Professional Documents
Culture Documents
Method of Statement For: Hot Works
Method of Statement For: Hot Works
Contract N. 4600038271
Vendor logo and business name Vendor Document ID
N/A N/a
Order N.
Facility Name Location Scale Sheet of Sheets
ZUBAIR MISHRIF DGS ONSHORE N/A 1 of 9
REVISION HISTORY
Table of Contents
1. Objective............................................................................................................................................................ 3
2. Purpose.............................................................................................................................................................. 4
3. Scope................................................................................................................................................................. 4
4. Definitions and Abbreviations......................................................................................................................... 4
5. Reference Documents:..................................................................................................................................... 4
5.1. Project Documents:..................................................................................................................................4
5.2. Project HSE Major Document:..................................................................................................................5
6. Responsibility.................................................................................................................................................... 5
6.1. CONSTRUCTION Manager.........................................................................................................................6
6.2. Site Engineer.............................................................................................................................................6
6.3. HSE Manager............................................................................................................................................6
6.4. QA/QC Manager.......................................................................................................................................6
6.5. Worker......................................................................................................................................................6
7. Machinery, Equipment’s & Tool....................................................................................................................... 6
8. Work Sequence................................................................................................................................................. 7
8.1. Welding, Cutting and Grinding Preparation..............................................................................................7
8.2. Welding, Cutting and Grinding Procedure................................................................................................8
9. Risk Assessment.............................................................................................................................................. 9
1. Objective
The Method statement has issued as a Guide to Employees to ensure that all activities required for
the hot works, would be carried out in compliance with Contractual and Health & Safety
Requirements.
2. Purpose
The purpose of this document is to identify the Hot works is any work that produces open flames, hot
slag or sparks. The Fire Code defines Hot Work as cutting, welding, brazing, soldering, grinding, ther-
mal spraying, thawing pipe, installation of torch applied roof systems, or any other similar situation
and all these activities to been performed in line with proper methodology and correct sequence
according to the approved documentation and requirements.
3. Scope
Hot Works is any work that produces open flames, hot slag or sparks, Hot Work as cutting, welding,
grinding and thermal spraying and the Main activities describe into this document are:
Welding.
Cutting and grinding.
5. Reference Documents:
1.
5.1. Project Documents:
251010DADMTB028 Main Substation -Formwork & Details - Plan at level +3.500 TOC
251010DADMTB029 Main Substation -Formwork & Details - Plan at level +9.300 TOC
251010DADMTB535 Main Substation Finishing -Transversal Sections
251010DADMTB536 Main substation Finishing - Thermal and Fire Insulation - Typical Section
251010DADMTB040 Main Substation Finishing Layout and Details - First floor
251010DADMTB041 Main Substation Finishing Layout and Details - Roof
251010DADMTB043 Main Substation Finishing - External Views from West and from South
251010DADMTB044 Main Substation Finishing - Longitudinal Sections
6. Responsibility
6.5. Worker
Qualified and trained person assigned to a specific task.
He has to perform his task in line with the related PTW without any deviation.
He has to act in respect of HSE System requirements.
Equipment Remarks
Mobile Scaffold Quantities will be decided as per the work
Small Cars for the Crew requirements
Tools Remarks
Measuring tape and Levelling Tools
Welding Machine
Quantities will be decided as
Portable Grinding Machine
per the work requirements
Spirit level, Right angle
Safety tools (warning tape, flags, gloves …etc.)
8. Work Sequence
• Ensure any sprinkler system in the area is operable and is set properly to prevent inadvertent
release, i.e., set high enough so heat from the hot work does not set off the sprinkler system.
9. Risk Assessment