Professional Documents
Culture Documents
PCM For Waterproofing Works
PCM For Waterproofing Works
PCM For Waterproofing Works
August. 2021
In Association
TANROADS with
Contents ` New Selander Bridge Project
3. Construction Plan
6. Q & A
Normally, Two types of Bridge deck waterproofing systems are available for use
A. Sheet type waterproofing
- Woven or nonwoven fabric with materials such as synthetic rubber, resin, plastic
- Place it and bond to concrete by using an adhesive or a torch
1 / 14
1. Waterproofing Types and Design `
LIQUID TYPE
2 / 14
2. Waterproofing Approved Material `
1) Information
Description Item Contents Remakrs
Product Name BBC-252
Beijing Oriental Yuhong Waterproof
Supplier www.yuhong.com.cn
Material Technology Co.Ltd
Polymer modified bitumen waterproofing
Type Bitumen + Polymer
material
Physical condition Liquid
3 / 14
2. Waterproofing Approved Material `
4 / 14
2. Waterproofing Approved Material `
3) Material Quantity
3.1) Construction Area
Quantity
Thickness Area
Theoretical *Actual Apply
t=1mm Unit Area (/m2) 1.15 kg 1.8~2.0 kg
Unit Area (/m2) 2.3 kg 4.0kg
t=2mm
Total Area (19,055m2) 43.8 ton 76.2 ton
*Actual Apply : Supplier’s recommendation is 1.8~2.0kg/m2 to make 1mm thickness considering the surface
roughness and evaporation. We adopt 2.0kg/m2 for 1mm thickness to ensure thickness
5 / 14
3. Construction Plan `
Previous Revised
SP12.5 SP 12.5
Surface Waterproofing
Grid Marking Pavement Tack coat Pavement
Preparation (*5 layer)
(1st layer) (2nd layer)
*5 layers : The liquid waterproofing material normally will be applied by several layers. If the paint thickness is brushed to 2 mm at a
time, it will cause the paint to dry on the outside but the internal moisture cannot be evaporated, the waterproof layer is weak and soft.
The waterproof effect is poor and the coating will break once touched
6 / 14
3. Construction Plan `
1) Surface Preparation
Before waterproofing, all dust, laitance, debris and any oil shall be removed from concrete deck to
ensure the bond of waterproofing to the deck. The surface should be dry, no sand and obvious stain.
Cleaning by broom machine Remove dust by air compressor Cleaning by water bowser
7 / 14
3. Construction Plan `
• Guaranteeing the waterproof coating thickness can be achieved by controlling the amount of
material per square meter.
• Therefore, grid marking will be done prior to coating and the area will be determined based on the
one drum of material quantity (50kg)
Total 4.0kg ※ From second layer, the grid marking will be done on
the kerbstone
8 / 14
3. Construction Plan `
9 / 14
4. Quality Control Plan `
Repairing method
Checking Item Checking Method Criteria for pass
(if not okay)
Surface
There should be no damage
Surface Cut and remove partially.
By eye such as crack, peeling or tearing
damage Re-apply
of the applied film
※ Wet film thickness gauge method ※ Digital dry film gauge method
10 / 14
4. Quality Control Plan `
Checking
No. Contents Remakrs
Item
Coating
1 Curing at least 4 ~7 hours before next layer application (non-stick by hand touch)
interval
SP12.5 The pavement work can be recommend to start within 1 week after completing
3
Pavement waterproofing works to ensure material function
Material 1. Store the material in dry place and no exposed to the weather.
4
Storage 2. Before applying waterproofing, the material will be stirred evenly before use
11 / 14
5. Trial Construction Plan `
1) Location
- 2 location at bridge (1m2 / location, at a different deck condition)
where surface preparation was done (between A1~P4)
3) Checking Points
- Applying quantity per m2
- Drying time
- Thickness
- Surface condition after completion
12 / 14
6. Q & A `
Applying Tack • Tack coat layer between waterproofing and 1st layer of SP12.5 layer was
6.7 The Contractor should pay omitted according to supplier’s comment. (Attachment)
Coat
attention to this section and
should submit the action plan on
how it is going to be achieved
• All paving equipment will be set on the bridge before applying waterproofing
to avoid passing on it.
Asphalt
6.8 Concrete • The tipper or paver will not be allowed to make turns on it and the driver
(SP12.5) Paving shall take extra precautions during paving works
※ Wheel rolling result by supplier (Attachment)
13 / 14
6. Q & A `
▣ Others
14 / 14
`
Ref. Required thickness of liquid waterproofing
0.025mm ~ 3mm
Attach. Digital dry film gauge method `
Attach. Picture for wheel rolling `
▣ Repairing Concept
Cutting picture
` New Selander Bridge Project
Thank You