 sq.mt.

3. BOX DAMPERS

a) No separate measurement of box dampers shall be done since they form part of
duct.
b) Fresh air dampers shall be measured as effective areas only. No separate
measurements for bird screen inlet / outlet louvers shall be done.

PMC: NSL HVAC 51


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
1.20 A) Insulation of Duct

1. This shall be measured on the basis of bare duct surface area i.e. the area of duct
insulation & area of duct shall be same.

B) Acoustic Lining of Duct & collars

This shall be measured on the basis of bare duct surface area i.e. the area of duct
lining & area of duct shall be same.

1.30 ELECTRICAL CABLING WORK

a) All power cables / controls cables shall be measured on linear basis in meters.

b) No extra price shall be paid on account of end termination of cables which


includes thimble, gland etc.

1.40 STRUCTURAL SUPPORTS

No extra price shall be paid on account of structural supports required for piping,
ducting & cabling work. All wooden frames for fixing like Grill etc. will be
provided by the AC Contractor.

END OF SECTION – 11

PMC: NSL HVAC 52


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION-12
PAINTING WORK

This section deals with painting of various equipment / material supplied under this
contract. It gives basic guidance for painting as specified below:-

a) Application: The original colour of all equipments like, air-handling units etc.
which if get damaged during transportation or during installation shall be painted
in original shade with the two coat of paint to give a final finish.

b) All chilled water pipes shall be painted as per standard code of practice and
arrows shall be marked to indicate direction of flow of water.

COLOUR SCHEME FOR THE EQUIPMENTS / MATERIALS

i) Electrical panels/sub-panel/ --- Light gray powder coated


Remote control console

ii) Cable trays --- Cadmium Plated

iii) Supports for ducts --- Silver

vi) Wooden Frame --- All Wooden frame for fixing of


Grills/ Louvers will be provided by
Contractor as per BOQ mentioned.

END OF SECTION -12

PMC: NSL HVAC 53


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION -13
LIST OF APPROVED MAKES OF EQUIPMENTS / MATERIALS

AS Per Section C
END OF SECTION-13

PMC: NSL HVAC 54


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION-14
BASIS OF DESIGN
1) DESIGN CRITERIA:

Site Location : DELHI


Altitude : 216mt m above mean sea level

Based on the data given in ISHRAE handbook for NEW DELHI the outdoor design
conditions have been considered as follows:-

Outside Design Data –Peak  IP (US)  SI (METRIC) 


SUMMER – DB/WB  110/75  43.3/23.9 
RELATIVE HUMIDITY %  20  20 
      
MONSOON – DB/WB  95/83  35/28.3 
RELATIVE HUMIDITY %  60  60 
      
WINTER – DB/WB  45/41  7.2/5.0 
RELATIVE HUMIDITY %  70  70 
        

INSIDE DESIGN CONDITIONS  IP(US)  SI(METRIC) 


Summer /Monsoon – WORKSTATION, ROOM  77° + 1.8 ° F 25 ° + 1° C 
AND CONFERENCE  
RELATIVE HUMIDITY *  Around 60%  Around 60% 

2) CHILLED WATER INLET TEMPRATURE :-


REQUIRED AT 7DEG C FROM DEVELOEPER

3) EQUIMENT PROVIDED BY DEVELOPER :- 2X13000CFM AHUS

END OF SECTION-14

PMC: NSL HVAC 55


SECTION-15
ASSOCIATED CIVIL/ ELECTRICAL AND OTHER WORKS TO BE
PROVIDED BY THE DEVELOPER SHALL NOT BE APART OF MVAC
BOQ.

a) Any Foundation of Equipment’s.

b) Minor masonry work such as opening in walls, slabs and making good.

c) Any kind of masonry trench / shaft for laying ducts and pipes.

d) Drain points in / near each Air-handling units

e) Any kind of exposed roof insulation.

f) Any kind of false ceiling work or return air boxing work.

g) Any kind of aluminum / wooden frame work for grills / diffusers fixing

END OF SECTION-15
SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION -16
STANDARD SPECIFICATION OF IMPORTED VARIABLE
REFRIGERANT VOLUME / FLOW SYSTEM

6.00 The specifications under this section covers the supply, installation, testing and
commissioning of the VARIABLE REFRIGERANT FLOW SYSTEM INVERTOR
CONTROLLED conforming to these specifications and in accordance with the Detailed
Bill of Quantities given in the tender.

6.01 General

Each VRF Unit shall be air cooled, split type multi-system air conditioner consisting of
outdoor units and number of indoor units, each having capability to cool and heat for the
requirements of the individual area to be air-conditioned. The VRF unit should be capable
of connecting minimum ten different types of indoor units to one refrigerant circuit and
controlled individually.
Each VRF unit shall have minimum two number scroll compressor and both inverter
Compressor (With inverter controller) and capable of changing the rotating speed to
follow variations in cooling loads. Each indoor units having capability to cool or heat
for the requirement of the rooms

Compressor shall be inverter controlled. Compressor installed in each outdoor module unit
shall be equipped with both inverter compressor in bigger (if modular) machines for higher
reliability, improved life, better backup and duty cycling purpose. The system shall be
capable of changing the rotating speed of inverter compressor by inverter controller to
follow variations in cooling and heating load.

The Outdoor units shall be suitable for mix-match connection of following type of indoor
units. All indoor units of any capacity shall be provided with condenser drain pump of
Imported Sumen or equivalent make only free of cost .
 Ceiling mounted cassette type (Double flow)
 Ceiling mounted cassette type (Multi flow)
 Ceiling mounted duct type.
 Ceiling suspended type.
 Wall mounted type
 Floor standing type
 Concealed floor standing type.
Please note that the refrigerant piping shall be capable of extending up to 100m with 50m
level difference without any oil traps.

Both indoor and outdoor units shall be factory assembled, tested and filled with first charge
of refrigerant. These being very hi-tech in construction with lots of factory checks being
conducted, hence no sub assembly should be done at site preferably.

PMC: NSL HVAC 57


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

6.02 OUTDOOR UNIT

The outdoor unit shall be factory assembled, weather proof casing, constructed from heavy
gauge mild steel panels and coated with baked enamel finish. The unit should be completely
factory wired, tested with all necessary controls tested prior to dispatch conforming to the
following specifications.
a. All outdoor units shall consist of minimum two scroll compressors, preferable both with
inverter drive,.

b. Outdoor units when consisting of more than 1 module (e.g. 36 HP = 18 HP +18 HP),
each should have both separate inverter driven compressors.
c. In such case, the units shall be provided with duty cycling arrangement for multiple
Inverter compressors.
d. The outdoor unit shall be modular in design to facilitate installation one after another
Close to each other Preference would be given to compact units having smaller
Footprint

e. Outdoor units should be rugged of anti-corrosion design and should have strong base
Plate for easy mounting of unit.

f. The outdoor unit shall comprise of sub-cooling feature to effectively use the entire coil
surface through proper circuit/bridge in order to prevent flushing of refrigerant owing
to large length of piping.
g. The condensing unit shall be provided with state-of-the-art microprocessor based
control panel.
h. The outdoor unit shall be provided with provided with Aero spiral design fan exhibiting
low noise level characteristics complete with aero fitting grille to facilitate spiral discharge
of airflow to effect reduction in pressure losses. The fan should be capable to respond to
external static pressure of 5mm.
i. Motor shall be speed controlled to ensure a stable operation for varying ambient by a
factory fitted direct acting head pressure activated variable speed drive for at least 15
steps to give precise discharge pressure and minimum power consumption of condenser
fan motor.
j. The condenser shall be complete with provisions for refrigerant piping connections, shut
off valves and any other standard accessories necessary with the equipment supplied.
The condensing unit shall be designed to facilitate fail safe operation when connected to
multiple indoor units. If possible, the system should work on standard operating parameters
like discharge pressures of not more than 300 PSI as the ref. Piping will be moving around
within a residential house, otherwise on any misfortune of any leakage it will act like a bullet
on higher pressures. If working on higher operating pressures, vendor to comply with all
safety codes of high pressure safety & testing as recommended by Japanese (being Japanese
design product) and give 2 sets of special tools to handle such equipment at site. All brazing

PMC: NSL HVAC 58


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

should be done by only qualified trained person who had training on HIGH PRESSURE
brazing, special tools & procedures.

6.03 SCROLL COMPRESSOR


The scroll compressor shall be an industrial quality rugged, cast iron, direct hermetic
compressor with scroll plates, suction & discharge service valves. The compressor shall be
completely enclosed in a chamber with no leakage path and providing the capability for
scroll plates to separate. The compressor shall be provided with industrial solid motor
mounts internal motor protection and vibration isolation pads. Each compressor shall be
independently wired and piped to its own circuit for efficient operation & ease of
maintenance. The compressor speed shall not exceed 3000 RPM.
The compressor shall be highly inverter control type. The inverter compressor shall change the
speed in accordance to the variation in cooling or heating load requirement:
a) All outdoor units shall have multiple steps of capacity control to meet load fluctuation and
indoor unit individual control. All parts of compressor shall be sufficiently lubricated stock.
Forced lubrication may also be employed.
b) Oil heater shall be provided in the compressor casing.

c) The inverter compressor shall preferably be efficient & reliable inverter compressor.

6.04 HEAT EXCHANGER


The heat exchanger shall be constructed with copper tubes mechanically bonded to
aluminum fins to form a cross fin coil.
a) The aluminum fins shall be covered by anti-corrosion resin film.
b) The unit should be with heat exchanger to optimize the path of heat exchanger and for
better efficiency of condenser.
c) The unit shall be provided with necessary number of direct driven low noise level
propeller type fans arranged for vertical discharge. Each fan shall have a safety guard.

6.05 REFRIGERANT CIRCUIT


The refrigerant circuit shall include liquid & gas shut-off valves and a solenoid valves at
condenser end. The equipment must have inbuilt refrigerant stabilization control for proper
refrigerant distribution.

All necessary safety devices shall be provided to ensure the safely operation of the system.

6.06 REFRIGERANT
The VRF units shall be selected on R-410A refrigerant. The units should be fully factory
charged with refrigerant & oil & spare refrigerant & oil must be sent along with the machine
for topping up of gas & oil as may be required.

6.07 SAFETY DEVICES

PMC: NSL HVAC 59


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

All necessary safety devices shall be provided to ensure safe operation of the system.
Following safety devices shall be integral part of the outdoor unit:
 High pressure switch
 Fan drive overload protection switch
 Fusible plug
 Overload relay including overload protection for inverter driven compressor.

6.08 OIL RECOVERY SYSTEM


Entire system shall be designed and capable of oil recovery to ensure stable operation with
long refrigeration piping lengths. The system should have inbuilt (avoid external) oil
balancing circuit to avoid poor lubrication.

END OF SECTION -16

PMC: NSL HVAC 60


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION -17
STANDARD SPECIFICATION OF INDOOR UNITS
7.00 INDOOR UNITS

This section deals with supply, erection, testing and commissioning of Various Type of
Indoor Units confirming to general specification and suitable for the duty selected. The type,
capacity and size of indoor units shall be as specified in Detailed Bill of Quantities. All
indoor units of any capacity shall be provided with condenser drain pump of Sumen
make only if recommended by consultant as per site conditions after the award of
work & contractor shall provide the same free of cost.

7.01 GENERAL
Indoor units shall be either ceiling mounted cassette type, or ceiling mounted ductable type
or floor standing type or wall mounted type or other as specified in BOQ. Each unit shall
have electronic control valve to control refrigerant flow rate respond to load variations of
the room.

a) The address of the indoor unit shall be set automatically in case of individual and group
control
b) In case of centralized control, it shall be set by liquid crystal remote controller
The fan shall be dual suction, aerodynamically designed turbo, multi blade type, statically &
dynamically balanced to ensure low noise and vibration free operation of the system. The fan
shall be direct driven type, mounted directly on motor shaft having supported from housing.

The cooling coil shall be made out of seamless copper tubes and have continuous aluminum
fins. The fins shall be spaced by collars forming an integral part. The tubes shall be staggered
in the direction of airflow. The tubes shall be hydraulically/ mechanically expanded for
minimum thermal contact resistance with fins. Each coils shall be factory tested at 21kg/sqm
air pressure under water.

Unit shall have cleanable type filter fixed to an integrally moulded plastic frame. The filter
shall be slide away type and neatly inserted.

Each indoor unit shall have computerized PID control for maintaining design room
temperature. Each unit shall be provided with microprocessor thermostat for cooling or
cooling and heating.

Each unit shall be with wired LCD type remote controller. The remote controller shall
memorize the latest malfunction code for easy maintenance. The controller shall have self-
diagnostic features for easy and quick maintenance and service. The controller shall be able
to change fan speed and angle of swing flap individually as per requirement.

7.02 CEILING MOIUNTED CASSETTE TYPE UNIT (ONE WAY FLOW TYPE)

The unit shall be ceiling mounted type. The unit shall include pre-filter, fan Section and DX-
coil Section. The housing of the unit shall be powder coated galvanized steel. The body shall

PMC: NSL HVAC 61


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

be light in weight and shall be able to suspend from four corners. The fan shall be
aerodynamically designed diffuser turbo fan type. Also Units shall have an external attractive
panel for supply and return air. Unit shall have four /One way supply air grilles on sides and
return air grille in center as detailed in the BOQ.

Each unit shall have high lift drain pump, fresh air intake connection with nut bolt etc to
connect the flexible duct & cassette properly and very low operating sound.
All the indoor units regardless of their difference in capacity should have same decorative
panel size for harmonious aesthetic point of view. It should have provision of connecting
branch ducts.

7.03 CEILING MOUNTED DUCTABLE TYPE UNIT


Unit shall be suitable for ceiling mounted type with drain pump. The unit shall include pre
filter, fan section & DX coil section .The housing of unit shall be light weight powder coated
galvanized steel. The unit shall have high static fan for Ductable arrangement. Each unit
shall have high lift drain pump, fresh air intake connection with nut bolt etc to connect the
flexible duct & cassette properly and very low operating sound. Each unit shall have high lift
drain pump, fresh air intake connection with nut bolt etc to connect the flexible duct &
cassette properly and very low operating sound.

7.04 CEILING SUSPENDED TYPE


Unit shall be suitable for ceiling suspended arrangement below false ceiling. The unit include
pre filter , fan section & DX coil section . The housing of unit shall be light weight powder
coated galvanized steel.

7.05 HIGH WALL MOUNTED UNITS


The units shall be wall-mounted type. The unit includes pre filter, fan section & DX coil
section. The housing of unit shall be light weight powder coated galvanized steel .Unit shall
have an attractive external casing for supply and return air.

7.06 FLOOR STANDING TYPE


Unit shall be suitable for floor standing arrangement. The unit includes pre filter, fan section
& DX coil section. The housing of unit shall be light weight powder coated galvanized steel
Each unit shall have high lift drain pump, fresh air intake connection with nut bolt etc to
connect the flexible duct & cassette properly and very low operating sound.

7.07 CENTRALIZED TYPE REMOTE CONTROLLER

A multifunctional compact centralized controller shall be provided with the system. The
controller should be LCD remote controller to act as an advanced air-conditioning
management system to give complete control of VRF air-conditioning Equipment, It should
have ease of use for the user and must have a user friendly panel and LCD display.

It shall be able to control up to minimum 180 indoor units with the following functions:-

PMC: NSL HVAC 62


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

a) Starting/stopping of Air-conditioners as a zone or group or individual unit.

b) Temperature settling for each indoor unit or zone.

c) Switching between temperature control modes, switching of fan speed and direction of
airflow, enabling/disabling of individual remote controller operation.

d) Monitoring of operation status such as operation mode & temperature setting of


individual indoor units, maintenance information, trouble shooting information.

e) OPTIONAL-Display of air conditioner operation history.

f) OPERATIONAL-Daily management automation through yearly schedule function with


possibility of various schedules.

The controller shall have wide screen user friendly LCD display and can be wired by a non
polar 2 wire transmission cable to a distance of 1 km. away from indoor unit.

7.08 COLOUR

The colour of indoor units should be white or to suit interiors as designed by the architects /
clients.

END OF SECTION -17

PMC: NSL HVAC 63


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION -18
STANDARD SPECIFICATION ON REFRIGERANT PIPING WORK
This section deals with supply, installation, testing & commissioning of refrigerant piping as
detailed below in specifications.

9.10 REFRIGERANT PIPING


All refrigerant piping for the air conditioning system shall be constructed from soft seamless
upto 19.1mm and hard drawn copper refrigerant pipes for above 19.1mm with copper
fittings and silver-soldered joints. The refrigerant piping arrangements shall be in accordance
with good practice within the air conditioning industry, and are to include charging
connections, suction line insulation and all other items normally forming part of proper
refrigerant circuits.

All joints in copper piping shall be sweat joints using low temperature brazing and or silver
solder. Before joining any copper pipe or fittings, its interiors shall be thoroughly cleaned by
passing a clean cloth via wire or cable through its entire length. The piping shall be
continuously kept clean of dirt etc. while constructing the joints. Subsequently, it shall be
thoroughly blown out using nitrogen.
After the refrigerant piping installation has been completed, the refrigerant piping system
shall be pressure tested using nitrogen at pressure of 20Kg per sq.cm and 10 Kg per sq.cm
(low side). Pressure shall be maintained in the system for 24 hours. The system shall then be
evacuated to minimum vacuum if 700mm hg and held for 24 hours.

The thickness of copper piping shall not be less than 20gauge for pipes up to 19.1mm and
18 guage for bigger sizes

The suction line pipe size and the liquid line pipe size shall be selected according to the
manufacturers specified outside diameter. All refrigerant pipes shall be properly supported
and anchored to the building structure using steel hangers, anchors, brackets and supports
which shall be fixed to the building structure by means of inserts or expansion shields of
adequate size and number to support the load imposed thereon.
The OD wall thicknesses & wall thickness size of Copper refrigerant piping shall be as follows:
Outside Diameter (mm) Wall Thickness (G)
a) 41.3 18
b) 34.9 18
c) 19.1 20

d) 15.90 20

PMC: NSL HVAC 64


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

e) 12.70 20

f) 9.5 20

g) 6.4 20

The air-conditioning system supplier shall design sizes and erect proper interconnections of

the complete refrigerant circuit.

END OF SECTION -18

PMC: NSL HVAC 65


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION-19
SCHEDULE OF EQUIPMENT (PROPOSED)
1.00 The capacity/rating of various equipments in this contract are given for guidance only.
The AC contractor shall check in detail the design parameters against selection of
equipment. The AC contractor shall be responsible for maintaining the desired inside
conditions with the equipments selected & offered by him and shall not deprive him of
the responsibility if selection of equipment is not thoroughly checked. In case of shortfall
the AC contractor shall replace / modify equipment for achieving desired parameter
without any extra cost to owner / employer. The contractor would be bound to replace the
equipment / equipments selected by him if design condition is not achieved by the AC
System offered & installed by him.

1.2 G.S.S. DUCTING

a) Class of Galvanizing VIII

b) Code of Fabrication ISS –655 (Revised)

c) Material of hangers MS

d) Quantity of sheet Lock forming quality

1.3 CLASS O NITRILE RUBBER INSULATION

a) For external thermal


Insulation of duct As per specification

b) Density 30 Kg / M³

1.4 CLASS 1 NITRILE RUBBER OPEN CELL

a) For acoustic lining of


Duct As per specification

b) Density 48 Kg / M³

END OF SECTION-19

PMC: NSL HVAC 66


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
SECTION - 20
TECHNICAL DATA
(T0 BE FURNISHED BY THE BIDDER IN METRIC SYSTEM ONLY)

1.1 GRILLS / DIFFUSERS / DAMPERS

Please indicate make / material / gauge of the following:

Make Material

a) Duct Dampers :

b) Grills / Diffusers :

c) Fire Dampers :

d) Smoke & Temperature :


Sensor

e) Fresh Air Louvers :

1.5 DUCT INSULATION

a) Manufactures Name :

b) Material :

c) Density Kg. Per Cmt :

d) Thermal Conductivity :
Kcal / Hr. Deg. C.

1.6 DUCT LINING

a) Manufactures Name :

b) Material :

c) Density Kg. Per Cmt :

d) Thermal Conductivity :

e) Kcal / Hr. Deg. C. :

PMC: NSL HVAC 67


SPECIFICATIONS: HVAC Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
1.7 ELECTRICAL ACCESSORIES

Please indicate the makes of the following.

a) Panel Manufacturer’s name :

b) Remote Control console :


Manufacturer’s name

c) ACB / MCCB :

d) HRC Fuses :

e) Rotary Switch :

f) Starter’s DOL / Star Delta :

g) Contractor :

h) Indicating Lights :

i) Push Buttons :

j) Control Cables :

k) Power Cables :

l) Ammeters :

m) Voltmeters :

n) Single Phase Preventers :

o) Current Transformer :

p) Bus-bar / Grade :

END OF SECTION-20

PMC: NSL HVAC 68


SPECIFICATIONS: PLUMBING Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi
 
 
 
 
 
 
 
 
 

 
 
 
SPECIFICATIONS FOR PLUMBING AND FIRE 
SECTION B4 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
                     

PMC: NSL
SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION I 
 GENERAL INSTRUCTIONS 
 
1.0  GENERAL REQUIREMENTS  
 
1.1  Scope of Work 
 
1.1.1  The  form  of  Contract  shall  be  according  to  the  “Conditions  of  Contract”.  The 
following clauses shall be considered as an extension and not in limitation of the 
obligation of the Contractor.  
 
1.1.2  Work  under  this  contract  shall  consist  of  furnishing  all  labour,  materials, 
equipment  and  appliances  necessary  and  required.  The  Contractor  is  required  to 
completely furnish all the Fire fighting and other specialized services as described 
hereinafter  and  as  specified  in  the  Schedule  of  Quantities  and/or  shown  on  the 
Plumbing Drawings. 
 
1.1.3  Without restricting to the generally of the foregoing, the sanitary installations shall 
include the following:‐ 
 
A. Fire Fighting Work 
a. Sprinkler System 
b. Fire Extinguishers 
1.1.4  Services rendered under this section shall be done without any extra charge. 
 
1.2  Specifications 
 
1.2.1   Work  under  this  contract  shall  be  carried  out  strictly  in  accordance  with 
Specifications attached with the tender. 
 
1.2.2    Items not covered under these Specifications due to any ambiguity or misprints, or 
additional works, the work shall be carried out as  per  Specifications of the latest 
Central Public Works Department with upto date amendments as applicable in the 
contract and or as per the requirement of the client or its representative. 
 
1.2.3  Works  not  covered  above  in  para  1.2.1  and  1.2.2  shall  be  carried  out  as  per 
relevant Indian Standards and in case of its absence as per British Standard Code 
of Practice.   
 
1.3.  Execution of Work 
 
1.3.1  The Contractor should visit and examine the site of work and satisfy himself as to 
the  nature  of  the  existing  roads  and  other  means  of  communication  and  other 
details  pertaining  to  the  work  and  local  conditions  and  facilities  for  obtaining  his 
own  information  on  all matters  affecting  the execution  of work.  No  extra charge 

PMC: NSL  F 1   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

made  in  consequence  of  any  misunderstanding,  incorrect  information  on  any  of 
these points or on ground of insufficient description will be allowed.     
 
1.3.2  The work shall be carried out in conformity with the Plumbing drawings and within 
the  requirements  of  Architectural,  HVAC,  Electrical,  Structural  and  Other 
specialized services drawings. 
 
1.3.3  The  Contractor  shall  cooperate  with  all  trades  and  agencies  working  on  the  site.  
He  shall  make  provision  for  hangers,  sleeves,  structural  openings  and  other 
requirements  well in advance to prevent hold up of progress of  the construction 
schedule. 
 
1.3.4  On  award  of  the  work,  Contractor  shall  submit  a  schedule  of  construction  in  the 
form  of  a  PERT  Chart  or  BAR  Chart  for  approval  of  the  Project 
Manager/Architect/Consultant.  All  dates  and  time  schedule  agreed  upon  should 
be  strictly  adhered  to,  within  the  stipulated  time  of  completion/commissioning 
along with the specified phasing, if any. 
 
1.4  Drawings 
 
1.4.1  Plumbing  drawings  are  diagrammatic  but  shall  be  followed  as  closely  as  actual 
construction  permits.    Any  deviations  made  shall  be  in  conformity  with  the 
Architectural and other services drawings. 
 
1.4.2       Architectural  drawings  shall  take  precedence  over  Plumbing  or  other 
services drawings as to all dimensions. 
 
1.4.3  Contractor shall verify all dimensions at site and bring to the notice of the Project 
Manager all discrepancies or deviations noticed.  Decision of the Project Manager 
shall be final. 
 
1.4.4  Large size details and manufacturers dimensions for materials to be incorporated 
shall take precedence over small scale drawings. 
 
1.4.5   All drawings issued by the Architects/Consultant for the work are the property of 
the Architects/Consultant and shall not be lent, reproduced or used on any works 
other than intended without the written permission of the Architects/Consultant. 
 
1.5  Inspection and Testing of Materials 
 
1.5.1  Contractor  shall  be  required,  if  requested,  to  produce  manufacturers  Test 
Certificate for the particular batch of materials supplied to him.  The tests carried 
out shall be as per the relevant Indian Standards. 
 
1.5.2  For  examination  and  testing  of  materials  and  works  at  the  site  Contractor  shall 
provide  all  Testing  and  Gauging  Equipment  necessary  but  not  limited  to  the 
followings:‐ 
 

PMC: NSL  F 2   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

a) Theodolite, Steel tapes 
b) Dumpy level 
c) Weighing machine 
d) Plumb bobs, Spirit levels, Hammers 
e) Micrometers, Tachometers  
f) Thermometers, Stoves 
g) Hydraulic test machine 
h) Smoke test machine 
 
1.5.3  All  such  equipment  shall  be  tested  for  calibration  at  any  approved  laboratory,  if 
required by the Project Manager. 
 
1.5.4  All Testing Equipment shall be preferably located in a special room meant for the 
purpose. 
 
1.5.5  Samples  of  all  materials  shall  be  got  approved  before  placing  order  and  the 
approved samples shall be deposited with the Architects or kept at site in a sample 
room  as  prepared  by  the  owners.  Any  materials  declared  defective  by  Project 
Manager/Architect/Consultant shall be removed from the site within 48 hours.     
 
1.6  Metric Conversion 
 
1.6.1  All dimensions and sizes of materials and equipment given in the tender document 
are commercial metric sizes. 
 
1.6.2  Any weights, or sizes given in the tender having changed due to metric conversion, 
the  nearest  equivalent  sizes  accepted  by  Indian  Standards  shall  be  acceptable 
without any additional cost. 
 
1.7  Reference Points 
 
1.7.1  Contractor  shall  provide  permanent  Bench  Marks,  Flag  Tops  and  other  reference 
points for the proper execution of work and these shall be preserved till the end of 
the work. 
 
1.7.2  All such reference points shall be in relation to the levels and locations given in the 
Architectural and Plumbing drawings. 
 
1.8  Reference Drawings 
 
1.8.1  The  Contractor  shall  maintain  one  set  of  all  drawings  issued  to  him  as  reference 
drawings. These shall not be used on site. All important drawings shall be mounted 
on boards and placed in racks indexed. No drawings shall be rolled.  
 
1.8.2  All corrections, deviations and changes made on the site shall be shown on these 
reference  drawings  for  final  incorporation  in  the  completion  drawings.  All   
changes to be made shall be initialed by the Project Manager or Architects. 
 

PMC: NSL  F 3   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

1.9  Shop Drawings 
 
1.9.1  The  Contractor  shall  submit  to  the  Project  Manager  three  copies  of  the  shop 
drawings.  
 
1.9.2  Shop drawings shall be submitted under following conditions:‐  
  
(a) Showing any changes in layout in the plumbing drawings. 
 
(b) Equipment layout, piping and wiring diagram.  
 
(c) Manufacturer’s  or  Contractor’s  fabrication  drawings  for  any  materials  or 
equipment supplied by him.  
 
1.9.3  The  Contractor  shall  submit  two  copies  of  catalogues,  manufacturer’s  drawings, 
equipment  characteristics  data  or  performance  charts  as  required  by  the  Project 
Manager.  
 
1.10  Completion Drawings 
 
1.10.1  On  completion  of  work,  Contractor  shall  submit  one  complete  set  of  original 
tracings  and  two  prints  of  “as  built”  drawings  to  the  Project  Manager.  These 
drawings shall have the following information.    
 
a) Run of all piping, diameters on all floors, vertical stacks and location of external 
services.    
 
b) Ground  and  invert  levels  of  all  drainage  pipes  together  with  location  of  all 
manholes and connections upto outfall. 
 
c) Run of all water supply lines with diameters, locations of control valves, access 
panels.   
 
d) Location of all mechanical equipment with layout and piping connections. 
 
No completion certificate shall be issued unless the above drawings are submitted.  
 
1.10.2  Contractor  shall  provide  two  sets  of  catalogues,  service  manuals  manufacturer’s 
drawings,  performance  data  and  list  of  spare  parts  together  with  the  name  and 
address of the manufacturer for all electrical and mechanical equipment provided 
by him.     
 
1.10.3  All  “Warranty  Cards”  given  by  the  manufacturers  shall  be  handed  over  to  the 
Project Manager.  
 
 
 
 

PMC: NSL  F 4   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
 
1.11.  Contractors Rates 
 
1.11.1  Rates  quoted  in  this  tender  shall  be  inclusive  of  cost  of  materials,  labour, 
supervision,  erection,  tools,  plant,  scaffolding,  service  connections,  transport  to 
site, taxes, octroi and levies, breakage, wastage and all such expenses as may be 
necessary and required to completely do all the items of work and put them in a 
working condition. 
 
1.11.2  Rates quoted are for all heights and depths and in all positions as may be required 
for this work. 
 
1.11.3  All  rates  quoted  must  be  for  complete  items  inclusive  of  all  such  accessories, 
Fixtures and fixing arrangements, nuts, bolts, hangers as are a standard part of the 
particular item except where specially mentioned otherwise. 
 
1.11.4  All  rates  quoted  are  inclusive  of  cutting  holes  and  chases  in  walls  and  floors  and 
making  good  the  same  with  cement  mortar/concrete/water  proofing  of 
appropriate  mix  and  strength  as  directed  by  Project  Manager.  Contractor  shall 
provide holes, sleeves and recesses in the concrete and masonry work as the work 
proceeds. 
 
1.11.5  The Contractor shall furnish the Architects with vouchers and test certificates, on 
request, to prove that the materials as specified and to indicate that the rates at 
which  the  materials  are  purchased  in  order  to  work  out  the  rate  analysis  of  non 
tendered items which he may be called upon to be carried out. 
 
1.12  Testing 
 
1.12.1  Piping and drainage works shall be tested as specified under the relevant clause(s) 
of the specifications. 
 
 
1.12.2  Tests shall be performed in the presence of the Project Manager/ Consultant. 
 
1.12.3  All  materials  and  equipment  found  defective  shall  be  replaced  and  whole  work 
tested to meet the requirements of the specifications. 
 
1.12.4  Contractor  shall  perform  all  such  tests  as  may  be  necessary  and  required  by  the 
local authorities to meet Municipal or other bye‐laws in force. 
 
1.12.5  Contractor shall provide all labour, equipment and materials for the performance 
of the tests. 
 
1.13  Site Clearance and Cleanup 
 

PMC: NSL  F 5   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

1.13.1  The Contractor shall, from time to time clear away all debris and excess materials 
accumulated at the site. 
 
1.13.2  After  the  Fixtures,  equipment  and  appliances  have  been  installed  and 
commissioned,  Contractor shall clean‐up the same and  remove all plaster, paints 
stains,  stickers  and  other  foreign  matter  of  discoloration  leaving  the  same  in  a 
ready to use condition. 
 
1.13.3  On completion of all works, Contractor shall demolish all stores, remove all surplus 
materials  and  leave  the  site  in  a  broom  clean  condition,  failing  which  the  same 
shall be done at Contractors risk and cost. 
 
1.14  License Permits and Authorities  
 
1.14.1  Contractor must keep constant liaison with the Municipal/statutory authority and 
obtain  all  approval  of  all  drainage,  water  supply  and  other  works  carried  out  by 
him. 
 
1.14.2  Contractor  shall  obtain,  from  the  Municipal  and  other  authority’s  necessary 
completion certificate(s) with respect to his work as required for occupation of the 
building.  Contractor  shall  obtain  permanent  water  supply  and  drainage 
connections  from  authorities  concerned.  Employer  shall  pay  all  fees/deposits  as 
required to be paid to the authorities towards connection charges. 
  
1.15  Recovery of Cost for Materials issued to Contractors Free of Cost  
 
1.15.1  If any materials issued to the Contractor free of cost, are damaged or pilfered, the 
cost of the same shall be recovered from the Contractor on the basis of actual cost 
to owner which shall include all freight and transportation, excise duty, sales tax, 
octroi,  import  duty  etc.  plus  100%.  The  decision  on  the  actual  cost  given  by  the 
Employer shall be final and binding on the Contractor.        
 
1.16  Cutting of Water Proofing Membrane  
 
  No  walls,  terraces  shall  be  cut  for  making  and  opening  after  water  proofing  has 
been  done  without  written  approval  of  Project  Manager/Architects.  Cutting  of 
water  proofing  membrane  shall  be  done  very  carefully  to  ensure  that  other 
portion(s) of water proofing is (are) not damaged. On completion of work at such 
place  the  water  proofing  membrane  shall  be  made  good  and  ensured  that  the 
opening/cutting is made fully water proof as per specifications and details of water 
proofing approved by Architects.       
 
1.17      Cutting of Structural Members  
 
No structural member shall be chased or cut without the written permission of the 
Project Manager. 
 
1.18.  Materials Supplied by Owner 

PMC: NSL  F 6   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
1.18.1  The Contractor shall verify that all materials supplied by the Employer confirm to 
the specifications of the relevant item in the tender.  Any discrepancy found shall 
be brought to the notice of the Project Manager. 
 
 
 
 
 
1.19  Materials 
 
1.19.1 Unless  otherwise  specified  and  expressly  approved  in  writing  by  the  Project 
Manager,  only  materials  of  makes  and  specifications  mentioned  in  the  list  of 
approved makes attached with the specifications shall be used.  
 
1.19.2 If required, the Contractor shall submit samples of materials proposed to be used 
in the works. Approved samples shall be kept in the office of the Project Manager 
and returned to the Contractor at the appropriate time.   
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

PMC: NSL  F 7   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
SECTION II:  
PIPING FOR FIRE FIGHTING SYSTEM 
1.0  Scope 
1.1  The  scope  of  work  covers,  supply,  fabrication,  laying,  testing,  painting  and 
commissioning  of  the  entire  piping  system  for  the  fire  fighting  installation  i.e.  fire 
hydrant and sprinkler systems. 
 
2.0  Piping   
 
2.2  Internal 
2.2.1 All internal pipes shall be, unless otherwise specified, heavy quality mild steel tubes 
to IS 1239 using wrought steel heavy duty screwed fittings. Flanges shall be provided 
to mate with valves and other equipment and shall conform to IS 6392. Flanges shall 
be screwed type. Flanges shall be rated for 2.0 N/sqmm. 
2.2.2 Valves shall be suitable for external piping. 
2.2.3 All pipes shall be of approved make and best quality without rust marks. Pipes and 
fittings  shall  be  fixed  in  a  manner  as  to  provide  easy  accessibility  for  repair, 
maintenance  and  shall  not  cause  obstruction  in  shafts,  passages  etc.  Pipes  and 
fittings  shall  be  fixed  truly  vertical,  horizontal  or  in  slopes  as  required  in  a  neat 
workmanship manner. Pipes shall be securely fixed to walls and ceilings by suitable 
supports at intervals specified. Only approved type of anchor fasteners shall be used 
for RCC ceiling and walls. 
2.2.4 All  pipes  shall  be  adequately  supported  from  ceiling  or  walls  through  structural 
supports  fabricated  from  mild  steel  structural  e.g.  rods,  channels,  angels  and  flats 
generally as shown on drawings. Fasteners shall be shear type anchor fasteners in 
concrete walls and ceilings and wrought steel spikes of at least 75mm long in brick 
walls. All pipes supports shall be painted with 1 coats of red oxide primer and two 
coats of black enamel paint.  
2.2.5 All low point loops in the piping shall be provided with 25mm Ball Valves with rising 
spindle  for  draining  the  system.  All  valves  shall  have  screwed  brass  caps.  Likewise 
25mm  gun metal air vents  shall be provided at all high point loops to prevent air‐
locking. 
2.2.6 All  piping  shall  have  flanged  joints  at  about  25m  intervals  to  facilitate  easy 
maintenance. 
 

PMC: NSL  F 8   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

3.0 Pipe Jointing 
3.1 All pipes shall be provided with threaded joints up to 50mm diameter and welded 
joints for pipe above 50mm diameters. Hold tight shall be used for sealing. 
3.2 All welded joints shall be tested by radiography test. 
3.3 Joints between CI and GI pipes shall be made by providing a suitable flanged tail or 
socket piece and MS flange on the GI pipe. Flanges shall have appropriate number of 
holes and shall be fastened with nuts, bolts and 1.5mm thick compressed asbestos 
gasket. 
4.0 Valves and other accessories 
4.1 Gate Valves 
4.1.1 Sluice / Gate valves shall be used for isolation of flow in pipe lines For sizes upto 65 
mm, gate valves shall be outside screw rising spindle type and shall be as per IS: 778 
Class‐I and Class‐II, as applicable. For sizes 80 mm to 300 mm, gate valve shall be as 
per  IS:  780,  PN=1.0  and  shall  be  of  inside  screw  and  non  rising  type  and  cast  iron 
double flanged. 
4.1.2 Gate valves shall be provided with a hand wheel, draining arrangement of seat valve 
and  locking  facility  (as  required).  Gate  valves  shall  have  back  setting  bush  to 
facilitate gland renewal during full open condition. 
4.1.3 The  Body,  bonnet,  Stuffing  Box,  cap  and  hand  wheel  shall  be  of  cast  iron  to 
IS:210/70,  grade  FG 200 / 260.  The  non  rising  spindle  shall  be  of  solid  forged  high 
tensile brass or carbon steel to AISI 304 construction. The Body seating and wedge 
ring  shall  be  of  solid  leaded  gun  metal.  The  Bonnet  gasket  shall  be  of  high  quality 
rubber. 
4.1.4 The  Valve  shall  be  PN 1.0  rated  but  shall  withstand  tests  of  upto  20 kg / cm2.  The 
ends shall be flanged. The batch number of the valve shall be punched on the top of 
the flange. The spindle shall be removable type, and shall be easily rotated. 
 
4.5  Pressure Gauge 
4.5.1  The Pressure Gauge shall be constructed of die cast aluminium and stove enameled. 
It shall be weather proof with an IP 55 enclosure. It shall be a stainless steel Bourden 
tube  type  Pressure  Gauge  with  a  scale  range  from  0  to  16  Kg  /  CM2  and  shall  be 
constructed  as  per  IS:  3624.  Each  Pressure  Gauge  shall  have  a  siphon  tube 
connection. The Shut off arrangement shall be by Ball Valve. 
4.6  Ball Valve  
4.6.1  The Ball Valve shall be made from die cast brass and tested to 14 Kg/cm2 pressure. 
4.6.2  The valve shall be internally threaded to receive pipe connections. 
4.6.3  The  Ball  shall  be  made  from  brass  and  machined  to  perfect  round  shape  and 
subsequently chrome plated. The seat of the valve body‐ bonnet gasket and gland 
packing shall be of Teflon. 
4.6.4 The handle shall be of chrome plated steel with PVC jacket. The handle shall also 
indicate  the direction of `open' and `closed' situations. The gap between  the ball 
and the teflon packing shall be sealed to prevent water seeping upto 14 Kg / cm2 
pressure. 
4.6.5 The handle shall also be provided with a lug to keep the movement of the ball valve 
within 90 degree. The lever shall be operated smoothly and without application of 
any unnecessary force. 
4.7 Non Return Valve 

PMC: NSL  F 9   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

4.7.1 Non‐return valves shall be cast iron spring action swing check type. An arrow mark 
in  the  direction  of  flow  shall  be  marked  on  the  body  of  the  valve.  The  valve  shall 
bear IS:531 certification.  
4.7.2 The Valve shall be of cast iron body and cover. The internal flap in the direction of 
water shall be of cast iron and hinged by a hinge pin of high tensile brass or stainless 
steel. Cast iron parts shall be conform to IS:210 / 70, grade 200 / 260 type. 
4.7.3 The gasket shall be of high quality rubber and flap seat ring of leaded gun metal to 
BS 1400 LG 2C.  At  high  pressure  of  water  flow  the  flapper  shall  seat  tightly  to  the 
seat. The Valve shall be capable of handling pressure upto 15 kg / cm2. 
 
 
4.8 Butterfly Valve 
4.8.1 The Butterfly Valve shall be suitable for waterworks and tested to minimum of 16 kg 
/ sq cm pressure. The Valves shall fulfil the requirements of AWWA (American Water 
Works Association) C 504, API 609 and MSS‐SP‐67. 
4.8.2 The body shall be of cast iron to IS:210 in circular shape and of high strength to take 
the minimum water pressure of 10 kg / cm2. The disc shall be heavy duty cast iron 
with anti corrosive epoxy or nickel coating.  
4.8.3 The valve seat shall be of high grade elastomer or nitrile rubber. The Valve in closed 
position shall have complete contact between the seat and the disc throughout the 
perimeter.  The  elastomer  rubber  shall  have  a  long  life  and  shall  not  give  away  on 
continuous applied water pressure. The shaft shall be of EN 8 grade carbon steel. 
4.8.4 The  Valve  shall  be  fitted  between  two  flanges  on  either  side  of  pipe  flanges.  The 
Valve edge rubber shall be projected outside such that they are wedged within the 
pipe flanges to prevent leakage. 
4.8.5 The Valves shall be supplied with manual gear operated opening / closing system by 
lever. 
 
5.0  Pipe supports 
  All pipes whether horizontal or vertical shall be suitably supported using galvanized 
mild steel clamps/clevis hanger manufactured by M/s Hitech Support (India) Pvt Ltd 
or equivalent product of good quality as approved by engineer in‐charge. 
 
5.1  Vertical Pipes 
5.1.1  The  pipes  running  vertical  shaft  shall  be  supported  by  galvanised  mild  steel  rigid 
clamps fixed to wall with anchor bolts and studs. 
5.1.2  When the horizontal distance between the centre line of two adjacent pipes is less 
than 300 mm a powder coated HITECH/or equivalent rail shall be fixed to wall the 
pipes independently clamped to the rail with `U' bolt clamps. 
 
5.2  Horizontal Pipes 
5.2.1  Pipes  running  horizontal  shall  be  supported  from  structural  beam/slab  by  using 
appropriate galvanised M.S. pipe clevis hangers. 
5.2.2  The spacing of supports shall be as follows: 
GI Pipes/MS Pipes  CI Spun Pipes 
Internal  Dia  Internal  dia 
Spacing (mm)  Spacing (mm) 
(mm)  (mm) 

PMC: NSL  F 10   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

15  1800 75‐150 2700 


20,25  2400  200‐250  3000 
32  2700 300 3600 
40‐50  3000     
65‐80  3600  
100  4000     
150  4500  
5.2.3 Supports for horizontal  piping longer than 15m  in a stretch shall be provided with 
swivel  clamps.  Otherwise,  the  clamps  shall  be  universal  clamps  or  rigid  clamps  as 
required by the project engineer. 
5.3  Fixing of clamps/rails etc. 
  All  clamps,  rails  and  accessories  shall  be  fixed  to  the  structure  (beam,  slab,  walls 
etc.) by using approved good quality anchor fasteners of appropriate size. 
 
6.0  Painting 
6.1  All exposed piping for fire fighting shall be distinctly painted `Fire red' shade 536 to 
IS:5‐1978. Pipes shall  first receive two coats of red oxide  primer uniformly applied 
and  two  coats  of  oil  paint  applied  thereafter.  All  pipes  supports  shall  be  painted 
black as specified for support & clamps. 
 
6.2  Painting Schedule 
6.2.1  All equipment and  piping  shall be  painted in accordance  with the following colour 
code: 
Equipment  Colour  Distinguishing Mark 
  a)  Pump motors    Fire Red Shade  
          No.536 to IS: 5 ‐1978 
  b)  Internal piping Fire Red    " 
  c)  Sprinkler pipes Fire Red 
6.2.2 All  surfaces  to  be  painted  shall  be  thoroughly  cleaned  with  wire  brush  to  remove 
completely  rust  and  other  extraneous  substances.  Over  the  cleaned  surfaces  one 
coat of red oxide primer shall be applied completely covering the exposed surfaces. 
Finishing coat of enamel paint shall be applied one day after the prime coat, after 
ensuring that the paint is dry. The second coat shall be done before the installation 
is handed over and after approval to do so from the Engineer‐in‐charge. 
7.0 Testing & commissioning 
  All  piping  after  installation  shall  be  tested  for  a  hydrostatic  test  pressure  of  10.5 
kg/sqcm  or  1.5  times  the  working  pressure  (whichever  is  less)  maintained  for  24 
hours.  All  joints  and  valves  shall  be  checked  for  leaks  and  rectified  and  retested. 
During testing all valves except drain & air valves shall be kept fully open. 
8.0 Makes of materials  
  For makes of materials refer to list of approved makes of material. 
 
9.0  Mode of measurement 
9.1  All external piping shall be measured along the centre line of the pipe and paid per 
unit length and shall include: 
9.1.1  All pipes & fittings 
9.1.2  Bituminous coating 

PMC: NSL  F 11   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

9.2  All internal piping shall be measured similarly but shall include for the pipe supports 
and clamps. 
9.3  All  valves,  air  valves,  drain  valves  together  with  flanges  or  tail  pieces  shall  be 
measured per unit. 
9.4  All  excavation  and  concrete  supports  and  thrust  blocks  shall  be  measured  as  per 
drawing and paid for per cum.  
9.5  The cost of pipe supports described above form part of the rate quoted for piping 
and no extra shall be payable on the account.  
  All  painting  shall  form  part  of  the  cost  of  equipment  piping  etc.  No  separate 
payment shall be admissible. 

PMC: NSL  F 12   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION ‐ III 
SPRINKLER SYSTEM 
1.0  Pendant type Sprinkler Head 
1.1  Sprinkler heads shall be of quartzoid bulb type with bulb, valve assembly, yoke and 
the deflector. The sprinkler shall be of approved make and type with 15 mm nominal 
dia outlets. 
1.2  The bulb shall be made of corrosion free material strong enough to withstand any 
water  pressure  likely  to  occur  in  the  system.  The  bulb  shall  shatter  when  the 
temperature of the surrounding air reaches at 68o C / 79o C. 
1.3  The nominal bore shall be 15 mm dia and colour of liquid shall be Red / Yellow.  
1.4  The Sprinkler head shall be approved by UL / FM. 
 
2.0  Upright type Sprinkler Head 
2.1  Upright sprinkler heads shall be similar to Pendent type in material construction and 
performance but designed to throw water Droplets upwards in umbrella fashion, to 
cool the underside of ceiling and extinguish any fire involving combustibles on the 
floor below.  
2.2  The Sprinkler head shall be approved by UL / FM. The nominal bore shall be 15 mm 
dia and the colour of liquid shall be red.  
2.3  Upright Sprinkler heads shall be use in lower and upper basement parking areas and 
above the false ceiling. 
 
3.0  Side Wall type Sprinkler Head 
3.1  Side  wall  sprinkler  heads  shall  be  similar  to  Pendent  type  in  material  construction 
and performance but designed to throw water Droplets horizontally.  
3.2  The Sprinkler head shall be approved by UL / FM. The nominal bore shall be 15 mm 
diameter and the colour of liquid shall be red.  
3.3  Side wall sprinkler heads shall be use in staircase landing and along the ramp. 
 
4.0  Powder coated Sprinkler with Powder coated Twin plate Rosette.  
4.1  Most  areas  below  false  ceiling  shall  be  provided  with  powder  coated  pendant 
sprinkler with twin plate sliding rosette. The sprinkler head shall be same as Pendent 
type  above  but  powder  coated  white.  The  sprinkler  head  shall  be  provided  with  a 
double plate powder coated rosette that shall seal the gap between the false ceiling 
and he sprinkler head. 
4.2  The adjustment allowable shall be 12 mm. The lower part shall have flared ends that 
shall fit tightly into the upper piece.   
4.3  The Sprinkler head shall be approved by UL / FM. The nominal bore shall be 15 mm 
diameter and the colour of liquid shall be red.  
 
4.0  Makes of materials  
  For makes of materials refer to list of approved makes of material. 
 
5.0       Mode of measurement 
5.1 Sprinkler  head  including  supports  and  clamps  for  fixing  shall  be  measured  as 
unit. 
5.2 All  alarm  control  valves  including  drain  valves,  butterfly  valve  and  all  other 
accessories together with flanges or tail pieces shall be measured per unit. 

PMC: NSL  F 13   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

5.3 All floor control valves including drain valves, butterfly valve, sight glass and all 
other accessories together with flanges or tail pieces shall be measured per unit.

PMC: NSL  F 14   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

SECTION ‐ IV 
PORTABLE FIRE EXTINGUISHERS  
1.0  Scope 
1.1  The scope of work covers the supply and installation of portable fire extinguishers. 
The following types are envisaged in these specifications and provided as shown in 
the schedule of portable fire extinguishers. 
 1.1.1 Dry powder extinguisher 
1.1.2  Carbon‐dioxide extinguisher 
1.1.3 Mono ammonia phosphate extinguisher 
1.1.4 Water expelling type. 
2.0  Standards 
2.1  The following standards and rules and regulations shall be applicable: 
2.1.1  Fire protection manual of the tariff advisory committee, Fire Insurance Association 
of India 
2.1.2  IS:2176 :Portable fire extinguisher Dry power type 
2.1.3  IS:2878 :Portable fire extinguisher carbon‐dioxide type 
2.1.4  Local Fire Brigade/Authority 
2.2  All standards mean the latest. 
3.0  Extinguishers 
3.1  Dry powder type 
3.1.1  The  extinguishers  shall  be  2,  5,  10  kg  capacity  and  cartridge  type  unless  specified 
otherwise. 
3.1.2  The body shall be of cold rolled carbon steel grade D and 1.5mm thick upto 5 kg and 
2mm  for  10  kg.  The  construction  shall  be  similar  to  `Soda  Acid  type'  but  of  the 
following dimensions. 
Capacity (kg)    Outside dia (mm)    Filler opening (mm) 
    2.00      100      45 
    5.00      150      45 
    10.00      175      45 
3.1.3  The discharge fitting  shall be  with  500mm  10mm dia hose  upto  5  kg and 750 mm 
12.5 mm dia for 10 kg with a trigger controlled nozzle capable of discharging 85% of 
the contents as follows: 
  Capacity (kg)    Time (sec)    Throw (m) 
    2.00        8 ‐ 10      2 
    5.00       15 ‐ 20     4 
    10.00       23 ‐ 30     6 
3.1.4  A carbon dioxide cartridge conforming to IS:4947 shall be fitted in a cartridge holder 
with an inner shell. A spring loaded piercing device shall be provided in the cap for 
piercing  the  seal  of  the  gas  cartridge.  A  syphon  tube  of  copper  or  PVC  shall  be 
provided for upright operation. The cap and neck ring shall be similar to Soda Acid 
type extinguisher. 
3.1.5  All  internal  and  external  components  and  surfaces  shall  receive  anti‐corrosive 
coating of not less than 12 microns shall be applied uniformly as indicated below: 
  a)  Body      Mild steel    Tin alloy 
  b)  Cage for acid    Brass sheets    Lead  or  tin  alloybottle  and 
spring 
  c)  Discharge fittings  Leaded ‐ Tin    Tin alloy 
          Bronze 

PMC: NSL  F 15   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

  d)  Strainer    Brass sheets    Lead or Tin alloy 


 
3.2  Carbon dioxide type 
3.2.1  The  extinguishers  shall  be  rated  for  2.0  and  4.5  kg  by  weight  or  carbon  dioxide, 
unless  stated  otherwise.  The  contents  shall  be  with  a  filling  ratio  not  exceeding 
0.667. 
3.2.2  The  body  shall  be  steel  cylinder  made  according  to  IS:2872  and  approved  by  the 
chief controller of explosives. 
3.2.3 The discharge head shall be simple and safe to operate conforming to IS:3224 with a 
safety release to IS:5903 set to 18.0 to 20.0 N/sqmm. A syphon  tube of copper  or 
PVC shall be fitted. A non‐conducting discharge horn and a high pressure hose (27.5 
N/sqmm pressure) shall be fitted with each extinguisher. 
3.2.4 The discharge system shall be designed to expel 95% of the contents in continuous 
discharge as follows: 
    Capacity (kg)    Time (Sec.) 
    2.0      8 ‐ 18 
    3.0      10 ‐ 20 
    4.5      10 – 24 
3.3  Mono ammonium phosphate type 
3.3.1  The capacities envisaged are 2 kg & 5 kg. The filling pressure shall be 0.95 +/‐ 0.055 
N/sqmm. 
3.3.2  The  body  shall  be  cylindrical  in  shape  and  made  of  cold  rolled  carbon  steel  grade 
D/DD  or  hot  rolled  steel  plate  with  radiographically  tested  welded  construction. 
Plate thickness shall conform to IS:11108. 
3.3.3  Discharge valve mechanism shall be a simple and safe squeeze grip valve. 4.5 kg and 
above  capacity  shall  have  a  high  pressure  (0.5  N/sqmm)  hose  and  non‐conducting 
horn and shall also be provided with a pressure gauge. 95% of the contents shall be 
discharged as follows: 
  Capacity (kg)    Time (sec)      Throw (m) 
    2.00    8 ‐ 16        2 
    5.00    15 ‐ 24       4 
3.3.4  The internal and external components and surface shall be treated for anti‐corrosion 
as for dry powder type extinguishers. 
3.4 Water CO2 Fire Extinguisher 
3.4.1 The  extinguishing  medium  shall  be  primarily  water  stored  under  normal  pressure, 
the  discharge  being  effected  by  release  of  carbon  dioxide  gas  from  a  60  gms 
cylinder. 
3.4.2 The capacity of the cylinder when filled shall be 9 litres +/‐ 5 %. 
3.4.3 The  cylinder  shall  be  fabricated  from  MS  sheet,  welded  at  seams,  with  dish  and 
dome, being of same thickness and of size not exceeding the diameter of the body. 
The neck shall be externally threaded with leaded tin bronze. 
3.4.4 The  cap  shall  be  of  leaded  tin  bronze.  The  siphon  tube  shall  of  brass  or  GI.  The 
cartridge holder, knob, discharge fittings and plunger shall be of leaded tin bronze 
and plunger of stainless steel with spring also of stainless steel. The discharge tube 
shall be of braided nylon, of 10 mm dia and 600 mm length with a brass nozzle. 
3.4.5 The  extinguisher  shall  be  treated  for  anti  corrosion  internally  and  externally  and 
painted fire red externally. The cartridge shall be IS  marked. The Extinguisher body 

PMC: NSL  F 16   


SPECIFICATIONS: FIRE Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

shall  be  tested  to  25  bar  pressure  for  2  minutes.  The  Extinguisher  shall  be  IS:940 
marked. 
 
 
 
3.5  General requirements 
3.5.1  All extinguishers shall be standard products approved by the Local Fire Authority and 
manufactured  and  tested  strictly  in  accordance  with  the  relevant  Indian  Standard. 
All  markings  and  test  results  shall  be  stamped  in  the  appropriate  colour  markings 
accordingly to the Indian Standards. 
3.5.2 All extinguishers shall have a structurally designed galvanised steel handle and also a 
suitable wall mounting bracket. 
 

PMC: NSL  F 17   


SPECIFICATIONS: Plumbing Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

TECHNICAL SPECIFICATIONS
PLUMBING SYSTEM

SECTION - 1

SANITARY FIXTURES & FITTINGS

a. The  execution  of  works  and  materials  used  shall  be  as  per  the  latest  relevant  I.S. 
specification.     
 
  Wherever reference has been made to Indian Standard or any other specifications, 
the same shall mean to refer to the latest specification irrespective of any particular 
edition of such specification being mentioned in the specifications below or Schedule 
of Quantities. 

b. WORKMANSHIP

The workmanship shall be best of its kind and shall conform to the specifications, as 
below or Indian Standard Specifications in every respect or latest trade practices and 
shall  be  subject  to  approval  of  the  Architects.  All  materials  and/or  Workmanship 
which  in  the  opinion  of  the  Engineer  is  defective  or  unsuitable  shall  be  removed 
immediately  from  the  site  and  shall  be  substituted  with  proper  materials  and/or 
workmanship forthwith. 
 
c. MATERIALS

All  materials  shall  be    best  of  their  kind  and  shall  conform  to  the  latest  Indian 
Standards. 
 
  All materials shall be of approved quality as per samples and origins approved by the 
Architects/Consultants.  
 
  As  and  when  required  by  the  Architect/Consultant,  the  contractor  shall  arrange  to 
test the materials and/or portions of works at his own cost to prove  their soundness 
and efficiency. If after tests any material, work or portions of work is found defective 
or  unsound  by  the  Architect/Consultant,  the  contractor  shall  remove  the  defective 
material  from  the  site,  pull  down  and  re‐execute  the  works  at  his  own  cost  to  the 
satisfaction  of  the  Architect/Consultant.  To  prove  that  the  materials  used  are  as 
specified,  the  contractor  shall  furnish  the  Architect/Consultant  with  original 
vouchers on demand. 
 

PMC: NSL PL1


1. INSTALLATION OF SANITARY FIXTURES AND FITTINGS

1.1 General Requirement

The fixtures and fittings shall be provided with all such accessories as are required 
to  complete  the  item  in  satisfactory  working  conditions,  whether  specifically  
mentioned or not in the schedule of quantities, Specifications and drawings. 
 
  The sanitary fixtures and fittings shall be installed at the correct assigned position as 
shown on the drawings and as directed by the Architect,  and shall fully meet with 
the  aesthetic and symmetrical requirements as demanded by the Architect. 
 
  All  fixtures and accessories shall be fixed in accordance with a set pattern matching 
the  tiles  or  interior  finish  as  per  Architect  requirements.  Wherever  necessary,  the 
fittings shall be  centered to dimensions and pattern as called for. 
 
  Fixtures shall be installed by skilled workman with appropriate tools according to the 
best trade practice. Manufacturer's instructions shall be followed for the installation 
of fixtures. Fixtures in all toilets shall be standard height mounting as called for on 
the drawings. Fixtures shall be mounted rigid, plumb, and true to alignment. 
 
1.2 Mock up and Trial Assembly

The  contractor  shall  have  to    assemble  at  least  one  set  of  each  type  of  sanitary 
fixtures and fittings in order to determine precisely the required supply and disposal 
connections.  Relevant  instructions  from  manufacturers  shall  be  followed  as 
applicable.  This  trial  assembly  shall  be  developed  to  determine  the  location  of 
puncture holes, holding devices etc. which will be required for final installation of all 
sanitary fixtures and fittings. The above assembly shall be subject to final approval by 
the Architect. 
 
  The  fixtures  in  the  trial  assembly  can  be  re‐used  for  final  installation  without  any 
additional payments for fixing or dismantling of the fixtures. 
 
1.3 Supporting and Fixing Devices

The contractor shall  provide all the necessary supporting and fixing devices to install 
the  sanitary  fixtures  and  fittings  securely  in  position.  The  fixing  devices  shall  be 
rigidly  anchored  into  the  building  structure.  The  devices  shall  be  rust  resistant  and 
shall  be  so  fixed    that  they  do  not  present  an  unsightly  appearance    in    the  final 
assembly. Where the location demands, the Architect may instruct the contractor to 
provide  chromium  plated  or  other  similarly  finished  fixing  devices.  In  such 
circumstances the contractor shall arrange to supply the fixing devices and shall be 
installed complete with appropriate vibration isolating pads, washers and gaskets. 
 
2
SPECIFICATIONS: Plumbing Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

1.4 Final Installation

The  contractor  shall  install  all  sanitary  fixtures  and  fittings  in  their  final  position  in 
accordance  with  approved  trial  assemblies  and  as  shown  on  drawings.  The 
installation shall be complete with all supply  and waste connections. The connection 
between building and piping system and the sanitary fixtures shall be through proper 
unions  and  flanges  to  facilitate  removal/replacement  of  sanitary  fixtures  without 
disturbing  the  built  in  piping  system.    All  unions  and    flanges  shall  match  in 
appearance with other exposed fittings. 
 
  Fixtures shall be mounted rigid, plumb and to alignment. The  outlets of water closet 
pans and similar appliances shall be examined to ensure that outlet ends are butting 
on  the  receiving    pipes  before  making  the  joints.  It  shall  be  ensured  that  the 
receiving pipes are clear of obstruction. When fixtures are being mounted, attention  
shall  be  paid  to  the  possibility  of  movement  and  settlement  by  other  causes. 
Overflows  shall  be  made  to  ensure  that  necessary  anchoring  devices  have  been 
provided for supporting water closets, wash basins, sinks and other appliances. 

2. PROTECTION AGAINST DAMAGE

The  contractor  shall  take  every  precaution  to  protect  all  sanitary  fixtures  against 
damage,  misuse,  cracking,  staining,  breakage  and  pilferage  by  providing  proper 
wrapping and locking arrangement till the completion of the installation. At the time 
of  handing over, the contractor shall clean, disinfect and polish all the fixtures and 
fittings.  Any  fixtures  and  fittings  found  damaged,  cracked  chipped  stained  or 
scratched shall be removed and new fixtures and fittings free from defects shall be 
installed at his own cost to complete the work. 
 

PMC: NSL PL3


SECTION - 2
WATER SUPPLY

1. PIPING MATERIAL

1.1 CPVC Pipes


 
All water supply CPVC pipes shall be manufactured using CPVC compound with cell 
class  234478  defined  by  ASTM  D1748  with  design  stress  of  2000  psi.  All  pipes  & 
fittings shall be jointed with solvent as supplied by the manufacture. All CPVC pipes 
&  fittings  shall  be  approved  by  CPWD.  Metal  hooks  or  nails  shall  not  be  used  to 
support/hold  or  put  pressure  on  the  pipes.  Straps  &  hangers  with  rough  or  sharp 
edges shall not be used. 
 
Horizontal support spacing shall be as follows. 
(Distance between pipe clamps). 
 
15 mm normal dia – 1m 
20 mm normal dia – 1.2m 
25 mm normal dia – 1.37m 
32 mm normal dia – 1.5m 
40 mm normal dia – 1.6m 
50 mm normal dia – 1.9m 
60 mm normal dia – 1.8m 
75 mm normal dia – 2.1m 
100 mm normal dia – 2.3m 
 
1.2 Valves & Controls
 
     All  valves  (gate,  check,  safety)  shall  be  of  gun  metal,  non  rising  spindle,  
suitable  for  the  particular  service  as  called  for.  All  valves  shall  be  of  the  
particular  duty  and  design  as  called  for.  Valves  shall  either  be  of  screwed 
type    or  flanged  type,  with  suitable  flanges  and  non‐corrosive  bolts  and 
gaskets. Gate and check valves shall conform to Indian Standard IS:776  
   
--------------------------------------------------------------------------------------
Type of valve Size Construction Ends.
---------------------------------------------------------------------------------------
a) G.M.valve    15mm to 65mm   Gun metal  Screwed. 
              65mm and above    Gun metal  Flanged.   
                

2. LAYING AND JOINTING OF PIPES


4
SPECIFICATIONS: Plumbing Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

  All pipes and fittings shall be fixed truly vertical and horizontal unless unavoidable. 
The  pipes  shall  be  fixed  to  walls  with  standard  slotted  angles  `U'  shape  threaded 
bolts,  nuts  for  clamping  pipes  to  angles.    Slotted  angles  shall  be  grouted  to  R.C.C. 
work with dash fasteners of size so as to fit tightly on the pipes when tightened with 
screwed  bolts.  These  slotted  angles  shall  be  spaced  at  regular  intervals  in  straight 
lengths and heights at 1.8m C/C. 
 
        The  pipes      and  fittings  shall  run  in  wall  chase  or  ceiling  or  as  specified.  The  fixing 
shall  be  done  by  means  of  standard  pattern  holder  bat  clamps  keeping  the  pipes 
about  1.5cm  clear  of  the  wall  where  to  be  laid  on  surface.  Where  it is specified to 
conceal  the  pipes,  chasing  may  be  adopted  or  pipes  fixed  in  the  shafts,  ducts  etc. 
provided there is  a sufficient space to work on the pipes with the usual tools. As far 
as possible, pipes may be buried for short distances provided adequate protection is 
given  against  damage  and  where  so  required  special  care  to  be  taken  at  joints. 
Where  directed  by  the  Architect,  pipe  sleeves  shall  be  fixed  at  a  place  where  the 
pipe is passing through a wall or floor for reception of the pipe and allow freedom 
for  expansion  and  contraction  and  other  movements.  Under  the  floors,  the  pipes 
shall be laid in layer of sand filling. 
 
       Pipes shall be jointed with solvent joints.  
 
  The pipes and fittings shall run in wall chase or ceiling or as specified. The fixing shall 
be  done  by  means  of  standard  pattern  holder  bat  clamps  keeping  the  pipes  about 
1.5 cm clear of the wall where to be laid on surface. Where it is specified to conceal 
the pipes, chasing may be adopted or pipes fixed in the shafts, ducts etc. provided 
there is sufficient space to work on the pipes with the usual tools. As far as possible, 
pipes  may  be  buried  for  short  distances  provided  adequate  protection  is  given 
against  damage  and  where  so  required  special  care  to  be  taken  at  joints.  Where 
directed  by  the  Architect,  pipe  sleeves  shall  be  fixed  at  a  place  the  pipe  is  passing 
through  a  wall  or  floor  for  reception  of  the  pipe  and  allow  freedom  for  expansion 
and    contraction  and  other  movements.  In  case  of  pipe  is  embedded  in  walls  or 
floors it should be provided with protection. 
   
3. PIPING INSTALLATION:

Piping  shall  be  properly  supported  on,  or  suspended  from,  on  stands,  clamps, 
hangers as specified and as required. The Contractor shall adequately provide all the 
brackets,  saddles,  anchor,  clamps  and  hangers,  and  be  responsible  for  their 
structural stability.  
 
      Pipe supports  shall be steel, adjustable for the height and primer coated with rust 
preventive paint and finish coated black. 
         
  Vertical  risers  shall  be  parallel  to  walls  and  column  lines  and  shall  be  straight  and 
plumb. Risers passing from floor to floor shall be supported at each floor by clamps 
PMC: NSL PL5
or  collars  attached  to  pipe  and  with  a  15  mm  thick  rubber  pad  or  any  resilient 
material.  
 
        All  pipe   work   shall   be   carried   out   in a proper  workman   like  manner, causing 
minimum  disturbance  to  the  existing  services,  buildings,  roads  and  structure.  The 
entire  piping  work  shall  be  organized  in  consultation  with  other  agencies  work,  so 
that area can be carried out in one stretch. 
 
        Cut‐outs  in  the  floor  slab  for  installing  the  various  pipes  area  are  indicated  in  the 
drawings. Contractor shall carefully examine the cut‐outs provided and clearly point 
out  wherever  the  cut‐outs  shown  in  the  drawings,  do  not  meet  with  the 
requirements. 
 
        The  contractor  shall  make  sure  that  the  clamps,  brackets,  saddles  and  hangers 
provided  for  pipe  supports  are  adequate.  Piping  layout  shall  take  due  care  for 
expansion and contraction in pipes and include expansion joints where required. 
 
        All pipes shall be accurately cut to the required sizes in accordance with relevant BIS 
codes and burrs removed before laying. Open ends of the piping shall be closed as 
the pipe is installed to avoid entrance of foreign matter.  

3.1 Cutting Chases in Masonry Walls

The  chases  upto  7.5  x  7.5  cm    shall  be  made  in  the  walls  for  housing  GI  pipes  etc. 
These shall be provided in correct positions as shown in the drawings or directed by 
the Architects. Chases shall be made by chiselling out the masonry to proper line and 
depth.  After  pipes  etc  are  fixed  in  chases,  the  chases  shall  be  filled  with  cement 
mortar  1:2:4    or    as  specified  may  be  made  flush  with  the  masonry  surface.  The 
concrete surface shall be roughened with wire brush to provide a key for plastering. 
Chase  cutting  in  walls  &  hole  cutting  in  conc.  slabs  shall  be  done  by  electric 
cutters/grinders. 
 
3.2 Water Fittings

  Unless otherwise specified all gunmetal  fittings such as gate, globe, check & safety 
valves shall be fitted in pipe line in a proper workman like manner. Necessary unions 
shall  be  provided  on  both  ends  of  the  valves  for  easy  replacement.  The  joints 
between      fittings  and  pipes  shall  be  leak‐proof  when  tested  to  a    pressure  of  2.5 
times  of  working  pressure.  The  defective  fittings  and  joints  shall  be  replaced  or 
redone. 

3.3 Shifting of Excavated Surplus Material

Contractor shall make his own arrangement to shift the surplus excavated material 
within the site limits as directed by Engineer‐in‐charge. 
 

6
SPECIFICATIONS: Plumbing Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

 
 
 
3.4 Testing
 
a) All water supply system shall be tested to hydrostatic pressure test of at last two 
and  half  time  the  maximum  pressure  but  not  less  than  10.0  Kg/Sq  Cm.  for  a 
period  of not  less than 24 hours. All leaks and defects  in joints revealed during 
the testing shall be rectified and got approved at site. 
 
b) Piping  required  subsequent  to  the  above  pressure  test  shall  be  retested  in  the 
same manner. 
 
c) System may be tested in sections and such sections shall be entirely retested on 
completion. 
 
d) The  Contractor  shall  make  sure  that  proper  noiseless  circulation  of  fluid  is 
achieved through the entire piping network of the system concerned. In case of 
improper  circulation,  the  contractor  shall  rectify  the  defective  connections.  He 
shall  bear  all  expenses  for  carrying  out  the  above  rectifications  including  the 
tearing up and refinishing of floors and walls as required. 
 
 

PMC: NSL PL7


SECTION - 3
INTERNAL DRAINAGE(SOIL,WASTE & VENT PIPES)

 1. BASIC PIPING SYSTEM

Soil,  waste  and  vent  pipes  in  shafts,  ducts  and  in  concealed  areas  i.e. false ceilings 
etc. shall consist  of UPVC pipes & fittings as called for. In general wastes and vents 
smaller than 50mm dia  shall be of  UPVC. 
 
The  soil  pipes  shall  be  circular  with  a  minimum  diameter  of  75mm.  Pipes  shall  be 
fixed by means of stout MS / GI clamps in two sections,  bolted together, built into 
the walls, wedged and neatly jointed as directed and approved by the Architect. All 
bends,  branches, swan neck  and  other parts shall conform to the requirement and 
standards  as  described  for  the  pipes.  Pipes  shall  be  rested  against  the  walls  on 
suitable  wooden  cradles.  Local  authority  regulations  applicable  to  the  installations 
shall be strictly followed. 
 
Where indicated, the soil pipes shall be continued upwards without any diminution 
in  its  diameter,  without  any  bend  or  angle  to  the  height  shown  in  the  drawings.  
Joints  throughout  shall  be  made  with  molten  lead  as  described  under  jointing  of 
pipes.  The  soil  pipes  shall  be  covered  on  top  with  cast  iron  terminal  outlets  as 
directed  and  approved.  All  vertical  soil  pipes  shall  be  firmly  fixed  to  the  walls  with 
properly fixed clamps, and shall as far as possible be kept 50mm clear of wall.  
 
Every  waste  pipe  shall  discharge  above  the  grating  of  properly  trapped  gully.  The 
contractor will ensure that this requirement is adequately met with. Wherever floor 
traps  are  provided,  it  shall  be  ensured  that  atleast  one  wash  is  connected  to  such 
floor traps to avoid drying of water seal in the trap. Ventilating pipes shall be UPVC 
pipes, conforming to the requirements laid down earlier.  
All  the  fittings  used  for  connections  between  soil,  waste  and  ventilation  pipes  and 
branch pipes shall be made by using pipe fittings with  inspection doors for cleaning. 
The doors shall be air and water tight. 
 
Where soil, waste and ventilating pipes are accommodated in shafts ducts, adequate 
access to cleaning eyes shall be provided. 

2. PIPING MATERIALS

 2.1 UPVC Pipes

UPVC pipes and fittings shall  be of good quality. The pipes and fittings shall 
be true to shape, smooth and cylindrical, their inner and outer surface being 
as nearly as practicable concentric. They shall be sound and nicely cast, shall 
be free from cracks, taps, pinholes and other manufacturing defects. 
 

8
SPECIFICATIONS: Plumbing Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

    The  pipes  and  fittings  shall  conform  to  IS  as  mentioned  in  schedule  of 
quantities.  Fittings  shall  be  of  required  degree  with or without access  door. 
All  access  doors shall be air and water tight. The fittings shall be of the same
manufacture as the pipes used for soil and waste.

All pipes and fittings shall bear the manufacturer's name and ISI specification to which
it conforms.

All pipes and fittings shall be coated internally and externally with the same material
at the factory.
All pipes and fittings before installation at site shall be tested hydrostatically to a
pressure of 0.4 Kg/sq. cm without showing any sign of leakage, sweating or other
defects of any kind. The pressure shall be applied internally and shall be maintained
for not less than 15 seconds. All these tests shall be carried out in the presence of
the representative of the Architects. Alternatively a test certificate from manufacturers
be obtained before despatch of material to site.

The pipes and fittings shal be as called for. The pipes and fittings shall be of uniform
material throughout and shall be free from all manufacturing defects.

2.2 UPVC Specialities

UPVC speciality item such as deep seal floor traps, urinal  traps, trap integral 
pieces  with  integral  inlet/outlet  connections  etc.  shall  be  fabricated  to  suit 
individual location requirements. The contractor shall arrange the fabrication 
of these items from an approved  source.  All traps shall have minimum 5cm 
deep seal. 

2.3 UPVC Pipes

          Waste  pipes  50mm  dia  below  and  where  called  for  shall  be  UPVC  pipes 
conforming  to  the  requirements  of  IS:4985.  The  pipes  and  sockets  shall  be 
cleanly  finished  and  free  from  cracks,  surface  flaws  and  other  defects.  All  
ends  shall  be  clean  and  well  cut.  All  pipes  and  fittings  shall  bear 
manufacturer's trade mark and conform to the IS as specified. 

3. INSTALLATION OF SOIL, WASTE & VENT PIPES

Soil,  waste  &  vent  pipes  in  shafts  under  the  floors  shall  consist  of  UPVC  pipes  as 
described earlier. Waste pipes from bottle trap to floor/urinal traps for wash basin, 
urinal and sink shall be of  UPVC pipes and fittings. 
 
  All  Horizontal  pipes  running  below  the  slab  and  along  the  ceiling,  shall  be  fixed  on 
structural  adjustable  clamps,  sturdy  hangers  of  the  design  as  called  for  in  the 
drawings. The pipes shall be laid in uniform slope and proper levels. All vertical pipes 
shall  be  truly  vertical  fixed  by  means  of  stout  clamps  in  two  sections,  bolted 
together, built into the walls, wedged and neatly jointed. The branch pipes shall be 
connected to the stack at the same angle as that of fittings. All connections between 
soil,  waste  and  ventilating  pipes  and  branch  pipes  shall  be  made  by  using  pipe 
PMC: NSL PL9
fittings  with  inspection  doors  for  cleaning.  Pipes  shall  be  fixed  in  a  manner  as  to 
provide easy accessibility for repair and maintenance and shall not cause obstruction 
in shafts. Where the horizontal run off the pipe is long or where the pipes cross over 
building  expansion  joints  etc.  suitable  allowance  shall  be  provided  for  any 
movements in the pipes by means of expansion joint etc. such that any such movement
does not damage the installation in any way.

All pipes and fittings shall be jointed with best quality solvent free from all impurities.

Before  jointing,  the  interior  of  the  socket  and  exterior  of  the  spigots  shall  be 
thoroughly cleaned and dried.  
   
  The joint shall not be covered till the pipe line has been tested under pressure. Rest 
of pipe line shall be covered so as to prevent the expansion and contraction due to 
variation in temperature. 

4. INSPECTION AND TESTING

Before  the  appliances  are  connected  all  opening  of  pipes  shall  be  inspected  and 
tested.  All  opening  of  pipes  shall  be  sealed  with  plugs  and  water  test  in  small 
sections of pipes shall be carried out to a static head of 4.5 meters. 
 
  The contractor shall give a smoke test to the drains and sewers at his own expense 
and charges as directed by the engineer‐in‐charge. 
 
  After installation of  all the appliances, discharge test shall be conducted individually 
and  collectively.  Obstruction  in  any  of  the  pipe  lines  shall  be  traced  and  whole 
system  is  examined  for  hydraulic  performance,  including  the  retention  of  any 
adequate  water  seal  in  each  trap.  Any  defect    revealed  by  the  tests  shall  be  made 
good and the tests are repeated until a satisfactory result is obtained. 
 
5. PIPE PROTECTION

Where pipes are embedded in floors, slabs, column, beams etc. they shall be 
Given a protection by encasing them with 100mm thick 1:3:6 cement concrete 
 All round the pipes and fittings as specified in Schedule of Quantities. 
  
6. NAHANI TRAP OR FLOOR TRAPS

Nahani traps or floor traps shall be UPVC deep seal with an effective seal of 50mm. 
The trap and waste pipes shall be set in cement concrete blocks firmly supported on 
the structural floor. The blocks shall be in 1:2:3 mix (1cement: 2coarse sand: 4 stone 
aggregate 20mm nominal size ) mixed with water proof compound and extended to 
40  mm  below  finished  floor  level.  Contractor  shall  provide  all  necessary  shuttering 
and  centering  for  the  blocks.  Size  of  the  block  shall  be  30x30  cms  of  the  required 
depth.  The  trap  shall  be  installed  at  lowest  point  ensure  no  ponding  occurs  at 
perimeters of the drain.  

10
SPECIFICATIONS: Plumbing Pharmacy Council of India, 3rd Floor,
NBCC Center, Okhla, New Delhi

7. CLEANOUT PLUGS

Contractor shall provide cast brass cleanout plugs in all horizontal run more than 15 
mtr  length  required  one  cleanout  plugs  shall  be  threaded  and  provided  with  key 
holes for opening. Cleanout plugs shall be threaded and provided with key holes for 
opening.  
 
 

PMC: NSL PL11


APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

LIST OF APPROVED MAKES 
SECTION C 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

NSL
PMC CONSULTANT 0  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

 
 
SCHEDULE OF APPROVED MAKES FOR INTERIOR WORKS 
The attached list schedule indicates the approved manufacturer for Interior works 
 
 
S.No.  Equipment/ Material            Acceptable Supplier/ Manufacturer 

1  Timber Wood  Ivory cost/ATI/  Burma Teak/ Equivalent 
2  Plywood   Century/Green Ply/Kitply 
3  MDF Board  Kitply/ Green Ply 
4  Particle Board/Ply board  Kitply/ Merino/ Green Ply 
5  Flush Door   Kitply/Century/Green Ply 
6   Glass  Saint Gobain/ Indo Asahi/ Modifloat/  
7  Gypsum board and sections  USG Boral/Armstrong/Gyprock/  
8  Veneer  Century/ Green Ply/ kitply 
9  Laminate sheet   Century/Royal Touch/Greenlam/ 
10  Flooring (Vitrified/wall)  Somany/ RAK/ Kajaria/ NITCO 
11  Grouting / Adhesive  Laticrate/ Fosrock/ferrouscrete 
12  Flooring wooden   Green Ply /Pergo/EGO 
13  Anti‐Static flooring  Armstrong / premier polyfilm  or approved equivalent make 
14  Carpets  Forbo flooring/  Interface/ Milliken  
15  Raised floor  Unifloor/ TATE/ Kingspan 
16  Acoustic Grid ceiling  Armstrong/USG Boral/ecophon 
17  Metal Ceiling   Armstrong/ USG Boral/ Unimet 
18  Adhesive  Fevicol / Vamicol/ Araldite/  
19  Anchor Fastener  Fischer/ Hilti/ or approved equivalent make 
20  Hardware Fittings     Dorma/FSB/Dline 
21  Signage  Neki/ 3m/  Or approved equivalent make 
22  Paint and polishes  Asian paints/ ICI/Dulux/ 
23  Glass Wool  UP TWIGA/ Kimmco/ or equivalent make 
24  Glass Graphics  3M   or approved equivalent make 
25  Window Blinds  Hunter Douglas/ Vista / D Decor 
26  Modular furniture  Godrej /HNI/Steel case 
27  Wall Paper  Marshall/Wallking/ Elemento/ 
28  Cement (OPC 43 grade)  Ultratech/ Birla Uttam/ JK Laxmi/ ACC 
29  Aluminum Skirting  Bottomlne or equivaent 
30  Planters and Pot  https://www.fourwalls.in/contact 
http://www.artificialplants.in/bamboo‐plant.html 
https://www.pepperfry.com/home‐decor‐garden‐decor‐artificial‐
plants.html 
31  Signages  Vansh Graphics, Insha Advertising, Gcom Advertising 
32  2 hr fire rated doors  Promat, Ardor, Doors n doors 

NSL
PMC CONSULTANT 1  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

 
 

SCHEDULE OF APPROVED MAKES FOR ELECTRICAL WORKS 
 
The attached list schedule indicates the approved manufacturer for electrical and Data Centre works. 
 
S.No.  Equipment/ Material            Acceptable Supplier/ Manufacturer 
1  MCCB’s & ACB’s  Legrand/Schneider/ABB/L&T 
2  MCB’s & DB's  Legrand/Schneider/Hager/L&T/MK‐Honeywell 
3  ELCB’s & RCBO’s  Legrand/Schneider/ABB/L&T/MK‐Honeywell 
4  MPCB’s :   Legrand/Schneider/Hager/L&T 
5  1100 V grade ZHLS (Zero Halogen low  PolyCab/RR Kable/KEI wires/Havells 
smoke) ZHLS Polymer insulated, 
unsheathed, flexible, copper conductor 
wires 
6  1100 V grade FRLS (Fire Retardant low  PolyCab/RR Kable/KEI wires/Havells 
smoke) HR FRLS PVC insulated unsheathed, 
flexible, copper conductor wires 
7  1.1/11/33kV grade LT/HT XLPE insulated,  PolyCab/RR Kable/KEI wires/Havells/ Ravin Cable 
HR PVC sheathed, stranded Al. / Cu. 
conductor, Armoured/ Unarmoured cables 
as per IS:7098 Part‐I  
8  1.1kV grade LT PVC insulated, PVC,  PolyCab/RR Kable/KEI wires/Havells 
sheathed, stranded Al. / Cu. conductor, 
Armoured/ Unarmoured cables as per 
IS:1554  
9  1.1kV grade Single core LT PVC insulated,  PolyCab/RR Kable/KEI wires/Havells 
unsheathed, multi strand, flexible Copper 
conductor Un. Ar. Cables as per IS:694. 
10  Cable lugs & thimbles   Dowell/Asian/Action 
11  Cable glands   PolyCab/Dowell/Commet 
12  TV Co‐axial Cable   Delton/Finolex/Havells 
13  Paging / Music Speaker Wire (Twin Twisted)  Delton/As recommonded by Speaker supplier 
14  MS/GI Conduits & Accessories   RKG/AKG/POLYPACK 
17  Data Wire (Cat6)  Legrand/AMP 
18  Occupancy Sensor  Philips/Wipro/Schneider/ M.K. (Honeywell) 
19  PAC   Emerson, Schneider, Bluebox 
20  UPS System   Emerson, Schneider, EATON, Numeric 
21  IT Racks   Panduit, Rittal, Schneider 
22  BMS System   SCHNEIDER, SIEMENS, JCI, HONEYWELL. 
23  Structured Cabling System (LSZH)   Panduit, TE, Schneider 
24  Hardware server/ Desktop Computers  HP/IBM/DELL 
25  Cable Tray  LEGRAND (CABLOFIL)/  Panduit / PROFAB/ MK 
26  NOVEC Gas System   UTC, Tyco, Siemens                                                                 
27  Fire Detection & Alarm System   Honeywell, UTC, Tyco, RAVEL 
28  VESDA System   Siemens, UTC, System Sensor, TYCO, HONEYWELL 
29  LED Light Fixture   Wipro, Philips, HAVELLS 

NSL
PMC CONSULTANT 2  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

30  Electrical Switchgear   ABB, Schneider, Siemens, L&T 


31  Energy meter                             Enercon / L & T / HPL Socomec                         
32  Industrial socket outlet (socket and top)      MDS‐Legrand / PCE (RR Kabel)/Clipsal/Hensel 
33  Earth Leakage Circuit Breaker         Legrand (MDS)/ABB/ L&T Hager 
34  Maintenance Free Earthing   Ampere Protection Service, Manav Energy, Servotech 
India Ltd. 
35  Raceway – with sheet steel  Applicam Industries / MK/ Profab 
     
     
 
SCHEDULE OF APPROVED MAKES FOR ELV WORKS 
 
 
S.No         Equipment/ Material  Acceptable Supplier/ Manufacturer 
A.  AV Equipment     
1  LED TV   Samsung, Sharp, LG 
2  Mount  Bronx, NB, Chief 
3  AV Hidden Connection Box           Bronx, Kramer, Altenix 
4  Multi format Switcher  Lightware, Extron, AMX 
5  Ceiling Speaker  TOA, Equipson SA, JBL 
6  Mixer Amplifier  TOA, Equipson SA, Crown 
7  Wireless Microphone System  TOA, Shure, Sennheiser 
8  Automatic Line / Mic Mixer  Tendzone, Biamp, Polycom 
9  Multipurpose Line / Mic Mixer  Tendzone, Sound craft 
10  Boundary Microphone  Bronx, Shure, Sennheiser 
11  Video Conference System  Polycom, Lifesize, Cisco 
12  Central Processor  Crestron, AMX, Cue 
13  Wifi    D Link, Netgear, or Approved Equivalent 
14  Relay System  Crestron, AMX, Bronx 
15  Dimming Module  Crestron, AMX, Lutron 
16  Equipment Rack  Bronx, Valrack, President 
17  Audio Video Cable  Kramer, Belden, Extron 
       
B  PUBLIC ADDRESS SYSTEM    
1  Ceiling Speaker   Bosch, TOA, Aties 
2  Wall Mount Speaker  Bosch, TOA, Aties 
3  Power Amplifier  Bosch, TOA, Aties 
4  System Pre Amplifier  Bosch, TOA, Aties 
5  DVD Player  Samsung, Philips, Sony 
6  Call Station  Bosch, TOA, Aties 
7  Control Unit  Bosch, TOA, Aties 
8  Microphone Unit  Bosch, TOA, Aties 
9  Equipment Rack  Bronx, Valrack, President 
10  Speaker Cable  MX, Kramer, Belden 
11  Priority Circuit  Bosch, TOA, Aties, or Approved Equivalent 
     
C  ACCESS CONTROL SYSTEM   
        

NSL
PMC CONSULTANT 3  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

1  Proximity card reader  HID, AWID, Motorola 
2  Proximity card reader with Keypad  HID, AWID, Motorola 
3  Electro Magnetic Lock  Bell, RBH 
4  Emergency door release  RBH, Lenel, Honeywell 
5  Card reader interface  RBH, Lenel, Honeywell 
6  Network controller  RBH, Lenel, Honeywell 
7  Proximity cards  HID, AWID, Motorola 
8  Access card photo ID printer  HID, AWID, Motorola 
9  Data Cable  Finolex, Delton, Polycab 
10  Access Control Software  RBH, Lenel, Honeywell 
11  Server  Dell, hp, IBM 
     
     
F  CCTV SYSTEM   
2  IP Dome Camera  Urmet, Sony, Axis 
3  Monitoring Software  Milestone, Urmet, Videonetics, Genetec, ISS 
5  Network Switch  Cisco, Juniper, Allied Telesis 
6  Server Storage  Milestone, Urmet, Videonetics, Genetec, ISS 
7  Equipment Rack  Rittal / APC / Arctic 
8 Armored Optical Fiber  Finolex, Excel, Delton, Molex 
9 Cat Cable  Finolex, Excel, Delton, Molex 
10 Server  Dell, hp, IBM 
11 Video Wall Panel  Samsung, Panasonic, LG 
12 RJ‐45 Out lets  Dlink, Netgear, Cisco 
14 Media Converter SM/SFP Module  Dlink, Netgear, Cisco 
15 LIU to Media converter  Dlink, Netgear, Cisco 
16 LIU box  Dlink, Netgear, Cisco 
   
F  LAN SYSTEM   
1 CAT 6 UTP Cable  Finolex, Excel, Delton, Molex 
2 Jack Panel  Finolex, Excel, Delton, Molex 
3 Cat 6 Patch Cords  Finolex, Excel, Delton, Molex 
4 2 Port Faceplate  Finolex, Excel, Delton, Molex 
5 Riser Cable  Finolex, Excel, Delton, Molex 
6 Krone Module  Krone or Approved Equivalent 
7 Armored Optical Fiber & Accessories  Finolex, Excel, Delton, Molex 
8 LIU box  Dlink, Netgear, Cisco 
9 Equipment Rack  Rittal / APC / Arctic 
 
 
 
 
 
 
 
 
 
 
 

NSL
PMC CONSULTANT 4  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

 
 
 
SCHEDULE OF APPROVED MAKES FOR HVAC WORKS 
 
The attached list schedule indicates the approved manufacturer for HVAC works. 
S.No         Equipment/ Material  Acceptable Supplier/ Manufacturer 
A HVAC EQUIPMENTS
1 Split Unit system   Carrier/MEI/Daikin/Midea
2 Variable Refrigerant Flow(VRF)  Carrier/MEI/Daikin/Midea 
3 Cooling Coil for AHUs & FCU Cariyare / Systemair/ Edgetech
4 AHU Fans Nikotra / Kruger/Cemfri

B PIPE FITTING & VALVES


1 Pipes TATA / JINDAL/SAIL
2 Fittings TATA / JINDAL/SAIL
3 Y-strainer Rapid Cool /Emerald /Emrald
4 Water duty butterfly valve Advance /Flowel /SM
5 Dual plate check valve Advance / Flowel/SM
6 Balancing valves Advance / Flowel /SM
7 Ball Valve CIM / Audco/ Kitz/ Zoloto
8 Auto Air Vent Valve Anergy / Rapid Cool/Emrald
9 Pressure Gauges Feibig / Emerald / Guru
Industrial type thermometer
10 (MERCURY filled V form WITH Emerald / Taylor /Feibig / Guru
VALVE)
11 Ventilation Fan Systemair/Kruger/Humidin
12 Closed Cell Linked Polythene(XEPL)  Cani /Supreme /K Flex 

   

C HVAC CONTROLS
1 Two-way Motorized Valve Honeywell / Danfoss/ Johnson Control
2 Thermostat Honeywell / Danfoss/ Johnson Control
Danfoss (Model : REND)
Honeywell (Model: T6571)/Johnson Control /Sauter
3 Actuator (Model: NRT 105 F061)/Schneider (TA-168-2)/Siemens
(Model: RDF 50.1)/Yamataki (Model: HY 7043)

4 Dial Thermometer Capillary Type Penn/Tadington/H-Guru/Emrald

D OTHER HVAC MISC ITEMS


Mapro/Resistoflex/Equivalent approved from AC
1 Flexible duct connector
Consultant
2 Heavy duty pipe support clamp Hira/Arosio/ Equivalent approved from AC Consultant

NSL
PMC CONSULTANT 5  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

Grooved Pipe Connector


3 Seven Star/Vectaulic
4 Paints ICI / Asian /Berger
5 Dash Fasteners Canon / Fisher / TKS
6 Welding Rods Advani / L&T / Esab
7 Tar felt / CPRX compound Shalimar tar product
8 Adhesive for Pipe Insulation - Pidilite SR-998/ 505
9 Aluminum Tape - Johnson / 3m/ Equivalent approved from AC Consultant
     
DUCTING GRILLE DIFFUSER
E
DAMPER ETC.
1 GSS Sheet Sail / Tata / Jindal
2 Factory Fabricated Duct Ductofab / Rolastar /Dustech/Ecoduct
3 Fire & Smoke Damper Spring Type Airflow / Greenheck / Tristar
4 Fire Damper Actuator Airflow / Greenheck / Tristar
Extruded aluminum Grills / FRuskin /Titus /Tristar /Airflow/Systemair/Dynamics
5
Diffusers
6 Pre Filters Thermodyne / Klenzoid/Mechmark
Loyyd / Rawcool / NGP
7 Rock Wool Insulation
8 XLPE Insulation Trocellin / Thermobreak/ Supreme
9 Fiber Glass U.P.Twiga / Owen Corning
Dunlop / Resistoflex / Equivalent approved from AC
10 Vibration Isolation Spring
Consultant
11 Nitrile Rubber K-Flex /Armacell / Eurobatex
Protective Coating over Closed Cell
12 Elastomeric – Fibreglass Woven Armacell Armachek/UP Twiga
Cloth
13 VAV Box Systemair/Trox/Tristar
F ELECTRICAL ACCESSORIES
1 Motor Control Centre & Bus Ducts Trikolite / Advance / KEPL
PVC insulated XLPE
aluminum/copper conductor
2 Skytone/ Havells / KEI / Gloster
armored MV Cables upto 1100 V
grade
ABB/ Bharat Bijlee/Kirloskar/Siemens/C. G / Siemens /
3 Three phase motors
Kirloskar / ABB.
ABB/Allen Bradley/Kirloskar
4 Starter
L & T/Schneider/Siemens
ABB/Danfoss/Siemens
5 Variable Frequency Drive (VFD)
6 Air-Circuit Breaker L&T / Siemens /GE/ABB
Moulded Case Circuit
7 L&T / GE / Siemens / ABB
Breaker(MCCB)
Motor Protection Circuit
8 L&T / GE / Siemens / ABB
Breaker(MPCB)
9 Miniature Circuit Breaker(MCB) L&T / GE / Siemens / ABB
10 HRC Fuse and Fittings L&T / Siemens / GE/ C & S

NSL
PMC CONSULTANT 6  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

11 Contactors L&T / Siemens / BCH./ GE / ABB


C & S/Havells/H H Elcon/HPL – Socomec
12 Change Over Switch
Larsen & Toubro/GE
Automatic Electric/Gilbert & Maxwell
Current Transformer & Control Indcoil/Matrix/Pragati/Precise
13
Transformer Reco

14 Protection Relay
15 Numeric Type ABB/Areva/Larsen & Toubro/Siemens
16 Electromagnetic Type ABB/Areva/Larsen & Toubro/Siemens
Indicating Lamps LED type and Altos /GE Power Controls/Larsen & Toubro
17
Push Button (ESBEE)/Schneider Electric (MG)
18 Power cable Skytone/Havells/Polycab
19 Control cable Skytone/Havells/Polycab
20 Voltmeter / Ammeter A.E. / IMP./ Rishab
21 Switches L&T / Siemens / GE
22 Selector / Toggle switch Kaycee / L&T/Schneider
23 Time Delay Device Siemens / L&T/ BCH.
24 Single Phase Device L&T / Minilec/Schneider
25 Overload Relays L&T / Siemens / BCH./GE / ABB
26 Prepaid Meters & accessories Actaris/Conzerve/Secure
Electronic Digital Meters ABB/Automatic Electric/Conzerv/El Measure
27 (A/V/PF/Hz/KW/KWH) with IME/L & T/Nippen/Schneider Electric
LED Display Secure
28 Fire Sealant & Fire Retardant Paint BTHM Engineering/Birla 3 M/HILTI/Promat
Automatic Electric/Rishabh (L&T) / Equivalent approved
29 Electromagnetic Meters
from AC Consultant
Conzerv
Static Power Meter & Logger
30 El measure/Larsen & Toubro/Nippen
(SPML) with RS 485 port
Schneider Electric
Automatic Power Factor Correction Areva/BELUK (Germany)/Conzerv/Datar
31
Relay(Numeric Type) Ducati/Siemens
ABB/Datar/Ducati /Meher(Larsen & Toubro)
32 Thyristerised APFC Control Panel
Power Matrix Solutions/Siemens
Cable Glands Double Compression
33 Baliga Lighting/Comet/Cosmos
with earthing links
Comet/Cosmos/Dowell’s (Biller India)/Hax Brass (Copper
34 Bimetallic Cable Lug
Alloy India)
PVC insulated copper conductor Finolex/Lapp Kabel/Rajanigandha/R R Kabel
35
stranded flexible wires (FRLS) - Batra Henlay
36 Mettalic Conduit (ISI approved) AKG/BEC/NIC/Vimco
ABB/BCH/GE Power Control/Larsen & Toubro
37 Timer
MDS Legrand/Schneider Electric /Siemens
Cadmium Coated Cable
38 Slotco / Pilco / KEPL / Ricco/Elcon
Tray(Factory Fabricated)
 

NSL
PMC CONSULTANT 7  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

 
 
 
SCHEDULE OF APPROVED MAKES FOR FIRE & PLUMBING WORKS 
 
The attached list schedule indicates the approved manufacturer for fire &plumbing works. 

  PLUMBING AND FIRE FIGHTING 
S.No.  Equipment/ Material            Acceptable Supplier/ 
Manufacturer 
1  Check Valves (Dual Slim type)  DRP / KARTAR/Advance 
2  Butterfly Valve  DRP / ZOLOTO / AIP 
3  Ball valves (15 to 40mm)  DRP/ZOLOTO/AIP  
4  Gate Valve  DRP/ ZOLOTO / AIP 
5  Fire fighting equipment (Hydrant, Hose Drum, F.B Inlet,  NEWAGE / SAFE GUARD / EXFLAME 
Branch) 
6  Fire Extinguishers  CEASE FIRE/ SAFE GUARD / MINIMAX 
7  Fire fighting first‐aid hose reel tubing  NEWAGE/JYOTI/DUNLOP / EXFLAME 
8  Fire pumps  MATHER + PLATT /KIRLOSKAR 
9  Motors  KIRLOSKAR/SIEMENS/ABB 
10  M.S. Pipes  JINDAL HISSAR/ PRAKASH 
SURYA/SAIL/TATA 
11  Sprinkler heads  VIKING/TYCO/H.D./NEWAGE 
12  M.S. FORGED FITTINGS    DRP‐M / V.S. or approved equivalent 
make 
13  C.I. Double Flanged Non‐Return Valves.  (80mm diameter  DRP / AIP / SANT 
and above) 
14  Welding Rod  ADWANI/ VICTOR/ ADOR/ Cosmos/ Supe
Bond (S) 
15  Alarm Control Valve  NEWAGE/ VIKING/TYCO 
16  Flow Switch  DANFOSS/ VIKING or approved make 
17  Dash Fasteners  HILTI/ canon or approved equivalent 
make 
18  Automatic Air Vent  DANFOSS/ IBP or approved equivalent 
make 
19  Water level indicator & controller  ITAL/  TECHNIKA/  Auto  Pump/  Cirru
Engineering/Technika/Techtrol
20  Pipe Clamps / Hangers / Support  CAMRY/ CHILLY or approved 
equivalent make 
21  Clamps & Support  CAMRY/ CHILLY or approved 
equivalent make 
22  Paint  Shalimar/ Asian/Dulux/Nerolac/K.S/ 
Unik/Zoloto 
23  Vitreous China Sanitaryware  Jaquar/Hindware/Kohlar 
24  C.P. Brass fittings  Jaquar/Kohlar/Hindware 
25  Cast iron pipes & fittings, Manhole covers and frames.  NECO/RIF 

NSL
PMC CONSULTANT 8  
 
APPROVED MAKE Pharmacy Council of India, 3rd Floor, NBCC Center, Okhla, New Delhi

26  G.I. pipes.  Jindal Hissar/Tata 


27  G.I. pipes fittings.  K.S. / Unik / Zoloto 
28  G.M. / Forged brass valves  Zoloto / Leader    
29  Gratings,Cleanouts,Funnels  GMGR/Neer 
30  PVC Pipes  Supreme / Prince/Astral 
31  Geyser  AO Smith/Racold/Venus 
32  Sink  Neelkanth/Kobra 
33  Water purifier  Eureka Forbes/Kent 
34  CPVC Pipes  Astral Fowguard/Supreme 
35  Gratings,Cleanouts,Funnels  GMGR/Neer 
 

NSL
PMC CONSULTANT 9  
 

You might also like